INGRESO DE DATOS :
P1 = 8.39
P2 = 9.75
sn = 5.80 tn/m2
AREA DE LA ZAPATA
Azap = 1.74 m2
LADOS ZAP. CUA. = 1.30 m
S= 1.50
VIGA DE CONECCION
h= 0.60 m
b= 0.30 m
RN(5.875) = P1 x L1 + Wv x (6.625^2)/2
RN = 10.75 tn
Az = 1.85 m2
Az = T x S
T= 1.25
X0 = P1u/(Wnu - Wvu)
X0 = 1.26 m COMFORME
ASUMIMOS "a" a= 12 cm
ASUMIMOS UN "d" A PARTIR DE "h" VIGA
d= 52.78 cm
As = 2.689
PRIMERA ITERACION
a= 2.531
As = 2.442
PRIMERA ITERACION
a= 2.298
As = 2.436 3.959
PRIMERA ITERACION
a= 2.293
r= 0.00250
r min= 0.00333 MAL
r max = 0.01594
r= 0.00500
r min= 0.00333 CONFORME
r max = 0.01594
3 Ф 5/8 ''
V1u = -2.47
V2u = 2.15
Vu/Ф = 3.30
Vc = 11.10 CONFORME
WNU = 11.251
Mumax = 1.14
w= 0.060
𝑊𝑁𝑈=𝑅𝑁𝑈/𝑇
Mu = Mumax
𝑀𝑢𝑚𝑎𝑥=𝑊𝑁𝑈 d = 9.39 cm
〖𝐿𝑣〗 ^2/2
USAREMOS h = 50 cm
ACERO = Ф 5/8 ''
d = 41.71 cm
Vud = 0.371 tn
Vn = 0.494 tn
Vc = 43.862 CONFORME
As = 0.797
PRIMERA ITERACION
a= 0.150
As = 0.766
PRIMERA ITERACION
a= 0.144
As = 0.766 1.267
PRIMERA ITERACION
a= 0.144
r= 0.00020
r min= 0.00333 MAL
r max = 0.01594
r= 0.00348
r min= 0.00333 CONFORME
r max = 0.01594
P2 efectivo = -10.15 tn
P2u = 13.25 tn
P2u efectivo = -13.64 tn
AREA DE LA ZAPATA
Az = 1.75 m2
LADO (L) = 1.30 m
𝐴𝑠 𝑡𝑒𝑚𝑝=𝑝𝑚𝑖𝑛.𝑏.𝑡
LADOS CUADRADOS DE LA ZAPATA 1.3 x 1.3 m2
Az = 1.69 m2
Wnu = 8.07 tn/m2
Lv = 0.48 m
SE USARA hmin = 50 cm
ACERO = Ф 5/8 ''
d= 44.0875
m= 1.10 m
n= 0.79 m
Vu = 6.65 tn
Vn = 8.86 tn
bo = 1.89 m
𝐿𝑣=((𝑆−𝑡2))/2
Vc = 116.615 tn
Vc > Vn COMFORME
Vud = 0.36 tn
Vn = 0.48 tn
Vc = 40.184 tn
Vc > Vn COMFORME
As = 0.603
PRIMERA ITERACION
a= 0.131
As = 0.579
PRIMERA ITERACION
a= 0.126
As = 0.579 1.267
PRIMERA ITERACION
a= 0.126
r= 0.00022
r min= 0.00333 MAL
r max = 0.01594
r= 0.00345
r min= 0.00333 CONFORME
r max = 0.01594
INGRESO DE DATOS :
P1 = 10.15
P2 = 11.84
sn = 5.80 tn/m2
AREA DE LA ZAPATA
Azap = 2.10 m2
LADOS ZAP. CUA. = 1.45 m
Usar S = 1.50
ASUMIMOS 1.50
VIGA DE CONECCION
h= 0.60 m
b= 0.30 m
RN(5.875) = P1 x L1 + Wv x (6.625^2)/2
RN = 12.67 tn
2
Az = 2.18 m
Az = T x S
T= 1.45
P1u = 13.01 tn
Wvu = 0.5184 tn/m
X0 = P1u/(Wnu - Wvu)
X0 = 1.27 m COMFORME
ASUMIMOS "a" a= 12 cm
ASUMIMOS UN "d" A PARTIR DE "h" VIGA
d= 52.78 cm
As = 3.206
PRIMERA ITERACION
a= 3.017
As = 2.925
PRIMERA ITERACION
a= 2.753
As = 2.917 3.800
PRIMERA ITERACION
a= 2.746
DISTRIBUCION DE ACERO F = 1/2 ''
USAR 3
r= 0.00240
r min= 0.00333 MAL
r max = 0.01594
4 Ф 5/8 ''
3 Ф 5/8 ''
V1u = -3.02
V2u = 2.32
Vu/Ф = 4.02
Vc = 11.10 CONFORME
ESTRIBO = Ф 3/8 '' @ 22.50 cm
ESTRIBO = Ф 3/8 '' 1@5+ 3 @ 10 + 5 @ 15 Rto @ 22.50 cm
WNU = 11.111
𝐿𝑣=((𝑆−𝑡2))/2
𝑀𝑢𝑚𝑎𝑥=𝑊𝑁𝑈
〖𝐿𝑣〗 ^2/2
𝑀𝑢𝑚𝑎𝑥=𝑊𝑁𝑈
〖𝐿𝑣〗 ^2/2
Mumax = 1.39
w= 0.058
Mu = Mumax
d = 10.58 cm
d = 41.71 cm
DISEÑO POR CORTE
Vud = 0.922 tn
Vn = 1.229 tn
Vc = 43.862 CONFORME
As = 0.972
PRIMERA ITERACION
a= 0.183
As = 0.935
PRIMERA ITERACION
a= 0.176
As = 0.935 1.979
PRIMERA ITERACION
a= 0.176
r= 0.00032
r min= 0.00333 MAL
r max = 0.01594
r= 0.00443
r min= 0.00333 CONFORME
r max = 0.01594
𝐴𝑠 𝑡𝑒𝑚𝑝=𝑝𝑚𝑖𝑛.𝑏.𝑡
P2 efectivo = -12.08 tn
P2u = 15.43 tn
P2u efectivo = -15.65 tn
AREA DE LA ZAPATA
2
Az = 2.08 m
LADO (L) = 1.45 m
2
LADOS CUADRADOS DE LA ZAPATA 1.45 x 1.45 m
2
Az = 2.1025 m
Lv = 0.50 m
SE USARA hmin = 50 cm
ACERO = Ф 1/2 ''
d= 43.77
VERIFICACION POR PUNZONAMIENTO
m= 1.17 m
n= 0.89 m
Vu = 7.92 tn
Vn = 10.57 tn
bo = 3.2254 m
Vc = 197.963 tn
Vc > Vn COMFORME
Vud = 0.67 tn
Vn = 0.90 tn
Vc = 44.498 tn
Vc > Vn COMFORME
As = 0.620
PRIMERA ITERACION
a= 0.121
As = 0.596
PRIMERA ITERACION
a= 0.116
As = 0.596 1.267
PRIMERA ITERACION
a= 0.116
DISTRIBUCION DE ACERO F = 1/2 ''
USAR 1
r= 0.00020
r min= 0.00333 MAL
r max = 0.01594
USAR As = 21.156 cm2
r= 0.00343
r min= 0.00333 CONFORME
r max = 0.01594