Está en la página 1de 1

ITEM DESCRIPCION MONTO SOLES %

1 MANO DE OBRA S/. 41,761.40 11.31%


2 MATERIALES S/. 4,301.41 1.17%

3 EQUIPOS Y HERRAMIENTAS S/. 296,292.41 80.25%

4 SUBCONTRATOS S/. 26,844.40 7.27%


COSTO DIRECTO S/. 369,199.62
GASTOS GENERALES 9.43% S/. 34,812.24
UTILIDAD 8.8% S/. 32,489.57
SUB TOTAL DE PRESUPUESTO S/. 436,501.42
IGV 18% S/. 78,570.26
PRESUPUESTO TOTAL S/. 515,071.68 100.00% S/. 26,117.93
S/. 9,327.83

ITEM DESCRIPCION MONTO %


1 OBRAS PRELIMINARES S/. 35,456.98 9.60%
2 PAVIMENTOS S/. 205,519.20 55.67%
3 TRANSPORTES S/. 119,686.15 32.42%
REPOSICIÓN DE SEÑALES
4 S/. 4,321.97 1.17%
VERTICALES

5 LIMPIEZA DE ALCANTARILLA S/. 1,202.78 0.33%

6 IMPACTO AMBIENTAL S/. 3,012.54 0.82%


TOTAL COSTO DIRECTO : S/. 369,199.62 100.00%

ITEM DESCRIPCION MONTO SOLES %


1 MANO DE OBRA S/. 41,761.40 11.31%
2 MATERIALES S/. 4,301.41 1.17%

3 EQUIPOS Y HERRAMIENTAS S/. 296,292.41 80.25%

4 SUBCONTRATOS S/. 26,844.40 7.27%


TOTAL COSTO DIRECTO : 369,199.62 100.00%

También podría gustarte