OE. 3 ARQUITECTURA
OE. 3.01 REVOQUES Y REVESTIMIENTOS
OE. 03.01.01 TARRAJEO RAYADO PRIMARIO
OE. 03.01.01.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO - ARENA m2 63.36
PRIMER PISO
SS.HH. (Social) 1.00 4.41 1.50 6.62
SEGUNDO PISO
SS.HH. (Completo 1) 1.00 4.18 1.50 6.27
1.00 2.78 2.10 5.84
menos ventana -1.00 1.25 0.18 -0.23
SEGUNDO PISO
Caja de Escaleras 1.00 2.75 2.43 6.67
1.00 6.62 2.33 15.39
menos puerta -1.00 1.00 2.10 -2.10
JARDIN DE DORMITORIO
Entre Eje 2 - 3 1.00 4.78 2.60 12.43
menos puerta -1.00 0.80 2.10 -1.68
menos ventana -1.00 1.50 1.60 -2.40
SEGUNDO PISO
Entre Eje 1 - 2 1.00 3.68 2.63 9.68
menos ventana -1.00 2.45 1.20 -2.94
Pasadizo
Columna 1 1.00 0.45 2.50 1.13
Columna 2 1.00 0.10 2.50 0.25
Sala - Comedor
Columna 1 1.00 1.70 2.50 4.25
Columna 2 1.00 1.10 2.50 2.75
Columna 3 1.00 0.45 2.50 1.13
Cocina
Columna 2 1.00 0.10 2.50 0.25
Patio de Servicio
Columna 2 1.00 0.20 2.50 0.50
Terraza
Columna 2 1.00 0.25 2.50 0.63
Columna 3 1.00 0.10 2.50 0.25
Dormitorio 1
Columna 2 1.00 0.50 2.50 1.25
SS.HH. (Completo)
Columna 2 1.00 0.35 2.50 0.88
Columna 3 1.00 0.10 2.50 0.25
Dormitorio 2
Columna 2 1.00 0.25 2.50 0.63
Columna 3 1.00 0.25 2.50 0.63
SEGUNDO PISO
Caja de Escaleras
Columna 4 1.00 0.35 2.60 0.91
1.00 0.50 2.50 1.25
Balcón
Columna 4 1.00 0.25 2.60 0.65
1.00 0.60 2.50 1.50
Pasadizo
Columna 1 1.00 0.90 2.60 2.34
Columna 2 1.00 0.10 2.60 0.26
Estar
Columna 1 1.00 0.60 2.50 1.50
Columna 2 1.00 0.20 2.50 0.50
Columna 3 1.00 0.10 2.50 0.25
Estudio
Columna 2 1.00 0.40 2.50 1.00
Dormitorio 1
Columna 1 1.00 0.33 2.50 0.83
Columna 2 1.00 0.10 2.50 0.25
Columna 3 1.00 0.20 2.50 0.50
Dormitorio 2
Columna 2 1.00 0.65 2.50 1.63
SS.HH. 2
Columna 2 1.00 0.28 2.50 0.70
Columna 3 1.00 0.10 2.50 0.25
Dormitorio 3
Columna 2 1.00 0.25 2.50 0.63
Columna 3 1.00 0.75 2.50 1.88
Caja de Escaleras
Viga Principal 101 1.00 2.75 0.30 0.83
Pasadizo
Viga Principal 102 1.00 5.78 0.20 1.16
Sala - Comedor
Viga Principal 102 1.00 3.75 0.45 1.69
1.00 3.63 0.20 0.73
Viga Principal 103 1.00 7.38 0.10 0.74
Cocina
Viga Principal 101 1.00 3.75 0.10 0.38
Patio de Servicio
Viga Principal 101 1.00 2.95 0.40 1.18
SS.HH. (Social)
Viga Secundaria 103A 1.00 1.00 0.10 0.10
Depósito
Viga Secundaria 104A 1.00 0.84 0.10 0.08
Dormitorio 1
Viga Principal 101 1.00 3.43 0.10 0.34
SS.HH. (Completo)
Viga Principal 102 1.00 2.60 0.20 0.52
SEGUNDO PISO
Balcón
Viga Secundaria 201A 1.00 2.39 0.65 1.55
1.00 1.00 0.45 0.45
Caja de Escaleras
Viga Principal 201 1.00 2.75 0.30 0.83
Pasadizo
Viga Principal 202 1.00 3.75 0.10 0.38
1.00 5.78 0.20 1.16
1.00 2.23 0.45 1.00
Estar
Viga Principal 203 1.00 3.63 0.20 0.73
Estudio
Viga Principal 201 1.00 3.75 0.20 0.75
Dormitorio 1
Viga Principal 202 1.00 3.75 0.20 0.75
Viga Principal 203 1.00 3.75 0.20 0.75
SS.HH. 1
Viga Secundaria 203A 1.00 0.84 0.10 0.08
Viga Secundaria 204A 1.00 0.84 0.10 0.08
Dormitorio 2
Viga Principal 201 1.00 3.43 0.20 0.69
SS.HH. 2
Viga Principal 202 1.00 2.60 0.20 0.52
Dormitorio 3
Viga Principal 202 1.00 3.30 0.10 0.33
Viga Principal 203 1.00 3.45 0.20 0.69
Pasadizo
Puerta 3 1.00 5.20 5.20
Puerta 7 1.00 6.60 6.60
Cocina
Puerta 4 1.00 5.00 5.00
Puerta 5 1.00 4.00 4.00
Ventana 3 1.00 3.40 3.40
SS.HH. (Social)
Puerta 5 1.00 4.90 4.90
Ventana 4 1.00 3.50 3.50
Depósito
Puerta 5 1.00 4.90 4.90
Ventana 5 1.00 4.00 4.00
Dormitorio 1
Puerta 4 1.00 3.90 3.90
Puerta 6 1.00 5.10 5.10
Ventana 6 1.00 4.60 4.60
SS.HH. (Completo)
Puerta 5 1.00 4.90 4.90
Ventana 4 1.00 3.50 3.50
Dormitorio 2
Puerta 6 1.00 5.10 5.10
Ventana 1.00 8.06 8.06
SEGUNDO PISO
Pasadizo
Puerta 3 1.00 5.20 5.20
Puerta 4 1.00 5.00 5.00
Estudio
Puerta 6 1.00 5.10 5.10
Ventana 9 1.00 6.48 6.48
Dormitorio 1
Puerta 6 1.00 5.10 5.10
Ventana 11 1.00 7.20 7.20
SS.HH. 1
Puerta 5 1.00 4.90 4.90
Ventana 4 1.00 3.50 3.50
Dormitorio 2
Puerta 6 1.00 5.10 5.10
Ventana 8 1.00 7.98 7.98
SS.HH. 2
Puerta 5 1.00 4.90 4.90
Ventana 7 1.00 3.80 3.80
Dormitorio 3
Puerta 6 1.00 5.10 5.10
Ventana 12 1.00 8.26 8.26
Tramo del Primer Piso al Segundo Piso 1.00 2.53 según CAD 2.53
1.00 1.13 según CAD 1.13
1.00 0.97 según CAD 0.97
1.00 1.20 según CAD 1.20
1.00 1.22 según CAD 1.22
1.00 1.56 según CAD 1.56
1.00 1.10 según CAD 1.10
1.00 1.35 según CAD 1.35
OE. 03.01.10.02 ACABADO CON GRANITO PULIDO DE REVESTIMIENTO LATERAL DE GRADAS m2 0.64
Tramo del Primer Piso al Segundo Piso 1.00 0.31 según CAD 0.31
3.00 0.11 según CAD 0.33
OE. 03.01.11 DESCANSOS
OE. 03.01.11.01 ACABADO DE DESCANSO CON GRANITO PULIDO m2 5.17
1.00 1.13 según CAD 1.13
1.00 1.13 según CAD 1.13
1.00 1.56 según CAD 1.56
1.00 1.35 según CAD 1.35
SEGUNDO PISO
Pasadizo 1.00 11.81 según CAD 11.81
Balcón 1.00 1.46 según CAD 1.46
Estar 1.00 13.01 según CAD 13.01
Estudio 1.00 10.01 según CAD 10.01
Dormitorio 1 1.00 12.84 según CAD 12.84
SS.HH. 1 1.00 2.49 según CAD 2.49
Dormitorio 2 1.00 8.91 según CAD 8.91
SS.HH. 2 1.00 3.60 según CAD 3.60
Dormitorio 3 1.00 11.70 según CAD 11.70