Está en la página 1de 1

CRONOGRAMA DE ADQUISICION DE MATERIALES

: “MANTENIMIENTO RUTINARIO MECANIZADO DE LA CARRETERA DEPARTAMENTAL MO-105 TRAMO “EMP. MO-103 (YUNGA) – TASSA – QUERALA – PILLONE – MATAZO – HUANCARANE – QUINSACHATA - (L.D. AREQUIPA)”, PROVINCIA
FICHA TECNICA MARISCAL NIETO, REGION MOQUEGUA”.

FECHA JUNIO - 2019

Código DESCRIPCION UND CANTIDAD P.U. TOTAL MES 1 MES 2


CAPATAZ hh 219.81 S/.10.20 S/.2,242.06 1,121.03 1,121.03
OBRERO CALIFCADO A hh 1,166.05 S/.9.80 S/.11,427.29 5,713.65 5,713.65
OBRERO CALIFCADO B hh 532.75 S/.8.60 S/.4,581.65 2,290.83 2,290.83
OBRERO NO CALIFCADO hh 3,913.75 S/.7.50 S/.29,353.13 14,676.56 14,676.56
TOPOGRAFO hh 91.48 S/.10.50 S/.960.54 480.27 480.27
PREVENCIONISTA EN SEGURIDAD día 18.00 S/.83.33 S/.1,499.94 749.97 749.97
MONITOR AMBIENTALISTA día 45.00 S/.66.67 S/.3,000.15 1,500.08 1,500.08
GASOLINA 90 OCTANOS gal 90.00 S/.15.00 S/.1,350.00 675.00 675.00
PETROLEO B5 gal 3,650.05 S/.13.50 S/.49,275.68 24,637.84 24,637.84
CLAVOS PARA MADERA CON CABEZA DE 3" kg 2.00 S/.5.50 S/.11.00 11.00 -
PLASTICO DOBLE ANCHO m 50.00 S/.8.00 S/.400.00 400.00 -
GIGANTOGRAFIA CON MARCO METALICO und 7.20 S/.15.00 S/.108.00 108.00 -
CEMENTO PORTLAND TIPO IP (42.5 kg) bol 2.00 S/.23.00 S/.46.00 46.00 -
YESO BOLSA 28 kg bol 11.44 S/.25.00 S/.286.00 286.00 -
MADERA TORNILLO p2 20.00 S/.8.50 S/.170.00 170.00 -
ROLLIZOS DE EUCALIPTO DE Ø 3"X4M und 20.00 S/.20.00 S/.400.00 400.00 -
PINTURA ESMALTE gal 1.14 S/.35.00 S/.39.90 39.90 -
CASCO DE SEGURIDAD und 20.00 S/.20.00 S/.400.00 400.00 -
LENTES DE SEGURIDAD und 40.00 S/.10.00 S/.400.00 400.00 -
PROTECTOR DE OIDOS TIPO TAPON und 40.00 S/.2.50 S/.100.00 100.00 -
GUANTES DE CUERO par 50.00 S/.10.00 S/.500.00 500.00 -
GUANTES DE BADANA PARA OPERARIOS par 20.00 S/.10.00 S/.200.00 200.00 -
CHOMPA DE LANA TIPO JORGE CHAVEZ und 20.00 S/.25.00 S/.500.00 500.00 -
CORTAVIENTO PARA CASCO und 20.00 S/.12.00 S/.240.00 240.00 -
CAMISA MANGA LARGA DE SEGURIDAD und 20.00 S/.20.00 S/.400.00 400.00 -
PANTALON DE SEGURIDAD und 20.00 S/.45.00 S/.900.00 900.00 -
CHALECOS DE SEGURIDAD und 20.00 S/.15.00 S/.300.00 300.00 -
PANTALON DE LANA und 20.00 S/.25.00 S/.500.00 500.00 -
PASAMONTAÑ AZ DE LANA und 20.00 S/.5.00 S/.100.00 100.00 -
ZAPATOS DE SEGURIDAD par 20.00 S/.50.00 S/.1,000.00 1,000.00 -
MANTA ARPILLERA m 100.00 S/.8.00 S/.800.00 800.00 -
CONO DE SEÑ ALIZACION NARANJA DE 28" DE ALTURA und 4.00 S/.35.00 S/.140.00 140.00 -
HERRAMIENTAS MANUALES %mo S/.1,375.33 1,375.33 -
MANTENIMIENTO DE MAQUINARIAS glb 236.04 S/.10.00 S/.2,360.40 2,360.40 -
REPUESTOS PARA MAQUINARIAS glb 236.04 S/.10.00 S/.2,360.40 S/.2,360.40 -
RODILLO LISO VIBRATORIO AUTOPROPULSADO 10-12 TON hm 116.16 S/.150.00 S/.17,424.00 8,712.00 8,712.00
CARGADOR SOBRE LLANTAS DE 160-195 HP 3.5 yd3 hm 103.71 S/.145.00 S/.15,037.95 7,518.98 7,518.98
MOTONIVELADORA 130 - 135 HP hm 132.33 S/.160.00 S/.21,172.80 10,586.40 10,586.40
CAMION VOLQUETE DE 15 m3 330 HP hm 94.80 S/.110.00 S/.10,428.00 5,214.00 5,214.00
CAMION CISTERNA (5,000 GLNS.) hm 92.93 S/.160.00 S/.14,868.80 7,434.40 7,434.40
CAMION TIPO BARANDA (MINIMO 4TN) día 60.00 S/.150.00 S/.9,000.00 4,500.00 4,500.00
GRUPO ELECTROGENO 10 HP hm 180.00 S/.25.00 S/.4,500.00 2,250.00 2,250.00
SC MARCO CON ESTRUCTURAS METALICAS und 2.00 S/.150.00 S/.300.00 S/.300.00
SC SUMINISTRO, ADECUACION Y ACONDICIONAMIENTO DE CAMPAMENTO glb 2.00 S/.2,000.00 S/.4,000.00 S/.4,000.00
SC SUMINISTRO DE ALIMENTOS PARA PERSONAL DE OBRA mes 3.00 S/.5,760.00 S/.17,280.00 8,640.00 8,640.00
SC MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.00 S/.16,000.00 S/.16,000.00 8,000.00 8,000.00

TOTAL COSTO DIRECTO S/.247,739.01 S/.133,038.02 S/.114,700.99