Está en la página 1de 16

E.

PRESU UNITARIU SERVISU

Tabela E – Analija Presu Unitariu Ba Kada Tipu Servisu

FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU
PROJETU : Reabilitasaun Estrada
PAKOTE :
ITEN PAGAMENTU : 1.2
TIPU SERVISU : Mobilizasaun
UNIDADE PAGAMENTU : Lump Sump (LS)
KUSTU ALUGA KUSTU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE KADA ORAS TOTAL KADA
(USD) VIAJEN (USD)

A EKIPAMENTU
Kodigu Kuantidade Deskrisaun Ekip.
1 E02 1 Aspal Finisher trip 1 86.33 86.33
2 E03 1 Aspal Sprayer trip 1 3.33 3.33
3 E04 2 Buldozer trip 1 45.53 91.06
4 E05 2 Air Compresor trip 1 13.71 27.42
5 E06 10 Concrete mixer trip 1 5.17 51.68
6 E08 20 Dump truck trip 1 34.30 686.02
7 E09 2 Excavator trip 1 50.27 100.54
8 E10 1 Generator set trip 1 44.64 44.64
9 E11 1 Motor Grader trip 1 41.66 41.66
10 E13 2 Whell Loader trip 1 42.82 85.63
11 E16 2 Tandem Roler trip 1 34.47 68.94
12 E17 1 Pneumatic Tire Roler trip 1 36.59 36.59
13 E18 2 Vibrator Roller trip 1 34.54 69.09
14 E19 4 Concrete Vibrator trip 1 1.96 7.82
15 E21 2 Water Tanker trip 1 34.30 68.60
16 E22 6 Tamper trip 1 2.34 14.05

TOTAL A 1,483.42

B FASILIDADE BASE CAMP


Kuantidade
1 1 Aluga rai ba base camp LS 1 900.00 900.00
2 1 Preparasaun Base Camp unit 1 1,200.00 1,200.00
3 1 Administrasaun no Dokumentasaun unit 1 5,629.68 5,629.68
4 1 Fatin Enkontru unit 1 2,955.58 2,955.58
5 1 Ofisina unit 1 1,266.67 1,266.67
6 1 Armajen unit 1 1,970.39 1,970.39
7 1 Selu-Seluk LS 1 750.00 750.00

TOTAL B 16,351.88
SOMATORIU HUSI (A + B ) 17,835.30
TOTAL PRESU UNITARIU SERVISU 17,835.30

FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 2.1
TIPU SERVISU : Hamo'os rai no normalijasaun rai
UNIDADE PAGAMENTU : ha

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Ajudante oras 15.873 0.65 10.31
2 Mandor oras 3.968 1.90 7.54

TOTAL 17.85

B MATERIAL
La presija Material - -

TOTAL -

C EKIPAMENTU
1 Buldozer 140 hp oras 3.9683 45.53 180.68
2 Wheel Loader, 1.5 m³ oras 10.6667 42.82 456.71
3 Dump Truck 5 Ton oras 20.0750 34.30 688.59
TOTAL 1,325.99
SOMATORIU HUSI (A + B + C) 1,343.84
TOTAL PRESU UNITARIU SERVISU 1,343.84

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 2.2
TIPU SERVISU : Preparasaun Estrada Lolon (Removal Existing Asphalt)
UNIDADE PAGAMENTU : ha

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Ajudante oras 0.0148 0.65 0.010
2 Mandor oras 0.0037 1.90 0.007

TOTAL 0.02

B MATERIAL
La presija Material - -

TOTAL -

C EKIPAMENTU
1 Hydraulic Excavator 1 m³ oras 0.0056 50.27 0.28
2 Wheel Loader, 1.5 m³ oras 0.0037 42.82 0.16
3 Dump Truck 5 Ton oras 0.0052 34.30 0.18
TOTAL 0.62
SOMATORIU HUSI (A + B + C) 0.63
TOTAL PRESU UNITARIU SERVISU 0.63

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 2.3
TIPU SERVISU :Servisu Ke'e Rai (Structural Excavation)
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Ajudante oras 0.096 0.65 0.06
2 Mandor oras 0.024 1.90 0.05

TOTAL 0.11

B MATERIAL
La presija Material - -

TOTAL -

C EKIPAMENTU
1 EXCAVATOR 1 m³ oras 0.024 50.27 1.21
TOTAL 1.21
SOMATORIU HUSI (A + B + C) 1.32
TOTAL PRESU UNITARIU SERVISU 1.32

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 2.4
TIPU SERVISU :Servisu Ateru rai (Structural Filling)
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Ajudante oras 0.042 0.65 0.03
2 Mandor oras 0.010 1.90 0.02

TOTAL 0.05

B MATERIAL
Material Ateru (tanah timbung) m³ 1.000 1.00 1.00

TOTAL 1.00

C EKIPAMENTU
1 Buldozer 140 hp oras 0.002 45.53 0.11
Vibrator Roller 7 ton oras 0.010 34.54 0.36

TOTAL 0.47
SOMATORIU HUSI (A + B + C) 1.52
TOTAL PRESU UNITARIU SERVISU 1.52

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 3.1
TIPU SERVISU :Servisu Ke'e Rai ba Drenajen
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Ajudante oras 0.0972 0.65 0.06
2 Mandor oras 0.0243 1.90 0.05

TOTAL 0.11

B MATERIAL
La presija Material - -

TOTAL -

C EKIPAMENTU
1 EXCAVATOR 1 m³ oras 0.0243 50.27 1.22
2 DUMP TRUCK oras 0.1102 34.30 3.78

TOTAL 5.00
SOMATORIU HUSI (A + B + C) 5.11
TOTAL PRESU UNITARIU SERVISU 5.11

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 3.2
TIPU SERVISU : Montajen Bueiru (RCPC Ø 800 mm- L2000 mm)
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Ajudante oras 0.004 0.65 0.003
Badaen Fatuk oras 0.170 1.27 0.216
2 Mandor oras 0.001 1.90 0.002

TOTAL 0.22

B MATERIAL
Bueiru/RCPC (Ø800 mm-L2000 mm) unit 1.000 300.80 300.80
Cement Portland kg 26.989 0.17 4.59
Rai-henek m³ 0.082 12.50 1.02
Back Fill (River Gravel Material) m³ 0.525 9.30 4.88

TOTAL 311.29

C EKIPAMENTU
1 TAMPER oras 0.007 2.34 0.02
2 DUMP TRUCK oras 0.085 34.30 2.91
C1 EKIPAMENTU AUXILIAR
1 Kanuru Boot LS 1.000 2.50 2.50
TOTAL 5.43
SOMATORIU HUSI (A + B + C) 316.94
TOTAL PRESU UNITARIU SERVISU 316.94

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 3.3
TIPU SERVISU : Montajen Fatuk ho Mortar (mekaniku)
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Mandor oras 0.578 1.90 1.10
2 Badaen Fatuk oras 2.600 1.27 3.31
3 Ajudante oras 5.200 0.65 3.38

TOTAL 7.79

B MATERIAL
Fatuk Mota m³ 1.14 26.100 29.86
Cement Portland kg 169.79 0.170 28.86
Rai-henek m³ 0.43 12.500 5.41

TOTAL 64.14

C EKIPAMENTU
1 Concrete Mixer oras 0.289 5.168 1.49
C1 Ekipamentu Auxiliar
1 Kanuru Boot Ls 1.00 2.500 2.50
2 Kanuru Kiik Ls 1.00 1.500 1.50
3 Balde Ls 1.00 1.000 1.00
4 Karosa Ls 1.00 30.000 30.00

TOTAL 36.49
SOMATORIU HUSI (A + B + C) 108.42
TOTAL PRESU UNITARIU SERVISU 108.42

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 4.1
TIPU SERVISU : Servisu Ke'e Rai Fundasaun Moru Suporte
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Ajudante oras 0.1632 0.65 0.11
2 Mandor oras 0.0408 1.90 0.08

TOTAL 0.18

B MATERIAL
La presija Material - -

TOTAL -

C EKIPAMENTU
1 EXCAVATOR 1 m³ oras 0.0408 50.27 2.05
2 DUMP TRUCK oras 0.1570 34.30 5.38

TOTAL 7.43
SOMATORIU HUSI (A + B + C) 7.62
TOTAL PRESU UNITARIU SERVISU 7.62

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 4.2
TIPU SERVISU : Servisu Montajen Gabion/Bronjong
UNIDADE PAGAMENTU : m²

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Ajudante oras 7.500 0.65 4.87
2 Badaen Fatuk oras 15.000 1.02 15.37

TOTAL 20.24

B MATERIAL
Bronjong/Gabion (2.00 m x 1.00 m x 1.00 m) unit 1.000 30.00 30.00
Arame Bronjong/Gabion kg 2.000 4.00 8.00
Fatuk Mota m³ 1.800 26.10 46.98

TOTAL 84.98

C EKIPAMENTU
1 DUMP TRUCK oras 0.025 34.30 0.84
C1 Ekipamentu Auxiliar
1 Alikate Arame LS 1.00 2.00 2.00
2 Tan Potong LS 1.00 2.00 2.00
TOTAL 4.84
SOMATORIU HUSI (A + B + C) 110.07
TOTAL PRESU UNITARIU SERVISU 110.07

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 4.3
TIPU SERVISU : Montajen Fatuk ho Mortar (mekaniku)
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Mandor oras 0.578 1.02 0.59
2 Badaen Fatuk oras 2.600 1.27 3.31
3 Ajudante oras 5.200 0.65 3.38

TOTAL 7.28

B MATERIAL
Fatuk Mota m³ 1.14 26.10 29.86
Cement Portland kg 169.79 0.17 28.86
Rai-henek m³ 0.43 12.50 5.41

TOTAL 64.14

C EKIPAMENTU
1 Concrete Mixer oras 0.289 5.17 1.49
C1 Ekipamentu Auxiliar
1 Kanuru Boot Ls 1.00 2.50 2.50
2 Kanuru Kiik Ls 1.00 1.50 1.50
3 Balde Ls 1.00 1.00 1.00
4 Karosa Ls 1.00 30.00 30.00

TOTAL 36.49
SOMATORIU HUSI (A + B + C) 107.91
TOTAL PRESU UNITARIU SERVISU 107.91

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 5.1
TIPU SERVISU : Konstrusaun Fundasaun Okos (Sub base preparation)
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Mandor oras 0.004 1.90 0.01
3 Ajudante oras 0.017 0.65 0.01

TOTAL 0.02

B MATERIAL
Agregate Sub Base m³ 1.00 52.20 52.20

TOTAL 52.20

C EKIPAMENTU
1 DUMP TRUCK Oras 0.522 34.30 17.90
2 Motor Grader >125 hp Oras 0.007 41.66 0.29
3 Water Tank Truck with Pump 5000 liter Oras 0.004 34.30 0.14
4 Tandem Roller Oras 0.009 34.47 0.31
5 Pneumatic Tire Roller 10 Ton Oras 0.006 36.59 0.22
C1 Ekipamentu Auxiliar
1 Kanuru Boot Ls 1.00 2.50 2.50

TOTAL 21.36
SOMATORIU HUSI (A + B + C) 73.58
TOTAL PRESU UNITARIU SERVISU 73.58

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 5.2
TIPU SERVISU : Konstrusaun Fundasaun Leten (Base Coarse Preparation)
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Mandor oras 0.004 1.90 0.01
3 Ajudante oras 0.017 0.65 0.01

TOTAL 0.02

B MATERIAL
Agregate Base Coarse m³ 1.00 52.20 52.20

TOTAL 52.20

C EKIPAMENTU
1 DUMP TRUCK Oras 0.522 34.30 17.90
2 Motor Grader >125 hp Oras 0.014 41.66 0.58
3 Water Tank Truck with Pump 5000 liter Oras 0.004 34.30 0.14
4 Tandem Roller Oras 0.018 34.47 0.62
5 Pneumatic Tire Roller 10 Ton Oras 0.012 36.59 0.43
C1 Ekipamentu Auxiliar
1 Kanuru Boot Ls 1.00 2.50 2.50

TOTAL 22.17
SOMATORIU HUSI (A + B + C) 74.39
TOTAL PRESU UNITARIU SERVISU 74.39

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 5.3
TIPU SERVISU : Prime Coat
UNIDADE PAGAMENTU : m²

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Mandor oras 0.002 1.90 0.00
3 Ajudante oras 0.015 0.65 0.01

TOTAL 0.01

B MATERIAL
Aspalt (Bidon 200 liter) Kg 0.657 17.20 11.31
Keroseniu/Mina rai Litru 0.363 2.00 0.73

TOTAL 12.03

C EKIPAMENTU
1 Asphalt Sprayer Oras 0.002 3.33 0.01
2 Air Compressor Oras 0.002 13.71 0.03
3 DUMP TRUCK Oras 0.036 34.30 1.22

TOTAL 1.26
SOMATORIU HUSI (A + B + C) 13.30
TOTAL PRESU UNITARIU SERVISU 13.30

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 5.4
TIPU SERVISU : Konstrusaun kamada superfisial (Surface Coarse Preparation)
UNIDADE PAGAMENTU : m³

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Mandor oras 0.001 1.90 0.00
3 Ajudante oras 0.011 0.65 0.01

TOTAL 0.01

B MATERIAL
1 Asphalt Concrete m³ 1.00 247.30 247.30

TOTAL 247.30

C EKIPAMENTU

1 Wheel Loader, 3 m³ Oras 0.0017 42.82 0.07


2 Asphalt Mixing Plant Oras 0.0045 523.70 2.35
3 Generator Set Oras 0.0045 44.64 0.20
4 Dump Truck 5 Ton Oras 0.1119 34.30 3.84
5 Asphalt Finisher, 4 m width Oras 0.0140 86.33 1.21
6 Tandem Roller 6-8 Ton Oras 0.0011 34.47 0.04
7 Pneumatic Tire Roller 10 Ton Oras 0.0018 36.59 0.07
C1 Ekipamentu Auxiliar
1 Sinais Tranzitu Ls 1.00 1.00 1.00
2 Karosa Ls 1.00 30.00 30.00
3 Kanuru boot Ls 1.00 2.50 2.50
4 Garfu dada rai Ls 1.00 2.50 2.50
5 Regua kontrolu espesura Ls 1.00 7.00 7.00

TOTAL 50.77
SOMATORIU HUSI (A + B + C) 298.08
TOTAL PRESU UNITARIU SERVISU 298.08
FOMULARIU PADRAUN
ANALIJA PRESU UNITARIU KADA TIPU SERVISU

PROJETU : Reabilitasaun Estrada


PAKOTE :
ITEN PAGAMENTU : 6.1
TIPU SERVISU : Markasaun Estrada (Thermoplastic Painting)
UNIDADE PAGAMENTU : m²

PRESU PRESU
No KOMPONENTE ANALIJA PRESU UNITARIU UNIDADE KOEFISIENTE UNITARIU UNITARIU
BAZIKU (USD) (USD)

A FORSA SERVISU
1 Mandor oras 0.098 1.90 0.19
2 Badaen oras 0.293 1.27
3 Ajudante oras 0.780 0.65 0.51

TOTAL 0.69

B MATERIAL
Tinta Termoplastika kg 4.10 20.60 84.36
Glass Bead kg 0.45 6.18 2.78

TOTAL 87.14

C EKIPAMENTU
1 Makina Pinta Oras 0.098 5.00 0.49
2 Dump Truck Oras 0.098 34.30 3.34
C1 EKIPAMENTU AUXILIAR
1 Metru Rollu 50 m Ls 1.00 15.00 15.00
2 Ai saar Kesak Ls 1.00 0.25 0.25
3 Ai saar Masa Ls 1.00 2.50 2.50
4 Sinais Tranzitu Seguransa Ls 1.00 1.00 1.00

TOTAL 22.58
SOMATORIU HUSI (A + B + C) 110.41
TOTAL PRESU UNITARIU SERVISU (USD) 110.41

Nota :
1 Unidade ba forsa servisu no ekipamentu pezadu bazeia ba oras operasaun, ba material bazeia volume no todan
2 Presu unitariu baziku ba iha ekipamentu pezadu inklui ona, kustu kombustivel, kustu operadores no seluk tan
3 Presu unitariu baziku husi komponente hirak ne'ebe iha inklui ona taxa de juros husi governu (exeptu taxa sira
ne'ebe iha kontratu nia laran).