Está en la página 1de 2

PROGRAMACION DE EJECUCION DE OBRA

CONSTRUCCION DE CANAL DE IRRIGACION SAN JOSE DE SUCRE


DEPARTAMENTO DE AYACUCHO
2 3 4 5 6
ID Nombre de tarea Duration Start Finish 3 6 9 121518212427 1 4 7 1013161922 252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11
1 INICIO DE OBRA 0 days Fri 2/7/20 Fri 2/7/20 2/7

2 OBRAS PROVISIONALES 4 days Fri 2/7/20 Wed 2/12/20


3 TRABAJOS PRELIMINARES 4 days Fri 2/7/20 Wed 2/12/20
4 BOCATOMA 49 days Thu 2/13/20 Tue 4/21/20
5 TRABAJOS PRELIMINARES 12 days Thu 2/13/20 Fri 2/28/20
6 MOVIMIENTO DE TIERRAS 15 days Mon 3/2/20 Fri 3/20/20
7 OBRAS DE CONCRETO SIMPLE 10 days Thu 4/2/20 Wed 4/15/20
8 OBRAS DE CONCRETO ARMADO 3 days Wed 4/15/20 Fri 4/17/20
9 ENCOFRADO Y DESENCOFRADO 8 days Mon 3/23/20 Wed 4/1/20
10 ACERO DE REFUERZO 9 days Thu 4/2/20 Tue 4/14/20
11 ESTRUCTURAS METALICAS 2 days Mon 4/20/20 Tue 4/21/20
12 CANAL DE CONDUCCION 28 days Mon 3/23/20 Wed 4/29/20
13 TRABAJOS PRELIMINARES 8 days Mon 3/23/20 Wed 4/1/20
14 MOVIMIENTO DE TIERRAS 8 days Thu 4/2/20 Mon 4/13/20
15 REVESTIMIENTO DE CANAL 10 days Tue 4/14/20 Mon 4/27/20
16 JUNTAS 2 days Tue 4/28/20 Wed 4/29/20
17 CANAL DESRIPEADOR 6 days Tue 4/14/20 Tue 4/21/20
18 CANAL PRINCIPAL 55 days Tue 4/14/20 Mon 6/29/20

Tarea Inactive Task Manual Summary


División Inactive Milestone Start-only
Hito Inactive Milestone Finish-only
"Proyecto Especial Sierra, Centro y Sur"
Resumen Inactive Summary External Tasks
P.E.S.C.S Resumen del proyecto Manual Task External Milestone
Tareas externas Duration-only Progreso
Hito externo Manual Summary Rollup Fecha límite

Página 1
PROGRAMACION DE EJECUCION DE OBRA
CONSTRUCCION DE CANAL DE IRRIGACION SAN JOSE DE SUCRE
DEPARTAMENTO DE AYACUCHO
2 3 4 5 6
ID Nombre de tarea Duration Start Finish 3 6 9 121518212427 1 4 7 1013161922 252831 3 6 9 12151821242730 3 6 9 12151821242730 2 5 8 11141720232629 2 5 8 11
19 OBRAS PRELIMINARES 12 days Tue 4/14/20 Wed 4/29/20
20 MOVIMIENTO DE TIERRAS 25 days Thu 4/30/20 Mon 6/29/20
21 INSTALACION DE TUBERIAS 20 days Wed 5/27/20 Tue 6/23/20
22 CAJAS DE INSPECCIÓN Y VOLTEO 12 days Thu 5/7/20 Fri 5/22/20
23 TOMAS LATERALES 12 days Mon 5/11/20 Tue 5/26/20
24 OBRAS DE ARTE 55 days Tue 4/14/20 Mon 6/29/20
25 DESARENADOR 10 days Tue 4/14/20 Mon 4/27/20
26 POZA DE CAPTACIÓN 8 days Tue 4/28/20 Thu 5/7/20
27 CANOAS 8 days Thu 4/30/20 Mon 5/11/20
28 RAPIDAS 8 days Thu 4/30/20 Mon 5/11/20
29 TOMA TIPICA DE INGRESO 8 days Tue 5/12/20 Thu 5/21/20
30 VERTEDERO DE EXEDENCIAS 4 days Tue 4/14/20 Fri 4/17/20
31 DADOS DE CONCRETO 10 days Thu 4/30/20 Wed 5/13/20
32 14 days
ALCANTARRILLAS DE CONCRETO ARMADO Thu 5/14/20 Tue 6/2/20
33 CANAL DE PURGA 6 days Wed 6/3/20 Wed 6/10/20

34

35

36 FIN DE OBRA 0 days Mon 6/29/20 Mon 6/29/20 6/29

Tarea Inactive Task Manual Summary


División Inactive Milestone Start-only
Hito Inactive Milestone Finish-only
"Proyecto Especial Sierra, Centro y Sur"
Resumen Inactive Summary External Tasks
P.E.S.C.S Resumen del proyecto Manual Task External Milestone
Tareas externas Duration-only Progreso
Hito externo Manual Summary Rollup Fecha límite

Página 2

También podría gustarte