2.1 Excavacion Material Comun M3 151,263.16 78.60 11,889,284.38 32,226.32 2,532,988.75 570.88 44,871.17 32,797.20 2,577,859.92 21.68 78.6
2.2 Excavacion Material Duro M2 100,842.10 175.00 17,647,367.50 12,486.37 2,185,114.75 730.15 127,776.25 13,216.52 2,312,891.00 13.11 175
2.3 Relleno M3 41,670.79 51.16 2,131,877.62 26,821.70 1,372,198.17 905.96 46,348.91 27,727.66 1,418,547.09 66.54 51.16
2.4 Acarreo Material Sobrante M3 210,434.47 27.00 5,681,730.69 5,287.00 142,749.00 0.00 5,287.00 142,749.00 2.51 27
2.5 Conformacion de Sub-Rasante M2 117,202.85 29.40 3,445,763.79 4,018.07 118,131.26 1,025.65 30,154.11 5,043.72 148,285.37 4.30 29.4
2.6 Sub-Base M3 23,440.57 346.56 8,123,563.94 979.52 339,462.45 256.41 88,861.45 1,235.93 428,323.90 5.27 346.56
2.7 Pavimento de Concreto Hidraulico
2.6.1 Pavimento de Concreto Hidraulico e=18cm en bulevard M2 26,437.60 760.50 20,105,794.80 5.85 4,448.93 0.00 5.85 4,448.93 0.02 760.5
2.6.2 Pavimento de Concreto Hidraulico e=15cm M2 67,324.68 633.75 42,667,015.95 3,720.54 2,357,892.23 1,160.90 735,720.38 4,881.44 3,093,612.60 7.25 633.75
2.8 Bordillos ML 17,152.20 271.08 4,649,618.38 777.64 210,802.65 450.18 122,034.79 1,227.82 332,837.45 7.16 271.08
2.9 Juntas ML 29,412.69 36.60 1,076,504.45 986.18 36,094.19 348.27 12,746.68 1,334.45 48,840.87 4.54 36.6
2.10. Acero de Juntas Kg 39,318.88 36.27 1,426,095.78 1,063.69 38,580.04 290.23 10,526.64 1,353.92 49,106.68 3.44 36.27
2.11 Area Verde M2 20,493.42 100.00 2,049,342.00 161.64 16,164.00 0.00 161.64 16,164.00 0.79 100
2.12 Aceras M2 14,472.72 360.00 5,210,179.20 439.72 158,299.20 0.00 439.72 158,299.20 3.04 360
Sub-Total 126,104,138.47 9,512,925.61 1,219,040.38 10,731,965.99
3 LOTES
3.1 Corte Material Comun M3 275,727.87 78.60 21,672,210.58 36,484.39 2,867,673.05 3,151.98 247,745.63 39,636.37 3,115,418.68 14.38 78.6
3.2 Corte Material Duro M3 183,818.52 175.00 32,168,241.00 20,436.34 3,576,359.50 1,291.78 226,061.50 21,728.12 3,802,421.00 11.82 175
3.3 Relleno M3 175,711.00 51.16 8,989,374.76 42,228.28 2,160,398.80 3,012.96 154,143.03 45,241.24 2,314,541.84 25.75 51.16
3.4 Acarreo Material Sobrante M3 384,623.00 27.00 10,384,821.00 13,438.96 362,851.92 0.00 13,438.96 362,851.92 3.49 27
3.5 Muros
3.4.1 Muros Mamposteria de Piedra M3 34,271.73 998.90 34,234,031.10 1,372.37 1,370,860.39 119.68 119,548.35 1,492.05 1,490,408.75 4.35 998.9
3.4.2 Excavacion M3 17,166.72 162.00 2,781,008.64 333.69 54,057.78 43.73 7,084.26 377.42 61,142.04 2.20 162
3.4.3 Relleno M3 1,186.50 58.74 69,695.01 605.65 35,575.88 0.00 605.65 35,575.88 51.05 58.74
3.4.4 Acarreo Material Sobrante M3 15,980.22 27.00 431,465.94 500.53 13,514.31 0.00 500.53 13,514.31 3.13 27
Sub-Total 110,730,848.03 10,441,291.64 754,582.77 11,195,874.42
4 ALCANTARILLADO SANITARIO
4.1 Tuberia PVC de 8" de diametro Mts 7,322.12 551.62 4,039,027.83 890.93 491,454.81 0.00 890.93 491,454.81 12.17 551.62
4.2 Excavacion Material Comun M3 10,287.27 162.00 1,666,537.74 917.27 148,597.74 0.00 917.27 148,597.74 8.92 162
4.3 Excavacion en Roca M2 2,571.82 1,101.24 2,832,191.06 353.64 389,442.51 0.00 353.64 389,442.51 13.75 1010.24
4.4 Relleno Material Comun M3 8,967.11 58.74 526,728.04 856.92 50,335.48 0.00 856.92 50,335.48 9.56 58.74
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: OBRAS DE URBANIZACION II ETAPA
ESTIMACION DE PAGO No.21 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL % 1
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
4.5 Relleno Material Selecto M3 2,925.55 247.55 724,219.90 277.48 68,690.17 0.00 277.48 68,690.17 9.48 247.55
4.6 Acarreo Material Sobrante M3 598.23 60.01 35,899.78 343.85 20,634.44 0.00 343.85 20,634.44 57.48 60.01
4.7 Pozos con altura comprendida entre 1.00 a 1.50mts UN 45.00 7,236.39 325,637.55 1.00 7,236.39 0.00 1.00 7,236.39 2.22 7236.39
4.8 Pozos con altura comprendida entre 1.50 a 2.00mts UN 68.00 9,648.52 656,099.36 15.00 144,727.80 0.00 15.00 144,727.80 22.06 9648.52
4.9 Pozos con altura comprendida entre 2.00 a 2.50mts UN 6.00 12,060.65 72,363.90 0.00 0.00 0.00 0.00 0.00 0.00 12060.65
4.10. Pozos con altura comprendida entre 2.50 a 3.00mts UN 10.00 14,472.78 144,727.80 0.00 0.00 0.00 0.00 0.00 0.00 14472.78
4.11 Pozos con altura comprendida entre 3.00 a 3.50mts UN 3.00 16,884.91 50,654.73 0.00 0.00 0.00 0.00 0.00 0.00 16884.91
Sub-Total 11,074,087.70 1,321,119.34 0.00 1,321,119.34
6 ALCANTARILLADO PLUVIAL
6.1 Tuberia PVC de 18" de diametro Mts 1,572.71 1,388.22 2,183,267.48 191.70 266,121.77 0.00 191.70 266,121.77 12.19 1388.22
6.2 Tuberia PVC de 24" de diametro Mts 758.35 2,146.39 1,627,714.86 49.00 105,173.11 60.00 128,783.40 109.00 233,956.51 14.37 2146.39
6.3 Tuberia PVC de 36" de diametro Mts 233.19 4,169.93 972,385.98 109.00 454,522.37 0.00 109.00 454,522.37 46.74 4169.93
6.4 Tuberia PVC de 42" de diametro Mts 37.65 7,939.32 298,915.40 50.23 398,792.04 0.00 50.23 398,792.04 133.41 7939.32
6.5 Tuberia PVC de 54" de diametro Mts 15.00 8,465.31 126,979.65 18.00 152,375.58 0.00 18.00 152,375.58 120.00 8465.31
6.6 Excavacion Comun M3 9,121.39 162.00 1,477,665.18 1,760.68 285,230.16 5.15 834.30 1,765.83 286,064.46 19.36 162
6.7 Excavacion en Roca M3 2,280.35 1,101.24 2,511,212.63 215.45 237,262.16 46.33 51,020.45 261.78 288,282.61 11.48 1101.24
6.8 Relleno Material Comun M3 8,115.47 58.74 476,702.71 1,060.35 62,284.96 105.30 6,185.32 1,165.65 68,470.28 14.36 58.74
6.9 Relleno Material Selecto M3 1,876.63 247.55 464,559.76 358.75 88,808.56 39.60 9,802.98 398.35 98,611.54 21.23 247.55
6.1 Acarreo Material Sobrante M3 751.29 60.01 45,084.91 754.59 45,282.95 55.38 3,323.35 809.97 48,606.30 107.81 60.01
6.11 Pozos con altura comprendida entre 2.00 a 2.50 mts Und 8.00 19,000.16 152,001.28 3.00 57,000.48 0.00 3.00 57,000.48 37.50 19000.16
6.12 Pozos con altura comprendida entre 2.50 a 3.00 mts Und 6.00 21,161.66 126,969.96 2.00 42,323.32 0.00 2.00 42,323.32 33.33 21161.66
6.13 Pozos con altura comprendida entre 3.00 a 3.50 mts Und 7.00 23,323.16 163,262.12 3.00 69,969.48 0.00 3.00 69,969.48 42.86 23323.16
6.14 Pozos con altura comprendida entre 3.50 a 4.00 mts Und 15.00 25,484.66 382,269.90 1.00 25,484.66 0.00 1.00 25,484.66 6.67 25484.66
6.15 Pozos con altura comprendida entre 4.00 a 4.50 mts Und 6.00 27,646.16 165,876.96 1.00 27,646.16 0.00 1.00 27,646.16 16.67 27646.16
6.16 Pozos con altura comprendida entre 4.50 a 5.00 mts Und 4.00 29,807.66 119,230.64 0.00 0.00 0.00 0.00 0.00 0.00 29807.66
6.17 Pozos con altura comprendida entre 5.00 a 5.50 mts Und 4.00 31,969.16 127,876.64 0.00 0.00 0.00 0.00 0.00 0.00 31969.16
6.18 Pozos con altura comprendida entre 5.50 a 6.00 mts Und 5.00 34,130.66 170,653.30 0.00 0.00 0.00 0.00 0.00 0.00 34130.66
6.19 Pozos con altura comprendida entre 6.00 a 6.50 mts Und 6.00 36,292.16 217,752.96 0.00 0.00 0.00 0.00 0.00 0.00 36292.16
6.2 Pozos con altura comprendida entre 6.50 a 7.00 mts Und 4.00 38,453.66 153,814.64 0.00 0.00 0.00 0.00 0.00 0.00 38453.66
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: OBRAS DE URBANIZACION II ETAPA
ESTIMACION DE PAGO No.21 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL % 1
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
Sub-Total 11,964,196.95 2,318,277.76 199,949.81 2,518,227.57
7 TRAGANTES
7.1 Tuberia PVC de 15" de diametro Mts 520.42 768.99 400,197.78 51.40 39,526.09 0.00 51.40 39,526.09 9.88 768.99
7.2 Tuberia PVC de 18" de diametro Mts 328.74 1,028.31 338,046.63 0.00 0.00 0.00 0.00 0.00 0.00 1028.31
7.3 Tuberia PVC de 24" de diametro Mts 135.61 1,589.92 215,609.05 0.00 0.00 0.00 0.00 0.00 0.00 1589.92
7.4 Excavacion Comun M3 2,680.08 162.00 434,172.96 57.23 9,271.26 0.00 57.23 9,271.26 2.14 162
7.5 Excavacion en Roca M3 670.20 1,101.24 738,051.05 3.01 3,314.73 0.00 3.01 3,314.73 0.45 1101.24
7.6 Relleno Material Comun M3 2,227.69 58.74 130,854.51 18.89 1,109.60 0.00 18.89 1,109.60 0.85 58.74
7.7 Relleno Material Selecto M3 607.16 247.55 150,302.46 26.91 6,661.57 0.00 26.91 6,661.57 4.43 247.55
7.8 Acarreo Material Sobrante M3 1,123.32 60.01 67,410.43 36.14 2,168.76 0.00 36.14 2,168.76 3.22 60.01
7.9 Tragantes UND 93.00 11,702.01 1,088,286.93 5.00 58,510.05 0.00 5.00 58,510.05 5.38 11702.01
Sub-Total 3,562,931.80 120,562.06 0.00 120,562.06
8 AGUA POTABLE
8.1 Tuberia PVC de 2" de diametro Mts 8,784.04 94.26 827,983.61 564.90 53,247.47 0.00 564.90 53,247.47 6.43 94.26
8.2 Tuberia PVC de 3" de diametro Mts 4,203.99 145.84 613,109.90 0.00 0.00 0.00 0.00 0.00 0.00 145.84
8.3 Tuberia PVC de 4" de diametro Mts 3,734.22 191.52 715,177.81 216.60 41,483.23 0.00 216.60 41,483.23 5.80 191.52
8.4 Tuberia PVC de 6" de diametro Mts 1,104.50 416.08 459,560.36 0.00 0.00 0.00 0.00 0.00 0.00 416.08
8.5 Tuberia PVC de 8" de diametro Mts 868.65 678.81 589,648.31 0.00 0.00 0.00 0.00 0.00 0.00 678.81
8.6 Tuberia PVC de 10" de diametro Mts 15.00 1,059.39 15,890.85 0.00 0.00 0.00 0.00 0.00 0.00 1059.39
8.7 Tanque y Accesorios UND 1.00 2,225,000.00 2,225,000.00 0.00 0.00 0.00 0.00 0.00 0.00 2225000
8.8 Excavacion M3 5,086.10 162.00 823,948.20 269.00 43,578.00 0.00 269.00 43,578.00 5.29 162
8.9 Relleno Material Comun M3 3,297.93 58.74 193,720.41 162.41 9,539.96 0.00 162.41 9,539.96 4.92 58.74
8.10. Relleno Material Selecto M3 1,741.93 247.55 431,214.77 111.57 27,619.15 0.00 111.57 27,619.15 6.40 247.55
8.11 Acarreo Material Sobrante M3 1,788.17 60.01 107,308.08 106.62 6,398.27 0.00 106.62 6,398.27 5.96 60.01
8.12 Acometidas UND 1,115.00 534.46 595,922.90 52.00 27,791.92 0.00 52.00 27,791.92 4.66 534.46
8.13 Cajas para Valvulas UND 54.00 1,350.24 72,912.96 6.00 8,101.44 0.00 6.00 8,101.44 11.11 1350.24
8.14 Concreto Anclajes M3 18.00 3,150.56 56,710.08 0.15 472.58 0.00 0.15 472.58 0.83 3150.56
Sub-Total 7,728,108.24 218,232.03 0.00 218,232.03
9 ACCESORIOS AGUA POTABLE
9.1 Tee PVC 8" UN 2.00 1,771.60 3,543.20 0.00 0.00 0.00 0.00 0.00 0.00 1771.6
9.2 Tee PVC 6" UN 4.00 873.18 3,492.72 0.00 0.00 0.00 0.00 0.00 0.00 873.18
9.3 Tee PVC 4" UN 51.00 370.18 18,879.18 5.00 1,850.90 0.00 5.00 1,850.90 9.80 370.18
9.4 Tee PVC 3" UN 12.00 201.89 2,422.68 0.00 0.00 0.00 0.00 0.00 0.00 201.89
9.5 Tee PVC 2" UN 10.00 84.85 848.50 0.00 0.00 0.00 0.00 0.00 0.00 84.85
9.6 Reductor PVC de 8" a 6" UN 1.00 886.11 886.11 0.00 0.00 0.00 0.00 0.00 0.00 886.11
9.7 Reductor PVC de 6" a 4" UN 5.00 428.88 2,144.40 0.00 0.00 0.00 0.00 0.00 0.00 428.88
9.8 Reductor PVC de 4" a 2" UN 31.00 113.04 3,504.24 3.00 339.12 0.00 3.00 339.12 9.68 113.04
9.9 Reductor PVC de 8" a 4" UN 1.00 873.25 873.25 0.00 0.00 0.00 0.00 0.00 0.00 873.25
9.10. Reductor PVC de 4" a 3" UN 10.00 119.58 1,195.80 0.00 0.00 0.00 0.00 0.00 0.00 119.58
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: OBRAS DE URBANIZACION II ETAPA
ESTIMACION DE PAGO No.21 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL % 1
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
9.11 Reductor PVC de 3" a 2" UN 19.00 86.63 1,645.97 0.00 0.00 0.00 0.00 0.00 0.00 86.63
9.12 Reductor PVC de 6" a 2" UN 2.00 415.38 830.76 0.00 0.00 0.00 0.00 0.00 0.00 415.38
9.13 Adaptador Hembra PVC 8" UN 4.00 756.08 3,024.32 0.00 0.00 0.00 0.00 0.00 0.00 756.08
9.14 Adaptador Hembra PVC 6" UN 6.00 522.80 3,136.80 0.00 0.00 0.00 0.00 0.00 0.00 522.8
9.15 Adaptador Hembra PVC 4" UN 54.00 149.46 8,070.84 4.00 597.84 0.00 4.00 597.84 7.41 149.46
9.16 Adaptador Hembra PVC 3" UN 18.00 124.92 2,248.56 0.00 0.00 0.00 0.00 0.00 0.00 124.92
9.17 Adaptador Hembra PVC 2" UN 35.00 36.69 1,284.15 6.00 220.14 0.00 6.00 220.14 17.14 36.69
9.18 Bridas de 8" Par 3.00 12,393.00 37,179.00 0.00 0.00 0.00 0.00 0.00 0.00 12393
9.19 Union Universal HG de 6" UN 6.00 5,765.56 34,593.36 0.00 0.00 0.00 0.00 0.00 0.00 5765.56
9.20. Union Universal HG de 4" UN 47.00 1,404.00 65,988.00 2.00 2,808.00 0.00 2.00 2,808.00 4.26 1404
9.21 Union Universal HG de 3" UN 15.00 864.00 12,960.00 0.00 0.00 0.00 0.00 0.00 0.00 864
9.22 Union Universal HG de 2" UN 31.00 330.75 10,253.25 3.00 992.25 0.00 3.00 992.25 9.68 330.75
9.23 Codo de 90° PVC de 8" UN 1.00 756.08 756.08 0.00 0.00 0.00 0.00 0.00 0.00 756.08
9.24 Codo de 90° PVC de 6" UN 3.00 522.80 1,568.40 0.00 0.00 0.00 0.00 0.00 0.00 522.8
9.25 Codo de 90° PVC de 4" UN 10.00 149.46 1,494.60 1.00 149.46 0.00 1.00 149.46 10.00 149.46
9.26 Codo de 90° PVC de 3" UN 8.00 124.92 999.36 0.00 0.00 0.00 0.00 0.00 0.00 124.92
9.27 Codo de 90° PVC de 2" UN 20.00 36.69 733.80 0.00 0.00 0.00 0.00 0.00 0.00 36.69
9.28 Niples HG 8" x 12" UN 7.00 2,694.60 18,862.20 0.00 0.00 0.00 0.00 0.00 0.00 2694.6
9.29 Niples HG 6" x 12" UN 8.00 1,784.70 14,277.60 0.00 0.00 0.00 0.00 0.00 0.00 1784.7
9.30. Niples HG 4" x 8" UN 76.00 384.75 29,241.00 0.00 0.00 0.00 0.00 0.00 0.00 384.75
9.31 Niples HG 3" x 6" UN 39.00 222.75 8,687.25 0.00 0.00 0.00 0.00 0.00 0.00 222.75
9.32 Niples HG 2" x 4" UN 92.00 132.30 12,171.60 0.00 0.00 0.00 0.00 0.00 0.00 132.3
9.33 Valvula de Compuerta de 8" UN 2.00 18,084.60 36,169.20 0.00 0.00 0.00 0.00 0.00 0.00 18084.6
9.34 Valvula de Compuerta de 6" UN 3.00 19,818.60 59,455.80 0.00 0.00 0.00 0.00 0.00 0.00 19818.6
9.35 Valvula de Compuerta de 4" UN 27.00 6,648.75 179,516.25 2.00 13,297.50 0.00 2.00 13,297.50 7.41 6648.75
9.36 Valvula de Compuerta de 3" UN 7.00 2,517.75 17,624.25 0.00 0.00 0.00 0.00 0.00 0.00 2517.75
9.37 Valvula de Compuerta de 2" UN 15.00 1,221.75 18,326.25 3.00 3,665.25 0.00 3.00 3,665.25 20.00 1221.75
9.38 Hidrante UN 13.00 13,502.40 175,531.20 0.00 0.00 0.00 0.00 0.00 0.00 13502.4
9.39 Tapon Hembra 2" UN 5.00 70.88 354.40 0.00 0.00 0.00 0.00 0.00 0.00 70.88
9.40. Tapon Hembra 4" UN 1.00 352.89 352.89 0.00 0.00 0.00 0.00 0.00 0.00 352.89
9.41 Codo de 45° PVC de 4" UN 13.00 234.99 3,054.87 0.00 0.00 0.00 0.00 0.00 0.00 234.99
9.42 Codo de 45° PVC de 2" UN 7.00 69.88 489.16 0.00 0.00 0.00 0.00 0.00 0.00 69.88
9.43 Codo de 45° PVC de 3" UN 7.00 139.41 975.87 0.00 0.00 0.00 0.00 0.00 0.00 139.41
9.44 Codo de 22-1/2" PVC de 4" UN 6.00 234.99 1,409.94 0.00 0.00 0.00 0.00 0.00 0.00 234.99
9.45 Codo de 22-1/2" PVC de 2" UN 9.00 69.88 628.92 0.00 0.00 0.00 0.00 0.00 0.00 69.88
Sub-Total 801,685.98 23,920.46 0.00 23,920.46
10 ELECTRIFICACION
10.1 Construccion Linea Primaria GL 1.00 3,771,502.42 3,771,502.42 0.00 0.00 0.07 264,005.17 0.07 264,005.17 7.00 3771502.42
10.2 Construccion Linea Segundaria GL 1.00 5,129,404.39 5,129,404.39 0.00 0.00 0.07 359,058.31 0.07 359,058.31 7.00 5129404.39
10.3 Transformadores GL 1.00 2,444,726.12 2,444,726.12 0.00 0.00 0.07 171,130.83 0.07 171,130.83 7.00 2444726.12
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: OBRAS DE URBANIZACION II ETAPA
ESTIMACION DE PAGO No.21 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL % 1
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
Sub-Total 11,345,632.93 0.00 794,194.31 794,194.31
9.- PISOS
9.1 Conformacion Terreno P.B. M2 380.72 14.99 5,705.50 342.65 5,136.32 0.00 342.65 5,136.32 90.02
9.2 Relleno Material Selecto P.B. M3 110.89 317.81 35,242.36 99.80 31,717.44 0.00 99.80 31,717.44 90.00
9.3 Firme de Concreto M2 2,079.06 274.47 570,646.87 1,871.15 513,574.54 0.00 1,871.15 513,574.54 90.00
9.4 Piso de Ceramica M2 2,159.49 487.15 1,051,986.19 0.00 0.00 0.00 0.00 0.00 0.00
9.5 Piso de Ceramica Antiderrapante M2 504.00 466.07 234,897.97 0.00 0.00 0.00 0.00 0.00 0.00
9.6 Moldura de Ceramica M.L. 2,168.01 74.60 161,743.66 0.00 0.00 0.00 0.00 0.00 0.00
9.7 Moldura de Ceramica Antiderrapante M.L. 157.00 74.60 11,712.93 0.00 0.00 0.00 0.00 0.00 0.00
9.8 Piso en Duchas M2 68.23 479.42 32,711.14 0.00 0.00 0.00 0.00 0.00 0.00
9.9 Bordillo en Duchas M.L. 71.00 165.62 11,758.88 0.00 0.00 0.00 0.00 0.00 0.00
9.10. Desniveles de Concreto M2 564.00 274.47 154,803.05 507.60 139,320.97 0.00 507.60 139,320.97 90.00
2,271,208.57 689,749.27 0.00 689,749.27
10.- ACABADOS
10.1 Repello y Pulido Paredes Interiores M2 6,099.34 234.74 1,431,750.78 5,489.38 1,288,577.06 0.00 5,489.38 1,288,577.06 90.00
10.2 Repello Pulido Paredes Fachadas M2 1,660.80 256.65 426,249.44 1,660.79 426,241.75 0.00 1,660.79 426,241.75 100.00
10.3 Stuco en Losa M2 1,886.40 150.27 283,476.05 0.00 0.00 0.00 0.00 0.00 0.00
10.4 Enchape de Ceramica (Baños y Cocina) M2 588.58 513.11 302,006.69 0.00 0.00 0.00 0.00 0.00 0.00
10.5 Pintura en Paredes Pulidas Interiores M2 6,099.34 66.34 404,633.86 0.00 0.00 0.00 0.00 0.00 0.00
10.6 Cielo Tabla-Yeso baños y cocina M2 290.10 390.94 113,412.12 0.00 0.00 0.00 0.00 0.00 0.00
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: EDIFICIO 20 APARTAMENTOS DE TRES (3) DORMITORIOS LOTES Nos. 21 y 22 DEL BLOQUE No.14
ESTIMACION No. 25 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
19.2 ESTRUCTURA
Concreto Reforzado Columnas M3 4.85 21,401.46 103,797.09 4.85 103,797.08 0.00 4.85 103,797.08 100.00
Concreto Reforzado Castillos M3 0.51 15,228.90 7,766.74 0.51 7,766.74 0.00 0.51 7,766.74 100.00
Concreto Reforzado Vigas Entrepiso M3 11.96 17,860.98 213,617.32 11.96 213,617.32 0.00 11.96 213,617.32 100.00
Concreto Reforzado Losa Entrepiso M3 37.68 11,692.35 440,567.89 37.68 440,567.89 0.00 37.68 440,567.89 100.00
765,749.04 765,749.03 0.00 765,749.03
19.3 GRADAS
Excavacion 0.51 271.48 138.46 0.51 138.45 0.00 0.51 138.45 100.00
Concreto Zapatas y Pedestales M3 0.27 5,363.34 1,448.10 0.27 1,448.10 0.00 0.27 1,448.10 100.00
Concreto Reforzado Gradas M3 1.17 14,379.04 16,823.48 1.17 16,823.48 0.00 1.17 16,823.48 100.00
Barandal M.L 28.90 1,605.53 46,399.86 0.00 0.00 0.00 0.00 0.00 0.00
Piso en Gradas (Huellas y Contrahuellas) 8.71 577.07 5,026.31 0.00 0.00 0.00 0.00 0.00 0.00
Stuco en Gradas M2 5.90 210.38 1,241.25 0.00 0.00 0.00 0.00 0.00 0.00
Refuerzo Kg 130.44 45.08 5,879.94 0.00 0.00 0.00 0.00 0.00 0.00
Formas M2 7.39 456.10 3,370.57 0.00 0.00 0.00 0.00 0.00 0.00
80,327.96 18,410.03 0.00 18,410.03
19.4 BARDAS
Excavacion M3 18.24 271.49 4,951.93 18.24 4,951.98 0.00 18.24 4,951.98 100.00
Concreto Reforzado Zapatas Barda M3 6.08 7,963.36 48,417.22 6.08 48,417.23 0.00 6.08 48,417.23 100.00
Concreto Reforzado Viga Cimentacion Bardas M3 3.15 14,462.64 45,557.32 3.15 45,557.32 0.00 3.15 45,557.32 100.00
Castillos Barandal M3 1.73 19,319.07 33,421.99 1.73 33,421.99 0.00 1.73 33,421.99 100.00
Paredes Barda 6" M2 195.75 416.60 81,549.93 195.75 81,547.37 0.00 195.75 81,547.37 100.00
Paredes Barda 4" M2 100.00 348.19 34,818.77 100.00 34,819.00 0.00 100.00 34,819.00 100.00
Concreto Solera Superior Bardas M3 1.26 21,443.31 27,018.58 1.26 27,018.57 0.00 1.26 27,018.57 100.00
Repello Bardas M2 491.50 202.31 99,436.45 491.50 99,435.37 0.00 491.50 99,435.37 100.00
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: EDIFICIO 20 APARTAMENTOS DE TRES (3) DORMITORIOS LOTES Nos. 21 y 22 DEL BLOQUE No.14
ESTIMACION No. 25 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
19.5 PAVIMENTO
Conformacion Terreno M2 460.80 30.79 14,186.48 460.80 14,188.03 0.00 460.80 14,188.03 100.00
Material Sub-Base M3 92.16 325.78 30,024.31 92.16 30,023.88 0.00 92.16 30,023.88 100.00
Pavimento Concreto 15cms M2 460.80 682.55 314,519.62 446.98 305,086.20 0.00 446.98 305,086.20 97.00
Bordillos M.L. 92.00 307.87 28,323.71 55.20 16,994.42 0.00 55.20 16,994.42 60.00
Aceras M2 94.50 400.61 37,857.31 75.60 30,286.12 18.90 7,571.53 94.50 37,857.65 100.00
Pintura Estacionamiento M.L. 136.20 16.29 2,218.59 0.00 0.00 0.00 0.00 0.00 0.00
Topes Unds 33.00 513.11 16,932.65 8.00 4,104.88 0.00 8.00 4,104.88 24.24
Jardineras S.G 1.00 22,261.95 22,261.95 0.00 0.00 0.00 0.00 0.00 0.00
466,324.62 400,683.54 7,571.53 408,255.06
6.24
2,932.06
53.57
271.49
271.49
271.49
66.71
66.71
66.71
362.27
5,283.14
16,341.13
10,337.16
9,637.09
18,717.90
14,463.72
1,147.93
17,436.26
75,751.12
403.81
13,838.81
223.02
223.02
1
1.04586966
10,317.53
1,056.04
531.40
98.75
138.38
1,063.60
1,025.62
13.80
292.66
252.75
448.59
429.18
68.70
68.70
441.48
152.51
252.75
216.16
236.34
138.38
472.50
61.09
360.00
1
1.04586966
61.09
81.10
130.91
15,000.00
3,051.35
4,725.00
4,725.00
4,725.00
*
9,660.00
3,780.00
3,080.00
2,100.00
27,753.40
13,171.20
13,524.00
1,468,729.30
525,811.00
145,783.59
103,116.00
24,424.20
37,210.03
8,580.00
1,745.30
1
1.04586966
155,839.27
27,448.20
2,146.50
3,631.50
3,192.75
2,092.50
2,671.07
1,621.48
2,106.00
229.64
249.75
189.00
136.00
931,500.00
182,750.00
25,740.00
17,550.00
13,500.00
2,295.00
2,536.25
250.00
1
1.04586966
4,938.81
10,074.30
13,209.83
73.72
19,707.62
14,023.59
16,447.35
10,766.95
250.00
4,938.85
13,241.00
1,478.46
531.40
193.73
41.51
420.00
250.00
7,333.09
13,317.98
17,790.04
383.63
320.63
19,746.16
186.30
1
1.04586966
71.43
28.35
300.00
628.53
283.50
368.90
15.00
472.50
20,500.00
5,000.00
32,000.00
12,000.00
75,000.00
17,235,440.56
1
1.04586966
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO VIVIENDA No.50 DEL BLOQUE No.37 MODELO VENECIA II
EN LOTE 8:00M X 20.00M.
ESTIMACION DE PAGO No.04 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL % 1.03832113
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
1.- PRELIMINARES
1.1 Limpieza de Lote M2 160.00 5.73 916.40 160.00 916.40 0.00 160.00 916.40 100.00 5.52
1.2 Marcacion y Nivelacion Gl. 1.00 945.03 945.03 1.00 945.03 0.00 1.00 945.03 100.00 910.15
1,861.43 1,861.43 0.00 1,861.43
2.- EXCAVACIÓN
2.1 Excavacion para Zapatas M3 12.37 210.01 2,597.79 12.37 2,597.79 0.00 12.37 2,597.79 100.00 202.26
2.2 Excavacion para Sistema de Drenaje M3 8.33 210.01 1,749.36 8.33 1,749.36 0.00 8.33 1,749.36 100.00 202.26
2.3 Excavacion para Agua Potable M3 3.10 210.01 651.02 3.10 651.02 0.00 3.10 651.02 100.00 202.26
4,998.17 4,998.17 0.00 4,998.17
4.- CIMENTACION
4.1 Excavacion Viga Cimentacion M3 10.50 210.02 2,205.16 10.50 2,205.16 0.00 10.50 2,205.16 100.00 202.26
4.2 Zapatas Aisladas M3 2.97 6,435.92 19,114.70 2.97 19,114.70 0.00 2.97 19,114.70 100.00 6,198.40
4.3 Pedestales M3 0.78 16,418.59 12,806.50 0.78 12,806.50 0.00 0.78 12,806.50 100.00 15,812.64
4.4 Viga de Cimentacion de 0.15mx0.30m. M3 2.26 12,191.36 27,552.48 2.26 27,552.48 0.00 2.26 27,552.48 100.00 11,741.42
4.5 Sobre-Elevacion de Bloques M2 9.30 740.42 6,885.94 9.30 6,885.94 0.00 9.30 6,885.94 100.00 713.10
4.6 Muros de Mamposteria de Piedra M3 6.30 1,189.14 7,491.60 6.30 7,491.60 0.00 6.30 7,491.60 100.00 1,145.25
76,056.39 76,056.39 0.00 76056.385792
5.- ESTRUCTURA
5.1 Columnas 1er. Nivel M3 1.03 14,351.12 14,781.65 1.03 14,781.65 0.00 1.03 14,781.65 100.00 13,821.46
5.2 Castillos 2do. Nivel M3 1.69 15,940.87 26,940.06 1.69 26,940.06 0.00 1.69 26,940.06 100.00 15,352.54
5.3 Concreto Vigas M3 2.87 17,372.65 49,859.50 2.87 49,859.50 0.00 2.87 49,859.50 100.00 16,731.48
5.4 Concreto Losa M2 78.00 1,200.38 93,629.31 78.00 93,629.31 0.00 78.00 93,629.31 100.00 1,156.07
185,210.53 185,210.53 0.00 185,210.53
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO VIVIENDA No.50 DEL BLOQUE No.37 MODELO VENECIA II
EN LOTE 8:00M X 20.00M.
ESTIMACION DE PAGO No.04 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL % 1.03832113
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
6.- PAREDES
6.1 Paredes 1er. Nivel de Ladrillo Rafon M2 89.53 440.25 39,415.73 89.53 39,415.73 0.00 89.53 39,415.73 100.00 424.00
6.2 Paredes 2do. Nivel de Ladrillo Rafon M2 188.36 446.65 84,130.27 188.36 84,130.27 0.00 188.36 84,130.27 100.00 430.16
6.3 Cargadores de Puertas y Ventanas M.L. 26.15 277.92 7,267.58 26.15 7,267.58 0.00 26.15 7,267.58 100.00 267.66
6.4 Solera Superior M3 1.46 15,628.55 22,817.69 1.46 22,817.69 0.00 1.46 22,817.69 100.00 15,051.75
6.5 Batientes de Ventanas M.L. 13.18 277.92 3,662.97 13.18 3,662.97 0.00 13.18 3,662.97 100.00 267.66
6.6 Entabicado M.L. 87.00 127.43 11,086.67 87.00 11,086.67 0.00 87.00 11,086.67 100.00 122.73
168,380.90 168,380.90 0.00 168,380.90
336,761.80
7.- ESCALERAS
7.1 Paredes y Relleno Material Selecto Gl 1.00 3,340.90 3,340.90 1.00 3,340.90 0.00 1.00 3,340.90 100.00 3,217.60
7.2 Concreto reforzado M3 1.90 18,666.57 35,466.48 1.90 35,466.48 0.00 1.90 35,466.48 100.00 17,977.65
7.3 Barandal M.L. 12.45 932.64 11,611.35 0.00 0.00 0.00 0.00 0.00 898.22
7.4 Estuco Gradas M2 2.94 192.01 564.50 0.00 0.00 0.00 0.00 0.00 184.92
50,983.23 38,807.39 0.00 38,807.39
8 TECHO
8.1 Techo Viga Vista, Panelit Machimbre y Lamina Acanalada
Standard Color Rojo M2 101.00 1,159.58 117,117.62 10.10 11,711.76 90.90 105,405.86 101.00 117,117.62 100.00 1,116.78
8.2 Techo Barbacoa y Lavanderia M2 17.60 634.96 11,175.32 0.00 17.60 11,175.32 17.60 11,175.32 100.00 611.53
8.3 Cielo Falso Barbacoa con Pintura M2 14.09 396.64 5,588.71 0.00 0.00 0.00 0.00 0.00 382.00
8.4 Canales Aguas Lluvias S:G 1.00 4,360.86 4,360.86 0.00 0.00 0.00 0.00 0.00 4,199.91
138,242.50 11,711.76 116,581.18 128,292.94
9.- PISOS
9.1 Conformacion Terreno M2 66.15 17.19 1,137.39 66.15 1,137.39 0.00 66.15 1,137.39 100.00 16.56
9.2 Relleno de Material Selecto M3 8.87 371.03 3,291.00 8.87 3,291.00 0.00 8.87 3,291.00 100.00 357.33
9.3 Firme de Concreto M2 182.44 315.06 57,479.15 18.24 5,746.65 164.20 51,732.50 182.44 57,479.15 100.00 303.43
9.4 Pisos de Ceramica M2 132.89 559.16 74,307.08 0.00 0.00 0.00 0.00 0.00 538.53
9.5 Batientes de Puertas M.L. 2.58 150.08 387.20 0.00 0.00 0.00 0.00 0.00 144.54
9.6 Moldura para Piso M.L. 106.48 85.63 9,117.49 0.00 0.00 0.00 0.00 0.00 82.47
9.7 Acabado Gradas Gl. 1.00 7,055.31 7,055.31 0.00 0.00 0.00 0.00 0.00 6,794.92
9.8 Ceramica Antiderrapante M2 47.13 534.98 25,213.59 0.00 0.00 0.00 0.00 0.00 515.24
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO VIVIENDA No.50 DEL BLOQUE No.37 MODELO VENECIA II
EN LOTE 8:00M X 20.00M.
ESTIMACION DE PAGO No.04 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL % 1.03832113
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
9.9 Moldura Cermica Antiderrapante M.L. 38.91 85.63 3,331.72 0.00 0.00 0.00 0.00 0.00 82.47
9.10 Bordillo en Ducha M.L. 3.45 190.10 655.84 0.00 0.00 0.00 0.00 0.00 183.08
181,975.76 10,175.05 51,732.50 61,907.54
10.- ACABADOS
10.1 Repello y Pulido de Paredes Interiores y Exteriores M2 543.68 235.66 128,124.43 217.47 51,249.30 0.00 217.47 51,249.30 40.00 226.96
10.2 Repello Confiteado en Paredes Exteriores M2 12.10 257.67 3,117.81 0.00 0.00 0.00 0.00 0.00 248.16
10.3 Repello y Tallado de Mochetas M.L. 124.94 53.99 6,745.37 49.38 2,665.97 75.56 4,079.40 124.94 6,745.37 100.00 52.00
10.4 Ceramica en Baños y Cocina M2 38.25 602.75 23,055.12 0.00 0.00 0.00 0.00 0.00 580.50
10.5 Ceramica en Pisos de Ducha M2 4.53 550.29 2,492.82 0.00 0.00 0.00 0.00 0.00 529.98
10.6 Pintura en Paredes Pulidas M2 543.68 76.09 41,370.54 0.00 0.00 0.00 0.00 0.00 73.29
10.7 Pintura en Paredes Confiteadas M2 12.10 183.47 2,220.03 0.00 0.00 0.00 0.00 0.00 176.70
10.8 Pintura en Cielo M2 83.32 129.74 10,810.33 0.00 0.00 0.00 0.00 0.00 124.96
10.9 Acabado en Losa M2 63.87 192.01 12,263.38 0.00 0.00 0.00 0.00 0.00 184.92
10.10 Colocacion Malla de Refuerzo en Repellos M.L. 59.49 34.08 2,027.20 0.00 0.00 0.00 0.00 0.00 32.82
10.11 Repello Pulido Columnas y Vigas M2 26.83 454.36 12,190.56 0.00 0.00 0.00 0.00 0.00 437.59
10.12 Juntas de Expansion M.L. 6.60 336.56 2,221.27 0.00 0.00 0.00 0.00 0.00 324.14
246,638.87 53,915.27 4,079.40 57,994.67
11.- PUERTAS
11.1 Puerta de Metal para Exteriores Vivienda Und 3.00 5,884.61 17,653.82 0.00 0.00 0.00 0.00 0.00 5,667.42
11.2 Puertas Termoformadas para Interiores Und 7.00 3,326.70 23,286.90 0.00 0.00 0.00 0.00 0.00 3,203.92
11.3 Puerta y Portones de Acceso Und 1.00 49,774.87 49,774.87 0.00 0.00 0.00 0.00 0.00 47,937.84
90,715.59 0.00 0.00 0.00
12.- VENTANAS
12.- Ventana Sala de 1.753m de ancho x 1.205m de alto Tipo Francesa Und 1.00 9,151.73 9,151.73 0.00 0.00 0.00 0.00 0.00 8,813.97
12.2- Ventana 1/2 Baño de 0.752m de ancho x 0.43m de alto Tipo Francesa Und 1.00 3,286.50 3,286.50 0.00 0.00 0.00 0.00 0.00 3,165.21
12.3 Ventana Comedor de 1.745m de ancho x 0.793m de alto Tipo Francesa Und 1.00 6,038.44 6,038.44 0.00 0.00 0.00 0.00 0.00 5,815.58
12.4 Puerta Comedor de 1.30m de ancho x 2.08m de alto Und 1.00 12,949.28 12,949.28 0.00 0.00 0.00 0.00 0.00 12,471.36
12.5 Ventana Dormitorio 1 y 2 de 1.50m de ancho x 1.20m de alto Tipo Francesa Und 2.00 7,890.17 15,780.34 0.00 0.00 0.00 0.00 0.00 7,598.97
12.6 Ventana Dormitorio Principal de 1.20m de ancho x 1.92m de alto Tipo Francesa Und 1.00 10,098.99 10,098.99 0.00 0.00 0.00 0.00 0.00 9,726.27
12.7 Ventana Estudio de 1.50m de ancho x 1.20m de alto, Tipo Francesa Und 1.00 7,890.17 7,890.17 0.00 0.00 0.00 0.00 0.00 7,598.97
12.8 Ventana Sala T.V. de 1.20m de ancho x 1.20m de alto, Tipo Francesa Und 1.00 6,414.77 6,414.77 0.00 0.00 0.00 0.00 0.00 6,178.02
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO VIVIENDA No.50 DEL BLOQUE No.37 MODELO VENECIA II
EN LOTE 8:00M X 20.00M.
ESTIMACION DE PAGO No.04 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL % 1.03832113
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
12.9 Ventana Baño de 0,80m de ancho x 0,50m de alto, Tipo Francesa Und 2.00 3,286.50 6,573.01 0.00 0.00 0.00 0.00 0.00 3,165.21
12.10 Ventana Dormitorio Empeda de 1,03m de ancho x 0,50m de alto, Celosia Und 1.00 1,043.48 1,043.48 0.00 0.00 0.00 0.00 0.00 1004.97
12.11 Ventana Baño de 0,70m de ancho x 0,40m de alto, Tipo Francesa Und 1.00 694.93 694.93 0.00 0.00 0.00 0.00 0.00 669.29
12.12 Albañileria M2 17.37 102.87 1,786.79 0.00 0.00 0.00 0.00 0.00 99.07
81,708.43 0.00 0.00 0.00
NUEVO/ 03/05-2Modificado
1,238,205.36
75.56
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO VIVIENDA DOS PLANTAS MODELO VENECIA II
EN LOTE 8:00M X 20.00M.
ESTIMACION DE PAGO No.34 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015. 1.05
VIVIENDAS DE LA No. 2,3,4 y 5 DEL BLOQUE No.17 y la No.41,42,43,44,51,52 y 53 DEL BLOQUE No.14
2.- EXCAVACIÓN
2.1 Excavacion para Cimientos M3 11.00 2,597.79 28,575.69 11.00 28,575.69 0.00 11.00 28,575.69 100.00 2,161.29
2.2 Excavacion para Sistema de Drenaje M3 11.00 1,749.36 19,242.96 10.00 17,493.60 0.00 10.00 17,493.60 90.91 1,455.42
2.3 Excavacion para Agua Potable M3 11.00 651.02 7,161.22 10.00 6,510.20 0.00 10.00 6,510.20 90.91 541.63
54,979.87 52,579.49 0.00 52,579.49
4.- CIMENTACION
4.1 Excavacion Viga Cimentación M3 11.00 2,205.16 24,256.76 11.00 24,256.76 0.00 11.00 24,256.76 100.00 1,834.56
4.2 Zapatas Aisladas M3 11.00 19,114.70 210,261.70 11.00 210,261.70 0.00 11.00 210,261.70 100.00 15,902.60
4.3 Pedestales M3 11.00 12,806.50 140,871.50 11.00 140,871.50 0.00 11.00 140,871.50 100.00 10,654.45
4.4 Viga de Cimentacion de 0.15mx0.30m. M3 11.00 27,552.48 303,077.28 11.00 303,077.28 0.00 11.00 303,077.28 100.00 22,922.46
4.5 Sobreelevacion de Bloque M2 11.00 6,885.94 75,745.34 11.00 75,745.34 0.00 11.00 75,745.34 100.00 5,728.80
4.6 Muros de Mamposteria de Piedra M3 11.00 7,491.60 82,407.60 10.00 74,916.00 0.00 10.00 74,916.00 90.91 6,232.65
836,620.18 829,128.58 0.00 829,128.58
5.- ESTRUCTURA
5.1 Columnas 1er. Nivel M3 11.00 14,781.65 162,598.15 10.00 147,816.50 0.00 10.00 147,816.50 90.91 12,297.69
5.2 Castillos 2do. Nivel M3 11.00 26,940.06 296,340.66 11.00 296,340.66 0.00 11.00 296,340.66 100.00 22,412.95
5.3 Concreto Vigas M3 11.00 49,859.50 548,454.50 11.00 548,454.50 0.00 11.00 548,454.50 100.00 41,480.91
5.4 Concreto Losa M2 11.00 93,629.31 1,029,922.41 11.00 1,029,922.41 0.00 11.00 1,029,922.41 100.00 77,895.48
2,037,315.72 2,022,534.07 0.00 2,022,534.07
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO VIVIENDA DOS PLANTAS MODELO VENECIA II
EN LOTE 8:00M X 20.00M.
ESTIMACION DE PAGO No.34 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015. 1.05
VIVIENDAS DE LA No. 2,3,4 y 5 DEL BLOQUE No.17 y la No.41,42,43,44,51,52 y 53 DEL BLOQUE No.14
6.- PAREDES
6.1 Paredes 1er. Nivel de Ladrillo Rafon M2 11.00 39,415.73 433,573.03 10.00 394,157.30 0.00 10.00 394,157.30 90.91 32,792.15
6.2 Paredes 2do. Nivel de Ladrillo Rafon M2 11.00 84,130.27 925,432.97 11.00 925,432.97 0.00 11.00 925,432.97 100.00 69,992.69
6.3 Cargadores de Puertas y Ventanas M.L. 11.00 7,267.58 79,943.38 10.30 74,856.07 0.00 10.30 74,856.07 93.64 6,046.40
6.4 Solera Superior M3 11.00 22,817.69 250,994.59 11.00 250,994.59 0.00 11.00 250,994.59 100.00 18,983.31
6.5 Batientes de Ventanas M.L. 11.00 3,662.97 40,292.67 11.00 40,292.67 0.00 11.00 40,292.67 100.00 3,047.48
6.6 Entabicado M.L. 11.00 11,086.67 121,953.37 10.00 110,866.70 0.00 10.00 110,866.70 90.91 9,223.74
1,852,190.01 1,796,600.30 0.00 1,796,600.30
7.- ESCALERAS
7.1 Paredes y Relleno Material Selecto Gl 11.00 3,340.90 36,749.90 11.00 36,749.90 0.00 11.00 36,749.90 100.00 2,779.59
7.2 Concreto reforzado M3 11.00 35,466.48 390,131.28 11.00 390,131.28 0.00 11.00 390,131.28 100.00 29,506.56
7.3 Barandal M.L. 11.00 11,611.35 127,724.85 10.00 116,113.50 0.00 10.00 116,113.50 90.91 9,660.08
7.4 Estuco Gradas M2 11.00 564.50 6,209.50 9.00 5,080.50 0.00 9.00 5,080.50 81.82 469.64
560,815.53 548,075.18 0.00 548,075.18
8 TECHO
8.1 Techo Viga Vista, Panelit Machimbre y Lamina Acanalada
Standard Color Rojo M2 11.00 117,117.62 1,288,293.82 10.00 1,171,176.20 0.00 10.00 1,171,176.20 90.91 97,436.72
8.2 Techo Barbacoa M2 11.00 11,175.32 122,928.52 9.00 100,577.88 0.00 9.00 100,577.88 81.82 9,297.38
8.3 Cielo Falso Barbacoa M2 11.00 5,588.71 61,475.81 8.60 48,062.91 0.00 8.60 48,062.91 78.18 4,649.56
8.4 Canales para Aguas Lluvias S.G. 11.00 4,360.86 47,969.46 8.00 34,886.88 0.00 8.00 34,886.88 72.73 3,628.04
1,520,667.61 1,354,703.87 0.00 1,354,703.87
9.- PISOS
9.1 Conformacion Terreno M2 11.00 1,137.39 12,511.29 10.50 11,942.60 0.00 10.50 11,942.60 95.45 945.95
9.2 Relleno de Material Selecto M3 11.00 3,291.00 36,201.00 9.00 29,619.00 0.00 9.00 29,619.00 81.82 2,737.99
9.3 Firme de Concreto M2 11.00 57,479.15 632,270.65 9.50 546,051.93 0.00 9.50 546,051.93 86.36 47,819.35
9.4 Pisos de Ceramica M2 11.00 74,307.08 817,377.88 8.00 594,456.64 0.00 8.00 594,456.64 72.73 61,820.43
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO VIVIENDA DOS PLANTAS MODELO VENECIA II
EN LOTE 8:00M X 20.00M.
ESTIMACION DE PAGO No.34 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015. 1.05
VIVIENDAS DE LA No. 2,3,4 y 5 DEL BLOQUE No.17 y la No.41,42,43,44,51,52 y 53 DEL BLOQUE No.14
11.- PUERTAS
11.1 Puerta de Metal para Exteriores Vivienda Und 11.00 17,653.82 194,192.02 8.00 141,230.56 0.00 8.00 141,230.56 72.73 14,687.20
11.2 Puertas Termoformadas para Interiores Und 11.00 23,286.90 256,155.90 8.00 186,295.20 0.00 8.00 186,295.20 72.73 19,373.69
11.3 Puerta y Portones de Acceso Und 11.00 49,774.87 547,523.57 8.00 398,198.96 0.00 8.00 398,198.96 72.73 41,410.50
997,871.49 725,724.72 0.00 725,724.72
12.- VENTANAS
12.1 Ventana Sala de 1.753m de ancho x 1.205m de alto Tipo Francesa Und 11.00 9,151.73 100,669.03 8.00 73,213.84 0.00 8.00 73,213.84 72.73 7,613.84
12.2 Ventana 1/2 Baño de 0.752m de ancho x 0.43m de alto Tipo Francesa Und 11.00 3,286.50 36,151.50 8.00 26,292.00 0.00 8.00 26,292.00 72.73 2,734.23
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO VIVIENDA DOS PLANTAS MODELO VENECIA II
EN LOTE 8:00M X 20.00M.
ESTIMACION DE PAGO No.34 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015. 1.05
VIVIENDAS DE LA No. 2,3,4 y 5 DEL BLOQUE No.17 y la No.41,42,43,44,51,52 y 53 DEL BLOQUE No.14
**
**
**
**
**
**
**
**
**
**
**
**
**
**
**
**
**
**
**
**
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: VIVIENDA MODELO CASTELLO
ESTIMACION DE PAGO No.05 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
VIVIENDA No.49 DEL BLOQUE No.37
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL %
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
1.- PRELIMINARES
1.1 Limpieza de Lote M2 160.00 5.72 915.20 160.00 915.20 0.00 160.00 915.20 100.00
1.2 Marcacion y Nivelacion S.G 1.00 945.04 945.04 1.00 945.04 0.00 1.00 945.04 100.00
1,860.24 1,860.24 0.00 1,860.24
2.- EXCAVACIÓN
2.1 Excavacion para Zapatas M3 16.08 184.29 2,963.35 16.08 2,963.35 0.00 16.08 2,963.35 100.00
2.2 Excavacion Sistema de Drenaje M3 12.36 184.29 2,277.80 12.36 2,277.80 0.00 12.36 2,277.80 100.00
2.3 Excavacion Tuberia Agua Potable M3 6.83 184.29 1,258.69 6.83 1,258.69 0.00 6.83 1,258.69 100.00
2.4 Excavacion Viga de Cimentacion M3 9.08 184.29 1,673.34 9.08 1,673.34 0.00 9.08 1,673.34 100.00
2.5 Excavacion Aguas Lluvias M3 8.41 184.29 1,549.86 0.00 0.00 8.41 1,549.86 8.41 1,549.86 100.00
9,723.03 8,173.17 1,549.86 9,723.03
4.- CIMENTACION
4.1 Concreto Zapatas Aisladas M3 2.89 6,693.65 19,344.64 2.89 19,344.64 0.00 2.89 19,344.64 100.00
4.2 Concreto Pedestales M3 0.85 17,318.26 14,720.52 0.85 14,720.52 0.00 0.85 14,720.52 100.00
4.3 Concreto Viga de Cimentación M3 3.03 11,497.20 34,836.52 3.03 34,836.52 0.00 3.03 34,836.52 100.00
4.4 Sobreelevacion de Bloques M2 9.30 740.42 6,885.86 9.30 6,885.86 0.00 9.30 6,885.86 100.00
4.5 Muros de Mamposteria de Piedra M3 6.30 1,189.14 7,491.56 6.30 7,491.56 0.00 6.30 7,491.56 100.00
83,279.10 83,279.10 0.00 83,279.10
5.- ESTRUCTURA
5.1 Concreto Columnas 1er. Nivel M3 1.26 13,946.45 17,572.53 1.26 17,572.53 0.00 1.26 17,572.53 100.00
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: VIVIENDA MODELO CASTELLO
ESTIMACION DE PAGO No.05 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
VIVIENDA No.49 DEL BLOQUE No.37
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL %
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
5.2 Concreto Castillos 1er. Nivel M3 0.53 16,291.07 8,634.27 0.53 8,634.27 0.00 0.53 8,634.27 100.00
5.3 Concreto Vigas M3 2.39 15,339.12 36,660.49 2.39 36,660.49 0.00 2.39 36,660.49 100.00
5.4 Concreto Losa M2 61.52 1,200.38 73,847.44 61.52 73,847.44 0.00 61.52 73,847.44 100.00
5.5 Canales de Concreto M.L. 6.75 2,753.40 18,585.45 0.00 0.00 0.00 0.00 0.00 0.00
155,300.17 136,714.72 0.00 136,714.72
6.- PAREDES
6.1 Paredes 1er. Nivel de Ladrillo Rafon M2 127.79 440.25 56,258.91 127.79 56,258.91 0.00 127.79 56,258.91 100.00
6.2 Paredes 2do. Nivel de Ladrillo Rafon M2 129.79 446.65 57,971.22 129.79 57,971.22 0.00 129.79 57,971.22 100.00
6.3 Castillos 2do Nivel M3 1.35 16,291.07 21,992.94 1.35 21,992.94 0.00 1.35 21,992.94 100.00
6.4 Cargadores de Puertas y Ventanas M.L. 42.85 277.91 11,908.61 42.85 11,908.61 0.00 42.85 11,908.61 100.00
6.5 Solera Superior M3 0.94 15,628.55 14,690.84 0.94 14,690.84 0.00 0.94 14,690.84 100.00
6.6 Batientes de Ventanas M.L. 23.85 277.91 6,628.25 11.93 3,315.51 0.00 11.93 3,315.51 50.02
169,450.77 166,138.04 0.00 166,138.04
7.- ESCALERAS
7.1 Paredes y Relleno Material Selecto S.G. 1.00 3,040.22 3,040.22 1.00 3,040.22 0.00 1.00 3,040.22 100.00
7.2 Concreto Reforzado M3 1.85 17,975.22 33,254.15 1.85 33,254.15 0.00 1.85 33,254.15 100.00
7.3 Barandal M.L. 12.45 848.71 10,566.38 0.00 0.00 0.00 0.00 0.00 0.00
7.4 Estuco Gradas M2 3.00 174.72 524.16 0.00 0.00 0.00 0.00 0.00 0.00
47,384.91 36,294.37 0.00 36,294.37
8.- TECHO
8.1 Techo Vigas Metalicas y Lamina Acanalda Metalica M2 82.16 568.71 46,725.30 0.00 0.00 82.16 46,725.30 82.16 46,725.30 100.00
8.2 Canales Aguas Lluvias S.G. 1.00 4,360.86 4,360.86 0.00 0.00 0.00 0.00 0.00 0.00
8.3 Cielo Falso Planta Alta, Tabla Yeso M2 71.19 423.54 30,151.81 0.00 0.00 0.00 0.00 0.00 0.00
81,237.97 0.00 46,725.30 46,725.30
9.- PISOS
9.1 Conformacion Terreno M2 56.20 17.19 965.85 56.20 965.85 0.00 56.20 965.85 100.00
9.2 Relleno de Material Selecto M3 8.43 371.03 3,127.81 8.43 3,127.81 0.00 8.43 3,127.81 100.00
9.3 Firme de Concreto M2 110.53 315.06 34,823.03 55.27 17,413.09 0.00 55.27 17,413.09 100.00
9.4 Pisos de Ceramica M2 104.46 559.16 58,409.44 0.00 0.00 0.00 0.00 0.00 0.00
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: VIVIENDA MODELO CASTELLO
ESTIMACION DE PAGO No.05 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
VIVIENDA No.49 DEL BLOQUE No.37
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL %
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
9.5 Batientes de Puertas M.L. 3.50 150.09 525.30 0.00 0.00 0.00 0.00 0.00 0.00
9.6 Moldura para Piso M.L. 114.92 85.63 9,840.71 0.00 0.00 0.00 0.00 0.00 0.00
9.7 Acabado Gradas Und 1.00 7,055.31 7,055.31 0.00 0.00 0.00 0.00 0.00 0.00
9.8 Bordillo en Ducha M2 4.60 190.10 874.46 0.00 0.00 0.00 0.00 0.00 0.00
115,621.90 21,506.75 0.00 21,506.75
10.- ACABADOS
10.1 Repello y Pulido de Paredes Interiores y Exteriores M2 526.48 235.66 124,072.38 263.24 62,036.19 0.00 263.24 62,036.19 100.00
10.2 Repello Confiteado en Paredes Exteriores M2 11.50 257.67 2,963.24 0.00 0.00 0.00 0.00 0.00 0.00
10.3 Repello y Tallado de Mochetas M.L. 104.29 53.99 5,630.51 52.14 2,814.99 0.00 52.14 2,814.99 100.00
10.4 Ceramica en Baños y Cocina M2 28.45 602.75 17,148.10 0.00 0.00 0.00 0.00 0.00 0.00
10.5 Ceramica Pisos Duchas M2 4.15 550.29 2,283.70 0.00 0.00 0.00 0.00 0.00 0.00
10.6 Pintura en Paredes Pulidas M2 526.48 76.09 40,059.34 0.00 0.00 0.00 0.00 0.00 0.00
10.7 Pintura en Paredes Confiteadas M2 11.50 183.47 2,109.89 0.00 0.00 0.00 0.00 0.00 0.00
10.8 Pintura Cielo 2do Nivel M2 59.97 129.74 7,780.51 0.00 0.00 0.00 0.00 0.00 0.00
10.9 Estuco Losa M2 48.02 192.01 9,220.32 0.00 0.00 0.00 0.00 0.00 0.00
10.10. Colocacion Malla de Refuerzo en Repellos M.L. 47.60 34.09 1,622.49 47.60 1,622.49 0.00 47.60 1,622.49 100.00
10.11 Repello Columnas y Vigas M2 24.15 454.36 10,972.87 24.15 10,972.87 0.00 24.15 10,972.87 100.00
10.12 Junta de Expansion M.L. 6.60 336.56 2,221.28 0.00 0.00 0.00 0.00 0.00 0.00
226,084.63 77,446.54 0.00 77,446.54
11.-PUERTAS
11.1 Puertas de Metal para Exteriores Vivienda Und 5.00 5,884.61 29,423.03 0.00 0.00 0.00 0.00 0.00
11.2 Puertas Termoformadas para Interiores Und 6.00 3,326.70 19,960.20 0.00 0.00 0.00 0.00 0.00
49,383.23 0.00 0.00 0.00
12.- VENTANAS
12.1 Ventana V-1 de 2.00m de ancho x 1.50m de alto Corrediza Und 2.00 7,176.00 14,352.00 0.00 0.00 0.00 0.00 0.00
12.2 Ventana V-2 de 1.00m de ancho x 0.60m de alto Corrediza Und 1.00 1,794.00 1,794.00 0.00 0.00 0.00 0.00 0.00
12.3 Ventana V-3 de 0.75m de ancho x 0.60m de alto Corrediza Und 4.00 1,794.00 7,176.00 0.00 0.00 0.00 0.00 0.00
12.4 Ventana V-4 de 1.50m de ancho x 1.20m de alto Corrediza Und 2.00 4,305.60 8,611.20 0.00 0.00 0.00 0.00 0.00
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: VIVIENDA MODELO CASTELLO
ESTIMACION DE PAGO No.05 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
VIVIENDA No.49 DEL BLOQUE No.37
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL %
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
12.5 Ventana V-5 de 2.00m de ancho x 1.20m de alto Corrediza Und 1.00 5,740.80 5,740.80 0.00 0.00 0.00 0.00 0.00
12.6 Ventana V-6 de 0.80m de ancho x 1.00m de alto Corrediza Und 1.00 1,913.60 1,913.60 0.00 0.00 0.00 0.00 0.00
12.7 Ventana V-7 de 1.20m de ancho x 1.00m de alto Corrediza Und 1.00 2,870.40 2,870.40 0.00 0.00 0.00 0.00 0.00
12.8 Ventana V-8 de 1.00m de ancho x 1.00m de alto Corrediza Und 1.00 2,392.00 2,392.00 0.00 0.00 0.00 0.00 0.00
12.9 Albañileria S.G. 1.00 1,809.60 1,809.60 0.00 0.00 0.00 0.00 0.00
46,659.60 0.00 0.00 0.00
4.4
726.95
141.76
141.76
141.76
141.76
141.76
51.55
51.55
51.55
5148.96
13321.74
8844
569.55
914.72
10728.04
1.3
12531.59
11799.32
923.37
2118
338.65
343.58
12531.59
213.78
12021.96
213.78
2338.63
13827.09
652.85
134.4
437.47 57.51
3354.51
325.8
13.22
285.41
242.35
430.12
1.3
115.45
65.87
5427.16
146.23
181.28
198.21
41.53
463.65
423.3
58.53
141.13
99.8
147.7
26.22
349.51
258.89
4526.62
2559
5520
1380
1380
3312
1.3
4416
1472
2208
1840
1392
10044.87
16730.75
6412.3
8659.5
2998.3
3099.5
4660.99
2794.05
2551.25
9314.7
1521.51
880
37.8
391.3
1521.51
1.3
8937.25
11100
1113.29
1762.3
3492.15
2622.07
1821.9
343.27
151.16
188.72
201.55
115.92
161.55
4950.72
10302.58
338.65
12021.96
41.54
181.28
58.53
540
339.1
11039.32
12629.78
76.92
1.3
302.15
25641.45
35482.45
12563.06
2.- EXCAVACIÓN
2.1 Excavacion Cimentacion M3 13.38 210.60 2,817.83 13.38 2,817.83 0.00 13.38 2,817.83 100.00
2.2 Excavacion Tuberia Aguas Negras M3 12.20 210.60 2,569.32 1.00 210.60 0.00 1.00 210.60 8.20
2.3 Excavacion Tuberia Agua Potable M3 3.50 210.60 737.10 1.00 210.60 0.00 1.00 210.60 28.57
2.4 Excavacion Tuberias Aguas Pluviales M3 6.40 210.60 1,347.84 1.00 210.60 0.00 1.00 210.60 15.63
Suma Lps. 7,472.09 3,449.63 0.00 3,449.63
3.- RELLENOS COMPACTADOS
3.1 Relleno de Cimientos M3 10.76 76.58 824.03 10.76 824.03 0.00 10.76 824.03 100.00
3.2 Relleno Tuberías Aguas Negras M3 11.80 76.58 903.68 1.00 76.58 0.00 1.00 76.58 8.47
3.3 Relleno Tuberías Agua Potable M3 3.30 76.58 252.72 1.00 76.58 0.00 1.00 76.58 30.30
3.4 Relleno Tuberias Aguas Pluviales M3 6.00 76.58 459.50 1.00 76.58 0.00 1.00 76.58 16.67
Suma Lps. 2,439.93 1,053.78 0.00 1,053.78
4.- CIMENTACION
4.1 Excavacion Viga de Cimentacion M3 10.87 210.60 2,289.22 10.87 2,289.22 0.00 10.87 2,289.22 100.00
4.2 Concreto Zapata Aislada M3 2.72 6,454.33 17,555.78 2.72 17,555.78 0.00 2.72 17,555.78 100.00
4.3 Concreto Pedestales M3 1.05 16,465.55 17,288.83 1.05 17,288.83 0.00 1.05 17,288.83 100.00
4.4 Concreto Viga Cimentacion M3 4.40 12,226.23 53,795.40 1.00 12,226.23 0.00 1.00 12,226.23 22.73
4.5 Sobreelevacion de Bloques M2 9.30 742.53 6,905.57 9.30 6,905.57 0.00 9.30 6,905.57 100.00
4.6 Muros de Mamposteria de Piedra M3 6.30 1,192.54 7,513.01 6.30 7,513.01 0.00 6.30 7,513.01 100.00
Suma Lps. 105,347.81 63,778.64 0.00 63,778.64
5.- PAREDES
5.1 Paredes de Ladrillo Rafon M2 253.96 441.51 112,124.86 1.00 441.51 0.00 1.00 441.51 0.39
5.2 Concreto Vigas M3 0.58 17,422.31 10,104.94 0.00 0.00 0.00 0.00 0.00 0.00
5.3 Concreto Castillos M3 2.94 14,392.27 42,313.29 1.00 14,392.27 0.00 1.00 14,392.27 34.01
5.4 Concreto Cargadores M.L 32.90 278.72 9,169.89 32.90 9,169.89 0.00 32.90 9,169.89 100.00
5.5 Concreto Batientes Puertas y Ventanas M.L 20.00 278.72 5,574.40 20.00 5,574.40 0.00 20.00 5,574.40 100.00
5.6 Concreto Solera Superior M3 2.23 15,673.24 34,951.33 2.23 34,951.33 0.00 2.23 34,951.33 100.00
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: VIVIENDA MODELO ARSENALE
ESTIMACION DE PAGO No.04 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015
4.42
729.05
162
162
162
162
58.91
58.91
58.91
58.91
162
4964.87
12665.81
9404.79
571.18
917.34
339.62
13,401.78
11,070.98
214.40
214.40
12,056.34
1.30
REALIZADO
454.97
247.57
2,287.45
960.00
507.97
300.00
13.26
286.22
243.04
431.36
115.78
66.06
412.70
66.06
146.65
181.80
41.65
469.61
58.70
58.70
26.29
259.63
424.51
4,539.56
1.30
REALIZADO
2,566.32
2,566.32
4,539.56
4,539.56
5,475.00
3,285.00
2,190.00
2,409.00
1,357.75
1,357.75
1,357.75
1,357.75
2,409.00
5,950.00
10,110.80
15,185.10
8,099.60
9,116.80
2,059.00
2,400.00
17,025.90
1,521.51
2,399.00
37.80
1.30
REALIZADO
391.30
1,525.00
7,593.60
3,368.55
1,100.00
1,767.34
3,098.39
2,347.13
1,414.24
1,715.42
151.60
189.26
202.12
116.24
162.00
4,964.87
10,714.68
352.19
12,502.84
11,480.90
13,134.97
94.26
188.52
60.87
314.23
345.65
1.30
REALIZADO
211.62
345.65
340.06
25,714.77
35,821.22
13,666.51
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: VIVIENDA DE DOS PLANTAS MODELO PRADO
SOLUCION: VIVIENDA CUATRO (4) DORMITORIOS CON 3 1/2 BAÑOS
ESTIMACION DE PAGO No. 37 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
VIIVENDAS Nos. 1,17 y 18 DEL BLOQUE No. 16 Y Viviendas Nos. 5 ,23 y 49 DEL BLOQUE No.14
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL %
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
1.- PRELIMINARES
1.1 Limpieza de Lote M2 6.00 1,373.08 8,238.48 6.00 8,238.48 0.00 6.00 8,238.48 100.00
1.2 Marcacion y Nivelacion S.G. 6.00 1,240.95 7,445.70 6.00 7,445.70 0.00 6.00 7,445.70 100.00
15,684.18 15,684.18 0.00 15,684.18
2.- EXCAVACION
2.1 Excavacion para Cimientos y Muros M3 6.00 7,350.38 44,102.28 6.00 44,102.28 0.00 6.00 44,102.28 100.00
2.2 Excavacion para Tuberia de Aguas Negras y Drenaje M3 6.00 3,591.19 21,547.14 6.00 21,547.14 0.00 6.00 21,547.14 100.00
2.3 Excavacion para Tuberia de Agua Potable M3 6.00 1,885.90 11,315.40 6.00 11,315.40 0.00 6.00 11,315.40 100.00
76,964.82 76,964.82 0.00 76,964.82
4.- CIMENTACION
4.1 Excavacion Viga Cimentacion M3 6.00 2,394.12 14,364.72 6.00 14,364.72 0.00 6.00 14,364.72 100.00
4.2 Concreto Reforzado Zapatas Aisladas M3 6.00 43,378.17 260,269.02 6.00 260,269.02 0.00 6.00 260,269.02 100.00
4.3 Concreto Reforzado Pedestales M3 6.00 23,642.78 141,856.68 6.00 141,856.68 0.00 6.00 141,856.68 100.00
4.4 Concreto Reforzado Vigas de Cimentacion M3 6.00 51,325.64 307,953.84 6.00 307,953.84 0.00 6.00 307,953.84 100.00
4.5 Sobre-elevacion de Bloques de Concreto M2 6.00 14,808.54 88,851.24 6.00 88,851.24 0.00 6.00 88,851.24 100.00
4.6 Muros de Mamposteria de Piedra M3 6.00 11,237.35 67,424.10 6.00 67,424.10 0.00 6.00 67,424.10 100.00
5.- ESTRUCTURA
5.1 Concreto Reforzado en Columnas y Castillos 1er. Nivel M3 6.00 60,418.23 362,509.38 6.00 362,509.38 0.00 6.00 362,509.38 100.00
5.2 Concreto Reforzado Castillos 2do. Nivel M3 6.00 56,590.08 339,540.48 6.00 339,540.48 0.00 6.00 339,540.48 100.00
5.3 Concreto Reforzado Vigas Entrepiso M3 6.00 94,159.76 564,958.56 6.00 564,958.56 0.00 6.00 564,958.56 100.00
5.4 Concreto Refrozado Losa Entrepiso M2 6.00 113,603.20 681,619.20 6.00 681,619.20 0.00 6.00 681,619.20 100.00
5.5 Viga Canal M.L 6.00 24,447.08 146,682.48 6.00 146,682.48 0.00 6.00 146,682.48 100.00
5.6 Viga Cargador 15 x 30 M.L 6.00 4,773.15 28,638.90 6.00 28,638.90 0.00 6.00 28,638.90 100.00
5.7 Solera de Remate M.L 6.00 36,355.67 218,134.02 6.00 218,134.02 0.00 6.00 218,134.02 100.00
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: VIVIENDA DE DOS PLANTAS MODELO PRADO
SOLUCION: VIVIENDA CUATRO (4) DORMITORIOS CON 3 1/2 BAÑOS
ESTIMACION DE PAGO No. 37 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
VIIVENDAS Nos. 1,17 y 18 DEL BLOQUE No. 16 Y Viviendas Nos. 5 ,23 y 49 DEL BLOQUE No.14
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL %
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
2,342,083.02 2,342,083.02 0.00 2,342,083.02 100.00
6.- PAREDES
6.1 Paredes del 1er. Nivel M2 6.00 73,829.62 442,977.72 6.00 442,977.72 0.00 6.00 442,977.72 100.00
6.2 Paredes del 2do. Nivel M2 6.00 113,894.27 683,365.62 6.00 683,365.62 0.00 6.00 683,365.62 100.00
6.3 Cargadores Puertas y Ventanas M.L 6.00 8,990.62 53,943.72 6.00 53,943.72 0.00 6.00 53,943.72 100.00
6.4 Batientes de Ventanas con Resalte M.L 6.00 3,345.38 20,072.28 5.00 16,726.90 0.00 5.00 16,726.90 83.33
6.5 Entabicado M.L 6.00 8,716.43 52,298.58 6.00 52,298.58 0.00 6.00 52,298.58 100.00
6.6 Batiente Sencillo en Ventanas M.L 6.00 2,848.65 17,091.90 6.00 17,091.90 0.00 6.00 17,091.90 100.00
7.- GRADAS
7.1 Concreto Reforzado Zapata y Pedestales M3 6.00 5,786.64 34,719.84 6.00 34,719.84 0.00 6.00 34,719.84 100.00
7.2 Concreto Reforzado en Gradas M3 6.00 24,266.55 145,599.30 6.00 145,599.30 0.00 6.00 145,599.30 100.00
7.3 Barandal M.L. 6.00 11,331.46 67,988.76 6.00 67,988.76 0.00 6.00 67,988.76 100.00
7.4 Piso en Gradas (Huellas y Contrahuellas) M2 6.00 8,652.46 51,914.76 6.00 51,914.76 0.00 6.00 51,914.76 100.00
7.5 Relleno en Gradas M3 6.00 656.73 3,940.38 6.00 3,940.38 0.00 6.00 3,940.38 100.00
7.6 Stuco en Gradas M2 6.00 564.50 3,387.00 6.00 3,387.00 0.00 6.00 3,387.00 100.00
7.7 Repello y Pulido M2 6.00 11,771.80 70,630.80 6.00 70,630.80 0.00 6.00 70,630.80 100.00
7.8 Pintura Paredes Pulidas M2 6.00 3,447.41 20,684.46 5.00 17,237.05 0.00 5.00 17,237.05 83.33
398,865.30 395,417.89 0.00 395,417.89
8.- TECHO
8.1 Techo Viga Vista, Machimbre y Lamina Standard Roja M2 6.00 157,238.54 943,431.24 6.00 943,431.24 0.00 6.00 943,431.24 100.00
8.2 Galera Barbacoa y Techo Area Servidumbre M2 6.00 26,655.81 159,934.86 6.00 159,934.86 0.00 6.00 159,934.86 100.00
8.3 Cielo Falso Panelit Area Servidumbre con Pintura M2 6.00 15,365.78 92,194.68 6.00 92,194.68 0.00 6.00 92,194.68 100.00
8.4 Canales Aguas Lluvias M.L 6.00 21,520.60 129,123.60 5.00 107,603.00 0.00 5.00 107,603.00 83.33
1,324,684.38 1,303,163.78 0.00 1,303,163.78
9,- PISOS
9.1 Conformacion Terreno M2 6.00 1,744.89 10,469.34 6.00 10,469.34 0.00 6.00 10,469.34 100.00
9.2 Relleno de Material Selecto M3 6.00 8,689.61 52,137.66 6.00 52,137.66 0.00 6.00 52,137.66 100.00
9.3 Firme de Concreto M2 6.00 69,064.69 414,388.14 6.00 414,388.14 0.00 6.00 414,388.14 100.00
9.4 Piso de Ceramica M2 6.00 109,801.60 658,809.60 5.00 549,008.00 0.00 5.00 549,008.00 83.33
PROYECTO: RESIDENCIAL VENECIA
PRESUPUESTO: VIVIENDA DE DOS PLANTAS MODELO PRADO
SOLUCION: VIVIENDA CUATRO (4) DORMITORIOS CON 3 1/2 BAÑOS
ESTIMACION DE PAGO No. 37 DEL 01 AL 30 DE SEPTIEMBRE DEL 2015.
VIIVENDAS Nos. 1,17 y 18 DEL BLOQUE No. 16 Y Viviendas Nos. 5 ,23 y 49 DEL BLOQUE No.14
OBRA CONTRATADA ACUMULADO ANTERIOR ESTE PERIODO ACUMULADO ACTUAL %
No. CONCEPTO UNIDAD CANTIDAD PRECIO TOTAL CANTIDAD TOTAL CANTIDAD TOTAL CANTIDAD TOTAL REALIZADO
UNITARIO
9.5 Piso de Ceramica Antiderrapante Terraza Exterior M2 6.00 17,960.11 107,760.66 6.00 107,760.66 0.00 6.00 107,760.66 100.00
9.6 Moldura de Ceramica M.L. 6.00 14,085.34 84,512.04 6.00 84,512.04 0.00 6.00 84,512.04 100.00
9.7 Piso en Duchas M2 6.00 2,267.24 13,603.44 6.00 13,603.44 0.00 6.00 13,603.44 100.00
9.8 Bordillo en Duchas M.L. 6.00 874.44 5,246.64 5.00 4,372.20 0.00 5.00 4,372.20 83.33
9.9 Batientes en Puertas M.L. 6.00 630.33 3,781.98 6.00 3,781.98 0.00 6.00 3,781.98 100.00
9,10. Relleno Arena de Tope en Baños 2da Planta M3 6.00 352.32 2,113.92 6.00 2,113.92 0.00 6.00 2,113.92 100.00
9.11 Moldura de Ceramica Antiderrapante M.L. 6.00 3,490.29 20,941.74 6.00 20,941.74 0.00 6.00 20,941.74 100.00
1,373,765.16 1,263,089.12 0.00 1,263,089.12
10,- ACABADOS
10.1 Repello y Pulido Paredes M2 6.00 192,084.32 1,152,505.92 6.00 1,152,505.92 0.00 6.00 1,152,505.92 100.00
10.2 Confiteado Pared Exterior M2 6.00 3,496.44 20,978.64 5.00 17,482.20 0.00 5.00 17,482.20 83.33
10.3 Stuco en Losa M2 6.00 18,519.01 111,114.06 6.00 111,114.06 0.00 6.00 111,114.06 100.00
10.4 Enchape de Ceramica Baños y Cocina (Incluye Repello) M2 6.00 47,677.18 286,063.08 6.00 286,063.08 0.00 6.00 286,063.08 100.00
10.5 Pintura en Paredes Pulidas M2 6.00 62,027.93 372,167.58 5.30 328,748.03 0.00 5.30 328,748.03 88.33
10.6 Pintura en Paredes Confiteadas M2 6.00 1,760.69 10,564.14 5.00 8,803.45 0.00 5.00 8,803.45 83.33
10.7 Pintura Madera Techo M2 6.00 24,473.18 146,839.08 6.00 146,839.08 0.00 6.00 146,839.08 100.00
10.8 Banda Ceramica 0.40cm Cocina M.L. 6.00 1,550.16 9,300.96 6.00 9,300.96 0.00 6.00 9,300.96 100.00
10.9 Juntas de Expansion M.L. 6.00 2,874.23 17,245.38 5.00 14,371.15 0.00 5.00 14,371.15 83.33
10.10. Repello Pulido Columnas y Vigas M2 6.00 11,545.26 69,271.56 6.00 69,271.56 0.00 6.00 69,271.56 100.00
10.11 Colocacion Malla de Refuerzo en Repello M.L. 6.00 2,104.98 12,629.88 6.00 12,629.88 0.00 6.00 12,629.88 100.00
2,208,680.28 2,157,129.37 0.00 2,157,129.37
11,- PUERTAS
11.1 Puerta Principal de Caoba P-1 Und 6.00 15,050.99 90,305.94 5.00 75,254.95 0.00 5.00 75,254.95 83.33
11.2 Puertas Metalicas P-2 Und 6.00 11,769.20 70,615.20 5.00 58,846.00 0.00 5.00 58,846.00 83.33
11.3 Puertas Termoformadas P-3 Und 6.00 29,940.28 179,641.68 5.00 149,701.40 0.00 5.00 149,701.40 83.33
11.4 Porton Vehicular y Puerta Acesso Und 6.00 54,550.87 327,305.22 5.00 272,754.35 0.00 5.00 272,754.35 83.33
1,200.78
1,032.42
6,115.09
2,987.66
1,568.96
1,795.45
1,086.42
570.53
1,991.81
36,088.72
19,669.75
42,700.68
12,320.00
9,348.94
50,265.30
47,080.46
78,336.78
94,513.18
20,338.89
3,971.00
30,245.16
1.05
61,423.48
94,755.45
7,479.84
2,783.20
7,251.68
2,369.97
4,814.23
20,188.70
9,427.27
7,198.49
546.36
469.64
9,793.20
2,868.02
130,816.03
22,176.35
12,783.81
17,904.46
1,451.52
7,229.22
57,459.25
91,351.02
1.05
14,942.17
11,717.83
1,886.21
727.50
524.42
293.10
2,903.63
159,808.51
2,909.00
15,406.92
39,665.49
51,601.12
1,464.77
20,360.01
1,289.66
2,391.20
9,605.23
1,751.18
12,521.76
9,791.47
24,909.02
45,383.93
18,379.95
9,149.13
3,573.88
1.05
1,708.89
22,464.37
5,741.86
4,101.34
12,230.18
693.79
1,191.89
2,618.61
3,624.58
30,164.04
16,770.35
36,478.46
4,374.89
4,913.90
7,801.59
3,491.52
1,346.04
15,548.08
6,575.71
1,410.50
544.20
1,955.10
5,424.96
1.05
6,733.33
5,154.28
14,230.19
1,512.43
14,179.40
9,852.32
11,912.51
1,906.00
3,776.91
1,485.04
11,183.95
1,020.53
1,089.90
817.45
3,448.91
5,461.50
12,069.79
3,223.67
31,711.66
3,938.34
16,110.88
5,307.01
6,012.87
3,487.19
4,371.09
1,154.35
4,719.17
11,617.98
959.21
1.05
27,732.33
63,692.23
4,141.58
11,988.48
3,856.89
6,907.85
18,708.78
51,521.11
12,520.79
14,711,843.43
PROYECTO: RESID
PRESUPUESTO: EDIFICIO 20 APARTAMENTOS DE TRES (3
ESTIMACION No. 35 DEL 01 A
OBRA CON
No. CONCEPTO UNIDAD
No. CONCEPTO UNIDAD
1.- PRELIMINARES
1.1 Limpieza del Lote M2
1.2 Marcacion y Nivelacion S.G.
1.3 Rellenos en Lote M3
2.- EXCAVACIONES
2.1 Excavacion para cimientos y Muros M3
2.2 Excavacion para Tuberias de Aguas Negras y Drenaje M3
2.3 Excavacion para Tuberias de Agua Potable M3
4.- CIMENTACIONES
4.1 Firme Concreto Zapatas DE Columnas y Muros M2
4.2 Concreto Reforzado Zapatas Corridas y Aisladas M3
4.3 Concreto Reforzado Pedestales M3
4.4 Concreto Reforzado Vigas de Cimentacion M3
4.5 Muros de Concreto M3
5.- ESTRUCTURA
5.1 Concreto Reforzado Columnas M3
5.2 Concreto Reforzado Vigas Entrepiso M3
5.3 Concreto Reforzado Losas Entrepiso M2
5.4 Concreto Reforzado en Cubo Elevadores (Zapatas,Vigas losa,etc.) M3
5.5 Tanque Elevado Agua Potable UND
6.- PAREDES
6.1 Paredes de Ladrillo M2
6.2 Castillos M3
6.3 Cargadores Puertas y Ventanas M.L.
6.4 Batientes de Ventanas M.L.
6.5 Paredes Cubo Elevadores M2
7.- GRADAS
7.1 Concreto Reforzado M3
7.2 Barandales M.L.
7.3 Piso en Gradas (Contrahuellas) M2
7.4 Zocalo en Gradas M.L.
7.5 Stuco en Gradas M2
8.- TECHO
8.1 Techo Viga Vista, Machimbre y Lamina acanalada standard color rojo M2
8.2 Canales Aguas Lluvias M.L.
9.- PISOS
9.1 Conformacion Terreno P.B. M2
9.2 Relleno Material Selecto P.B. M3
9.3 Firme de Concreto M2
9.4 Piso de Ceramica M2
9.5 Piso de Ceramica Antiderrapante M2
9.6 Moldura de Ceramica M.L.
9.7 Moldura de Ceramica Antiderrapante M.L.
9.8 Piso en Duchas M2
9.9 Bordillo en Duchas M.L.
9.10. Desniveles de Concreto M2
10.- ACABADOS
10.1 Repello y Pulido Paredes Interiores M2
10.2 Repello Pulido Paredes Fachadas M2
10.3 Stuco en Losa M2
10.4 Enchape de Ceramica (Baños y Cocina) M2
10.5 Pintura en Paredes Pulidas Interiores M2
10.6 Cielo Tabla-Yeso baños y cocina M2
10.7 Pintura Cielos Tabla-Yeso M2
10.8 Pintura Fachadas M2
10.9 Pintura Cielo de Machimbre M2
11.- PUERTAS
11.1 P-01 .-Puerta Principal UND
11.2 P-02.- Puertas Dormitorios UND
11.3 P-03.- Baños,Lavanderia,Pileta de Aseo y Azotea UND
11.4 P-04.- Tragaluces UND
11.5 P/B.- Basurero UND
19.2 ESTRUCTURA
Concreto Reforzado Columnas M3
Concreto Reforzado Castillos M3
Concreto Reforzado Vigas Entrepiso M3
Concreto Reforzado Losa Entrepiso M3
19.3 GRADAS
Excavacion
Concreto Zapatas y Pedestales M3
Concreto Reforzado Gradas M3
Barandal M.L
Piso en Gradas (Huellas y Contrahuellas)
Stuco en Gradas M2
Refuerzo Kg
Formas M2
19.4 BARDAS
Excavacion M3
Concreto Reforzado Zapatas Barda M3
Concreto Reforzado Viga Cimentacion Bardas M3
Castillos Barandal M3
Paredes Barda 6" M2
Paredes Barda 4" M2
Concreto Solera Superior Bardas M3
Repello Bardas M2
Pintura Bardas M2
19.5 PAVIMENTO
Conformacion Terreno M2
Material Sub-Base M3
Pavimento Concreto 15cms M2
Bordillos M.L.
Aceras M2
Pintura Estacionamiento M.L.
Topes Unds
Jardineras S.G
PREPARO:_____________________
Ing. Pedro Morales h.
Mes de Enero/15 no se cobro nada
Mes de Marzo/15 no se cobro nada
Mes de Abril/15 no se cobro nada
Mes de Mayo/15 no se cobro nada
Mes Junio/15 no se cobro nada
Mes de Julio/15 no se cobro nada
Mes de Agosto/15 no se cobro nada
Mes de Septiembre/15 no se cobro nada
PROYECTO: RESIDENCIAL VENECIA
ARTAMENTOS DE TRES (3) DORMITORIOS LOTES Nos. 44 y 45 DEL BLOQUE No.10
CION No. 35 DEL 01 AL 28 DE FEBRERO DEL 2015.
REVISO:_______________________ APROBO:____________________
Lic. Andres Salinas Ing. Felix Adrian Lobo
Inmobiliaria Los Robles Gerente General
QUE No.10
27,912,037.82
_______________
Felix Adrian Lobo
erente General