Está en la página 1de 8

CANTIDADES DE MAMPOSTERIA

DIMESNIONES
REFERENCIA
TOTALES VANOS
EJES LONG 1 (m) LONG 2 (m) ÁREA TOTAL LONG 1 (m) LONG 2 (m) ÁREA VANOS ÁREA NETA
ALCOBA 1
B, 7-8 1.83 2.32 4.25 0 4.25
A, 6-8 2.74 2.32 6.36 1 1 1 5.36
6, A-B 2.56 2.32 5.94 0 5.94
8, A-B 2.61 2.32 6.06 0 6.06
SUBTOTAL 21.60
ALCOBA 2
B, 4-5' 1.96 2.32 4.55 0 4.55
A, 4-6 2.78 2.32 6.45 1 1 1 5.45
4, A-B 2.61 2.32 6.06 0 6.06
SUBTOTAL 16.05
ALCOBA 3
B,1-3 1.82 2.32 4.22 0 4.22
A,1-4 2.67 2.32 6.19 1 1 1 5.19
1,A-B 2.61 2.32 6.06 0 6.06
SUBTOTAL 15.47
DEPOSITO/HALL
D,3-5 1.13 2.32 2.62 0 2.62
C,3-5 1.25 2.32 2.90 0 2.90
4,C-D 0.16 2.32 0.37 0 0.37
2,B-C 0.9 2.32 2.09 0 2.09
SUBTOTAL 7.98
COMEDOR/COCINA
E,5-7 2.73 2.32 6.33 1 1 1 5.33
5,C-E 2.27 2.32 5.27 0 5.27
7,C-E 2.47 2.32 5.73 0 5.73
SUBTOTAL 16.33
BAÑO
3,D-E 0.58 2.3 1.33 0 1.33
2,D-E 0.74 2.3 1.70 0 1.70
E,2-5 2.12 2.3 4.88 0 4.88
SUBTOTAL 7.91
CANTIDAD DE MATERIALES

CONVERSION LONGITUD DE
MEDIDA DE LADRILLO EN CM LADRILLO+PEGA (1CM)
EN M
EN METROS
LARGO 24 0.24 0.25
ALTO 6.5 0.065 0.075
ANCHO 12 0.12

COMEDOR/
ALCOBA 1 ALCOBA 2 ALCOBA 3 HALL
COCINA
AREAS MURO 21.6 16.05 15.47 7.98 16.33
MORTERO 1 2.59 1.93 1.86 0.96 1.96
MORTERO 2 2.16 1.60 1.54 0.80 1.63
VOL. MORTERO
0.44 0.32 0.31 0.16 0.33
m3
LADRILLO 1152 856 825 426 871
CEMENTO 5.23 3.88 3.74 1.93 3.95
ARENA 0.42 0.31 0.30 0.15 0.32
AGUA 131 97 94 48 99
RIALES

AREA DE
LABRILLO

0.019

Suma
BAÑO
TOTAL
7.91 85.34
COSTOS
0.95 10.24
V/UNI
0.79 8.52

0.16 1.72

422 4552 $ 600 $ 2,730,910 DOSIFICACION 1:2


1.91 20.70 $ 28,000 $ 579,473 600 KG DESPERDICI
O DE
0.15 1.70 $ 25,000 $ 42,541 0.96 M3 CEMENTO:
48 516 $ 13 $ 6,710 300 L
TOTAL EN COSTOS $ 3,359,634
5%

También podría gustarte