Item Descripción Und. Metrado Precio (S/.) Parcial (S/.

)
01 OBRAS PRELIMINARES 37,766.89
01.01 CAMPAMENTOS PROVISIONAL DE OBRA m2 400.00 23.76 9,504.00
01.02 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPO PESADO vje 1.00 12,761.77 12,761.77
01.03 LIMPIEZA Y DESFORESTACION ZONA SIERRA m2 55,000.00 0.23 12,650.00
01.04 TRAZO NIVELES Y REPLANTEO PRELIMINAR km 5.50 209.48 1,152.14
01.05 TRAZO Y REPLANTEO DURANTE EL PROCESO DE EJECUCION km 5.50 209.48 1,152.14
01.06 CARTEL DE OBRA E INSTALACION und 1.00 546.84 546.84
02 MOVIMIENTO DE TIERRAS 547,844.85
02.01 CORTE DE MATERIAL SUELTO R=570 M3/DIA m3 63,121.50 5.35 337,700.03
02.02 CORTE ROCA SUELTA (PERF. Y DISP.) RENDIMIENTO=250 M3/DIA m3 7,133.19 12.71 90,662.84
02.03 CORTE ROCA FIJA (PERF. Y DISP.) RENDIMIENTO=260 M3/DIA m3 2,116.51 21.21 44,891.18
02.04 CONFORMACION DE TERRAPLENES m3 3,955.00 5.76 22,780.80
02.05 PERFILADO Y COMPACTACION SUB RASANTE: REND.=2,860 M2/DIA m2 33,000.00 1.57 51,810.00
03 PAVIMENTOS 223,238.40
03.01 EXTRACCION Y APILAMIENTO DEL MATERIAL PARA EL AFIRMADO m3 7,920.00 5.78 45,777.60
03.02 ZARANDEO DEL MATERIAL PARA EL AFIRMADO m3 7,920.00 7.40 58,608.00
03.03 CARGUIO DEL MATERIAL PARA AFIRMADO m3 7,920.00 2.38 18,849.60
03.04 TRANSPORTE DEL MATERIAL PARA AFIRMADO m3 7,920.00 5.96 47,203.20
03.05 EXTENDIDO Y COMPACTACION DEL MATERIAL PARA EL AFIRMADO E=0.20 M m2 33,000.00 1.60 52,800.00
04 OBRAS DE ARTE Y DRENAJE 306,392.02
04.01 ALCANTARILLA TIPO II ( 0.8X0.8 CAJA COLECTORA) - 01 UNID. 13,309.89
04.01.01 TRAZO Y REPLANTEO m2 25.76 1.55 39.93
04.01.02 EXCAVACION PARA ESTRUCTURAS C/MAQUINARIA m3 31.21 2.98 93.01
04.01.03 NIVELACION Y APISONADO CON PLANCHA COMPACTADORA m2 33.22 2.64 87.70
04.01.04 RELLENO Y COMPACTACION CON MATERIAL SELECCIONADO m3 2.64 11.64 30.73
04.01.05 ELIMINACION DE MATERIAL EXCEDENTE d<= 1 KM m3 34.29 7.51 257.52
04.01.06 SOLADO DE CONCRETO C:H, 1:12 (e=7.5cm) m2 13.20 24.66 325.51
04.01.07 ACERO F'Y = 4200 KG/CM2 kg 682.36 5.10 3,480.04
04.01.08 CONCRETO F'C=210 KG/CM2 m3 11.05 480.13 5,305.44
04.01.09 ENCOFRADO Y DESENCOFRADO EN ALCANTARILLAS: REND.=15 M2/DIA m2 76.27 27.45 2,093.61
04.01.10 EMBOQUILLADO DE CONCRETO m3 5.21 306.41 1,596.40
04.02 ALCANTARILLA TIPO I ( INGRESO Y SALIDA: MUROS DE ALERO Y MURO DE CABECERA) - 01 UNID. 244,812.66
04.02.01 TRAZO Y REPLANTEO m2 333.44 1.55 516.83
04.02.02 EXCAVACION PARA ESTRUCTURAS C/MAQUINARIA m3 453.87 2.98 1,352.53
04.02.03 NIVELACION Y APISONADO CON PLANCHA COMPACTADORA m2 478.60 2.64 1,263.50
04.02.04 RELLENO Y COMPACTACION CON MATERIAL SELECCIONADO m3 32.45 11.64 377.72
04.02.05 ELIMINACION DE MATERIAL EXCEDENTE d<= 1 KM m3 505.71 7.51 3,797.88
04.02.06 SOLADO DE CONCRETO C:H, 1:12 (e=7.5cm) m2 154.00 24.66 3,797.64
04.02.07 ACERO F'Y = 4200 KG/CM2 kg 10,024.00 5.10 51,122.40
04.02.08 CONCRETO F'C=210 KG/CM2 m3 127.44 480.13 61,187.77
04.02.09 ENCOFRADO Y DESENCOFRADO EN ALCANTARILLAS: REND.=15 M2/DIA m2 581.00 27.45 15,948.45
04.02.10 EMBOQUILLADO DE CONCRETO m3 344.14 306.41 105,447.94
04.03 BADEN TIPO I (L=5 m)- 1 UNID. 35,140.32
04.03.01 TRAZO Y REPLANTEO m2 180.00 1.55 279.00
04.03.02 EXACAVCION EN CONGLOMERADO m3 100.20 9.46 947.89
04.03.03 CONCRETO F'C=175 KG/CM2 m3 20.00 371.72 7,434.40
04.03.04 CONCRETO CICLOPEO FC=140KG/CM2 + 30 % PM. m3 55.20 305.38 16,856.98
04.03.05 JUNTAS ASFALTICAS m 40.00 7.87 314.80
04.03.06 EMBOQUILLADO DE CONCRETO m3 25.00 306.41 7,660.25
04.03.07 ENCOFRADO Y DESENCOFRADO NORMAL m2 60.00 27.45 1,647.00
04.04 CUNETAS 13,129.15
04.04.01 CONSTRUCCION DE CUNETA EN TERRENO NATURAL m 4,797.10 0.73 3,501.88
04.04.02 CONSTRUCCION DE CUNETA EN ROCA SUELTA m 542.30 7.80 4,229.94
04.04.03 CONSTRUCCION DE CUNETA EN ROCA FIJA m 16.06 19.28 309.64
04.04.04 LIMPIEZA Y PERFILADO MANUAL EN CUNETAS m 5,355.46 0.95 5,087.69
05 SEÑALIZACION Y SEGURIDAD VIAL 8,639.70
05.01 SEÑALES INFORMATIVAS und 2.00 350.00 700.00
05.02 SEÑALES PREVENTIVAS und 23.00 200.00 4,600.00
05.03 SEÑALES REGLAMENTARIAS und 5.00 200.00 1,000.00
05.04 HITOS KILOMETRICOS und 6.00 389.95 2,339.70
06 PROTECCION AMBIENTAL 6,387.86
06.01 TALLERES DE CAPACITACION SOBRE EDUCACIÓN AMBIENTAL glb 2.00 1,250.00 2,500.00
06.02 INSTALACION DE LETRINAS EN CAMPAMENTO und 1.00 1,960.00 1,960.00
06.03 INSTALACION Y DISPOSICION DE CONTENDOR PARA RESIDUOS SOLIDOS und 1.00 412.52 412.52
06.04 MICRO RELLENO SANITARIO m3 2.40 86.39 207.34
06.05 ADECUACION Y REPOSICION DE CANTERAS m2 400.00 2.71 1,084.00
06.06 ADECUACION Y REPOSICION DEL AREA DE CAMPAMENTO m2 400.00 0.56 224.00
07 FLETE 22,385.65
07.01 FLETE TERRESTRE DE MATERIALES Y HERRAMIENTAS (AYACUCHO - OBRA) glb 1.00 22,385.65 22,385.65
08 OTROS 12,247.27
08.01 LIMPIEZA FINAL DE OBRA ha 2.20 5,566.94 12,247.27
COSTO DIRECTO ###