HOJA DE METRADOS
PART. N° DESCRIPCION N° VECES MEDIDAS PARCIAL TOTAL UND.
LARGO ANCHO ALTO
2 ESTRUCTURAS
2.1 MOVIMIENTO DE TIERRAS
2.1.1 EXCAVACIONES
2.1.1.1 EXCAVACIONES SIMPLES 15.10 m3
VERTICALES
EJE A-A , ENTRE 1 Y 3 1 6.000 0.60 1.1 3.96
EJE A'-A' , ENTRE 1 Y 2 1 2.125 0.40 1.1 0.94
EJE B-B , , ENTRE 1 Y 3 1 6.000 0.60 1.1 3.96

HORIZONTAL
EJE 1-1 , ENTRE A Y B 1 3.40 0.60 1.1 2.24
CORTE 3-3
EJE 2-2, ENTRE A Y B 1 2.30 0.40 1.1 1.01
CORTE 5-5
EJE 2-2, ENTRE A Y B 1 1.10 0.40 1.1 0.48
CORTE 2-2
EJE 3-3, ENTRE A Y B 1 2.80 0.60 1.1 1.85
CORTE 4-4
EJE 3-3, ENTRE A Y B 1 1.00 0.60 1.1 0.66

2.1.2 RELLENOS
2.1.2.1 RELLENOS CON MATERIAL PROPIO 2.54 m3
VERTICALES
EJE A-A , ENTRE 1 Y 3 1 5.550 0.35 0.3 0.58
EJE A'-A' , ENTRE 1 Y 2 1 1.825 0.25 0.3 0.14
EJE A'-A' , ENTRE 1 Y 2 1 0.125 0.15 0.3 0.01
EJE B-B , , ENTRE 1 Y 3 1 5.550 0.35 0.3 0.58

HORIZONTAL
EJE 1-1 , ENTRE A Y B 1 3.40 0.45 0.3 0.46
CORTE 3-3
EJE 2-2, ENTRE A Y B 1 2.30 0.25 0.3 0.17
CORTE 5-5
EJE 2-2, ENTRE A Y B 1 1.10 0.25 0.3 0.08
CORTE 2-2
EJE 3-3, ENTRE A Y B 1 2.80 0.45 0.3 0.38
CORTE 4-4
EJE 3-3, ENTRE A Y B 1 1.00 0.45 0.3 0.14

2.1.4 ELIMINACION DE MATERIAL EXCEDENTE 14.92 m3


Volumen Excavado * (1+ esponjamiento (25%)) e=25% 18.88
Volumen Relleno Vrell*(1+ ESPONJAMIENTO (25%))^2 3.96
2.2 OBRAS DE CONCRETO SIMPLE
2.2.1 CIMIENTOS CORRIDOS
2.2.1.1 CONCRETO 1:10 + 30% PG 10.98 m3
VERTICALES
EJE A-A , ENTRE 1 Y 3 1 6.000 0.60 0.8 2.88
EJE A'-A' , ENTRE 1 Y 2 1 2.125 0.40 0.8 0.68
EJE B-B , , ENTRE 1 Y 3 1 6.000 0.60 0.8 2.88

HORIZONTAL
EJE 1-1 , ENTRE A Y B 1 3.40 0.60 0.8 1.63
CORTE 3-3
EJE 2-2, ENTRE A Y B 1 2.30 0.40 0.8 0.74
CORTE 5-5
EJE 2-2, ENTRE A Y B 1 1.10 0.40 0.8 0.35
CORTE 2-2
EJE 3-3, ENTRE A Y B 1 2.80 0.60 0.8 1.34
CORTE 4-4
EJE 3-3, ENTRE A Y B 1 1.00 0.60 0.8 0.48

2.2.4 SOBRECIMIENTOS
2.2.4.1 PARA EL CONCRETO 2.41 m2
VERTICALES
EJE A-A , ENTRE 1 Y 3 1 5.250 0.25 0.5 0.66
EJE A'-A' , ENTRE 1 Y 2 1 2.000 0.15 0.5 0.15
EJE B-B , , ENTRE 1 Y 3 1 5.250 0.25 0.5 0.66

HORIZONTAL
EJE 1-1 , ENTRE A Y B 1 4.35 0.15 0.5 0.33
CORTE 3-3
EJE 2-2, ENTRE A Y B 1 2.55 0.15 0.5 0.19
CORTE 5-5
EJE 2-2, ENTRE A Y B 1 1.80 0.15 0.4 0.11
CORTE 2-2
EJE 3-3, ENTRE A Y B 1 3.50 0.15 0.5 0.26
CORTE 4-4
EJE 3-3, ENTRE A Y B 1 1.00 0.15 0.4 0.06

2.3.4.2 ENCOFRADO Y DESENCOFRADO 25.14 m2


VERTICALES
EJE A-A , ENTRE 1 Y 3 2 5.250 0.5 5.25
EJE A'-A' , ENTRE 1 Y 2 2 2.000 0.5 2.00
EJE B-B , , ENTRE 1 Y 3 2 5.250 0.5 5.25

HORIZONTAL
EJE 1-1 , ENTRE A Y B 2 4.35 0.5 4.35
CORTE 3-3
EJE 2-2, ENTRE A Y B 2 2.55 0.5 2.55
CORTE 5-5
EJE 2-2, ENTRE A Y B 2 1.80 0.4 1.44
CORTE 2-2
EJE 3-3, ENTRE A Y B 2 3.50 0.5 3.50
CORTE 4-4
EJE 3-3, ENTRE A Y B 2 1.00 0.4 0.80

2.3.6.1 LOSAS ALIGERADAS CON VIGUETAS PREFABRICADAS


2.3.6.1.1 PARA EL CONCRETO 2.1375 m3

AREA POR VOLUMEN VOLUMEN


VOLUMEN DE CONCRETO
PAÑO POR PAÑO DE LADRILLO
TOTAL m3
PRIMER PISO 2.1375 m3
PAÑO A1 7.2 1.44 2.7675
PAÑO A2 17.325 3.465
TOTAL 4.905
2.3.6.1.2 PARA EL ENCOFRADO Y DESENCOFRADO 24.525 m2
PRIMER PISO 24.525 m2
PAÑO A1 7.2
PAÑO A2 17.325

2.3.6.1.3 PARA LA ARMADURA DE ACERO 135 kg


2.3.6.1.4 PARA EL LADRILLO , BLOQUES HUECOS (0.30x0.30x0.15) 205 Und
Area por Cantidad de
PRIMER PISO
paño m2 ladrillo REDONDEO
PAÑO A1 7.2 60.0 60
PAÑO A2 17.325 144.3 145