CRONOGRAMA VALORIZADO

: MEJORAMIENTO DE LA TRANSITABILIDAD EN LA CARRETERA VECINAL RUTA N° PI-523: EMP. PI-102 - EMP. PI-101 (EL ARENAL), TRAMO DV. PUEBLO NUEVO (SAN LUCAS)
PROYECTO
- EMP. PI-101 (EL ARENAL) - PROVINCIA DE PAITA – PIURA. Código SNIP N° 213907.
UBICACIÓN : DISTRITO: EL ARENAL - PROVINCIA: PAITA - DEPARTAMENTO: PIURA
CLIENTE : GOBIERNO REGIONAL PIURA
PLAZO DE EJECUCION : 180 DIAS CALENDARIOS FECHA: JULIO - 2017

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES ACUMULADO %

01 TRABAJOS PRELIMINARES 354,474.21 159,159.03 95,420.70 22,567.32 16,925.49 16,925.49 43,476.18 354,474.21 100%
01.01 CARTEL DE OBRA 3.60x7.20 und 2.00 2,032.08 4,064.16 4,064.16 - - - - - 4,064.16 100%
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS glb 1.00 55,440.00 55,440.00 27,720.00 - - - - 27,720.00 55,440.00 100%
01.03 TOPOGRAFIA Y GEOREFERENCIACION km 4.23 5,528.68 23,386.32 4,677.26 4,677.26 4,677.26 3,507.95 3,507.95 2,338.64 23,386.32 100%
01.04 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL glb 1.00 89,450.28 89,450.28 13,417.54 17,890.06 17,890.06 13,417.54 13,417.54 13,417.54 89,450.28 100%
01.05 CAMPAMENTOS glb 1.00 182,133.45 182,133.45 109,280.07 72,853.38 - - - - 182,133.45 100%
02 MOVIMIENTO DE TIERRAS 2,241,795.83 286,157.81 849,355.51 620,269.50 486,013.01 - - 2,241,795.83 100%
02.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS ha 0.60 4,208.26 2,524.96 1,767.47 757.49 - - - - 2,524.96 100%
02.02 EXCAVACION CLASIFICADA - MATERIAL SUELTO m3 53,209.97 6.33 336,819.11 101,045.73 101,045.73 101,045.73 33,681.92 - - 336,819.11 100%
02.03 TERRAPLENES-MATERIAL PROPIO m3 880.24 13.21 11,627.97 4,651.19 4,651.19 2,325.59 - - - 11,627.97 100%
02.04 TERRAPLENES-MATERIAL PROPIO TRANSPORTADO m3 31,045.74 16.67 517,532.49 155,259.75 207,013.00 103,506.50 51,753.24 - - 517,532.49 100%
02.05 TERRAPLENES-MATERIAL PRESTAMO DE CANTERA m3 31,072.91 41.23 1,281,136.08 - 512,454.43 384,340.82 384,340.83 - - 1,281,136.08 100%
02.06 OBRAS DE ENCAUZAMIENTO DE RIOS Y QUEBRADAS m3 1,084.40 12.95 14,042.98 - - 5,617.19 8,425.79 - - 14,042.98 100%
02.07 CONFORMACION Y ACOMODO EN DME m3 21,283.99 3.67 78,112.24 23,433.67 23,433.67 23,433.67 7,811.23 - - 78,112.24 100%
03 PAVIMENTOS 3,333,857.54 - 215,075.02 440,923.27 1,000,157.27 1,005,686.65 672,015.33 3,333,857.54 100%
03.01 SUB BASE GRANULAR m3 9,972.08 46.79 466,593.62 - 93,318.72 93,318.72 139,978.09 139,978.09 - 466,593.62 100%
03.02 BASE GRANULAR m3 8,160.61 74.60 608,781.51 - 121,756.30 121,756.30 182,634.45 182,634.45 0.01 608,781.51 100%
03.03 IMPRIMACION ASFALTICA. m2 45,529.73 4.25 193,501.35 - - 19,350.14 58,050.41 58,050.41 58,050.39 193,501.35 100%
03.04 PAVIMENTO DE CONCRETO ASFALTICO EN CALIENTE (MAC) m3 3,133.38 641.38 2,009,687.26 - - 200,968.73 602,906.18 602,906.18 602,906.17 2,009,687.26 100%
03.05 SELLADO DE SOBRE ANCHOS TSM m2 7,125.49 7.76 55,293.80 - - 5,529.38 16,588.14 22,117.52 11,058.76 55,293.80 100%
04 OBRAS DE ARTE Y DRENAJE 1,796,133.30 14,451.13 370,959.61 498,983.01 518,921.06 292,655.61 100,162.88 1,796,133.30 100%
04.01 ALCANTARILLAS 771,868.44 14,451.13 212,019.88 236,191.27 260,297.54 48,908.62 - 771,868.44 100%
04.01.01 ALCANTARILLAS CON TUBERIA METALICA CORRUGADA TMC 210,936.74 5,861.71 46,978.16 48,838.09 60,350.16 48,908.62 - 210,936.74 100%
04.01.01.01 TRAZO, NIVELES Y REPLANTEO m2 790.76 3.18 2,514.62 502.92 754.39 754.39 502.92 - - 2,514.62 100%
04.01.01.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 737.60 14.88 10,975.49 2,195.10 3,292.65 3,292.65 2,195.09 - - 10,975.49 100%
04.01.01.03 NIVELACION Y COMPACTACION DE TERRENO m2 790.76 4.15 3,281.65 656.33 984.50 984.50 656.33 (0.01) - 3,281.65 100%
04.01.01.04 RELLENOS PARA ESTRUCTURAS - MATERIAL PROPIO m3 207.63 31.06 6,448.99 1,289.80 1,934.70 1,934.70 1,289.80 (0.01) - 6,448.99 100%
04.01.01.05 RELLENO COMPACTADO PARA ESTRUCTURAS CON MAT. HORMIGON m3 67.68 89.95 6,087.82 1,217.56 1,826.35 1,826.35 1,217.56 - - 6,087.82 100%
04.01.01.06 CONCRETO ESTRUCTURAL CLASE G (140Kg/cm2+30%PM, Cimentación ym3
Solado) 54.03 344.24 18,599.29 - 5,579.79 7,439.72 5,579.79 (0.01) - 18,599.29 100%
04.01.01.07 CONCRETO ESTRUCTURAL CLASE D (210Kg/cm2) m3 46.88 490.74 23,005.89 - 4,601.18 4,601.18 6,901.77 6,901.76 - 23,005.89 100%
04.01.01.08 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 241.24 72.89 17,583.98 - 3,516.80 3,516.80 5,275.19 5,275.19 - 17,583.98 100%
04.01.01.09 CONCRETO ESTRUCTURAL CLASE G (140Kg/cm2+30%PM, Aliviadero) m3 88.43 341.24 30,175.85 - 6,035.17 6,035.17 9,052.76 9,052.75 - 30,175.85 100%
04.01.01.10 TUBERIA METALICA CORRUGADA CIRCULAR DE DIAMETRO D= 36" ( 1 OJO
m ) 187.92 429.16 80,647.75 - 16,129.55 16,129.55 24,194.33 24,194.32 - 80,647.75 100%
04.01.01.11 TUBERIA METALICA CORRUGADA CIRCULAR DE DIAMETRO D= 36" ( 2 OJO
m ) 13.77 843.53 11,615.41 - 2,323.08 2,323.08 3,484.62 3,484.63 - 11,615.41 100%
04.01.02 ALCANTARILLAS TIPO MARCO CONCRETO ARMADO - MCA 560,931.70 8,589.42 165,041.72 187,353.18 199,947.38 (0.00) - 560,931.70 100%
04.01.02.01 TRAZO, NIVELES Y REPLANTEO m2 1,148.19 3.18 3,651.24 730.25 730.25 2,190.74 - - - 3,651.24 100%
04.01.02.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 2,356.88 14.88 35,070.37 7,014.07 7,014.07 21,042.22 - 0.01 - 35,070.37 100%
04.01.02.03 NIVELACION Y COMPACTACION DE TERRENO m2 1,018.19 4.15 4,225.49 845.10 845.10 2,535.29 - - - 4,225.49 100%
04.01.02.04 RELLENOS PARA ESTRUCTURAS - MATERIAL PROPIO m3 762.29 31.06 23,676.73 - 7,103.02 9,470.69 7,103.02 - - 23,676.73 100%
04.01.02.05 RELLENO COMPACTADO PARA ESTRUCTURAS CON MAT. HORMIGON m3 117.50 89.95 10,569.13 - 4,227.65 6,341.48 - - - 10,569.13 100%
04.01.02.06 CONCRETO ESTRUCTURAL CLASE F (140Kg/cm2) m3 16.42 396.55 6,511.35 - 1,953.41 2,604.54 1,953.41 (0.01) - 6,511.35 100%
04.01.02.07 CONCRETO ESTRUCTURAL CLASE C (280Kg/cm2) m3 355.88 574.15 204,328.50 - 61,298.55 61,298.55 81,731.40 - - 204,328.50 100%

Página 1
CRONOGRAMA VALORIZADO

: MEJORAMIENTO DE LA TRANSITABILIDAD EN LA CARRETERA VECINAL RUTA N° PI-523: EMP. PI-102 - EMP. PI-101 (EL ARENAL), TRAMO DV. PUEBLO NUEVO (SAN LUCAS)
PROYECTO
- EMP. PI-101 (EL ARENAL) - PROVINCIA DE PAITA – PIURA. Código SNIP N° 213907.
UBICACIÓN : DISTRITO: EL ARENAL - PROVINCIA: PAITA - DEPARTAMENTO: PIURA
CLIENTE : GOBIERNO REGIONAL PIURA
PLAZO DE EJECUCION : 180 DIAS CALENDARIOS FECHA: JULIO - 2017

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES ACUMULADO %

04.01.02.08 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 1,179.74 72.89 85,991.25 - 25,797.38 25,797.38 34,396.50 (0.01) - 85,991.25 100%
04.01.02.09 ACERO DE REFUERZO (fy=4,200 Kg/cm2). kg 29,624.61 4.85 143,679.36 - 43,103.81 43,103.81 57,471.74 - - 143,679.36 100%
04.01.02.10 CONCRETO ESTRUCTURAL CLASE G (140Kg/cm2+30%PM, Aliviadero) m3 126.68 341.24 43,228.28 - 12,968.48 12,968.48 17,291.31 0.01 - 43,228.28 100%
04.02 PONTON DE CONCRETO ARMADO 523,450.46 - 158,939.73 162,628.86 108,379.20 93,502.67 - 523,450.46 100%
04.02.01 TRAZO, NIVELES Y REPLANTEO m2 502.56 3.18 1,598.14 - 639.26 639.26 319.62 - - 1,598.14 100%
04.02.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,101.93 14.88 16,396.72 - 6,558.69 6,558.69 3,279.34 - - 16,396.72 100%
04.02.03 NIVELACION Y COMPACTACION DE TERRENO m2 253.25 4.15 1,050.99 - 420.40 420.40 210.20 (0.01) - 1,050.99 100%
04.02.04 RELLENOS PARA ESTRUCTURAS - MATERIAL PROPIO m3 864.35 31.06 26,846.71 - 8,054.01 10,738.68 8,054.01 0.01 - 26,846.71 100%
04.02.05 CONCRETO ESTRUCTURAL CLASE F (140Kg/cm2) m3 25.33 396.55 10,044.61 - 3,013.38 4,017.84 3,013.38 0.01 - 10,044.61 100%
04.02.06 CONCRETO ESTRUCTURAL CLASE D (210Kg/cm2) m3 252.45 490.74 123,887.31 - 37,166.19 37,166.19 24,777.46 24,777.47 - 123,887.31 100%
04.02.07 CONCRETO ESTRUCTURAL CLASE C (280Kg/cm2) m3 155.35 574.15 89,194.20 - 26,758.26 26,758.26 17,838.84 17,838.84 - 89,194.20 100%
04.02.08 ENCOFRADO Y DESENCOFRADO NORMAL m2 117.94 54.05 6,374.66 - 1,912.40 1,912.40 1,274.93 1,274.93 - 6,374.66 100%
04.02.09 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 864.22 72.89 62,993.00 - 18,897.90 18,897.90 12,598.60 12,598.60 - 62,993.00 100%
04.02.10 ACERO DE REFUERZO (fy=4,200 Kg/cm2). kg 38,157.55 4.85 185,064.12 - 55,519.24 55,519.24 37,012.82 37,012.82 - 185,064.12 100%
04.03 CUNETAS REVESTIDAS CON CONCRETO 500,814.40 - - 100,162.88 150,244.32 150,244.32 100,162.88 500,814.40 100%
04.03.01 CUNETA TRIANGULAR 2.00 x 0.50 M, CONCRETO F'C=175 kg/cm2 m 1,160.00 276.89 321,192.40 - - 64,238.48 96,357.72 96,357.72 64,238.48 321,192.40 100%
04.03.02 CUNETA TRIANGULAR 1.60 x 0.40 M, CONCRETO F'C=175 kg/cm2 m 900.00 199.58 179,622.00 - - 35,924.40 53,886.60 53,886.60 35,924.40 179,622.00 100%
05 OBRAS COMPLEMENTARIAS 69,365.24 40,256.04 - - - 26,002.33 3,106.87 69,365.24 100%
05.01 REMOCION DE EDIFICACIONES, CERCOS Y/U OTROS m2 4,000.00 3.69 14,760.00 14,760.00 - - - - - 14,760.00 100%
05.02 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 100.00 247.18 24,718.00 24,718.00 - - - - - 24,718.00 100%
05.03 DEMOLICION Y REPOSICION DE NICHOS EXISTENTES und 4.00 194.51 778.04 778.04 - - - - - 778.04 100%
05.04 BARANDAS METALICAS H=1.10 m m 38.40 404.54 15,534.34 - - - - 12,427.47 3,106.87 15,534.34 100%
05.05 JUNTA METALICA e=0.05 m m 47.68 162.05 7,726.54 - - - - 7,726.54 - 7,726.54 100%
05.06 APOYO DE NEOPRENO GRADO 60 DE 0.50 x 0.30 x 0.025 m und 8.00 649.14 5,193.12 - - - - 5,193.12 - 5,193.12 100%
05.07 TUBERIA PVC PARA DRENAJE D=3" und 16.00 40.95 655.20 - - - - 655.20 - 655.20 100%
06 TRANSPORTE 2,328,198.92 184,673.43 393,943.26 665,719.82 561,425.58 424,217.28 98,219.55 2,328,198.92 100%
06.01 TRANSPORTE DE MATERIAL PROPIO D<=1 km m3k 27,320.25 6.82 186,324.11 46,581.03 46,581.03 55,897.23 37,264.82 - 186,324.11 100%
06.02 TRANSPORTE DE MATERIAL PROPIO D>1 km m3k 7,358.12 1.02 7,505.28 1,876.32 1,876.32 2,251.58 1,501.06 - 7,505.28 100%
06.03 TRANSPORTE DE MATERIAL GRANULAR D<=1 km m3k 29,049.82 6.82 198,119.77 29,717.97 29,717.97 59,435.93 39,623.95 39,623.95 198,119.77 100%
06.04 TRANSPORTE DE MATERIAL GRANULAR D>1 km m3k 412,183.42 1.15 474,010.93 71,101.64 71,101.64 142,203.28 94,802.19 94,802.18 474,010.93 100%
06.05 TRANSPORTE DE MATERIAL PARA BASE Y SUB BASE D<=1 km m3k 15,956.76 6.82 108,825.10 - 21,765.02 32,647.53 32,647.53 21,765.02 - 108,825.10 100%
06.06 TRANSPORTE DE MATERIAL PARA BASE Y SUB BASE D>1 km m3k 663,306.93 1.28 849,032.87 - 169,806.57 254,709.86 254,709.86 169,806.58 - 849,032.87 100%
06.07 TRANSPORTE DE MEZCLA ASFALTICA D<=1 km m3k 2,757.38 7.32 20,184.02 - - 4,036.80 4,036.80 6,055.21 6,055.21 20,184.02 100%
06.08 TRANSPORTE DE MEZCLA ASFALTICA D>1 km m3k 217,882.61 1.41 307,214.48 - - 61,442.90 61,442.90 92,164.34 92,164.34 307,214.48 100%
06.09 TRANSPORTE DE MATERIAL EXCEDENTE D<=1 km m3k 24,785.61 6.82 169,037.86 33,807.57 50,711.36 50,711.36 33,807.57 - - 169,037.86 100%
06.10 TRANSPORTE DE MATERIAL EXCEDENTE D>1 km m3k 6,908.26 1.15 7,944.50 1,588.90 2,383.35 2,383.35 1,588.90 - - 7,944.50 100%

Página 2
CRONOGRAMA VALORIZADO

: MEJORAMIENTO DE LA TRANSITABILIDAD EN LA CARRETERA VECINAL RUTA N° PI-523: EMP. PI-102 - EMP. PI-101 (EL ARENAL), TRAMO DV. PUEBLO NUEVO (SAN LUCAS)
PROYECTO
- EMP. PI-101 (EL ARENAL) - PROVINCIA DE PAITA – PIURA. Código SNIP N° 213907.
UBICACIÓN : DISTRITO: EL ARENAL - PROVINCIA: PAITA - DEPARTAMENTO: PIURA
CLIENTE : GOBIERNO REGIONAL PIURA
PLAZO DE EJECUCION : 180 DIAS CALENDARIOS FECHA: JULIO - 2017

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES ACUMULADO %

07 SEÑALIZACION Y SEGURIDAD VIAL 264,015.36 - - - - - 264,015.36 264,015.36 100%


07.01 SEÑAL PREVENTIVA 0.60 x 0.60 M und 28.00 787.18 22,041.04 - - - - - 22,041.04 22,041.04 100%
07.02 SEÑAL REGLAMENTARIA RECTANGULARES 0.60 x 0.90 M und 11.00 792.46 8,717.06 - - - - - 8,717.06 8,717.06 100%
07.03 SEÑALES INFORMATIVAS und 8.00 992.42 7,939.36 - - - - - 7,939.36 7,939.36 100%
07.04 POSTES DELINEADORES und 304.00 142.85 43,426.40 - - - - - 43,426.40 43,426.40 100%
07.05 TACHAS RETROREFLECTIVAS und 740.00 27.09 20,046.60 - - - - - 20,046.60 20,046.60 100%
07.06 MARCAS EN EL PAVIMENTO m2 1,513.92 16.96 25,676.08 - - - - - 25,676.08 25,676.08 100%
07.07 GUARDAVIAS METALICO m 731.52 183.15 133,977.89 - - - - - 133,977.89 133,977.89 100%
07.08 POSTES KILOMETRICOS und 5.00 181.99 909.95 - - - - - 909.95 909.95 100%
07.09 PINTADO DE PARAPETOS DE MUROS Y ALCANTARILLAS m2 65.49 19.56 1,280.98 - - - - - 1,280.98 1,280.98 100%
08 INTERFERENCIAS 370,387.24 118,701.69 186,386.28 52,569.67 - 3,818.88 8,910.72 370,387.24 100%
08.01 DUCTOS DE CONCRETO ( CRUCE CON TUBERIAS EXISTENTES) 128,950.77 118,701.69 10,249.08 - - - - 128,950.77 100%
08.01.01 TRAZO, NIVELES Y REPLANTEO m2 156.00 3.82 595.92 595.92 - - - - - 595.92 100%
08.01.02 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 293.85 15.82 4,648.71 4,648.71 - - - - - 4,648.71 100%
08.01.03 NIVELACION Y COMPACTACION DE TERRENO m2 156.00 3.30 514.80 514.80 - - - - - 514.80 100%
08.01.04 RELLENO COMPACTADO PARA ESTRUCTURAS CON MAT. PROPIO m3 29.85 35.60 1,062.66 - 1,062.66 - - - - 1,062.66 100%
08.01.05 RELLENO COMPACTADO PARA ESTRUCTURAS CON MAT. HORMIGON m3 264.00 95.67 25,256.88 25,256.88 - - - - - 25,256.88 100%
08.01.06 CONCRETO SIMPLE f´c = 100 kg/cm2 PARA SOLADO E=0.5 CM m2 156.00 32.10 5,007.60 5,007.60 - - - - - 5,007.60 100%
08.01.07 CONCRETO ESTRUCTURAL CLASE D (210Kg/cm2) m3 85.14 490.74 41,781.60 37,603.44 4,178.16 - - - - 41,781.60 100%
08.01.08 ENCOFRADO Y DESENCOFRADO DE DUCTO DE CONCRETO m2 695.40 55.63 38,685.10 34,816.59 3,868.51 - - - - 38,685.10 100%
08.01.09 ACERO DE REFUERZO (fy=4,200 Kg/cm2). kg 2,350.00 4.85 11,397.50 10,257.75 1,139.75 - - - - 11,397.50 100%
08.02 OTROS 241,436.47 - 176,137.20 52,569.67 - 3,818.88 8,910.72 241,436.47 100%
08.02.01 REPOSICION DE LOSA DE CONCRETO m2 90.00 141.44 12,729.60 - - - - 3,818.88 8,910.72 12,729.60 100%
08.02.02 REPOSICION DE LAS EDIFICACIONES m2 30.00 450.00 13,500.00 - 6,750.00 6,750.00 - - - 13,500.00 100%
08.02.03 REUBICACION DE TUBERIA DE AGUA POTABLE HACIA EL ARENAL DIAMETRO
m 800mm
30.00 926.10 27,783.00 - 19,448.10 8,334.90 - - - 27,783.00 100%
08.02.04 REUBICACION DE FIBRA OPTICA TELEFONIA PUBLICA m 1.00 187,423.87 187,423.87 - 149,939.10 37,484.77 - - - 187,423.87 100%
09 PLAN DE MANEJO SOCIO AMBIENTAL 371,710.65 71,911.99 60,154.89 43,423.98 46,303.98 53,243.98 96,671.83 371,710.65 100%
09.01 MONITOREO ARQUEOLOGICO 46,200.00 8,800.00 6,700.00 6,000.00 8,880.00 15,820.00 - 46,200.00 100%
09.01.01 EJECUCION DE PLAN DE MONITOREO ARQUEOLOGICO 40,700.00 8,800.00 6,700.00 6,000.00 8,880.00 10,320.00 - 40,700.00 100%
09.01.01.01 MONITOREO ARQUEOLOGICO mes 4.00 7,500.00 30,000.00 6,000.00 6,000.00 6,000.00 6,000.00 6,000.00 - 30,000.00 100%
09.01.01.02 PAGO DE SUPERVISION Y EVALUACION TECNICA DE CAMPO (MC) mes 1.00 3,500.00 3,500.00 2,800.00 700.00 - - - - 3,500.00 100%
09.01.01.03 HALLAZGOS ARQUEOLOGICOS EVENTUALES mes 1.00 7,200.00 7,200.00 - - - 2,880.00 4,320.00 - 7,200.00 100%
09.01.02 INFORME FINAL ARQUEOLOGICO 5,500.00 - - - - 5,500.00 - 5,500.00 100%
09.01.02.01 INFORME FINAL ARQUEOLOGICO und 1.00 5,500.00 5,500.00 - - - - 5,500.00 - 5,500.00 100%

Página 3
CRONOGRAMA VALORIZADO

: MEJORAMIENTO DE LA TRANSITABILIDAD EN LA CARRETERA VECINAL RUTA N° PI-523: EMP. PI-102 - EMP. PI-101 (EL ARENAL), TRAMO DV. PUEBLO NUEVO (SAN LUCAS)
PROYECTO
- EMP. PI-101 (EL ARENAL) - PROVINCIA DE PAITA – PIURA. Código SNIP N° 213907.
UBICACIÓN : DISTRITO: EL ARENAL - PROVINCIA: PAITA - DEPARTAMENTO: PIURA
CLIENTE : GOBIERNO REGIONAL PIURA
PLAZO DE EJECUCION : 180 DIAS CALENDARIOS FECHA: JULIO - 2017

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES ACUMULADO %

09.02 MITIGACION AMBIENTAL 290,472.41 45,592.87 35,935.77 37,423.98 37,423.98 37,423.98 96,671.83 290,472.41 100%
09.02.01 PROGRAMACION DE ABANDONO 290,472.41 45,592.87 35,935.77 37,423.98 37,423.98 37,423.98 96,671.83 290,472.41 100%
RESTAURACION DE AREAS AFECTADA POR CAMPAMENTOS, PATIO
09.02.01.01 m2 1,369.00 5.16 7,064.04 - - - - - 7,064.04 7,064.04 100%
DE MAQUINAS Y PLANTAS PROCESADORAS
09.02.01.02 RESTAURACION DE AREAS DE CANTERAS m2 8,949.33 4.70 42,061.85 - - - - - 42,061.85 42,061.85 100%
09.02.01.03 SELLADO DE LETRINAS und 5.00 678.60 3,393.00 - - - - - 3,393.00 3,393.00 100%
09.02.01.04 PROGRAMA DE EDUCACION Y CAPACITACION AMBIENTAL mes 6.00 3,950.00 23,700.00 3,792.00 3,792.00 4,029.00 4,029.00 4,029.00 4,029.00 23,700.00 100%
09.02.01.05 PROGRAMA DE SEÑALIZACION AMBIENTAL und 8.00 670.76 5,366.08 858.57 858.57 912.23 912.23 912.23 912.25 5,366.08 100%
09.02.01.06 PROGRAMA DE PREVENCION DE RIESGOS Y CONTINGENCIAS glb 1.00 16,775.00 16,775.00 2,684.00 2,684.00 2,851.75 2,851.75 2,851.75 2,851.75 16,775.00 100%
09.02.01.07 PROGRAMA DE SEGUIMIENTO Y VIGILANCIA mes 6.00 9,750.00 58,500.00 9,360.00 9,360.00 9,945.00 9,945.00 9,945.00 9,945.00 58,500.00 100%
09.02.01.08 PROGRAMA DE MONITOREO AMBIENTAL mes 6.00 7,000.00 42,000.00 6,720.00 6,720.00 7,140.00 7,140.00 7,140.00 7,140.00 42,000.00 100%
09.02.01.09 PROGRAMA DE MONITOREO SOCIO AMBIENTAL mes 6.00 4,100.00 24,600.00 3,936.00 3,936.00 4,182.00 4,182.00 4,182.00 4,182.00 24,600.00 100%
09.02.01.10 PROGRAMA DE MANEJO DE IMPACTOS SOCIALES mes 6.00 4,100.00 24,600.00 3,936.00 3,936.00 4,182.00 4,182.00 4,182.00 4,182.00 24,600.00 100%
09.02.01.11 PROGRAMA DE PREVENCIÓN Y CORRECCIÓN DE IMPACTOS mes 6.00 4,100.00 24,600.00 3,936.00 3,936.00 4,182.00 4,182.00 4,182.00 4,182.00 24,600.00 100%
09.02.01.12 CONSTRUCCION DE CELDA PARA RESIDUO glb 1.00 7,500.00 7,500.00 7,500.00 - - - - - 7,500.00 100%
09.02.01.13 REVEGETACION ha 1.03 6,532.95 6,728.94 - - - - - 6,728.94 6,728.94 100%
09.02.01.14 TALA Y RETIRO DE ARBOLES und 15.00 158.49 2,377.35 1,664.15 713.20 - - - - 2,377.35 100%
09.02.01.15 DESMONTAJE Y REPOSICION DE CERCO m 33.00 36.55 1,206.15 1,206.15 - - - - - 1,206.15 100%
09.03 PLAN DE COMPENSACION Y REASENTAMIENO INVOLUNTARIO - PACRI 35,038.24 17,519.12 17,519.12 - - - - 35,038.24 100%
09.03.01 ADQUISICION AREA AFECTADAS - TRAMITES INSCRIPCIONES Y EGISTROS
glb 1.00 27,600.00 27,600.00 13,800.00 13,800.00 - - - - 27,600.00 100%
09.03.02 ACTIVIDAD DURANTE EJECUCON DE OBRA - PROGRAMA DE CONTINGENCIA
glb 1.00 7,438.24 7,438.24 3,719.12 3,719.12 - - - - 7,438.24 100%
COSTO DIRECTO 11,129,938.29 875,311.12 2,171,295.27 2,344,456.57 2,629,746.39 1,822,550.22 1,286,578.72 11,129,938.29
GASTOS GENERALES VARIABLES (10.00%) 1,112,993.83 87,531.11 217,129.53 234,445.66 262,974.64 182,255.02 128,657.87 1,112,993.83
UTILIDAD (10.00%) 1,112,993.83 87,531.11 217,129.53 234,445.66 262,974.64 182,255.02 128,657.87 1,112,993.83

COSTO TOTAL 13,355,925.95 1,050,373.34 2,605,554.33 2,813,347.89 3,155,695.67 2,187,060.26 1,543,894.46 13,355,925.95
IGV (18.00%) 2,404,066.67 189,067.20 468,999.78 506,402.61 568,025.22 393,670.85 277,901.00 2,404,066.67

COSTO TOTAL GENERAL 15,759,992.62 1,239,440.54 3,074,554.11 3,319,750.50 3,723,720.89 2,580,731.11 1,821,795.46 15,759,992.62

% AVANCE MENSUAL 7.86% 19.51% 21.06% 23.63% 16.38% 11.56% 100.00%

% AVANCE ACUMULADO 7.86% 27.37% 48.44% 72.07% 88.44% 100.00%