Documentos de Académico
Documentos de Profesional
Documentos de Cultura
OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, LAS DALIAS, LOS FAICALES, 2 DE MAYO, LOS ROSALES, DEL DISTRITO DE SANTA CRUZ –
PROVINCIA DE SANTA CRUZ – CAJAMARCA"
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras)
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego)
AREA GEOGRÁFICA: 4
TOTAL COSTO DIRECTO S/. 539,966.43 798,202.50 589,546.87 566,923.18 354,547.59 170,467.51 3,019,654.08
GASTOS GENERALES (8%) 43,197.31 63,856.20 47,163.75 45,353.85 28,363.81 13,637.40 241,572.33
UTILIDAD (7%) 37,797.65 55,874.18 41,268.28 39,684.62 24,818.33 11,932.73 211,375.79
SUBTOTAL 620,961.39 917,932.88 677,978.90 651,961.66 407,729.73 196,037.64 3,472,602.20
IMPUESTO GENERAL A LAS VENTAS (IGV 18%) 111,773.05 165,227.92 122,036.20 117,353.10 73,391.35 35,286.78 625,068.40
TOTAL PRESUPUESTO S/. 732,734.44 1,083,160.80 800,015.11 769,314.75 481,121.08 231,324.42 4,097,670.60
% DE AVANCE FISICO PROGRAMADO 17.88% 26.43% 19.52% 18.77% 11.74% 5.65% 100.00%
% DE AVANCE FISICO ACUMULADO 17.88% 44.32% 63.84% 82.61% 94.35% 100.00%
RESUMÉN DE VALORIZACIÓN Nº 03 - CONTRATISTA DE EJECUCION
OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, LAS DALIAS, LOS FAICALES, 2 DE MAYO, LOS
ROSALES, DEL DISTRITO DE SANTA CRUZ – PROVINCIA DE SANTA CRUZ – CAJAMARCA"
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras)
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego)
AREA GEOGRÁFICA: 4
2.00 REAJUSTE ®
2.01 REAJUSTE 0.00 0.00 0.00
7.00 MULTAS
7.01 MULTAS POR ATRASO DE OBRA (M) 0.00 0.00 0.00
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE SANTA CRUZ OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, VALORIZACION DE OBRA Nº 03
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras) LAS DALIAS, LOS FAICALES, 2 DE MAYO, LOS ROSALES, DEL DISTRITO DE SANTA CRUZ – PROVINCIA DE SANTA (DEL 01/12/2014 AL 31/12/2014)
CRUZ – CAJAMARCA
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego) DEPARTAMENTO: CAJAMARCA PROVINCIA : SANTA CRUZ
ESPECIFICACION PRESUPUESTO BASE VALORIZACION ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR VALORIZAR
PARTIDA DESCRIPCION UNIDADMETRADO PRECIO UNI PARCIAL METRADO PARCIAL % AVANCMETRADOPARCIAL % AVANC METRADO PARCIAL % AVANCE METRADO PARCIAL % AVANCE
01 OBRAS PROVISIONALES
01.01 ALMACEN DE OBRA MES 6.00 600.00 3,600.00 2.00 1,200.00 33.33% 1.00 600.00 16.67% 3.00 1,800.00 50.00% 3.00 1,800.00 50.00%
01.02 CARTEL DE IDENTIFICACION DE OBRA DE 8.50 X 3.60 m UND 1.00 1,519.38 1,519.38 1.00 1,519.38 100.00% 0.00 0.00 0.00% 1.00 1,519.38 100.00% 0.00 0.00 0.00%
01.03 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPOS GLB 1.00 31,213.00 31,213.00 0.70 21,849.10 70.00% 0.10 3,121.30 10.00% 0.80 24,970.40 80.00% 0.20 6,242.60 20.00%
01.04 MANTENIMIENTO Y SEGURIDAD EN OBRA GLB 1.00 12,775.00 12,775.00 0.70 8,942.50 70.00% 0.10 1,277.50 10.00% 0.80 10,220.00 80.00% 0.20 2,555.00 20.00%
02 PAVIMENTO RIGIDO
02.01 TRABAJOS PRELIMINARES
02.01.01 DEMOLICION DE PAVIMENTO DE CONCRETO DE 8" M2 1,277.55 29.86 38,147.64 0.00 0.00 0.00% 766.53 22,888.59 60.00% 766.53 22,888.59 60.00% 511.02 15,259.05 40.00%
02.01.02 LIMPIEZA DE TERRENO MANUAL M2 1,716.00 2.37 4,066.92 1,581.85 3,748.98 92.18% 50.04 118.59 2.92% 1,631.89 3,867.58 95.10% 84.11 199.34 4.90%
02.01.03 TRAZO Y REPLANTEO CON EQUIPO M2 8,710.38 1.39 12,107.43 7,988.60 11,104.16 91.71% 320.45 445.43 3.68% 8,309.05 11,549.59 95.39% 401.33 557.84 4.61%
02.02 MOVIMIENTO DE TIERRAS
02.02.01 CORTE MATERIAL SUELTO A NIVEL DE SUBRASANTE C/EQUIPO M3 7,262.62 14.21 103,201.83 5,134.76 72,964.94 70.70% 250.56 3,560.46 3.45% 5,385.32 76,525.40 74.15% 1,877.30 26,676.43 25.85%
02.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 435.98 24.10 10,507.12 399.23 9,621.54 91.57% 20.45 492.85 4.69% 419.68 10,114.38 96.26% 16.30 392.74 3.74%
02.02.03 ELIM. MAT.CARG.MANUAL/VOLQUETE 10 M3,V=30 D= 7 KMS. M3 8,605.38 13.15 113,160.75 6,023.77 79,212.52 70.00% 1,200.34 15,784.47 13.95% 7,224.11 94,996.99 83.95% 1,381.27 18,163.76 16.05%
02.02.04 CONFORMACION Y COMPACTACION DE SUBRASANTE CON MAQUINARIA M2 8,710.38 3.38 29,441.08 6,097.27 20,608.76 70.00% 743.23 2,512.12 8.53% 6,840.50 23,120.88 78.53% 1,869.88 6,320.20 21.47%
02.02.05 MEJORAMIENTO DE SUBRASANTE (PIEDRA OVER) E = .20 M M2 8,710.38 20.08 174,904.43 6,968.30 139,923.54 80.00% 600.45 12,057.04 6.89% 7,568.75 151,980.58 86.89% 1,141.63 22,923.85 13.11%
02.02.06 BASE CON AFIRMADO Y/O MAT. GRANULAR E=.20 M M2 8,710.38 27.08 235,877.09 6,097.27 165,113.96 70.00% 600.34 16,257.21 6.89% 6,697.61 181,371.17 76.89% 2,012.77 54,505.92 23.11%
02.03 CONCRETO EN PAVIMENTOS
02.03.01 LOSA DE CONCRETO E=0.20m f'c= 210 Kg/cm2 M2 8,710.38 82.50 718,606.35 2,519.50 207,858.75 28.93% 1,981.35 163,461.38 22.75% 4,500.85 371,320.13 51.67% 4,209.53 347,286.23 48.33%
02.03.02 ENCOFRADO Y DESENCOFRADO LOSA DE CONCRETO M2 996.08 31.49 31,366.56 291.39 9,175.87 29.25% 211.02 6,645.02 21.19% 502.41 15,820.89 50.44% 493.67 15,545.67 49.56%
02.03.03 DOWEL ENTRE LOSAS RIGIDAS 1" UND 2,568.00 16.84 43,245.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,568.00 43,245.12 100.00%
02.03.04 JUNTAS AISLAMIENTO CON TECNOPOR 1/2" M 2,832.87 9.53 26,997.25 320.00 3,049.60 11.30% 197.01 1,877.51 6.95% 517.01 4,927.11 18.25% 2,315.86 22,070.14 81.75%
02.03.05 CURADO CONCRETO M2 8,586.73 1.19 10,218.21 2,519.50 2,998.21 29.34% 1,981.35 2,357.81 23.07% 4,500.85 5,356.01 52.42% 4,085.88 4,862.20 47.58%
02.03.06 SELLADO JUNTAS CON ASFALTO 1" M 5,996.93 6.51 39,040.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 5,996.93 39,040.01 100.00%
02.04 RAMPA DE CONCRETO
02.04.01 LOSA DE CONCRETO E=0.20m f'c= 210 Kg/cm2 M2 136.14 82.50 11,231.55 0.00 0.00 0.00% 68.07 5,615.78 50.00% 68.07 5,615.78 50.00% 68.07 5,615.78 50.00%
02.04.02 ENCOFRADO Y DESENCOFRADO LOSA DE CONCRETO M2 18.04 31.49 568.08 0.00 0.00 0.00% 9.02 284.04 50.00% 9.02 284.04 50.00% 9.02 284.04 50.00%
02.04.03 JUNTAS AISLAMIENTO CON TECNOPOR 1/2" M 54.43 9.53 518.72 0.00 0.00 0.00% 27.22 259.36 50.00% 27.22 259.36 50.00% 27.22 259.36 50.00%
02.04.04 CURADO CONCRETO M2 123.65 1.19 147.14 0.00 0.00 0.00% 61.83 73.57 50.00% 61.83 73.57 50.00% 61.83 73.57 50.00%
02.04.05 SELLADO JUNTAS CON ASFALTO 1" M 82.18 6.51 534.99 0.00 0.00 0.00% 41.09 267.50 50.00% 41.09 267.50 50.00% 41.09 267.49 50.00%
02.05 VARIOS
02.05.01 NIVELACION DE BUZONES UND 24.00 263.50 6,324.00 9.00 2,371.50 37.50% 5.00 1,317.50 20.83% 14.00 3,689.00 58.33% 10.00 2,635.00 41.67%
03 MURO DE CONTENCION EN AV. CAJAMARCA
03.01 OBRAS PRELIMINARES
03.01.01 TRAZO Y REPLANTEO CON EQUIPO M2 596.00 1.39 828.44 537.25 746.78 90.14% 20.24 28.13 3.40% 557.49 774.91 93.54% 38.51 53.53 6.46%
03.02 MOVIMIENTO DE TIERRAS
03.02.01 EXCAVACION ZANJAS MURO DE CONTENCION CON MAQUINARIA M3 2,214.67 14.30 31,669.78 1,328.80 19,001.87 60.00% 664.40 9,500.93 30.00% 1,993.20 28,502.80 90.00% 221.47 3,166.98 10.00%
03.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO M3 2,008.00 24.10 48,392.80 401.60 9,678.56 20.00% 602.40 14,517.84 30.00% 1,004.00 24,196.40 50.00% 1,004.00 24,196.40 50.00%
03.02.03 FILTRO CON GRAVA PARA DRENAJE DE MURO M3 16.32 147.54 2,407.85 3.26 481.57 20.00% 4.90 722.36 30.00% 8.16 1,203.93 50.00% 8.16 1,203.92 50.00%
03.02.04 ELIM. MAT.CARG.MANUAL/VOLQUETE 10 M3,V=30 D= 7 KMS. M3 358.74 13.15 4,717.43 179.37 2,358.72 50.00% 107.62 1,415.23 30.00% 286.99 3,773.94 80.00% 71.75 943.49 20.00%
03.03 CONCRETO SIMPLE
03.03.01 SOLADO CONCRETO f'c = 140 KG/CM2 E = .10 M2 596.00 74.02 44,115.92 178.80 13,234.78 30.00% 178.80 13,234.78 30.00% 357.60 26,469.55 60.00% 238.40 17,646.37 40.00%
03.04 CONCRETO ARMADO
03.04.01 ZAPATAS
03.04.01.01 CONCRETO f'c= 210 kg/cm2 M3 362.60 480.44 174,207.54 108.78 52,262.26 30.00% 181.30 87,103.77 50.00% 290.08 139,366.04 80.00% 72.52 34,841.50 20.00%
03.04.01.02 ACERO DE REFUERZO f'y=4200 GRADO 60 KG 16,212.79 3.99 64,689.03 4,863.84 19,406.71 30.00% 8,106.40 32,344.52 50.00% 12,970.23 51,751.23 80.00% 3,242.56 12,937.80 20.00%
03.04.02 PANTALLA
03.04.02.01 CONCRETO f'c= 210 kg/cm2 M3 169.75 480.44 81,554.69 50.93 24,466.41 30.00% 67.90 32,621.88 40.00% 118.83 57,088.28 70.00% 50.93 24,466.41 30.00%
03.04.02.02 ENCOFRADO Y DESENCOFRADO MUROS DE CONTENCION M2 1,138.63 36.03 41,024.84 341.59 12,307.45 30.00% 455.45 16,409.94 40.00% 797.04 28,717.39 70.00% 341.59 12,307.45 30.00%
03.04.02.03 ACERO DE REFUERZO f'y=4200 GRADO 60 KG 11,438.25 3.99 45,638.62 3,431.48 13,691.59 30.00% 4,575.30 18,255.45 40.00% 8,006.78 31,947.03 70.00% 3,431.48 13,691.59 30.00%
03.04.02.04 JUNTAS CONTRACCION 1" SELLADAS CON ASFALTO M 55.90 11.93 666.89 0.00 0.00 0.00% 22.36 266.75 40.00% 22.36 266.75 40.00% 33.54 400.14 60.00%
03.04.02.05 JUNTAS DILATACION TECNOPOR 1" SELLADAS CON ASFALTO M 44.40 14.05 623.82 13.32 187.15 30.00% 17.76 249.53 40.00% 31.08 436.67 70.00% 13.32 187.15 30.00%
03.05 BARANDAS DE SEGURIDAD
03.05.01 BARANDA DE TUBO FIERRO GALVANIZADO M 150.00 53.17 7,975.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 150.00 7,975.50 100.00%
03.05.02 PINTURA EN BARANDAS METALICAS M 150.00 9.15 1,372.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 150.00 1,372.50 100.00%
VALORIZACIÓN DE OBRA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE SANTA CRUZ OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, VALORIZACION DE OBRA Nº 03
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras) LAS DALIAS, LOS FAICALES, 2 DE MAYO, LOS ROSALES, DEL DISTRITO DE SANTA CRUZ – PROVINCIA DE SANTA (DEL 01/12/2014 AL 31/12/2014)
CRUZ – CAJAMARCA
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego) DEPARTAMENTO: CAJAMARCA PROVINCIA : SANTA CRUZ
ESPECIFICACION PRESUPUESTO BASE VALORIZACION ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR VALORIZAR
PARTIDA DESCRIPCION UNIDADMETRADO PRECIO UNI PARCIAL METRADO PARCIAL % AVANCMETRADOPARCIAL % AVANC METRADO PARCIAL % AVANCE METRADO PARCIAL % AVANCE
04 CONSTRUCCION DE SARDINELES Y VEREDAS
04.01 OBRAS PRELIMINARES
04.01.01 DEMOLICION DE VEREDAS DE 0.10 m M2 673.97 17.27 11,639.46 269.59 4,655.78 40.00% 101.10 1,745.92 15.00% 370.68 6,401.70 55.00% 303.29 5,237.76 45.00%
04.01.02 TRAZO Y REPLANTEO CON EQUIPO M2 3,880.18 1.39 5,393.45 1,940.09 2,696.73 50.00% 582.03 809.02 15.00% 2,522.12 3,505.74 65.00% 1,358.06 1,887.71 35.00%
04.02 MOVIMIENTO DE TIERRAS 0.00
04.02.01 CORTE MATERIAL SUELTO H=.25 DE PROFUNDIDAD MANUAL M2 3,880.18 10.46 40,586.68 2,328.11 24,352.01 60.00% 582.03 6,088.00 15.00% 2,910.14 30,440.01 75.00% 970.05 10,146.67 25.00%
04.02.02 RELLENO CON AFIRMADO Y/O MAT. GRANULAR E = .15 M M2 3,880.18 19.49 75,624.71 1,552.07 30,249.88 40.00% 582.03 11,343.71 15.00% 2,134.10 41,593.59 55.00% 1,746.08 34,031.12 45.00%
04.02.03 EXCAVACION MANUAL DE ZANJA PARA SARDINEL (UÑAS) M3 79.85 40.17 3,207.57 31.94 1,283.03 40.00% 11.98 481.14 15.00% 43.92 1,764.17 55.00% 35.93 1,443.40 45.00%
04.02.04 ELIM. MAT.CARG.MANUAL/VOLQUETE 10 M3,V=30 D= 7 KMS. M3 1,414.52 13.15 18,600.94 848.71 11,160.56 60.00% 212.18 2,790.14 15.00% 1,060.89 13,950.70 75.00% 353.63 4,650.24 25.00%
04.03 CONCRETO EN VEREDAS
04.03.01 CONCRETO EN VEREDAS f'c = 175 KG/CM2 E = .10 M, ACABADO BRUÑADO M3 385.99 446.59 172,379.27 154.40 68,951.71 40.00% 57.90 25,856.89 15.00% 212.29 94,808.60 55.00% 173.70 77,570.67 45.00%
04.03.02 CONCRETO f'c=175 kg/cm2 EN UÑAS DE VEREDAS M3 79.85 433.22 34,592.62 31.94 13,837.05 40.00% 11.98 5,188.89 15.00% 43.92 19,025.94 55.00% 35.93 15,566.68 45.00%
04.03.03 ENCOFRADO Y DESENCOFRADO DE VEREDAS M2 918.30 28.60 26,263.38 367.32 10,505.35 40.00% 137.75 3,939.51 15.00% 505.07 14,444.86 55.00% 413.24 11,818.52 45.00%
04.03.04 CONCRETO F'C = 175 KG/CM2 GRADAS EN VEREDA e=0.10M M3 2.02 449.40 907.79 0.00 0.00 0.00% 1.01 453.89 50.00% 1.01 453.89 50.00% 1.01 453.90 50.00%
04.03.05 ENCOFRADO Y DESENCOFRADO GRADAS M2 9.65 33.90 327.14 0.00 0.00 0.00% 4.83 163.57 50.00% 4.83 163.57 50.00% 4.83 163.57 50.00%
04.03.06 CURADO CONCRETO M2 3,880.18 1.19 4,617.41 1,552.07 1,846.97 40.00% 1,164.05 1,385.22 30.00% 2,716.13 3,232.19 70.00% 1,164.05 1,385.22 30.00%
04.03.07 JUNTAS DILATACION TECNOPOR 1" SELLADAS CON ASFALTO M 1,294.54 14.05 18,188.29 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,294.54 18,188.29 100.00%
04.04 SARDINELES
04.04.01 MOVIMIENTO DE TIERRAS
04.04.01.01 EXCAVACION MANUAL DE ZANJA PARA SARDINEL M3 0.84 40.17 33.74 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.84 33.74 100.00%
04.04.02 CONCRETO EN SARDINELES
04.04.02.01 CONCRETO EN SARDINELES, F'C=175 KG/CM2 M3 1.19 446.59 531.44 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.19 531.44 100.00%
04.04.02.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES M2 4.26 28.60 121.84 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.26 121.84 100.00%
04.04.02.03 ACERO DE REFUERZO f'y=4200 GRADO 60 KG 12.27 3.99 48.96 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.27 48.96 100.00%
04.05 VARIOS
04.05.01 ENCIMADO DE CAJAS DOMICILIARIAS DE AGUA UND 119.00 72.57 8,635.83 54.00 3,918.78 45.38% 23.00 1,669.11 19.33% 77.00 5,587.89 64.71% 42.00 3,047.94 35.29%
04.05.02 ENCIMADO DE CAJAS DOMICILIARIAS DE DESAGUE UND 119.00 75.59 8,995.21 54.00 4,081.86 45.38% 23.00 1,738.57 19.33% 77.00 5,820.43 64.71% 42.00 3,174.78 35.29%
04.06 JARDINERIA
04.06.01 OBRAS PRELIMINARES
04.06.01.01 TRAZO Y REPLANTEO CON EQUIPO M2 803.70 1.39 1,117.14 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 803.70 1,117.14 100.00%
04.06.02 MOVIMIENTO DE TIERRAS
04.06.02.01 EXCAVACION MANUAL DE TERRENO M3 160.74 40.17 6,456.93 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.74 6,456.93 100.00%
04.06.02.02 ELIM. MAT.CARG.MANUAL/VOLQUETE 10 M3,V=30 D= 7 KMS. M3 200.93 13.15 2,642.23 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 200.93 2,642.23 100.00%
04.06.03 OBRAS DE CONCRETO
04.06.03.01 SARDINELES DE CONCRETO DE f'c=175 kg/cm2 EN JARDINERAS M3 30.35 446.59 13,554.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 30.35 13,554.01 100.00%
04.06.03.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES M2 269.80 36.19 9,764.06 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 269.80 9,764.06 100.00%
04.06.04 AREAS VERDES
04.06.04.01 AREAS VERDES M2 803.70 44.73 35,949.50 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 803.70 35,949.50 100.00%
04.06.04.02 PLANTONES UND 90.00 25.32 2,278.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 90.00 2,278.80 100.00%
VALORIZACIÓN DE OBRA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE SANTA CRUZ OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, VALORIZACION DE OBRA Nº 03
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras) LAS DALIAS, LOS FAICALES, 2 DE MAYO, LOS ROSALES, DEL DISTRITO DE SANTA CRUZ – PROVINCIA DE SANTA (DEL 01/12/2014 AL 31/12/2014)
CRUZ – CAJAMARCA
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego) DEPARTAMENTO: CAJAMARCA PROVINCIA : SANTA CRUZ
ESPECIFICACION PRESUPUESTO BASE VALORIZACION ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR VALORIZAR
PARTIDA DESCRIPCION UNIDADMETRADO PRECIO UNI PARCIAL METRADO PARCIAL % AVANCMETRADOPARCIAL % AVANC METRADO PARCIAL % AVANCE METRADO PARCIAL % AVANCE
05 OBRAS DE ARTE
05.01 ALCANTARILLA DE CONCRETO ARMADO DE 0.9x0.90M
05.01.01 OBRAS PRELIMINARES
05.01.01.01 DEMOLICION DE ALCANTARILLAS M2 22.00 29.27 643.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 643.94 100.00%
05.01.01.02 TRAZO Y REPLANTEO CON EQUIPO M2 25.20 1.39 35.03 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 25.20 35.03 100.00%
05.01.02 MOVIMIENTO DE TIERRAS
05.01.02.01 EXCAVACION MANUAL PARA ALCANTARILLA M3 13.37 48.19 644.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.37 644.30 100.00%
05.01.02.02 REFINE Y NIVELACION DE EXCAVACION M 10.40 5.21 54.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.40 54.18 100.00%
05.01.02.03 RELLENO CON MATERIAL PROPIO M3 13.10 15.07 197.42 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 13.10 197.42 100.00%
05.01.02.04 ELIM. MAT.CARG.MANUAL/VOLQUETE 10 M3,V=30 D= 7 KMS. M3 19.58 13.15 257.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.58 257.48 100.00%
05.01.03 CONCRETO SIMPLE
05.01.03.01 ENBOQUILLADO DE PIEDRA 8" CON MORTERO M2 2.88 45.60 131.33 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.88 131.33 100.00%
05.01.03.02 SOLADO CONCRETO f'c = 140 KG/CM2 E = .10 M2 22.68 74.02 1,678.77 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.68 1,678.77 100.00%
05.01.04 CONCRETO ARMADO EN ESTRUCTURAS DE ENTRADA Y SALIDA
05.01.04.01 CONCRETO f'c= 210 kg/cm2 EN LOSA DE FONDO M3 2.70 513.66 1,386.88 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.70 1,386.88 100.00%
05.01.04.02 CONCRETO f'c= 210 kg/cm2 EN LOSA DE SUPERIOR M3 2.81 513.66 1,443.38 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.81 1,443.38 100.00%
05.01.04.03 CONCRETO f'c= 210 kg/cm2 EN MUROS Y ALETAS M3 6.19 513.66 3,179.56 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 6.19 3,179.56 100.00%
05.01.04.04 ENCOFRADO Y DESENCOFRADO DE ALCANTARILLAS M2 19.92 45.06 897.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 19.92 897.60 100.00%
05.01.04.05 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 KG 1,144.93 3.99 4,568.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1,144.93 4,568.27 100.00%
05.01.05 TARRAJEO DE ALCANTARILLAS
05.01.05.01 TARRAJEO EN MUROS M2 44.97 41.18 1,851.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 44.97 1,851.86 100.00%
05.02 ALCANTARILLA DE CONCRETO ARMADO DE 1.5x(2.5-3.5)M
05.02.01 OBRAS PRELIMINARES
05.02.01.01 DEMOLICION DE ALCANTARILLAS M2 22.00 29.27 643.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 22.00 643.94 100.00%
05.02.01.02 TRAZO Y REPLANTEO CON EQUIPO M2 35.68 1.39 49.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.68 49.60 100.00%
05.02.02 MOVIMIENTO DE TIERRAS
05.02.02.01 EXCAVACION MANUAL PARA ALCANTARILLA M3 14.46 48.19 696.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 14.46 696.83 100.00%
05.02.02.02 REFINE Y NIVELACION DE EXCAVACION M 10.40 5.21 54.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.40 54.18 100.00%
05.02.02.03 RELLENO CON MATERIAL PROPIO M3 10.08 15.07 151.91 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.08 151.91 100.00%
05.02.02.04 ELIM. MAT.CARG.MANUAL/VOLQUETE 10 M3,V=30 D= 7 KMS. M3 18.97 13.15 249.46 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.97 249.46 100.00%
05.02.03 CONCRETO SIMPLE
05.02.03.01 ENBOQUILLADO DE PIEDRA 8" CON MORTERO M2 4.00 45.60 182.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.00 182.40 100.00%
05.02.03.02 SOLADO CONCRETO f'c = 140 KG/CM2 E = .10 M2 32.79 74.02 2,427.12 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.79 2,427.12 100.00%
05.02.04 CONCRETO ARMADO EN ESTRUCTURAS DE ENTRADA Y SALIDA
05.02.04.01 CONCRETO f'c= 210 kg/cm2 EN LOSA DE FONDO M3 4.84 513.66 2,486.11 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.84 2,486.11 100.00%
05.02.04.02 CONCRETO f'c= 210 kg/cm2 EN LOSA DE SUPERIOR M3 4.10 513.66 2,106.01 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 4.10 2,106.01 100.00%
05.02.04.03 CONCRETO f'c= 210 kg/cm2 EN MUROS Y ALETAS M3 17.63 513.66 9,055.83 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 17.63 9,055.83 100.00%
05.02.04.04 ENCOFRADO Y DESENCOFRADO DE ALCANTARILLAS M2 47.13 45.06 2,123.68 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 47.13 2,123.68 100.00%
05.02.04.05 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 KG 3,195.61 3.99 12,750.48 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 3,195.61 12,750.48 100.00%
05.02.05 TARRAJEO DE ALCANTARILLAS
05.02.05.01 TARRAJEO EN MUROS M2 114.34 41.18 4,708.52 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 114.34 4,708.52 100.00%
VALORIZACIÓN DE OBRA
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE SANTA CRUZ OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, VALORIZACION DE OBRA Nº 03
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras) LAS DALIAS, LOS FAICALES, 2 DE MAYO, LOS ROSALES, DEL DISTRITO DE SANTA CRUZ – PROVINCIA DE SANTA (DEL 01/12/2014 AL 31/12/2014)
CRUZ – CAJAMARCA
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego) DEPARTAMENTO: CAJAMARCA PROVINCIA : SANTA CRUZ
ESPECIFICACION PRESUPUESTO BASE VALORIZACION ANTERIOR VALORIZACION ACTUAL VALORIZACION ACUMULADO SALDO POR VALORIZAR
PARTIDA DESCRIPCION UNIDADMETRADO PRECIO UNI PARCIAL METRADO PARCIAL % AVANCMETRADOPARCIAL % AVANC METRADO PARCIAL % AVANCE METRADO PARCIAL % AVANCE
05.03 ALCANTARILLA DE TMC 36"
05.03.01 OBRAS PRELIMINARES
05.03.01.01 DEMOLICION DE ALCANTARILLAS M2 18.00 29.27 526.86 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 18.00 526.86 100.00%
05.03.01.02 TRAZO Y REPLANTEO CON EQUIPO M2 35.37 1.39 49.16 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 35.37 49.16 100.00%
05.03.02 MOVIMIENTO DE TIERRAS
05.03.02.01 EXCAVACION MANUAL PARA ALCANTARILLA M3 1.05 48.19 50.60 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.05 50.60 100.00%
05.03.02.02 REFINE Y NIVELACION DE EXCAVACION M 10.40 5.21 54.18 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.40 54.18 100.00%
05.03.02.03 RELLENO CON MATERIAL PROPIO M3 15.17 15.07 228.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 15.17 228.61 100.00%
05.03.02.04 ELIM. MAT.CARG.MANUAL/VOLQUETE 10 M3,V=30 D= 7 KMS. M3 12.11 13.15 159.25 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 12.11 159.25 100.00%
05.03.02.05 RELLENO CON AFIRMADO Y/O MAT. GRANULAR E = .15 M M2 23.13 19.49 450.80 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 23.13 450.80 100.00%
05.03.03 CONCRETO SIMPLE
05.03.03.01 ENBOQUILLADO DE PIEDRA 8" CON MORTERO M2 0.43 45.60 19.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.43 19.61 100.00%
05.03.03.02 SOLADO CONCRETO f'c = 140 KG/CM2 E = .10 M2 7.29 74.02 539.61 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 7.29 539.61 100.00%
05.03.04 CONCRETO ARMADO EN ALCANTARILLAS
05.03.04.01 CONCRETO f'c= 210 kg/cm2 EN CABEZAL ENTRADA Y SALIDA M3 2.44 463.23 1,130.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.44 1,130.28 100.00%
05.03.04.02 CONCRETO f'c= 210 kg/cm2 EN LOSA DE ENTRADA Y SALIDA M3 1.27 463.23 588.30 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.27 588.30 100.00%
05.03.04.03 ENCOFRADO Y DESENCOFRADO DE ALCANTARILLAS M2 26.88 45.06 1,211.21 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 26.88 1,211.21 100.00%
05.03.04.04 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 KG 152.76 3.99 609.51 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 152.76 609.51 100.00%
05.03.05 TUBERIA PARA ALCANTARILLA
05.03.05.01 TMC 36" M 10.40 595.33 6,191.43 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.40 6,191.43 100.00%
05.03.06 TARRAJEO DE ALCANTARILLAS
05.03.06.01 TARRAJEO EN MUROS M2 10.91 41.18 449.27 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 10.91 449.27 100.00%
05.04 CONSTRUCCION DE CUNETAS
05.04.01 OBRAS PRELIMINARES
05.04.01.01 TRAZO Y REPLANTEO CON EQUIPO M2 283.00 1.39 393.37 56.60 78.67 20.00% 120.00 166.80 42.40% 176.60 245.47 62.40% 106.40 147.90 37.60%
05.04.02 MOVIMIENTO DE TIERRAS
05.04.02.01 EXCAVACION MANUAL PARA CUNETAS M3 113.20 40.17 4,547.24 22.64 909.45 20.00% 45.28 1,818.90 40.00% 67.92 2,728.35 60.00% 45.28 1,818.89 40.00%
05.04.02.02 REFINE Y NIVELACION DE FONDO CAJA DE CUNETA M 471.66 5.16 2,433.77 94.33 486.75 20.00% 188.66 973.51 40.00% 283.00 1,460.26 60.00% 188.66 973.51 40.00%
05.04.02.03 ELIM. MAT.CARG.MANUAL/VOLQUETE 10 M3,V=30 D= 7 KMS. M3 141.50 13.15 1,860.73 28.30 372.15 20.00% 56.60 744.29 40.00% 84.90 1,116.44 60.00% 56.60 744.30 40.00%
05.04.03 CONCRETO CUNETAS
05.04.03.01 CONCRETO PARA CUNETAS F'C=175 KG/CM2 M3 66.03 446.59 29,488.34 13.21 5,897.67 20.00% 26.41 11,795.34 40.00% 39.62 17,693.00 60.00% 26.41 11,795.34 40.00%
05.04.03.02 ENCOFRADO Y DESENCOFRADO CUNETA M2 543.03 36.19 19,652.26 108.61 3,930.45 20.00% 217.21 7,860.90 40.00% 325.82 11,791.35 60.00% 217.21 7,860.91 40.00%
05.04.03.03 TAPAS DE CONCRETO F'C=175 KG/CM2 CUNETA E = .10 M M3 26.28 446.59 11,736.39 5.26 2,347.28 20.00% 10.51 4,694.55 40.00% 15.77 7,041.83 60.00% 10.51 4,694.56 40.00%
05.04.03.04 ACERO DE REFUERZO f'y=4200 GRADO 60 KG 1,602.79 3.99 6,395.13 320.56 1,279.03 20.00% 641.12 2,558.05 40.00% 961.67 3,837.08 60.00% 641.12 2,558.05 40.00%
05.04.03.05 REJILLA SUMIDERO A=0.40 m PLATINA 1 1/2"x1/4" @ 2" Y MARCO "L" 2 x 1/4" UND 70.00 234.31 16,401.70 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 70.00 16,401.70 100.00%
05.04.04 VARIOS
05.04.04.01 JUNTAS DILATACION TECNOPOR 1" SELLADAS CON ASFALTO M 189.00 14.05 2,655.45 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 189.00 2,655.45 100.00%
06 SEÑALIZACION
06.01 SEÑALES VERTICALES
06.01.01 SEÑALES PREVENTIVAS P-56 UND 1.00 294.62 294.62 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 294.62 100.00%
06.01.02 SEÑALES REGULADORAS R-30 UND 2.00 294.62 589.24 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2.00 589.24 100.00%
06.02 MARCAS EN EL PAVIMENTO
06.02.01 CRUCE PEATONAL M2 32.12 3.74 120.13 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 32.12 120.13 100.00%
06.02.02 LINEA CONTINUA M 487.48 3.04 1,481.94 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 487.48 1,481.94 100.00%
06.02.03 LINEA DISCONTINUA M 256.82 3.04 780.73 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 256.82 780.73 100.00%
06.02.04 PINTADO DE SARDINEL DE MURO M 160.00 3.04 486.40 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 160.00 486.40 100.00%
06.02.05 PINTADO DE SARDINEL DE VEREDA M 2,661.64 3.04 8,091.39 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 2,661.64 8,091.39 100.00%
06.02.06 SIMBOLOS Y FLECHAS M2 69.20 26.03 1,801.28 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 69.20 1,801.28 100.00%
07 OTROS
07.01 LIMPIEZA DE OBRA M2 12,873.56 1.40 18,022.98 5,149.42 7,209.19 40.00% 2,574.71 3,604.60 20.00% 7,724.14 10,813.79 60.00% 5,149.42 7,209.19 40.00%
07.02 FLETE TERRESTRE GLB 1.00 113,842.54 113,842.54 0.70 79,689.78 70.00% 0.19 21,687.00 19.05% 0.89 101,376.78 89.05% 0.11 12,465.76 10.95%
TOTLA DE COSTO DIRECTO 3,019,654.08 1,208,827.27 40.03% 607,503.60 20.12% 1,816,330.88 60.15% 1,203,323.20 39.85%
GASTOS GENERALES (8.00%) 241,572.33 96,706.18 48,600.29 145,306.47 96,265.86
UTILIDAD (7.00%) 211,375.79 84,617.91 42,525.25 127,143.16 84,232.63
SUB TOTAL 3,472,602.20 1,390,151.36 40.03% 698,629.14 20.12% 2,088,780.51 60.15% 1,383,821.69 39.85%
IMPUESTO GENERAL A LAS VENTAS (IGV 18%) 625,068.40 250,227.25 125,753.25 375,980.49 249,087.91
TOTAL 4,097,670.60 1,640,378.61 40.03% 824,382.39 20.12% 2,464,761.00 60.15% 1,632,909.60 39.85%
FACTOR DE RELACION 1.00000 1.00000 1.00000 1.00000 1.00000
TOTAL PRESUPUESTO POR F.R. 4,097,670.60 1,640,378.61 824,382.39 2,464,761.00 1,632,909.60
COMPARATIVO DE AVANCE DE OBRA Nº 01 - CURVA "S"
OBRA: "REMODELACION DE AULA DE INNOVACION PEDAGOGICA; EN EL (LA) IE Nº 16488 CHIRINOS, DISTRITO DE CHIRINOS, PROVINCIA DE SAN IGNACIO – DEPARTAMENTO DE CAJAMARCA"
ENTIDAD EJECUTORA: MUNICIPALIDAD DISTRITAL CHIRINOS RESIDENTE DE OBRA: Ing. Rony Castillo Garcia
MONTO TOTAL S/. 71,820.24 INSPECTOR : Ing. Rolando Durand de la Cruz
FECHA DE INICIO DE OBRA 4/29/2020
A V A N C E M E N S U A L A C U M U L A D O (% )
VALORIZACIÓN N° 01
90%
80%
70%
60%
50%
40%
30%
PROGRAMADO
CONTROL DE REAJUSTE
PROGRAMADO
Nº MES VALORIZACION KA K REAJUSTE
V-1 ÒCTUBRE - 2014 620,961.39 1.000 1.000 0.00
V-2 NOVIEMBRE 917,932.88 1.000 1.000 0.00
V-3 DICIEMBRE 677,978.90 1.000 1.000 0.00
EJECUTADO
Nº MES VALORIZACION KA K REAJUSTE
V-1 ÒCTUBRE - 2014 620,961.39 1.000 1.000 0.00
V-2 NOVIEMBRE 769,189.97 1.000 1.000 0.00
V-3 DICIEMBRE 698,629.14 1.000 1.000 0.00
NOTA: Como el reajuste ejecutado es menor que el reajuste programado, se paga el 100% el reajuste ejecutado
FORMULA POLINÓMICA
OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, LAS DALIAS, LOS FAICALES, 2 DE
MAYO, LOS ROSALES, DEL DISTRITO DE SANTA CRUZ – PROVINCIA DE SANTA CRUZ – CAJAMARCA"
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras)
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego)
AREA GEOGRÁFICA: 4
COEFICIENT
CODIGO I.U. BASE I.U. SET -
MONOMIO ELEMENTO SIMBOLO E %
I.U. MAY - 2014 2014
INCIDENCIA
1 MANO DE OBRA M 47 0.228 100.00% 309.81 309.81 0.228
2 AGREGADO GRUESO A `05 0.183 100.00% 305.20 305.20 0.183
3 CEMENTO PORTLAND TIPO I C 21 0.159 100.00% 300.48 300.48 0.159
4 ACERO DE CONSTRUCCION CORRUGADO A `03 0.087 100.00% 288.30 288.30 0.087
5 MAQUINARIA Y EQUIPO IMPORTADO M 49 0.198 100.00% 268.30 268.30 0.198
6 INDICE GENERAL DE PRECIOS AL CONSUMIDOR I 39 0.145 100.00% 325.32 325.32 0.145
K= 1.000
FACTOR DE ADELANTO DIRECTO Y ADELANTO DE MATERIALES - DICIEMBRE 2014
OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, LAS DALIAS, LOS FAICALES, 2 DE MAYO,
LOS ROSALES, DEL DISTRITO DE SANTA CRUZ – PROVINCIA DE SANTA CRUZ – CAJAMARCA"
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras)
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego)
AREA GEOGRÁFICA: 4
COEFICIENT
CODIGO I.U. BASE I.U. SET -
MONOMIO ELEMENTO SIMBOLO E %
I.U. MAY - 2014 2014
INCIDENCIA
1 MANO DE OBRA M 47 0.228 100.00% 309.81 309.81
2 AGREGADO GRUESO A `05 0.183 100.00% 305.20 305.20
3 CEMENTO PORTLAND TIPO I C 21 0.159 100.00% 300.48 300.48
4 ACERO DE CONSTRUCCION CORRUGADO A `03 0.087 100.00% 288.30 288.30
5 MAQUINARIA Y EQUIPO IMPORTADO M 49 0.198 100.00% 268.30 268.30
6 INDICE GENERAL DE PRECIOS AL CONSUMIDOR I 39 0.145 100.00% 325.32 325.32
K=
LES - DICIEMBRE 2014
S DALIAS, LOS FAICALES, 2 DE MAYO,
0.228
0.183
0.159
0.087
0.198
0.145
1.000
RESUMEN DE LA VALORIZACION N° 03 - DEL SUPERVISOR DE OBRA
OBRA: "CREACION DE PISTAS Y VEREDAS EN LAS CALLES CAJAMARCA, TRUJILLO, LOS PINOS, SERGIO ORREGO, LAS DALIAS, LOS FAICALES, 2 DE MAYO, LOS ROSALES, DEL DISTRITO DE
SANTA CRUZ – PROVINCIA DE SANTA CRUZ – CAJAMARCA"
MODALIDAD DE EJECUCION: POR CONTRATA (A SUMA ALSADA)
CONTRATISTA: CONSORCIO RIOS (ING. Armando A. Salomón Higueras)
SUPERVISOR : HONSAMAA S.A.C. (ING. Manuel Ulises Cotrina Orrego)
FECHA DE VALORIZACIÓN : DEL 01 DE DICIEMBRE DEL 2014 AL 31 DE DICIEMBRE DEL 2014
PRESUPUESTO CONTRATADO CONSORCIO RIOS 4,097,670.60 1,640,378.61 40.03% 824,382.39 20.12% 2,464,761.00 60.15% 1,632,909.60 39.85%
SUPERVISION DE OBRA (HONSAMAA SAC) 122,930.12 49,211.36 24,731.47 73,942.83 48,987.29
COSTO TOTAL DE OBRA 4,220,600.72 1,689,589.97 849,113.86 2,538,703.83 1,681,896.89