Nombre de tarea Costo NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO

MEJORAMIENTO DEL SERVICIO EDUCATIVO S/53,101.46 S/131,528.30 S/101,198.86 S/67,310.07 S/88,976.78 S/240,394.58 S/43,698.11
S/726,208.16
N°1RA
40479 MIGUEL
ETAPA CASCOGRAU
GRIS (AULA INICIAL y S/344,596.24 S/53,101.46 S/131,528.30 S/101,198.86 S/58,767.62
TALLERES)
OBRAS PROVISIONALES
TRABAJOS PRELIMINARES S/91,865.78 S/53,101.46 S/38,764.32
TRANSPORTE DE EQUIPO Y S/30,000.00
HERRAMIENTAS MANUALES
LIMPIEZA DE TERRENO MANUAL S/14,087.92
DESMONTAJE DE PUERTAS Y VENTANAS S/545.67
DEMOLICION DE ARQUITECTURA S/8,467.87 S/465.27
DEMOLICION DE ESTRUCTURA S/35,061.48
TRAZO, NIVELACION Y REPLANTEO S/3,237.57
INICIO DE OBRA
MOVIMIENTO DE TIERRAS S/42,351.45 S/42,351.45
EXCAVACION DE ZANJAS Y ZAPATAS, S/42,351.45
NIVELACION
ESTRUCTURAS. S/210,379.01 S/50,412.53 S/101,198.86 S/58,767.62
OBRAS DE CONCRETO SIMPLE S/13,500.04 S/13,500.04
SOLADO EN ZAPATAS, S/13,500.04
SOBRECIMIENTOS
OBRAS DE CONCRETO ARMADO S/196,878.97 S/36,912.49 S/101,198.86 S/58,767.62
ZAPATA S/56,088.38 S/36,912.49 S/19,175.89
ACERO ESTRUCTURAL TRABAJADO S/4,637.80
PARA ZAPATAS
ACERO DE REFUERZO EN COLUMNAS S/32,274.69 S/686.70
ENCOFRADO NORMAL EN ZAPATAS S/5,439.15
CONCRETO EN ZAPATAS S/13,050.04
F'C=210KG/CM2
COLUMNAS S/52,341.18 S/52,341.18
ENCOFRADO Y DESENCOFRADO S/30,169.39
NORMALCONCRETO
EN COLUMNAS
EN COLUMNAS S/22,171.79
F'C=210KG/CM2
VIGAS S/49,483.38 S/29,681.79 S/19,801.59
ACERO DE REFUERZO EN VIGAS S/29,681.79
ENCOFRADO NORMAL EN VIGAS S/19,801.59
LOSA ALIGERADA S/38,966.03 S/38,966.03
ENCOFRADO NORMAL EN LOSAS S/11,407.16
ALIGERADAS
ACERO ESTRUCTURAL TRABAJADO S/8,084.24
PARA LOSAS ALIGERADAS
CONCRETO EN VIGAS Y LOSA S/19,474.63
ALIGERADAS F'C=210KG/CM2
2DA ETAPA CASCO GRIS (BAÑO) S/70,663.04 S/8,542.45 S/62,120.59
TRABAJOS PRELIMINARES S/11,439.32 S/8,542.45 S/2,896.87
LIMPIEZA DE TERRENO MANUAL S/162.56
DESMONTAJE DE PUERTAS Y VENTANAS S/134.68
DEMOLICION DE ARQUITECTURA S/702.76
DEMOLICION DE ESTRUCTURA S/7,542.45 S/2,514.15
TRAZO, NIVELACION Y REPLANTEO S/382.72
INICIO/FIN DE OBRA
MOVIMIENTO DE TIERRAS S/10,733.15 S/10,733.15
EXCAVACION DE ZANJAS Y ZAPATAS, S/10,733.15
NIVELACION
ESTRUCTURAS S/48,490.57 S/48,490.57
OBRAS DE CONCRETO SIMPLE S/5,137.54 S/5,137.54
SOLADO EN ZAPATAS, S/5,137.54
SOBRECIMIENTOS
OBRAS DE CONCRETO ARMADO S/43,353.03 S/43,353.03
ZAPATA S/11,405.84 S/11,405.84
ACERO ESTRUCTURAL TRABAJADO S/943.82
PARA ZAPATAS
ACERO DE REFUERZO EN COLUMNAS S/7,034.54
ENCOFRADO/DESENCOFRADO S/1,019.10
NORMALCONCRETO
EN ZAPATASEN ZAPATAS S/2,408.38
F'C=210KG/CM2
COLUMNAS S/7,664.70 S/7,664.70
ENCOFRADO/DESENCOFRADO S/4,365.66
NORMALCONCRETO
EN COLUMNAS
EN COLUMNAS S/3,299.04
F'C=210KG/CM2
VIGAS S/7,930.84 S/7,930.84
ACERO DE REFUERZO EN VIGAS S/4,347.75
ENCOFRADO NORMAL EN VIGAS S/3,583.09
LOSA ALIGERADA S/16,351.65 S/16,351.65
ENCOFRADO/DESENCOFRADO S/1,419.40
NORMALACEROEN LOSAS ALIGERADAS
ESTRUCTURAL TRABAJADO S/1,135.89
PARA LOSAS ALIGERADAS
CONCRETO EN VIGAS Y LOSA S/3,796.67
ALIGERADAS F'C=210KG/CM2
LADRILLO HUECO DE ARCILLA S/9,999.69
15X30X30 CM PARA TECHO
3RA ETAPA ARQUITECTURA (S1,S2,S3) S/261,493.02 S/26,856.19 S/234,636.83
MUROS & TABIQUES S/33,570.24 S/26,856.19 S/6,714.05
MUROS Y LADRILLOS KK CON CEMENTO S/26,856.19 S/6,714.05
Y ARENA
REVOQUES Y ENLUCIDOS S/58,106.00 S/58,106.00
TARRAJEO EN AMBIENTES S/58,106.00
PISOS S/61,935.31 S/61,935.31
PISOS, ZOCALOS, PAVIMENTOS Y S/61,935.31
VEREDAS
PINTURA S/33,718.00 S/33,718.00
PINTURA LATEX S/33,718.00
CARPINTERIA S/61,104.12 S/61,104.12
CARPINTERIA, CERRAJERIA, VIDRIOS Y S/61,104.12
CUBIERTA
VARIOS S/13,059.35 S/13,059.35
VARIOS S/13,059.35
4TA ETAPA JUEGOS S/26,664.60 S/5,757.75 S/20,906.86
TRABAJOS PRELIMNARES S/4,508.98 S/4,508.98
LIMPIEZA DE TERRENO MANUAL S/861.06
DEMOLICION S/1,620.70
TRAZO, NIVELACION Y REPLANTEO S/2,027.22
INICIO DE OBRA
MOVIMIENTO DE TIERRAS S/663.92 S/663.92
NIVELACION, EXCAVACION Y S/663.92
ELIMINACION
ESTRUCTURAS. S/21,491.70 S/584.85 S/20,906.86
OBRAS DE CONCRETO SIMPLE Y VARIOS S/21,491.70 S/584.85 S/20,906.86
ENCOFRADO EN SARDINELES S/584.85 S/584.85
CONCRETO F'C =140 KG/CM2 +25% S/1,808.35
PARA SARDINELES
VEREDAS, PINTURA, CERRAJERIA S/15,628.84
ENTRE OTROS
LIMPIEZA FINAL (S1,S2,S3,S4) S/2,884.82
INSTALACIONES ELECTRICAS S/14,517.65 S/14,517.65
IIEE S/14,517.65 S/14,517.65
CABLEADO, CAJAS, TABALERO ENTRE S/14,517.65
OTROS
INSTALACIONES SANITARIAS S/8,273.60 S/8,273.60
IISS S/8,273.60 S/8,273.60
SUMINISTRO DE AGUA, DESFOGUE DE S/8,273.60
DESAGUE Y SISTEMA DE LLUVIA

COSTO DIRECTO S/726,208.16 S/53,101.46 S/131,528.30 S/101,198.86 S/67,310.07 S/88,976.78 S/240,394.58 S/43,698.11
GASTOS GENERALES(10%) S/72,620.82 S/5,310.15 S/13,152.83 S/10,119.89 S/6,731.01 S/8,897.68 S/24,039.46 S/4,369.81
UTIIDAD(10%) S/72,620.82 S/5,310.15 S/13,152.83 S/10,119.89 S/6,731.01 S/8,897.68 S/24,039.46 S/4,369.81
SUB TOTAL S/871,449.79 S/63,721.75 S/157,833.96 S/121,438.63 S/80,772.08 S/106,772.14 S/288,473.50 S/52,437.73
IMPUESTO GENERAL A LAS VENTAS (18%) S/156,860.96 S/11,469.92 S/28,410.11 S/21,858.95 S/14,538.98 S/19,218.98 S/51,925.23 S/9,438.79
PRESUPUESTO DE OBRA S/1,028,310.75 S/75,191.67 S/186,244.07 S/143,297.59 S/95,311.06 S/125,991.12 S/340,398.73 S/61,876.52

S/75,191.67 S/261,435.74 S/404,733.33 S/500,044.39 S/626,035.51 S/966,434.23 S/1,028,310.75


% DE PROGRAMA ACUMULADO
7% 25% 39% 49% 61% 94% 100%

CURVA ''S''

S/1,028,310.75

S/966,434.23

S/626,035.51

S/500,044.39

S/450,000.00

S/404,733.33
S/380,474.98

S/261,435.74

S/200,000.00

S/154,246.61

S/92,547.97
S/75,191.67
S/50,000.00

NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO ABRIL MAYO

PV EV AC
PARCIAL ACUMULADO PARCIAL ACUMULADO PARCIAL ACUMULADO
PARCIAL(S/.) PARCIAL(S/.) PARCIAL(S/.)
ACUMULADO (%) ACUMULADO (%) ACUMULADO (%)
NOVIEMBRE S/75,191.67 S/75,191.67 7% S/92,547.97 S/92,547.97 9% S/50,000.00 S/50,000.00 -
DICIEMBRE S/186,244.07 S/261,435.74 25% S/61,698.65 S/154,246.61 15% S/150,000.00 S/200,000.00 -
ENERO S/143,297.59 S/404,733.33 39% S/226,228.37 S/380,474.98 37% S/250,000.00 S/450,000.00 -
FEBRERO S/95,311.06 S/500,044.39 49% - - - - - -
MARZO S/125,991.12 S/626,035.51 61% - - - - - -
ABRIL S/340,398.73 S/966,434.23 94% - - - - - -
MAYO S/61,876.52 S/1,028,310.75 100% - - - - - -