MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE LA OROYA, PROVINCIA DE YAULI, DEPARTAMENTO DE JUNIN, DE ACUERDO

CON EL SIGUIENTE DETALLE:


SERVICIO:
1. CALLE IQUITOS - CUMBRE HUASQUI
2. ESTANCIA HUAYNACANCHA

ENTIDAD: MUNICIPALIDAD PROVINCIAL DE YAULI


REGIÓN: JUNÍN
PROVINCIA: YAULI
DISTRITO: LA OROYA

Item Descripción Und. Metrado Precio S/. Parcial S/.


1 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 S/ 105,961.12 S/ 105,961.12
1.02 TRAZO Y REPLANTEO KM 21.55 S/ 250.16 S/ 5,390.95
2 PAVIMENTOS
2.01 CAPA NIVELANTE E=0.05 M M3 3,371.25 S/ 9.26 S/ 31,217.78
2.02 MATERIAL GRANULAR DE CANTERA PARA AFIRMADO E=0.15 M M3 10,113.75 S/ 32.46 S/ 328,292.33
3 TRANSPORTE
3.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3K 10,751.50 S/ 10.52 S/ 113,105.78
3.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1 KM M3K 13,950.37 S/ 8.70 S/ 121,368.22
3.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3K 3,582.44 S/ 10.73 S/ 38,439.58
3.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM M3K 5,822.40 S/ 8.88 S/ 51,702.91
4 OBRAS DE ARTE Y DRENAJE
4.01 RECONFORMACION DE CUNETAS ML 21,550.00 S/ 1.22 S/ 26,291.00
5 SEÑALIZACION
5.01 INSTALACION DE POSTES KILOMETRICOS UND 23.00 S/ 254.72 S/ 5,858.56
5.02 SEÑALES PREVENTIVAS UND 38.00 S/ 202.40 S/ 7,691.20
5.03 SEÑALES REGLAMENTARIAS UND 5.00 S/ 347.68 S/ 1,738.40
5.04 SEÑALES INFORMATIVAS UND 7.00 S/ 764.35 S/ 5,350.45
6 IMPACTO AMBIENTAL
6.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA 1.72 S/ 2,000.00 S/ 3,440.00
7 EMERGENCIA SANITARIA
7.01 EMERGENCIA SANITARIA COVID 19 GLB 1.00 S/ 15,513.07 S/ 15,513.07
S/ 861,361.34
COSTO DIRECTO (CD)
GASTOS GENERALES 10% S/ 86,136.13
UTILIDAD 10% S/ 86,136.13
-----------------------------------
SUB TOTAL S/ 1,033,633.60
IGV 18% S/ 186,054.05
----------------------------------
COSTO DE LA EJECUCIÓN DEL MANTENIMIENTO PERIÓDICO 21.55 S/ 1,219,687.65
COSTO DEL SERVICIO PARA LA EJECUCIÓN DEL MANTENIMIENTO PERIÓDICO Y RUTINARIO

FASES DESCRIPCIÓN UND CANTIDAD PARCIAL TOTAL


FASE I Elaboración del Plan de Trabajo
Plan de Trabajo % 1 S/ 14,695.03 S/ 14,695.03
FASE II Ejecución del mantenimiento periódico
Ejecución del mantenimiento periódico KM 21.55 S/ 56,598.03 S/ 1,219,687.65
FASE III Ejecución del mantenimiento rutinario
Ejecución del mantenimiento rutinario x 12 meses KM 21.55 S/ 10,228.56 S/ 220,425.49
Inventario de Condición Vial % 1 S/ 14,695.03 S/ 14,695.03
TOTAL S/ 1,469,503.20
BIOSEGURIDAD (COVID-19)
MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE LA OROYA, PROVINCIA DE YA
ACUERDO CON EL SIGUIENTE DETALLE:
SERVICIO:
1. CALLE IQUITOS - CUMBRE HUASQUI
2. ESTANCIA HUAYNACANCHA

ENTIDAD: MUNICIPALIDAD PROVINCIAL DE YAULI


REGIÓN: JUNÍN
PROVINCIA: YAULI
DISTRITO: LA OROYA

ITEM DESCRIPCION PARTIDA UND. Nº VECES


1 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00
1.02 TRAZO Y REPLANTEO KM
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
2 PAVIMENTO
2.01 CAPA NIVELANTE E=0.05 M M3
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
2.02 MATERIAL GRANULAR DE CANTERA PARA ESTABILIZADO = 0.15 M M3
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
3 TRANSPORTE
3.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM M3K
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
3.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1KM M3K
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
3.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1KM M3K
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
3.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM M3K
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
4 OBRAS DE ARTE Y DRENAJE
2.02.01 RECONFORMACION DE CUNETAS ML.
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
5 SEÑALIZACION
5.01 INSTALACION DE POSTES KILOMETRICOS UND
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
5.02 SEÑALES PREVENTIVAS UND
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
5.03 SEÑALES REGLAMENTARIAS UND
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
5.04 SEÑALES INFORMATIVAS UND
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
6 IMPACTO AMBIENTAL
6.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA
1. YANEC - QUISHUAR- PUTACA 1.00
2. EMP. JU-543 (CHUPAN) - HUACAN 1.00
7 EMERGENCIA SANITARIA
7.01 EMERGENCIA SANITARIA COVID-19 GLB 1.00
O DE LA OROYA, PROVINCIA DE YAULI, DEPARTAMENTO DE JUNIN, DE

LARGO ANCHO ALTO SUB - TOTAL TOTAL

105,961.12 105,961.12
21.55
16.00 16.00
5.55 5.55

3,371.25
16,000.00 3.00 0.05 2,400.00
5,550.00 3.50 0.05 971.25
10,113.75
16,000.00 3.00 0.15 7,200.00
5,550.00 3.50 0.15 2,913.75

10,751.50
7,330.60
3,420.90
13,950.37
6,339.81
7,610.56
3,582.44
2,457.94
1,124.50
5,822.40
3,281.40
2,541.00

21,550.00
16,000.00 16,000.00
5,550.00 5,550.00

23.00
17.00 17.00
6.00 6.00
38.00
29.00 29.00
9.00 9.00
5.00
4.00 4.00
1.00 1.00
7.00
5.00 5.00
2.00 2.00

1.72
1.28 1.28
0.44 0.44

14,530.95 1.00
MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE LA OROYA, PROVINCIA DE
YAULI, DEPARTAMENTO DE JUNIN, DE ACUERDO CON EL SIGUIENTE DETALLE:
PROYECTO:
1. CALLE IQUITOS - CUMBRE HUASQUI
2. ESTANCIA HUAYNACANCHA

MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO HUANCAYO-OROYA

1.0 EQUIPO TRANSPORTADO


UNIDAD DESCRIPCIÓN DE MAQUINARIA CANTIDAD PESO EN KG OBSERVACIÓN
1.00 CARGADOR SOBRE LLANTAS 200-250 HP 4.1 YD3. 1.00 20,286.00 (2)
1.00 EXCAVADORA SOBRE ORUGAS 115-165 HP 0.750 - 1.6 YD3 1.00 23,400.00 (2)
1.00 MOTONIVELADORA 145 - 150 HP 1.00 13,540.00 (2)
1.00 RODILLO TANDEM VIBRATORIO AUTOPROPULSADO 111-130 HP 9-11 TON 1.00 8,000.00 (2)

COSTO EN SOLES
Nº Viajes VEHÍCULO COSTO ALQUILER
PESO TOTAL (KG) TIEMPO VIAJE (HRS) SUB TOTAL
(HM)
0 CAMION CAMA BAJA 18TON 248.45 S/. -
0 CAMION CAMA BAJA 19 TON 248.45 S/. -
3 CAMION CAMA BAJA 25 TON 41,826.00 22.00 300.50 S/. 27,766.20
1 CAMION CAMA BAJA 40 TON (Inc. Escolta) 8,000.00 22.00 420.50 S/. 12,951.40
SEGUROS DE CARGA DE MAQUINARIA 8143.52 S/. 8,143.52
FALSO FLETE S/. 48,861.12
TOTAL S/. (MOV Y DESMV. INCLUIDO FALSO FLETE) S/. 48,861.12
COTIZACIÓN SEGÚN REVISTA COSTOS
NOTA : (1) EQUIPO TRANSPORTADO EN VOLQUETES
(2) EQUIPO TRANSPORTADO EN CAMIÓN PLATAFORMA
(3) EQUIPO AUTOTRANSPORTADO
TRACTO Y CAMA BAJA PARA TRANSPORTE DE MAQUINARIA PESADA (PBM: 40 TON)

Intervalo de Capacidad : (30-40 Ton)

CÁLCULO DE DISTANCIA VIRTUAL (Dv)


ORIGEN - DESTINO Dr(Km) fc Dv(Km) Tipo de Pavimento
Huancayo-Junin (Asfaltado) 193.80 1.40 271.00 asfaltado
Junin-Z. descraga (afirmado) 17.00 2.80 48.00 afirmado

TIPO DE CARRETERA
REGIÓN ALTURA(m.s.n.m.)
ASFALTADO AFIRMADO SIN AFIRMAR
COSTA 0000 - 1000 1.00 1.58 2.15
INTERMEDIO 1000 - 2500 1.20 2.10 2.90
SIERRA Más de 2500 1.40 2.80 3.90

CÁLCULO DE HORAS DE VIAJE DE CAMA Distancia Velocidad TOTAL


BAJA Dv(Km) KM/HR Tiempo
Huancayo-Junin (Asfaltado) 271.00 35.00 9.00
Junin-Z. descraga (afirmado) 17.00 25.00 2.00
288.00 11.00

OBSERVACIONES:
LOS PRECIOS DE LOS EQUIPOS DE TRANSPORTE COMO CAMA BAJA SE HAN TOMADO DE LA REVISTA COSTOS,
ASUMIENDO QUE NO SE CUENTA CON ESTOS EQUIPOS EL SEMITRAILER SE TOMO DE REFERENCIA PRECIOS MTC P/HORA.
2.0 EQUIPO AUTOTRANSPORTADO
COSTO EN SOLES
CANTIDAD VEHÍCULO TIEMPO DE VIAJE
ALQ / HOR SUB TOTAL
IDA VUELTA
HUANCAYO - INGRESO 1. YANEC - QUISHUAR- PUTACA
1.00 CAMION CISTERNA 3,000 GAL (INC MOTOBOMBA) 8.00 8.00 150.00 S/. 2,400.00
4.00 CAMION VOLQUETE DE 15 M3 8.00 8.00 170.00 S/. 10,880.00
1. YANEC - QUISHUAR- PUTACA - 2. EMP. JU-543 (CHUPAN) - HUACAN
1.00 CAMION CISTERNA 3,000 GAL (INC MOTOBOMBA) 2.00 2.00 150.00 S/. 600.00
4.00 CAMION VOLQUETE DE 15 M3 2.00 2.00 170.00 S/. 2,720.00
2.01 EQUIPO AUTOTRANSPORTADO (ZONA DE DESCARGA - YANEC - CHUPAN)
Z. DESCARGA - CALLE IQUITOS YANEC-CASITA CINCO
1.00 CARGADOR SOBRE LLANTAS 200-250 HP 4.1 YD3. 3.00 5.00 250.00 S/. 2,000.00
1.00 EXCAVADORA SOBRE ORUGAS 115-165 HP 0.750 - 1.6 5.00 10.00 400.00 S/. 6,000.00
1.00 MOTONIVELADORA 145 - 150 HP 2.00 3.00 260.00 S/. 1,300.00
1.00 RODILLO TANDEM VIBRATORIO AUTOPROPULSADO 11 3.00 5.00 175.00 S/. 1,400.00
HUANCAYO - JUNIN JUNIN - OROYA - CURIPATA
1.00 CAMIONETA 4x4 3.00 2.00 250.00 S/. 1,250.00
TOTAL S/. 57,100.00

TOTAL
RESUMEN
1.0 EQUIPO TRANSPORTADO S/. 48,861.12
2.0 EQUIPO AUTOTRANSPORTADO S/. 57,100.00
TOTAL MOVILIZACION Y DESMOVILIZACION S/. 105,961.12

Distancia Velocidad TOTAL


CAMION CISTERNA
KM KM/HR Tiempo
Huancayo-Junin (Asfaltado) 193.80 40.00 6.00
Junin-Yanec 39.00 30.00 2.00
232.80 8.00
Yanec-Huacan 27.00 30.00 2.00
27.00 2.00

Distancia Velocidad TOTAL


CAMION VOLQUETE
KM KM/HR Tiempo
Huancayo-Junin (Asfaltado) 193.80 40.00 6.00
Junin-Yanec 39.00 30.00 2.00
232.80 8.00
Yanec-Huacan 27.00 30.00 2.00
27.00 2.00

CARGADOR SOBRE LLANTAS 200-250 HP 4.1 Distancia Velocidad TOTAL


YD3. KM KM/HR Tiempo
Z. descraga - Yanec 22.00 10.00 3.00
Yanec - Huacan - Z. descarga 44.00 10.00 5.00
66.00 8.00

EXCAVADORA SOBRE ORUGAS 115-165 HP Distancia Velocidad TOTAL


0.750 - 1.6 YD3 KM KM/HR Tiempo
Z. descraga - Yanec 22.00 5.00 5.00
Yanec - Huacan - Z. descarga 44.00 5.00 10.00
66.00 15.00

Distancia Velocidad TOTAL


MOTONIVELADORA 145 - 150 HP
KM KM/HR Tiempo
Z. descraga - Yanec 22.00 20.00 2.00
Yanec - Huacan - Z. descarga 44.00 20.00 3.00
66.00 5.00

RODILLO TANDEM VIBRATORIO Distancia Velocidad TOTAL


AUTOPROPULSADO 111-130 HP 9-11 TON KM KM/HR Tiempo
Z. descraga - Yanec 22.00 10.00 3.00
Yanec - Huacan - Z. descarga 44.00 10.00 5.00
66.00 8.00

Distancia Velocidad TOTAL


CAMIONETA 4X4
KM KM/HR Tiempo
Huancayo-Junin (Asfaltado) 193.80 60.00 3.00
Junin-Yanec-Huacan 66.00 40.00 2.00
259.80 5.00
MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE LA OROYA,
PROVINCIA DE YAULI, DEPARTAMENTO DE JUNIN, DE ACUERDO CON EL SIGUIENTE DETALLE:
PROYECTO :
1. CALLE IQUITOS - CUMBRE HUASQUI
2. ESTANCIA HUAYNACANCHA

ACTIVIDAD: 01.00 TRANSPORTES


FECHA: AGOSTO 2020
RESUMEN DE METRADOS
09.00 TRANSPORTE

1. YANEC - QUISHUAR- PUTACA


ITEM PARTIDA UNIDAD METRADO

01.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM m³-km 7,330.60


01.02 TRANSPORTE DE MATERIAL GRANULAR D> 1 KM m³-km 6,339.81
01.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM m³-km 2,457.94
01.04 TRANSPORTE DE MATERIAL EXCEDENTE D> 1 KM m³-km 3,281.40

2. EMP. JU-543 (CHUPAN) - HUACAN


ITEM PARTIDA UNIDAD METRADO

01.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM m³-km 3,420.90


01.02 TRANSPORTE DE MATERIAL GRANULAR D> 1 KM m³-km 7,610.56
01.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM m³-km 1,124.50
01.04 TRANSPORTE DE MATERIAL EXCEDENTE D> 1 KM m³-km 2,541.00

MANTENIMIENTO PERIODICO DEL CAMINO VECINAL EMP. SM-102-BAJO ALGARROBO-ALTO ALGARROBO L=5+340 KM.
MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE LA OROYA, PROVINCIA DE YAULI, DEPARTAMENTO DE JUNIN, DE ACUERDO CON EL
SIGUIENTE DETALLE:
PROYECTO :
1. CALLE IQUITOS - CUMBRE HUASQUI
2. ESTANCIA HUAYNACANCHA

ACTIVIDAD:01.00 TRANSPORTES
FECHA AGOSTO 2020
SUSTENTO DE METRADOS DE TRANSPORTE DE BASE GRANULAR
1. YANEC - QUISHUAR- PUTACA

Cantera: C-1 Cantera: C-2 Cantera: C-3


Ubicación: 0.00 Ubicación: 5.54 Ubicación: 13.06
Acceso (m): 820 Acceso (m): 0 Acceso (m): 0

Afirmado de e = 0.15 m
00+000 Ancho promedio= 3.00 m 16+000
INICIO FIN

01.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM 7,330.60 m3-km


01.02 TRANSPORTE DE MATERIAL GRANULAR D> 1 KM 6,339.81 m3-km
PLATAFORMA DE RODADURA
PROGRESIVA Ecuación Ub. D.L.P.
Proporción Acceso Distancia Espesor Volumen Momento D<=1km D > 1km
INICIO FIN Empalme Cantera Cantera 120.00 m Longitud (m) Ancho (m) Área (m2) F. E.
% (km) (km) (m) (m3) (m3-km) (m3-km) (m3-km)
(km) (km) (m) (km) (km)
00+000 01+000 - C-1 0.00 100.00% 0.82 0.12 1.20 1,000.00 3.00 3,000.00 0.15 1.20 540.00 648.00 540.00 108.00
01+000 02+000 - C-1 0.00 100.00% 0.82 0.12 2.20 1,000.00 3.00 3,000.00 0.15 1.20 540.00 1,188.00 540.00 648.00
02+000 02+360 - C-1 0.00 100.00% 0.82 0.12 2.88 360.00 3.00 1,080.00 0.15 1.20 194.40 559.87 194.40 365.47
02+360 03+000 - C-2 5.54 100.00% - 0.12 2.74 640.00 3.00 1,920.00 0.15 1.20 345.60 946.94 345.60 601.34
03+000 04+000 - C-2 5.54 100.00% - 1.12 0.92 1,000.00 3.00 3,000.00 0.15 1.20 540.00 496.80 496.80 -
04+000 05+000 - C-2 5.54 100.00% - 0.12 0.92 1,000.00 3.00 3,000.00 0.15 1.20 540.00 496.80 496.80 -
05+000 05+540 - C-2 5.54 100.00% - 0.12 0.15 540.00 3.00 1,620.00 0.15 1.20 291.60 43.74 43.74 -
05+540 06+000 - C-2 5.54 100.00% - 0.12 0.11 460.00 3.00 1,380.00 0.15 1.20 248.40 27.32 27.32 -
06+000 07+000 - C-2 5.54 100.00% - 0.12 0.84 1,000.00 3.00 3,000.00 0.15 1.20 540.00 453.60 453.60 -
07+000 08+000 - C-2 5.54 100.00% - 0.12 1.84 1,000.00 3.00 3,000.00 0.15 1.20 540.00 993.60 540.00 453.60
08+000 09+000 - C-2 5.54 100.00% - 0.12 2.84 1,000.00 3.00 3,000.00 0.15 1.20 540.00 1,533.60 540.00 993.60
09+000 09+300 - C-2 5.54 100.00% - 0.12 3.49 300.00 3.00 900.00 0.15 1.20 162.00 565.38 162.00 403.38

MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES


09+300 10+000 - C-3 13.06 100.00% - 0.12 3.29 700.00 3.00 2,100.00 0.15 1.20 378.00 1,243.62 378.00 865.62
10+000 11+000 - C-3 13.06 100.00% - 0.12 2.44 1,000.00 3.00 3,000.00 0.15 1.20 540.00 1,317.60 540.00 777.60
11+000 12+000 - C-3 13.06 100.00% - 0.12 1.44 1,000.00 3.00 3,000.00 0.15 1.20 540.00 777.60 540.00 237.60
12+000 13+000 - C-3 13.06 100.00% - 0.12 0.44 1,000.00 3.00 3,000.00 0.15 1.20 540.00 237.60 237.60 -
13+000 13+060 - C-3 13.06 100.00% - 0.12 -0.09 60.00 3.00 180.00 0.15 1.20 32.40 - 2.92 - 2.92 -
13+060 14+000 - C-3 13.06 100.00% - 0.12 0.35 940.00 3.00 2,820.00 0.15 1.20 507.60 177.66 177.66 -
14+000 15+000 - C-3 13.06 100.00% - 0.12 1.32 1,000.00 3.00 3,000.00 0.15 1.20 540.00 712.80 540.00 172.80
15+000 16+000 - C-3 13.06 100.00% - 0.12 2.32 1,000.00 3.00 3,000.00 0.15 1.20 540.00 1,252.80 540.00 712.80
16,000.00 48,000.00 8,640.00 13,670.41 7,330.60 6,339.81
Dist.Media (km): 1.58

2. EMP. JU-543 (CHUPAN) - HUACAN

Cantera: C-1
Ubicación: 0.00
Acceso (m): 500

Afirmado de e = 0.15 m
00+000 Ancho promedio= 3.50 m 05+550
INICIO FIN

01.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM 3,420.90 m3-km


01.02 TRANSPORTE DE MATERIAL GRANULAR D> 1 KM 7,610.56 m3-km
PLATAFORMA DE RODADURA
PROGRESIVA Ecuación Ub. D.L.P.
Proporción Acceso Distancia Espesor Volumen Momento D<=1km D > 1km
INICIO FIN Empalme Cantera Cantera 120.00 m Longitud (m) Ancho (m) Área (m2) F. E.
% (km) (km) (m) (m3) (m3-km) (m3-km) (m3-km)
(km) (km) (m) (km) (km)
00+000 01+000 - C-1 0.00 100.00% 0.50 0.12 0.88 1,000.00 3.50 3,500.00 0.15 1.20 630.00 554.40 554.40 -
01+000 02+000 - C-1 0.00 100.00% 0.50 0.12 1.88 1,000.00 3.50 3,500.00 0.15 1.20 630.00 1,184.40 630.00 554.40
02+000 03+000 - C-1 0.00 100.00% 0.50 0.12 2.88 1,000.00 3.50 3,500.00 0.15 1.20 630.00 1,814.40 630.00 1,184.40
03+000 04+000 - C-1 0.00 100.00% 0.50 0.12 3.88 1,000.00 3.50 3,500.00 0.15 1.20 630.00 2,444.40 630.00 1,814.40
04+000 05+000 - C-1 0.00 100.00% 0.50 0.12 4.88 1,000.00 3.50 3,500.00 0.15 1.20 630.00 3,074.40 630.00 2,444.40
05+000 05+550 - C-1 0.00 100.00% 0.50 0.12 5.66 550.00 3.50 1,925.00 0.15 1.20 346.50 1,959.46 346.50 1,612.96
5,550.00 19,425.00 3,496.50 11,031.46 3,420.90 7,610.56
Dist.Media (km): 3.16

MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES


MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE LA OROYA, PROVINCIA DE YAULI, DEPARTAMENTO DE JUNIN, DE ACUERDO CON EL SIGUIENTE
DETALLE:
PROYECTO :
1. CALLE IQUITOS - CUMBRE HUASQUI
2. ESTANCIA HUAYNACANCHA

ACTIVIDAD:01.00 TRANSPORTES
FECHA AGOSTO 2020
SUSTENTO DE METRADOS DE TRANSPORTE DE MATERIAL EXCEDENTE
1. YANEC - QUISHUAR- PUTACA

Botadero B-1 Cantera: B-2


Ubicación: 5.54 Ubicación: 13.06
Acceso (m): 0 Acceso (m): 0

Corte de e = 0.05 m
00+000 Ancho promedio= 3.00 m 16+000
INICIO FIN

01.01 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM 2,457.94 m3-km


01.02 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM 3,281.40 m3-km
PLATAFORMA DE RODADURA
PROGRESIVA Ecuación Ub. D.L.P.
Proporción Acceso Distancia Espesor Volumen
INICIO FIN Empalme Cantera Cantera 120.00 m Longitud (m) Ancho (m) Área (m2) F. E. Momento (m3-km) D<=1km (m3-km) D > 1km (m3-km)
% (km) (km) (m) (m3)
(km) (km) (m) (km) (km)
00+000 01+000 - B-1 5.54 100.00% - 0.12 4.92 1,000.00 3.00 3,000.00 0.05 1.20 180.00 885.60 180.00 705.60
01+000 02+000 - B-1 5.54 100.00% - 0.12 3.92 1,000.00 3.00 3,000.00 0.05 1.20 180.00 705.60 180.00 525.60
02+000 03+000 - B-1 5.54 100.00% - 0.12 2.92 1,000.00 3.00 3,000.00 0.05 1.20 180.00 525.60 180.00 345.60
03+000 04+000 - B-1 5.54 100.00% - 0.12 1.92 1,000.00 3.00 3,000.00 0.05 1.20 180.00 345.60 180.00 165.60
04+000 05+000 - B-1 5.54 100.00% - 0.12 0.92 1,000.00 3.00 3,000.00 0.05 1.20 180.00 165.60 165.60 -
05+000 05+540 B-1 5.54 100.00% - 0.12 0.15 540.00 3.00 1,620.00 0.05 1.20 97.20 14.58 14.58 -
05+540 06+000 - B-1 5.54 100.00% - 0.12 0.11 460.00 3.00 1,380.00 0.05 1.20 82.80 9.11 9.11 -
06+000 07+000 - B-1 5.54 100.00% - 0.12 0.84 1,000.00 3.00 3,000.00 0.05 1.20 180.00 151.20 151.20 -
07+000 08+000 - B-1 5.54 100.00% - 0.12 1.84 1,000.00 3.00 3,000.00 0.05 1.20 180.00 331.20 180.00 151.20
08+000 09+000 - B-1 5.54 100.00% - 0.12 2.84 1,000.00 3.00 3,000.00 0.05 1.20 180.00 511.20 180.00 331.20
09+000 09+300 B-1 5.54 100.00% - 0.12 3.49 300.00 3.00 900.00 0.05 1.20 54.00 188.46 54.00 134.46
09+300 10+000 - B-2 13.06 100.00% - 0.12 3.29 700.00 3.00 2,100.00 0.05 1.20 126.00 414.54 126.00 288.54
10+000 11+000 - B-2 13.06 100.00% - 0.12 2.44 1,000.00 3.00 3,000.00 0.05 1.20 180.00 439.20 180.00 259.20
11+000 12+000 - B-2 13.06 100.00% - 0.12 1.44 1,000.00 3.00 3,000.00 0.05 1.20 180.00 259.20 180.00 79.20
12+000 13+000 - B-2 13.06 100.00% - 0.12 0.44 1,000.00 3.00 3,000.00 0.05 1.20 180.00 79.20 79.20 -
13+000 13+060 - B-2 13.06 100.00% - 0.12 -0.09 60.00 3.00 180.00 0.05 1.20 10.80 - 0.97 - 0.97 -

MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES


13+060 14+000 - B-2 13.06 100.00% - 0.12 0.35 940.00 3.00 2,820.00 0.05 1.20 169.20 59.22 59.22 -
14+000 15+000 - B-2 13.06 100.00% - 0.12 1.32 1,000.00 3.00 3,000.00 0.05 1.20 180.00 237.60 180.00 57.60
15+000 16+000 - B-2 13.06 100.00% - 0.12 2.32 1,000.00 3.00 3,000.00 0.05 1.20 180.00 417.60 180.00 237.60
16,000.00 48,000.00 2,880.00 5,739.34 2,457.94 3,281.40
Dist.Media (km): 1.99

2. EMP. JU-543 (CHUPAN) - HUACAN

Botadero B-1
Ubicación: 0.00
Acceso (m): 500

Corte de e = 0.05 m
00+000 Ancho promedio= 3.50 m 05+550
INICIO FIN

01.01 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM 1,124.50 m3-km


01.02 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM 2,541.00 m3-km
PLATAFORMA DE RODADURA
PROGRESIVA Ecuación Ub. D.L.P.
Proporción Acceso Distancia Espesor Volumen
INICIO FIN Empalme Cantera Cantera 120.00 m Longitud (m) Ancho (m) Área (m2) F. E. Momento (m3-km) D<=1km (m3-km) D > 1km (m3-km)
% (km) (km) (m) (m3)
(km) (km) (m) (km) (km)
00+000 01+000 - B-1 5.54 100.00% 0.50 0.12 5.42 1,000.00 3.50 3,500.00 0.05 1.20 210.00 1,138.20 210.00 928.20
01+000 02+000 - B-1 5.54 100.00% 0.50 0.12 4.42 1,000.00 3.50 3,500.00 0.05 1.20 210.00 928.20 210.00 718.20
02+000 03+000 - B-1 5.54 100.00% 0.50 0.12 3.42 1,000.00 3.50 3,500.00 0.05 1.20 210.00 718.20 210.00 508.20
03+000 04+000 - B-1 5.54 100.00% 0.50 0.12 2.42 1,000.00 3.50 3,500.00 0.05 1.20 210.00 508.20 210.00 298.20
04+000 05+000 - B-1 5.54 100.00% 0.50 0.12 1.42 1,000.00 3.50 3,500.00 0.05 1.20 210.00 298.20 210.00 88.20
05+000 05+550 - B-1 5.54 100.00% 0.50 0.12 0.65 550.00 3.50 1,925.00 0.05 1.20 115.50 74.50 74.50 -
5,550.00 19,425.00 1,165.50 3,665.50 1,124.50 2,541.00
Dist.Media (km): 3.15

MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES


MANTENIMIENTO RUTINARIO
CARGAS DE TRABAJO COSTO PARCIAL COSTO TOTAL POR RUBRO
CODIGO DESCRIPCION UND P.U (S/.)
IB IA IIB IIA IIIB IIIA IB IA IIB IIA IIIB IIIA IB IA IIB IIA IIIB IIIA
´(01) ´(02) ´(03) ´(04) ´(05) ´(06) ´(07) ´(08) ´(09) ´(10) ´(11) ´(12) ´(13) ´(14) ´(15) ´(16) ´(17) ´(18) ´(18) ´(20) ´(21) ´(22)

MR-100 CONSERVACION DE CALZADA 4,064.58


km
MR-101 Limpieza de Calzada 0.40 0.50 0.70 0.90 1.00 1.40 290.82 203.57
m2
MR-102 Bacheo - Camino Tipo I - 340.00 360.00 0.00 0.00
m2
Bacheo - Camino Tipo II - 380.00 420.00 9.58 3,640.40
m2
Bacheo - Camino Tipo III - 460.00 520.00 0.00 0.00
m3
MR-103 Desquinche 0.00 0.00 2.00 2.00 3.00 3.00 23.05 46.10
m3
MR-104 Remocion de Derrumbe 3.00 3.00 9.00 9.00 15.00 15.00 19.39 174.51
m2
Sec. 305 Perfilado de la Superficie sin aporte de material 1,000.00 1,200.00 1,300.00 1,400.00 1,500.00 1,700.00 0.00 0.00

MR-200 LIMPIEZA DE OBRAS DE DRENAJE 1,149.51


ml
MR-201 Limpieza de Cunetas 1,000.00 1,200.00 1,200.00 1,400.00 1,800.00 2,400.00 0.48 576.00
und
MR-202 Limpieza de Alcantarilla 1.00 1.00 3.00 3.00 6.00 6.00 87.24 261.72
m2
MR-203 Limpieza de Baden 9.60 9.60 32.00 40.00 50.00 80.00 5.76 184.32
ml
MR-204 Limpieza de Zanja de Coronacion 5.00 5.00 10.00 10.00 20.00 25.00 0.00 0.00
und
MR-205 Limpieza de Pontones 0.25 0.25 0.50 0.50 0.50 0.50 115.26 57.63
ml
MR-206 Encauzamiento de Pequeños Cursos de Agua 35.00 35.00 24.00 24.00 20.00 20.00 2.91 69.84

MR-300 CONTROL DE VEGETACION 540.00


m2
MR-301 Roce y Limpieza 900.00 1,500.00 3,600.00 6,000.00 9,000.00 12,600.00 0.15 540.00

MR-400 SEGURIDAD VIAL 32.90


und
MR-401 Conservacion de Señales 1.50 1.50 2.00 2.00 3.00 3.00 16.45 32.90

MR-500 MEDIO AMBIENTE 114.00


und
MR-501 Reforestacion 0.00 0.00 200.00 200.00 250.00 250.00 0.57 114.00

MR-600 VIGILANCIA Y CONTROL VIAL 1,322.57


km
MR-601 Vigilancia y Control 24.00 48.00 24.00 48.00 24.00 48.00 55.11 1,322.57

MR-700 ACTIVIDADES COMPLEMENTARIAS 0.00


m3
MR-701 Reparacion de Muros Secos 50.00 0.50 2.00 2.00 2.00 2.00 0.00 0.00
und
MR-702 Reparacion de Pontones 0.15 0.15 0.15 0.15 0.15 15.00 0.00 0.00
A COSTO DIRECTO S/ 0.00 0.00 7,223.56 0.00 0.00 0.00
B COSTO INDIRECTO (%) S/ 0.00 0.00 722.36 0.00 0.00 0.00
C UTILIDAD (%) S/ 0.00 0.00 722.36 0.00 0.00 0.00
D SUB - TOTAL S/ 0.00 0.00 8,668.27 0.00 0.00 0.00
F IGV (18%) S/ 0.00 0.00 1,560.29 0.00 0.00 0.00
G TARIFA POR TIPO DE CAMBIO Y NIVEL DE SERVICIO S/ 0.00 0.00 10,228.56 0.00 0.00 0.00

COSTO KM PROMEDIO DE LA EJECUCION DEL MANTENIMIENTO RUTINARIO S/ 10,228.56


COSTO POR LA EJECUCION DEL MANTENIMIENTO RUTINARIO (21.55) S/ 220,425.49
MANTENIMIENTO PERIODICO Y RUTINARIO DE LOS CAMINOS VECINALES DEL DISTRITO DE LA OROYA, PROVINCIA DE YAULI, DEPARTAMENTO DE JUNIN, DE ACUERDO CON EL SIGUIENTE DETALLE:
SERVICIO: 1. CALLE IQUITOS - CUMBRE HUASQUI
2. ESTANCIA HUAYNACANCHA

ENTIDAD: MUNICIPALIDAD PROVINCIAL DE YAULI


REGIÓN: JUNÍN
PROVINCIA: YAULI
DISTRITO: LA OROYA

DETALLE DE GASTOS GENERALES


IMPORTE KM TOTAL ( KM) PARCIAL TOTAL
Gastos Generales Mantenimiento Periodico S/ 86,136.13 1 S/ 86,136.13
S/ 88,730.59
Gastos Generales Promedio Mantenimiento Rutinario S/ 120.39 21.55 S/ 2,594.46

Tiempo en Importe Sub Total TOTAL


DESCRIPCIÓN Unidad Cantidad % (incidencia)
meses S/. S/. S/.
A.- SUELDOS Y SALARIOS (Incluye Leyes Sociales) 83,916.67
a.-Personal Profesional 83,916.67
Ing. Civil Residente GLB 1.00 15.83 1.00 3,500.00 55,416.67
Asistente de residente GLB 1.00 15.83 1.00 1,800.00 28,500.00
B.-MATERIALES Y UTILES DE OFICINA 1,789.39
Utiles de oficina y dibujo M 1.00 3.00 596.46 1,789.39
COSTO PARCIAL (A+B) 85,706.06