ESTUDIO DEFINITIVO PARA LA CONSTRUCCION DEL PUENTE EL TINGO Y ACCESOS

RESUMEN DE METRADOS - PAVIMENTO ASFALTICO

METRADO
ITEM PARTIDAS UNIDAD
TOTAL

03.03 PAVIMENTO ASFÁLTICO


03.03.01 IMPRIMACIÓN ASFÁLTICA m2 2,094.20
03.03.02 RIEGO DE LIGA EN PUENTES m 2
753.99
03.03.03 CONCRETO ASFÁLTICO EN CALIENTE m3 223.70
03.03.04 EMULSION ASFALTICA l 339.30
03.03.05 ASFALTO DILUIDO MC-30 l 2,303.62
CONSORCIO

PAVIMENTO ASFALTICO
ESTUDIO DEFINITIVO PARA LA CONSTRUCCION DEL PUENTE EL TINGO Y ACCESOS

METRADO PAVIMENTO ASFALTICO


SECCION TRANSVERSAL IMPRIMACION ASFALTICA RIEGO DE LIGA EN PUENTES CONCRETO ASFALTICO
03.03.01 03.03.05 03.03.02 03.03.04 03.03.03

PROGRESIVA DISTANCIA BERMA S/A ANCHO S/A BERMA ANCHO ANCHO A ASFALTO ANCHO
RIEGO DE EMULSION ANCHO ESPESOR CONCRETO
IMPRIMACIÓN DILUIDO RIEGO
IZQ. IZQ. DE VIA DER. DER. TOTAL IMPRIMAR LIGA EN ASFALTICA CARPETA CARPETA ASFÁLTICO
ASFÁLTICA MC-30 LIGA
PUENTES EN CALIENTE
1.10 l/m2 0.45 l/m2
(km) (m) (m) (m) (m) (m) (m) (m) (m) (m2) (l) (m) (m2) (l) (m) (m) (m3)
132+970
132+971 1.20 6.60 1.20 7.80 8.07 9.68 10.65 - - 7.94 0.09 0.86
132+980 8.80 0.70 6.60 1.20 8.50 8.77 77.18 84.90 - - 8.64 0.09 6.84
132+990 10.00 0.70 6.60 1.20 8.50 8.77 87.70 96.47 - - 8.64 0.09 7.77
133+000 10.00 0.70 6.60 2.31 1.20 10.81 11.08 110.80 121.88 - - 10.95 0.09 9.85
133+010 10.00 1.20 6.60 2.37 1.20 11.37 11.64 116.40 128.04 - - 11.51 0.09 10.35
133+020 10.00 1.20 6.60 2.92 1.20 11.92 12.19 121.90 134.09 - - 12.06 0.09 10.85
133+030 10.00 1.20 6.60 2.92 1.20 11.92 12.19 121.90 134.09 - - 12.06 0.09 10.85
133+039 9.10 1.20 6.60 2.92 1.20 11.92 12.19 110.93 122.02 - 12.06 0.09 9.87
133+040 0.90 - - - - 11.43 10.29 4.63 11.43 0.05 0.51
133+050 10.00 - - - - 9.72 97.20 43.74 9.72 0.05 4.86
133+060 10.00 - - - - 9.00 90.00 40.50 9.00 0.05 4.50
133+070 10.00 - - - - 9.00 90.00 40.50 9.00 0.05 4.50
133+080 10.00 - - - - 9.85 98.50 44.33 9.85 0.05 4.93
133+090 10.00 - - - - 9.00 90.00 40.50 9.00 0.05 4.50
133+100 10.00 - - - - 9.00 90.00 40.50 9.00 0.05 4.50
133+110 10.00 - - - - 9.00 90.00 40.50 9.00 0.05 4.50
133+120 10.00 - - - - 9.80 98.00 44.10 9.80 0.05 4.90
133+121 1.40 1.20 6.60 1.80 1.20 10.80 11.07 15.50 17.05 - - 10.94 0.09 1.38
133+130 8.60 1.20 6.60 2.40 1.20 11.40 11.67 100.36 110.40 - - 11.54 0.09 8.93
133+140 10.00 1.20 6.60 2.40 1.20 11.40 11.67 116.70 128.37 - - 11.54 0.09 10.38
133+150 10.00 1.20 6.60 2.40 1.20 11.40 11.67 116.70 128.37 - - 11.54 0.09 10.38
133+160 10.00 1.20 6.60 0.90 1.20 9.90 10.17 101.70 111.87 - - 10.04 0.09 9.03
133+170 10.00 1.20 6.60 0.61 1.20 9.61 9.88 98.80 108.68 - - 9.75 0.09 8.77
133+180 10.00 1.20 6.60 1.20 9.00 9.27 92.70 101.97 - - 9.14 0.09 8.22
133+190 10.00 1.20 6.60 1.20 9.00 9.27 92.70 101.97 - - 9.14 0.09 8.22
133+200 10.00 1.20 6.60 1.20 9.00 9.27 92.70 101.97 - - 9.14 0.09 8.22
133+210 10.00 1.20 6.60 1.20 9.00 9.27 92.70 101.97 - - 9.14 0.09 8.22
133+220 10.00 1.20 6.60 1.20 9.00 9.27 92.70 101.97 - - 9.14 0.09 8.22
133+230 10.00 1.20 6.60 1.20 9.00 9.27 92.70 101.97 - - 9.14 0.09 8.22
133+240 10.00 1.20 6.60 1.20 9.00 9.27 92.70 101.97 - - 9.14 0.09 8.22
133+250 10.00 1.20 6.60 1.20 9.00 9.27 92.70 101.97 - - 9.14 0.09 8.22
133+255 5.00 1.20 6.60 1.20 9.00 9.27 46.35 50.99 - - 9.14 0.09 4.11

TOTAL 2,094.20 2,303.62 753.99 339.30 223.70


OBRAS DE ARTE
ESTUDIO DEFINITIVO PARA EL MEJORAMIENTO DE LA CARRETERA SAN MARCOS - CAJABAMBA - SAUSACOCHA
TRAMO: SAN MARCOS - CAJABAMBA

METRADO DE TRATAMIENTO SUPERFICIAL BICAPA

405.A
PROGRESIVA PROGRESIVA ANCHO TRATAMIENTO
LARGO
INICIO FINAL (PROMEDIO) SUPERFICIAL OBSERVACIONES
BICAPA

(km) (km) (m) (m) (m2)

5+800 6+380 580.00 11.63 6745.40 PEDRAPLEN


45+930 46+040 110.00 11.58 1273.80 PEDRAPLEN
46+240 46+525 285.00 11.26 3209.10 PEDRAPLEN
46+820 46+910 90.00 11.43 1028.70 PEDRAPLEN
47+300 47+380 80.00 10.94 875.20 PEDRAPLEN
47+460 47+600 140.00 10.84 1517.60 PEDRAPLEN
47+700 47+830 130.00 11.65 1514.50 PEDRAPLEN
58+380 58+500 120.00 9.34 1120.80 PEDRAPLEN

TOTAL 17285.10

Estudio Definitivo para el Mejoramiento de la Carretera San Marcos - Cajabamba - Sausacocha


Tramo : San Marcos - Cajabamba
Estudio Definitivo para el Mejoramiento y Rehabilitación de la Carretera Andahuaylas

S/A
PI S Km. S/A Lt
LI LD

También podría gustarte