CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROYECTO: "MEJORAMIENTO DE LAS PRINCIPALES VIAS DE ACCESO AL HOSPITAL ESSALUD DE TARAPOTO Y MORALES, PROVINVIA DE SAN MARTIN, DEPARTAMENTO DE SAN MARTIN" - CODIGO
SNIP: 305453

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09
01 OBRAS PRELIMINARES 13,315.78
01.01 CARTEL DE OBRA DE 3.60 x 8.50 m. und 2.00 1,485.15 2,970.30 2,970.30
01.02 MOVILIZACION Y DESMOVILIZACION GLB 1.00 4,790.00 4,790.00 4,790.00
01.03 DEMOLICION VEREDAS EXISTENTES m3 198.41 28.00 5,555.48 5,555.48
02 PAVIMENTO ASFALTICO 2,517,017.92
02.01 TRAZO, NIVELACION Y REPLANTEO m2 ### 1.04 24,551.32 24,167.71 383.61
02.02 CORTE DE TERRENO NATURAL C/MAQUINARIA m3 ### 4.53 50,217.68 50,217.68
02.03 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 ### 9.22 122,650.89 122,650.89
02.04 PERFILADO Y COMPACTADO DE SUBRASANTE m2 ### 1.62 38,243.40 38,243.40
02.05 SUB BASE GRANULAR m3 5,901.76 93.13 549,630.91 549,630.91
02.06 BASE GRANULAR m3 4,131.23 105.35 435,225.08 365,278.19 69,946.89
02.07 IMPRIMACION ASFALTICA m2 ### 6.68 157,695.03 157,695.03
02.08 CARPETA ASFALTICA EN CALIENTE E=0.05m m2 ### 48.24 1,138,803.61 1,138,803.61
03 VEREDAS, RAMPA Y MARTILLOS 648,952.56
03.01 LIMPIEZA DE TERRENO MANUAL m2 ### 0.79 8,026.20 8,026.20
03.02 TRAZO, NIVELACION Y REPLANTEO m2 ### 1.04 10,566.14 10,566.14
03.03 EXCAVACION DE VEREDAS m3 2,031.95 29.68 60,308.28 60,308.28
03.04 BASE GRANULAR e=0.10 m m3 1,015.98 131.21 133,306.74 32,493.52 100,813.22
03.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 2,438.34 9.22 22,481.49 2,458.91 20,022.58
03.06 CONCRETO SIMPLE F'C=175 KG/CM2, EN VEREDAS INC. BRUÑADO m3 1,015.98 378.62 384,670.35 384,670.35
03.07 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 585.64 28.01 16,403.78 10,416.40 5,987.38
03.08 JUNTA ASFALTICA EN VEREDAS m 2,438.00 5.41 13,189.58 1,154.09 12,035.49
04 SARDINELES 236,766.06
04.01 LIMPIEZA DE TERRENO MANUAL m2 462.79 0.79 365.60 365.60
04.02 TRAZO, NIVELACION Y REPLANTEO m2 462.79 1.04 481.30 481.30
04.03 EXCAVACION DE SARDINELES m3 208.26 29.68 6,181.16 6,181.16
04.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 249.91 9.22 2,304.17 2,304.17
04.05 CONCRETO ARMADO FC=210 KG/CM2 EN SARDINELES m3 277.68 430.70 119,596.78 17,192.04 102,404.74
04.06 ACERO DE REFUERZO fy=4,200 Kg/m2 EN SARDINELES kg 3,858.49 4.76 18,366.41 18,366.41
04.07 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 3,702.34 23.49 86,967.97 34,352.35 52,615.62
04.08 JUNTA ASFALTICA EN SARDINELES m 462.60 5.41 2,502.67 2,502.67
05 CUNETAS 1,124,284.97
05.01 LIMPIEZA DE TERRENO MANUAL m2 3,917.70 0.79 3,094.98 3,094.98
05.02 TRAZO, NIVELACION Y REPLANTEO m2 3,917.70 1.04 4,074.41 4,074.41
05.03 EXCAVACION MANUAL PARA ESTRUCTURAS m3 2,986.01 29.68 88,624.78 88,624.78
05.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 3,583.22 9.22 33,037.29 33,037.29
05.05 CONCRETO SIMPLE F'C=175 KG/CM2, EN CUNETA m3 1,140.59 378.62 431,850.19 40,485.96 391,364.23
05.06 CONCRETO SIMPLE F'C=100 KG/CM2, PARA SOLADOS m3 123.40 243.83 30,088.62 6,268.46 23,820.16
05.07 CONCRETO ARMADO FC=210 KG/CM2 PARA CUNETAS m3 338.48 411.49 139,281.14 60,587.30 78,693.84
05.08 ACERO DE REFUERZO fy=4,200 Kg/cm2 PARA CUNETAS kg ### 4.76 161,190.21 161,190.21
05.09 ENCOFRADO Y DESENCOFRADO DE CUNETAS m2 7,792.95 28.44 221,631.50 6,464.25 215,167.25
05.10 JUNTA ASFALTICA PARA CUNETAS m 2,109.40 5.41 11,411.85 11,411.85
06 ALCANTARILLA DE CRUCE 341,391.32
06.01 LIMPIEZA DE TERRENO MANUAL m2 636.53 0.79 502.86 502.86
06.02 TRAZO, NIVELACION Y REPLANTEO m2 636.53 1.04 661.99 661.99
06.03 EXCAVACION MANUAL PARA ESTRUCTURAS m3 815.45 29.68 24,202.56 24,202.56
06.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 978.54 9.22 9,022.14 9,022.14
06.05 CONCRETO SIMPLE F'C=100 KG/CM2, PARA SOLADOS m3 63.65 243.83 15,519.78 15,519.78
06.06 CONCRETO ARMADO FC=210 KG/CM2 PARA ALCANTARILLAS m3 269.10 411.49 110,731.96 40,659.39 70,072.57
06.07 ACERO DE REFUERZO fy=4,200 Kg/cm2 PARA ALCANTARILLAS kg ### 4.76 112,368.37 112,368.37
06.08 ENCOFRADO Y DESENCOFRADO DE ALCANTARILLA m2 2,214.86 28.44 62,990.62 37,400.68 25,589.94
06.09 JUNTA ASFALTICA PARA ALCANTARILLAS m 379.40 5.41 2,052.55 2,052.55
06.10 TAPAS DE INSPECCION DE ALCANTARILLAS und 57.00 58.57 3,338.49 3,338.49
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: "MEJORAMIENTO DE LAS PRINCIPALES VIAS DE ACCESO AL HOSPITAL ESSALUD DE TARAPOTO Y MORALES, PROVINVIA DE SAN MARTIN, DEPARTAMENTO DE SAN MARTIN" - CODIGO
SNIP: 305453

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 MES 09
07 TOMAS LATERALES 98,252.82
07.01 LIMPIEZA DE TERRENO MANUAL m2 203.41 0.79 160.69 160.69
07.02 TRAZO, NIVELACION Y REPLANTEO m2 203.41 1.04 211.55 211.55
07.03 EXCAVACION MANUAL PARA ESTRUCTURAS m3 213.58 29.68 6,339.05 6,339.05
07.04 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 256.30 9.22 2,363.09 2,363.09
07.05 CONCRETO SIMPLE F'C=100 KG/CM2, PARA SOLADOS m3 20.34 243.83 4,959.50 4,959.50
07.06 CONCRETO ARMADO FC=210 KG/CM2 PARA TOMAS LATERALES m3 81.36 419.20 34,106.11 34,106.11
07.07 ACERO DE REFUERZO fy=4,200 Kg/cm2 PARA TOMAS LATERALES kg 5,849.88 4.76 27,845.43 19,392.35 8,453.08
07.08 ENCOFRADO Y DESENCOFRADO DE TOMAS LATERALES m2 752.62 28.67 21,577.62 21,577.62
07.09 JUNTA ASFALTICA PARA TOMAS LATERALES m 127.50 5.41 689.78 689.78
08 BERMAS LATERALES 298,365.90
08.01 LIMPIEZA DE TERRENO MANUAL m2 3,474.93 0.79 2,745.19 2,745.19
08.02 TRAZO, NIVELACION Y REPLANTEO m2 3,474.93 1.04 3,613.93 3,613.93
08.03 EXCAVACION MANUAL H=0.25m m3 868.73 29.68 25,783.91 24,333.57 1,450.34
08.04 BASE GRANULAR e=0.10 m m3 347.49 131.21 45,594.16 45,594.16
08.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO (DM=3.00 Km) m3 1,042.48 9.22 9,611.67 9,611.67
08.06 ENCOFRADO Y DESENCOFRADO NORMAL EN BERMA m2 282.13 29.03 8,190.23 6,768.32 1,421.91
08.07 CONCRETO SIMPLE F'C=175 KG/CM2, BERMAS m3 521.24 378.62 197,351.89 197,351.89
08.08 JUNTA ASFALTICA EN BERMAS m 1,012.00 5.41 5,474.92 5,474.92
09 SEÑALIZACION VIAL 35,302.44
09.01 SEÑALIZACION VERTICAL und 46.00 317.81 14,619.26 14,619.26
09.02 MARCAS CON PINTURA DE TRANSITO m2 1,770.82 11.68 20,683.18 20,683.18
10 ARBORIZACION Y JARDINERIA 94,736.28
10.01 GRASS AMERICANO m2 6,717.27 13.65 91,690.74 91,690.74
10.02 SEMBRADO DE PLANTAS ORNAMENTALES und 263.00 11.58 3,045.54 3,007.47 38.07
11 VARIOS 61,290.22
11.01 NIVELACIÓN DE TAPA PARA CAJA DOMICILIARIA DE AGUA und 297.00 60.95 18,102.15 527.98 17,574.17
11.02 NIVELACIÓN DE TAPA PARA CAJA DOMICILIARIA DE DESAGUE und 297.00 125.97 37,413.09 1,091.22 36,321.87
11.03 NIVELACION DE TAPAS DE BUZONES und 39.00 137.82 5,374.98 587.89 4,787.09
11.04 PLACA RECORDATORIA und 1.00 400.00 400.00 400.00
COSTO DIRECTO 5,469,676.27 124,709.92 152,610.03 586,910.31 525,650.01 953,520.88 314,082.31 283,640.16 1,003,753.79 1,524,798.86
GASTOS GENERALES 8%CD 437,574.10 9,976.79 12,208.80 46,952.82 42,052.00 76,281.67 25,126.58 22,691.21 80,300.31 121,983.92
UTILIDAD 7%CD 382,877.34 8,729.69 10,682.70 41,083.72 36,795.50 66,746.46 21,985.76 19,854.81 70,262.77 106,735.93
SUB TOTAL 6,290,127.71 143,416.40 175,501.53 674,946.85 604,497.51 1,096,549.01 361,194.65 326,186.18 1,154,316.87 1,753,518.71
IGV 18% 1,132,222.99 25,814.95 31,590.28 121,490.43 108,809.55 197,378.82 65,015.04 58,713.51 207,777.04 315,633.37
COSTO DE OBRA 7,422,350.70 169,231.35 207,091.81 796,437.28 713,307.06 1,293,927.83 426,209.69 384,899.69 1,362,093.91 2,069,152.08
PORCENTAJE 100% 2.28% 2.79% 10.73% 9.61% 17.43% 5.74% 5.19% 18.35% 27.88%
PORCENTAJE ACUMULADO 2.28% 5.07% 15.80% 25.41% 42.84% 48.59% 53.77% 72.12% 100.00%
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS ADYACENTES AL JR. MARTÍNEZ DE COMPAGÑON DE LA PARTE BAJA DEL BARRIO HUAYCO DE LA CIUDAD DE
TARAPOTO DEL DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTÍN - DEPARTAMENTO DE SAN MARTÍN"
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04
01 OBRAS PROVISIONALES 4,218.24
01.01 CARTEL DE OBRA 4.80X3.60 m und 1.00 1,818.24 1,818.24 1,818.24
01.02 ALQUILER DE ALMACEN Y/O DEPOSITO PARA OBRA mes 4.00 600.00 2,400.00 2,400.00
02 OBRAS PRELIMINARES 4,303.20
02.01 MOVILIZACION Y DESMOVILIZACIÓN DE MAQUINARIAS Y EQUIPOS est 1.00 4,303.20 4,303.20 4,303.20
03 SEGURIDAD SALUD Y MEDIO AMBIENTE 146,968.00
03.01 SEGURIDAD Y SALUD 110,636.00
03.01.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE GLB 1.00 52,128.00 52,128.00 13,032.00 13,032.00 13,032.00 13,032.00
03.01.02 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 2,200.00 2,200.00 2,200.00
03.01.03 EQUIPOS DE PROTECCION INDIVIDUAL GLB 1.00 438.00 438.00 438.00
03.01.04 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1,870.00 1,870.00 1,870.00
03.01.05 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00 14,000.00 14,000.00 3,500.00 3,500.00 3,500.00 3,500.00
03.01.06 RECURSO PARA RESPUESTA ANTE EMERGENCIA EN SEGURIDAD Y S GLB 1.00 40,000.00 40,000.00 10,000.00 10,000.00 10,000.00 10,000.00
03.02 MITIGACION AMBIENTAL 36,332.00
03.02.01 MONITOREO AMBIENTAL 21,932.00
03.02.01.01 MONITOREO DE CALIDAD DEL AIRE und 8.00 2,000.00 16,000.00 4,000.00 4,000.00 4,000.00 4,000.00
03.02.01.02 MONITOREO DE CALIDAD DE RUIDOS und 8.00 500.00 4,000.00 1,000.00 1,000.00 1,000.00 1,000.00
03.02.01.03 TRATAMIENTO DE RESIDUOS SOLIDOS und 4.00 483.00 1,932.00 483.00 483.00 483.00 483.00
03.02.02 CAPACITACION Y EDUCACION AMBIENTAL 14,400.00
03.02.02.01 CHARLA AL PERSONAL DE OBRA und 4.00 1,200.00 4,800.00 1,200.00 1,200.00 1,200.00 1,200.00
03.02.02.02 CHARLA A POBLACION BENEFICIARIA und 4.00 1,200.00 4,800.00 1,200.00 1,200.00 1,200.00 1,200.00
03.02.02.03 SEMINARIO TALLER A PERSONAL TECNICO und 4.00 1,200.00 4,800.00 1,200.00 1,200.00 1,200.00 1,200.00
04 PAVIMENTO FLEXIBLE 873,482.19
04.01 OBRAS PRELIMINARES 13,863.10
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 5,153.57 0.78 4,019.78 4,019.78
04.01.02 TRAZO, NIVELACION Y REPLANTEO m2 5,153.57 1.91 9,843.32 9,843.32
04.02 MOVIMIENTO DE TIERRAS 131,654.33
04.02.01 EXCAVACION MASIVA CON MAQUINARIA EN MATERIAL COMUN m3 5,307.59 7.55 40,072.30 26,047.00 14,025.31
04.02.02 RELLENO CON MATERIAL SELECTO DE PRESTAMO m3 71.56 67.44 4,826.01 4,826.01
04.02.03 DEMOLICION DE PAVIMENTO EXISTENTE m2 984.40 5.24 5,158.26 1,547.48 3,610.78
04.02.04 CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE m3 6,696.23 10.20 68,301.55 68,301.55
04.02.05 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 5,153.57 2.58 13,296.21 10,636.97 2,659.24
04.03 PAVIMENTO 698,803.55
04.03.01 MEJORAMIENTO DE LA SUBRASANTE m3 481.14 88.86 42,754.10 42,754.10
04.03.02 SUB BASE GRANULAR E= 0.15 M m2 5,153.57 20.39 105,081.29 105,081.29
04.03.03 BASE GRANULAR E=0.15 M m2 5,153.57 22.20 114,409.25 114,409.25
04.03.04 IMPRIMACION m2 5,153.57 8.30 42,774.63 42,774.63
04.03.05 CARPETA ASFALTICA E=0.5M m2 5,153.57 76.41 393,784.28 393,784.28
04.04 SEÑALIZACION VIAL 26,396.56
04.04.01 SEÑALIZACION VERTICAL 5,400.00
04.04.01.01 POSTE DE SEÑAL REGULADORA und 9.00 600.00 5,400.00 5,400.00
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS ADYACENTES AL JR. MARTÍNEZ DE COMPAGÑON DE LA PARTE BAJA DEL BARRIO HUAYCO DE LA CIUDAD DE
TARAPOTO DEL DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTÍN - DEPARTAMENTO DE SAN MARTÍN"
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04
04.04.02 SEÑALIZACION HORIZONTAL 20,996.56
04.04.02.01 PINTADO DE PAVIMENTO (LINEAS DE CARRIL Y BORDE) m 1,812.52 9.57 17,345.82 17,345.82
04.04.02.02 PINTADO DE TRAFICO (SIMBOLOS Y LETRAS) m2 160.12 22.80 3,650.74 3,650.74
04.05 VARIOS 2,764.65
04.05.01 NIVELACION DE TAPAS DE BUZONES und 7.00 394.95 2,764.65 2,764.65
05 BERMAS DE CONCRETO 183,002.74
05.01 OBRAS PRELIMINARES 3,597.71
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,337.44 0.78 1,043.20 1,043.20
05.01.02 TRAZO, NIVELACION Y REPLANTEO m2 1,337.44 1.91 2,554.51 2,554.51
05.02 MOVIMIENTO DE TIERRAS 26,661.88
05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL EN BERMAS m3 401.25 34.51 13,847.14 13,847.14
05.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 501.56 19.71 9,885.75 9,885.75
05.02.03 PERFILADO Y COMPACTADO EN BERMAS m2 1,337.44 2.19 2,928.99 2,928.99
05.03 CONCRETO 152,743.15
05.03.01 MATERIAL GRANULAR e=0.10m m2 133.76 11.22 1,500.79 1,500.79
05.03.02 CONCRETO FC=210 KG/CM2 EN BERMAS m3 267.49 499.65 133,651.38 60,143.12 73,508.26
05.03.03 ENCOFRADO Y DESENCOFRADO EN BERMAS m2 169.22 47.32 8,007.49 8,007.49
05.03.04 JUNTA DE DILATACION EN BERMAS m 871.75 9.72 8,473.41 8,473.41
05.03.05 CURADO DE CONCRETO m2 1,337.44 0.83 1,110.08 1,110.08
06 VEREDAS, RAMPAS Y MARTILLOS 422,874.38
06.01 VEREDAS DE CONCRETO 322,287.91
06.01.01 OBRAS PRELIMINARES 7,587.69
06.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,820.70 0.78 2,200.15 2,200.15
06.01.01.02 TRAZO, NIVELACION Y REPLANTEO m2 2,820.70 1.91 5,387.54 5,387.54
06.01.02 MOVIMIENTO DE TIERRAS 58,451.28
06.01.02.01 DEMOLICION DE ESTRUCTURAS EXISTENTES m3 184.76 98.91 18,274.61 18,274.61
06.01.02.02 EXCAVACION MANUAL EN TERRENO NORMAL EN VEREDAS m3 499.95 34.51 17,253.27 17,253.27
06.01.02.03 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 624.94 19.71 12,317.57 12,317.57
06.01.02.04 PERFILADO Y COMPACTADO EN VEREDAS m2 2,820.70 3.76 10,605.83 10,605.83
06.01.03 CONCRETO 229,621.09
06.01.03.01 MATERIAL GRANULAR e=0.05m m2 2,820.70 6.44 18,165.31 18,165.31
06.01.03.02 CONCRETO FC=175 KG/CM2 PARA VEREDAS, INC. BRUÑADO m3 423.08 422.13 178,594.76 151,805.55 26,789.21
06.01.03.03 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 544.84 37.42 20,387.91 20,387.91
06.01.03.04 JUNTA DE DILATACION EN VEREDAS m 1,042.38 9.72 10,131.93 10,131.93
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS ADYACENTES AL JR. MARTÍNEZ DE COMPAGÑON DE LA PARTE BAJA DEL BARRIO HUAYCO DE LA CIUDAD DE
TARAPOTO DEL DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTÍN - DEPARTAMENTO DE SAN MARTÍN"
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04
06.01.03.05 CURADO DE CONCRETO m2 2,820.70 0.83 2,341.18 2,341.18
06.01.04 VARIOS 26,627.85
06.01.04.01 NIVELACION DE CAJA DE REGISTRO DE AGUA und 71.00 180.63 12,824.73 11,542.26 1,282.47
06.01.04.02 NIVELACION DE CAJA DE REGISTRO DESAGUE und 72.00 191.71 13,803.12 12,422.81 1,380.31
06.02 MARTILLOS Y RAMPAS 100,586.47
06.02.01 OBRAS PRELIMINARES 2,597.57
06.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 965.64 0.78 753.20 753.20
06.02.01.02 TRAZO, NIVELACION Y REPLANTEO m2 965.64 1.91 1,844.37 1,844.37
06.02.02 MOVIMIENTO DE TIERRAS 9,343.58
06.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL EN RAMPAS Y MARTIL m3 96.58 34.51 3,332.98 3,332.98
06.02.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 120.74 19.71 2,379.79 2,379.79
06.02.02.03 PERFILADO Y COMPACTADO EN RAMPAS Y MARTILLOS m2 965.64 3.76 3,630.81 3,630.81
06.02.03 CONCRETO 88,645.32
06.02.03.01 MATERIAL GRANULAR e=0.05m m2 965.64 6.44 6,218.72 6,218.72
06.02.03.02 CONCRETO FC=175 KG/CM2 EN RAMPAS Y MARTILLOS, INC. BRUÑA m3 183.51 422.13 77,465.08 77,465.08
06.02.03.03 ENCOFRADO Y DESENCOFRADO DE RAMPAS Y MARTILLOS m2 132.59 37.42 4,961.52 4,961.52
07 DRENAJE 843,196.83
07.01 CUNETAS (0.40x0.40) 714,989.35
07.01.01 OBRAS PRELIMINARES 2,725.56
07.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,013.22 0.78 790.31 790.31
07.01.01.02 TRAZO, NIVELACION Y REPLANTEO m2 1,013.22 1.91 1,935.25 1,935.25
07.01.02 MOVIMIENTO DE TIERRAS 45,838.99
07.01.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 759.92 30.67 23,306.75 23,306.75
07.01.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 949.90 19.71 18,722.53 18,722.53
07.01.02.03 PERFILADO Y COMPACTADO EN DRENAJE m2 1,013.22 3.76 3,809.71 3,809.71
07.01.03 CONCRETO 666,424.80
07.01.03.01 CONCRETO SIMPLE 281,547.96
07.01.03.01.01 SOLADO, CONCRETO F'C=140 KG/CM2 m2 1,027.06 274.13 281,547.96 281,547.96
07.01.03.02 CONCRETO ARMADO 384,876.84
07.01.03.02.01 CONCRETO F'C=175 KG/CM2 EN CUNETAS m3 363.56 422.13 153,469.58 153,469.58
07.01.03.02.02 ENCOFRADO Y DESENCOFRADO EN CUNETAS m2 3,472.37 37.42 129,936.09 103,948.87 25,987.22
07.01.03.02.03 ACERO F'Y=4200 KG/CM2 EN DRENAJE kg ### 4.68 92,284.36 18,456.87 73,827.49
07.01.03.02.04 JUNTA DE DILATACION EN CUNETAS m 1,000.70 8.34 8,345.84 8,345.84
07.01.03.02.05 CURADO DE CONCRETO m2 1,013.22 0.83 840.97 840.97
07.02 ALCANTARILLAS (0.60x0.60) 128,207.48
07.02.01 OBRAS PRELIMINARES 302.88
07.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 145.88 0.78 113.79 113.79
07.02.01.02 TRAZO, NIVELACION Y REPLANTEO m2 99.00 1.91 189.09 189.09
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS ADYACENTES AL JR. MARTÍNEZ DE COMPAGÑON DE LA PARTE BAJA DEL BARRIO HUAYCO DE LA CIUDAD DE
TARAPOTO DEL DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTÍN - DEPARTAMENTO DE SAN MARTÍN"
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 MES 03 MES 04
07.02.02 MOVIMIENTO DE TIERRAS 9,019.91
07.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 153.17 30.67 4,697.72 4,697.72
07.02.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 191.46 19.71 3,773.68 3,773.68
07.02.02.03 PERFILADO Y COMPACTADO EN DRENAJE m2 145.88 3.76 548.51 548.51
07.02.03 CONCRETO 118,884.69
07.02.03.01 SOLADO, CONCRETO F'C=140 KG/CM2 m2 145.88 274.13 39,990.08 39,990.08
07.02.03.02 CONCRETO FC=210 KG/CM2 EN DRENAJE m3 85.73 472.07 40,470.56 40,470.56
07.02.03.03 ENCOFRADO Y DESENCOFRADO EN DRENAJE m2 540.44 37.42 20,223.26 20,223.26
07.02.03.04 ACERO F'Y=4200 KG/CM2 EN DRENAJE kg 3,837.71 4.68 17,960.48 17,960.48
07.02.03.05 CURADO DE CONCRETO m2 289.53 0.83 240.31 240.31
08 SARDINELES 173,440.56
08.01 OBRAS PRELIMINARES 811.20
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 301.56 0.78 235.22 235.22
08.01.02 TRAZO, NIVELACION Y REPLANTEO m2 301.56 1.91 575.98 575.98
08.02 MOVIMIENTO DE TIERRAS 7,805.16
08.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 120.62 30.67 3,699.42 3,699.42
08.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 150.78 19.71 2,971.87 2,971.87
08.02.03 PERFILADO Y COMPACTADO EN SARDINEL m2 301.56 3.76 1,133.87 1,133.87
08.03 CONCRETO 164,824.20
08.03.01 SOLADO, CONCRETO F'C=140 KG/CM2 m2 301.56 274.13 82,666.64 82,666.64
08.03.02 CONCRETO F'C=175KG/CM2 PARA SARDINEL m3 154.53 422.13 65,231.75 65,231.75
08.03.03 ENCOFRADO Y DESENCOFRADO EN SARDINEL m2 452.32 37.42 16,925.81 16,925.81
09 AREAS VERDES 23,016.93
09.01 MOVIMIENTO DE TIERRAS 23,016.93
09.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 124.71 30.67 3,824.86 3,824.86
09.01.02 MATERIAL DE PRESTAMO PARA AREAS VERDES m3 155.89 99.35 15,487.67 15,487.67
09.01.03 SEMBRADO DE PLANTONES INC. SUMINISTRO Y TAPADO DE HOYOS und 168.00 22.05 3,704.40 3,704.40
10 VARIOS 11,533.21
10.01 LIMPIEZA FINAL DE OBRA m2 ### 0.28 3,247.61 3,247.61
10.02 INSTALACION DE TACHO DE BASURA und 30.00 259.52 7,785.60 7,785.60
10.03 PLACA RECORDATORIA und 1.00 500.00 500.00 500.00
COSTO DIRECTO 2,686,036.28 729,281.17 1,000,042.18 178,940.72 777,772.21
GASTOS GENERALES 10%CD 268,603.63 72,928.12 100,004.22 17,894.07 77,777.22
UTILIDAD 10%CD 214,882.90 58,342.49 80,003.37 14,315.26 62,221.78
SUB TOTAL 3,169,522.81 860,551.78 1,180,049.77 211,150.05 917,771.21
IGV 18% 570,514.11 154,899.32 212,408.96 38,007.01 165,198.81
COSTO DE OBRA 3,740,036.92 1,015,451.10 1,392,458.73 249,157.06 1,082,970.02
PORCENTAJE 100% 27.15% 37.23% 6.66% 28.96%
PORCENTAJE ACUMULADO 27.15% 64.38% 71.04% 100.00%
OBRAS PROVISIONALES
CARTEL DE OBRA DE 3.60x8.50m S/1,800.49
ALQUILER DE ALMACEN Y/O DEPOSITO PARA OBRA S/2,400.00
OBRAS PRELIMINARES
MOVILIZACION Y DESMOVILIZACIÓN DE MAQUINARIAS Y EQUIPOS S/4,204.20
PAVIMENTO FLEXIBLE
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/5,423.67 S/2,172.63
TRAZO, NIVELACION Y REPLANTEO S/18,737.57 S/6.54
MOVIMIENTO DE TIERRAS
EXCAVACION MASIVA CON MAQUINARIA EN MATERIAL COMUN S/30,599.51
ELIMINACION MATERIAL EXCEDENTE (D=5KM) S/74,266.67
PERFILADO Y COMPACTADO DE SUB-RASANTE S/21,309.09
PAVIMENTO
SUB BASE GRANULAR E=0.20M S/192,077.78
BASE GRANULAR E=0.20M S/181,606.94
IMPRIMACION
CARPETA ASFALTICA 0.05M
SEÑALIZACION
SEÑALES REGLAMENTARIAS VERTICALES
MARCAS RETROREFLECTIVAS EN EL PAVIMENTO
VARIOS
NIVELACION DE TAPAS DE BUZONES
BERMAS DE CONCRETO
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/245.72
TRAZO, NIVELACION Y REPLANTEO S/606.33
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL EN BERMAS S/2,056.86
ELIMINACION MATERIAL EXCEDENTE MANUAL S/1,469.08
PERFILADO Y COMPACTADO EN BERMAS S/721.21
CONCRETO
MATERIAL GRANULAR e=0.10m S/3,593.29
CONCRETO FC=210 KG/CM2 EN BERMAS S/19,170.06 S/4,803.93
ENCOFRADO Y DESENCOFRADO EN BERMAS S/2,265.89
JUNTA DE DILATACION EN BERMAS S/910.44
VEREDAS, RAMPAS, MARTILLOS Y ACCESOS
VEREDAS DE CONCRETO
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/2,166.13
TRAZO, NIVELACION Y REPLANTEO S/5,345.00
MOVIMIENTO DE TIERRAS
DEMOLICION DE ESTRUCTURAS EXISTENTES S/8,845.34
EXCAVACION MANUAL EN TERRENO NORMAL EN VEREDAS S/11,334.74
RELLENO CON MATERIAL PROPIO PARA ESTRUCTURA S/5,330.23
ELIMINACION MATERIAL EXCEDENTE MANUAL
PERFILADO Y COMPACTADO EN VEREDAS S/10,436.82
CONCRETO
MATERIAL GRANULAR e=0.05m S/18,197.83 S/3.32
CONCRETO FC=175 KG/CM2 PARA VEREDAS, INC. BRUÑADO S/149,715.25
ENCOFRADO Y DESENCOFRADO EN VEREDAS S/12,660.71 S/6,809.91
JUNTA DE DILATACION EN VEREDAS S/6,501.08
VARIOS
NIVELACION DE CAJA DE REGISTRO DE AGUA S/11,336.70
NIVELACION DE CAJA DE REGISTRO DESAGUE S/11,829.73
RAMPAS Y MARTILLOS
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/554.09
TRAZO, NIVELACION Y REPLANTEO S/1,367.24
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL EN RAMPAS Y MARTILLOS S/2,434.41
ELIMINACION MATERIAL EXCEDENTE MANUAL S/1,739.31
PERFILADO Y COMPACTADO EN RAMPAS Y MARTILLOS S/2,669.72
CONCRETO
MATERIAL GRANULAR e=0.05m S/4,655.81
CONCRETO FC=175 KG/CM2 EN RAMPAS Y MARTILLOS, INC. BRUÑADO S/55,503.47 S/5.36
ENCOFRADO Y DESENCOFRADO DE RAMPAS Y MARTILLOS S/4,033.65
ACCESO PEATONAL
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/184.35
TRAZO, NIVELACION Y REPLANTEO S/454.88
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL EN ACCESOS S/719.58
ELIMINACION MATERIAL EXCEDENTE MANUAL S/578.93
PERFILADO Y COMPACTADO EN ACCESOS S/888.21
CONCRETO
MATERIAL GRANULAR e=0.05m S/1,548.98
CONCRETO FC=175 KG/CM2 PARA ACCESOS S/9,805.32
CONCRETO FC=210 KG/CM2 PARA ACCESOS S/5,021.83
ENCOFRADO Y DESENCOFRADO EN ACCESOS S/5,322.65
ACERO F'Y=4200 KG/CM2 EN ACCESOS S/3,050.26
DRENAJE
DRENAJE (0.40x0.40)
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/310.03
TRAZO, NIVELACION Y REPLANTEO S/765.02
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL S/8,242.49
RELLENO CON MATERIAL PROPIO PARA ESTRUCTURA S/254.09
ELIMINACION MATERIAL EXCEDENTE MANUAL S/6,538.37
PERFILADO Y COMPACTADO EN DRENAJE S/1,493.79
CONCRETO
CONCRETO FC=175 KG/CM2 EN CUNETAS S/70,116.42
ENCOFRADO Y DESENCOFRADO EN CUNETAS S/42,182.77 S/3.84
JUNTA DE DILATACION EN CUNETAS S/2,715.84
DRENAJE (0.60x0.60)
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/790.84
TRAZO, NIVELACION Y REPLANTEO S/1,951.41
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL S/21,280.85 S/5,322.98
ELIMINACION MATERIAL EXCEDENTE MANUAL S/21,377.24
PERFILADO Y COMPACTADO EN DRENAJE S/1,087.55 S/2,722.84
CONCRETO
SOLADO, CONCRETO F'C=140 KG/CM2 S/35,782.77
CONCRETO FC=210 KG/CM2 EN DRENAJE S/203,889.95
ENCOFRADO Y DESENCOFRADO EN DRENAJE ### S/15,838.36
ACERO F'Y=4200 KG/CM2 EN DRENAJE ### S/10,218.01
JUNTA DE DILATACION EN DRENAJE S/5,265.40
DRENAJE (0.80x0.80)
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/31.35
TRAZO, NIVELACION Y REPLANTEO S/77.37
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL S/1,591.61
RELLENO CON MATERIAL PROPIO PARA ESTRUCTURA S/471.14
ELIMINACION MATERIAL EXCEDENTE MANUAL S/826.36
PERFILADO Y COMPACTADO EN DRENAJE S/151.07
CONCRETO
SOLADO, CONCRETO F'C=140 KG/CM2 S/1,418.68
CONCRETO FC=210 KG/CM2 EN DRENAJE S/12,737.62
ENCOFRADO Y DESENCOFRADO EN DRENAJE S/6,204.97
ACERO F'Y=4200 KG/CM2 EN DRENAJE S/5,753.15
JUNTA DE DILATACION EN DRENAJE S/346.93
SARDINEL Y MURO DE CONFINAMIENTO
OBRAS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL S/258.60
TRAZO, NIVELACION Y REPLANTEO S/638.12
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL S/4,853.60
RELLENO CON MATERIAL PROPIO PARA ESTRUCTURA
ELIMINACION MATERIAL EXCEDENTE MANUAL
PERFILADO Y COMPACTADO EN SARDINEL Y MURO DE CONFINAMIENTO S/1,246.00
CONCRETO
SOLADO, CONCRETO F'C=140 KG/CM2 S/11,701.01
CONCRETO FC=175 KG/CM2 PARA SARDINEL Y MURO DE CONFINAMIENTO
ENCOFRADO Y DESENCOFRADO EN SARDINEL Y MURO DE CONFINAMIENTO S/35,182.57
ACERO F'Y=4200 KG/CM2 EN SARDINEL Y MURO DE CONFINAMIENTO S/31,236.38
JUNTA DE DILATACION EN SARDINEL Y MURO DE CONFINAMIENTO
AREAS VERDES
MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL EN TERRENO NORMAL S/1,584.39
RELLENO CON MATERIAL PROPIO S/2,783.03
MATERIAL DE PRESTAMO PARA AREAS VERDES S/1,034.24
VARIOS
LIMPIEZA FINAL DE OBRA
PLACA RECORDATORIA
S/25,367.47
S/81,882.16
###

S/9,490.00
S/27,373.62

S/7,206.12

S/5,337.63
S/4,532.89

S/2,577.36
S/13,029.68

S/2,610.06

S/1,869.52
S/3,275.66
S/75,410.39
S/7,458.95
S/2,096.23
S/1,589.83

S/4,488.12
S/500.00
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS ADYACENTES AL JR. MARTÍNEZ DE COMPAGÑON DE LA PARTE BAJA DEL BARRIO HUAYCO DE LA CIUDAD DE
TARAPOTO DEL DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTÍN - DEPARTAMENTO DE SAN MARTÍN"
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
MESMETRADO
01 01 METRADO 02 METRADO 03 METRADO 04
01 OBRAS PROVISIONALES 4,218.24
01.01 CARTEL DE OBRA 4.80X3.60 m und 1.00 1,818.24 1,818.24
### 1.00 0.00 0.00 0.00
01.02 ALQUILER DE ALMACEN Y/O DEPOSITO PARA OBRA mes 4.00 600.00 2,400.00
### 4.00 0.00 0.00 0.00
02 OBRAS PRELIMINARES 4,303.20
02.01 MOVILIZACION Y DESMOVILIZACIÓN DE MAQUINARIAS Y EQUIPOS est 1.00 4,303.20 4,303.20
### 1.00 0.00 0.00 0.00
03 SEGURIDAD SALUD Y MEDIO AMBIENTE 146,968.00
03.01 SEGURIDAD Y SALUD 110,636.00
03.01.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE GLB 1.00 52,128.00 52,128.00
### 0.25 0.25 0.25 0.25
03.01.02 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 2,200.00 2,200.00
### 1.00 0.00 0.00 0.00
03.01.03 EQUIPOS DE PROTECCION INDIVIDUAL GLB 1.00 438.00 438.00
### 1.00 0.00 0.00 0.00
03.01.04 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1,870.00 1,870.00
### 1.00 0.00 0.00 0.00
03.01.05 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00 14,000.00 14,000.00
### 0.25 0.25 0.25 0.25
03.01.06 RECURSO PARA RESPUESTA ANTE EMERGENCIA EN SEGURIDAD Y S GLB 1.00 40,000.00 40,000.00
### 0.25 0.25 0.25 0.25
03.02 MITIGACION AMBIENTAL 36,332.00
03.02.01 MONITOREO AMBIENTAL 21,932.00
03.02.01.01 MONITOREO DE CALIDAD DEL AIRE und 8.00 2,000.00 16,000.00
### 2.00 2.00 2.00 2.00
03.02.01.02 MONITOREO DE CALIDAD DE RUIDOS und 8.00 500.00 4,000.00
### 2.00 2.00 2.00 2.00
03.02.01.03 TRATAMIENTO DE RESIDUOS SOLIDOS und 4.00 483.00 1,932.00
### 1.00 1.00 1.00 1.00
03.02.02 CAPACITACION Y EDUCACION AMBIENTAL 14,400.00
03.02.02.01 CHARLA AL PERSONAL DE OBRA und 4.00 1,200.00 4,800.00
### 1.00 1.00 1.00 1.00
03.02.02.02 CHARLA A POBLACION BENEFICIARIA und 4.00 1,200.00 4,800.00
### 1.00 1.00 1.00 1.00
03.02.02.03 SEMINARIO TALLER A PERSONAL TECNICO und 4.00 1,200.00 4,800.00
### 1.00 1.00 1.00 1.00
04 PAVIMENTO FLEXIBLE 873,482.19
04.01 OBRAS PRELIMINARES 13,863.10
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 5,153.57 0.78 4,019.78 0.00 5,153.57 0.00 0.00
04.01.02 TRAZO, NIVELACION Y REPLANTEO m2 5,153.57 1.91 9,843.32 0.00 5,153.57 0.00 0.00
04.02 MOVIMIENTO DE TIERRAS 131,654.33
04.02.01 EXCAVACION MASIVA CON MAQUINARIA EN MATERIAL COMUN m3 5,307.59 7.55 40,072.30 0.00 3,449.93 1,857.66 0.00
04.02.02 RELLENO CON MATERIAL SELECTO DE PRESTAMO m3 71.56 67.44 4,826.01 0.00 0.00 71.56 0.00
04.02.03 DEMOLICION DE PAVIMENTO EXISTENTE m2 984.40 5.24 5,158.26 0.00 295.32 689.08 0.00
04.02.04 CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE m3 6,696.23 10.20 68,301.55 0.00 0.00 6,696.23 0.00
04.02.05 PERFILADO Y COMPACTADO DE SUB-RASANTE m2 5,153.57 2.58 13,296.21 0.00 0.00 4,122.86 1,030.71
04.03 PAVIMENTO 698,803.55
04.03.01 MEJORAMIENTO DE LA SUBRASANTE m3 481.14 88.86 42,754.10 0.00 0.00 0.00 481.14
04.03.02 SUB BASE GRANULAR E= 0.15 M m2 5,153.57 20.39 105,081.29 0.00 0.00 0.00 5,153.57
04.03.03 BASE GRANULAR E=0.15 M m2 5,153.57 22.20 114,409.25 0.00 0.00 0.00 5,153.57
04.03.04 IMPRIMACION m2 5,153.57 8.30 42,774.63 0.00 0.00 0.00 5,153.57
04.03.05 CARPETA ASFALTICA E=0.5M m2 5,153.57 76.41 393,784.28 0.00 0.00 0.00 5,153.57
04.04 SEÑALIZACION VIAL 26,396.56
04.04.01 SEÑALIZACION VERTICAL 5,400.00
04.04.01.01 POSTE DE SEÑAL REGULADORA und 9.00 600.00 5,400.00 0.00 0.00 0.00 9.00
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS ADYACENTES AL JR. MARTÍNEZ DE COMPAGÑON DE LA PARTE BAJA DEL BARRIO HUAYCO DE LA CIUDAD DE
TARAPOTO DEL DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTÍN - DEPARTAMENTO DE SAN MARTÍN"
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
MESMETRADO
01 01 METRADO 02 METRADO 03 METRADO 04
04.04.02 SEÑALIZACION HORIZONTAL 20,996.56
04.04.02.01 PINTADO DE PAVIMENTO (LINEAS DE CARRIL Y BORDE) m 1,812.52 9.57 17,345.82 0.00 0.00 0.00 1,812.52
04.04.02.02 PINTADO DE TRAFICO (SIMBOLOS Y LETRAS) m2 160.12 22.80 3,650.74 0.00 0.00 0.00 160.12
04.05 VARIOS 2,764.65
04.05.01 NIVELACION DE TAPAS DE BUZONES und 7.00 394.95 2,764.65 0.00 0.00 7.00
05 BERMAS DE CONCRETO 183,002.74
05.01 OBRAS PRELIMINARES 3,597.71
05.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,337.44 0.78 1,043.20
### 1,337.44 0.00 0.00 0.00
05.01.02 TRAZO, NIVELACION Y REPLANTEO m2 1,337.44 1.91 2,554.51
### 1,337.44 0.00 0.00 0.00
05.02 MOVIMIENTO DE TIERRAS 26,661.88
05.02.01 EXCAVACION MANUAL EN TERRENO NORMAL EN BERMAS m3 401.25 34.51 13,847.14
### 401.25 0.00 0.00 0.00
05.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 501.56 19.71 9,885.75
### 501.56 0.00 0.00 0.00
05.02.03 PERFILADO Y COMPACTADO EN BERMAS m2 1,337.44 2.19 2,928.99
### 1,337.44 0.00 0.00 0.00
05.03 CONCRETO 152,743.15
05.03.01 MATERIAL GRANULAR e=0.10m m2 133.76 11.22 1,500.79
### 133.76 0.00 0.00 0.00
05.03.02 CONCRETO FC=210 KG/CM2 EN BERMAS m3 267.49 499.65 133,651.38
### 120.37 147.12 0.00 0.00
05.03.03 ENCOFRADO Y DESENCOFRADO EN BERMAS m2 169.22 47.32 8,007.49
### 169.22 0.00 0.00 0.00
05.03.04 JUNTA DE DILATACION EN BERMAS m 871.75 9.72 8,473.41 0.00 871.75 0.00 0.00
05.03.05 CURADO DE CONCRETO m2 1,337.44 0.83 1,110.08 0.00 1,337.45 0.00 0.00
06 VEREDAS, RAMPAS Y MARTILLOS 422,874.38
06.01 VEREDAS DE CONCRETO 322,287.91
06.01.01 OBRAS PRELIMINARES 7,587.69
06.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 2,820.70 0.78 2,200.15 0.00 2,820.71 0.00 0.00
06.01.01.02 TRAZO, NIVELACION Y REPLANTEO m2 2,820.70 1.91 5,387.54 0.00 2,820.70 0.00 0.00
06.01.02 MOVIMIENTO DE TIERRAS 58,451.28
06.01.02.01 DEMOLICION DE ESTRUCTURAS EXISTENTES m3 184.76 98.91 18,274.61 0.00 184.76 0.00 0.00
06.01.02.02 EXCAVACION MANUAL EN TERRENO NORMAL EN VEREDAS m3 499.95 34.51 17,253.27 0.00 499.95 0.00 0.00
06.01.02.03 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 624.94 19.71 12,317.57 0.00 624.94 0.00 0.00
06.01.02.04 PERFILADO Y COMPACTADO EN VEREDAS m2 2,820.70 3.76 10,605.83 0.00 2,820.70 0.00 0.00
06.01.03 CONCRETO 229,621.09
06.01.03.01 MATERIAL GRANULAR e=0.05m m2 2,820.70 6.44 18,165.31 0.00 2,820.70 0.00 0.00
06.01.03.02 CONCRETO FC=175 KG/CM2 PARA VEREDAS, INC. BRUÑADO m3 423.08 422.13 178,594.76 0.00 359.62 63.46 0.00
06.01.03.03 ENCOFRADO Y DESENCOFRADO EN VEREDAS m2 544.84 37.42 20,387.91 0.00 544.84 0.00 0.00
06.01.03.04 JUNTA DE DILATACION EN VEREDAS m 1,042.38 9.72 10,131.93 0.00 0.00 1,042.38 0.00
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS ADYACENTES AL JR. MARTÍNEZ DE COMPAGÑON DE LA PARTE BAJA DEL BARRIO HUAYCO DE LA CIUDAD DE
TARAPOTO DEL DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTÍN - DEPARTAMENTO DE SAN MARTÍN"
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
MESMETRADO
01 01 METRADO 02 METRADO 03 METRADO 04
06.01.03.05 CURADO DE CONCRETO m2 2,820.70 0.83 2,341.18 0.00 0.00 2,820.70 0.00
06.01.04 VARIOS 26,627.85
06.01.04.01 NIVELACION DE CAJA DE REGISTRO DE AGUA und 71.00 180.63 12,824.73 0.00 63.90 7.10 0.00
06.01.04.02 NIVELACION DE CAJA DE REGISTRO DESAGUE und 72.00 191.71 13,803.12 0.00 64.80 7.20 0.00
06.02 MARTILLOS Y RAMPAS 100,586.47
06.02.01 OBRAS PRELIMINARES 2,597.57
06.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 965.64 0.78 753.20 0.00 965.64 0.00 0.00
06.02.01.02 TRAZO, NIVELACION Y REPLANTEO m2 965.64 1.91 1,844.37 0.00 965.64 0.00 0.00
06.02.02 MOVIMIENTO DE TIERRAS 9,343.58
06.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL EN RAMPAS Y MARTIL m3 96.58 34.51 3,332.98 0.00 96.58 0.00 0.00
06.02.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 120.74 19.71 2,379.79 0.00 120.74 0.00 0.00
06.02.02.03 PERFILADO Y COMPACTADO EN RAMPAS Y MARTILLOS m2 965.64 3.76 3,630.81 0.00 965.64 0.00 0.00
06.02.03 CONCRETO 88,645.32
06.02.03.01 MATERIAL GRANULAR e=0.05m m2 965.64 6.44 6,218.72 0.00 965.64 0.00 0.00
06.02.03.02 CONCRETO FC=175 KG/CM2 EN RAMPAS Y MARTILLOS, INC. BRUÑA m3 183.51 422.13 77,465.08 0.00 183.51 0.00 0.00
06.02.03.03 ENCOFRADO Y DESENCOFRADO DE RAMPAS Y MARTILLOS m2 132.59 37.42 4,961.52 0.00 132.59 0.00 0.00
07 DRENAJE 843,196.83
07.01 CUNETAS (0.40x0.40) 714,989.35
07.01.01 OBRAS PRELIMINARES 2,725.56
07.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 1,013.22 0.78 790.31
### 1,013.22 0.00 0.00 0.00
07.01.01.02 TRAZO, NIVELACION Y REPLANTEO m2 1,013.22 1.91 1,935.25
### 1,013.22 0.00 0.00 0.00
07.01.02 MOVIMIENTO DE TIERRAS 45,838.99
07.01.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 759.92 30.67 23,306.75
### 759.92 0.00 0.00 0.00
07.01.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 949.90 19.71 18,722.53
### 949.90 0.00 0.00 0.00
07.01.02.03 PERFILADO Y COMPACTADO EN DRENAJE m2 1,013.22 3.76 3,809.71
### 1,013.22 0.00 0.00 0.00
07.01.03 CONCRETO 666,424.80
07.01.03.01 CONCRETO SIMPLE 281,547.96
07.01.03.01.01 SOLADO, CONCRETO F'C=140 KG/CM2 m2 1,027.06 274.13 281,547.96
### 1,027.06 0.00 0.00 0.00
07.01.03.02 CONCRETO ARMADO 384,876.84
07.01.03.02.01 CONCRETO F'C=175 KG/CM2 EN CUNETAS m3 363.56 422.13 153,469.58 0.00 363.56 0.00 0.00
07.01.03.02.02 ENCOFRADO Y DESENCOFRADO EN CUNETAS m2 3,472.37 37.42 129,936.09
### 2,777.90 694.47 0.00 0.00
07.01.03.02.03 ACERO F'Y=4200 KG/CM2 EN DRENAJE kg ### 4.68 92,284.36
### 3,943.78 15,775.10 0.00 0.00
07.01.03.02.04 JUNTA DE DILATACION EN CUNETAS m 1,000.70 8.34 8,345.84 0.00 1,000.70 0.00 0.00
07.01.03.02.05 CURADO DE CONCRETO m2 1,013.22 0.83 840.97 0.00 1,013.22 0.00 0.00
07.02 ALCANTARILLAS (0.60x0.60) 128,207.48
07.02.01 OBRAS PRELIMINARES 302.88
07.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 145.88 0.78 113.79
### 145.88 0.00 0.00 0.00
07.02.01.02 TRAZO, NIVELACION Y REPLANTEO m2 99.00 1.91 189.09
### 99.00 0.00 0.00 0.00
CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA
PROYECTO: “MEJORAMIENTO DE VÍAS ADYACENTES AL JR. MARTÍNEZ DE COMPAGÑON DE LA PARTE BAJA DEL BARRIO HUAYCO DE LA CIUDAD DE
TARAPOTO DEL DISTRITO DE TARAPOTO - PROVINCIA DE SAN MARTÍN - DEPARTAMENTO DE SAN MARTÍN"
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
MESMETRADO
01 01 METRADO 02 METRADO 03 METRADO 04
07.02.02 MOVIMIENTO DE TIERRAS 9,019.91
07.02.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 153.17 30.67 4,697.72
### 153.17 0.00 0.00 0.00
07.02.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 191.46 19.71 3,773.68
### 191.46 0.00 0.00 0.00
07.02.02.03 PERFILADO Y COMPACTADO EN DRENAJE m2 145.88 3.76 548.51
### 145.88 0.00 0.00 0.00
07.02.03 CONCRETO 118,884.69
07.02.03.01 SOLADO, CONCRETO F'C=140 KG/CM2 m2 145.88 274.13 39,990.08
### 145.88 0.00 0.00 0.00
07.02.03.02 CONCRETO FC=210 KG/CM2 EN DRENAJE m3 85.73 472.07 40,470.56
### 85.73 0.00 0.00 0.00
07.02.03.03 ENCOFRADO Y DESENCOFRADO EN DRENAJE m2 540.44 37.42 20,223.26
### 540.44 0.00 0.00 0.00
07.02.03.04 ACERO F'Y=4200 KG/CM2 EN DRENAJE kg 3,837.71 4.68 17,960.48
### 3,837.71 0.00 0.00 0.00
07.02.03.05 CURADO DE CONCRETO m2 289.53 0.83 240.31
### 289.53 0.00 0.00 0.00
08 SARDINELES 173,440.56
08.01 OBRAS PRELIMINARES 811.20
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 301.56 0.78 235.22 0.00 301.56 0.00 0.00
08.01.02 TRAZO, NIVELACION Y REPLANTEO m2 301.56 1.91 575.98 0.00 301.56 0.00 0.00
08.02 MOVIMIENTO DE TIERRAS 7,805.16
08.02.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 120.62 30.67 3,699.42 0.00 120.62 0.00 0.00
08.02.02 ELIMINACION MATERIAL EXCEDENTE MANUAL m3 150.78 19.71 2,971.87 0.00 150.78 0.00 0.00
08.02.03 PERFILADO Y COMPACTADO EN SARDINEL m2 301.56 3.76 1,133.87 0.00 301.56 0.00 0.00
08.03 CONCRETO 164,824.20
08.03.01 SOLADO, CONCRETO F'C=140 KG/CM2 m2 301.56 274.13 82,666.64 0.00 301.56 0.00 0.00
08.03.02 CONCRETO F'C=175KG/CM2 PARA SARDINEL m3 154.53 422.13 65,231.75 0.00 154.53 0.00 0.00
08.03.03 ENCOFRADO Y DESENCOFRADO EN SARDINEL m2 452.32 37.42 16,925.81 0.00 452.32 0.00 0.00
09 AREAS VERDES 23,016.93
09.01 MOVIMIENTO DE TIERRAS 23,016.93
09.01.01 EXCAVACION MANUAL EN TERRENO NORMAL m3 124.71 30.67 3,824.86 0.00 124.71 0.00 0.00
09.01.02 MATERIAL DE PRESTAMO PARA AREAS VERDES m3 155.89 99.35 15,487.67 0.00 155.89 0.00 0.00
09.01.03 SEMBRADO DE PLANTONES INC. SUMINISTRO Y TAPADO DE HOYOS und 168.00 22.05 3,704.40 0.00 168.00 0.00 0.00
10 VARIOS 11,533.21
10.01 LIMPIEZA FINAL DE OBRA m2 ### 0.28 3,247.61 0.00 0.00 0.00 11,598.61
10.02 INSTALACION DE TACHO DE BASURA und 30.00 259.52 7,785.60 0.00 0.00 0.00 30.00
10.03 PLACA RECORDATORIA und 1.00 500.00 500.00 0.00 0.00 0.00 1.00
COSTO DIRECTO 2,686,036.28
###
GASTOS GENERALES 10%CD 268,603.63
###
UTILIDAD 10%CD 214,882.90
###
SUB TOTAL 3,169,522.81
###
IGV 18% 570,514.11
###
COSTO DE OBRA 3,740,036.92
###
PORCENTAJE 100%
###
PORCENTAJE ACUMULADO ###