CALCULO DE COSTO DE ASFALTO PARA LA VIA NUEVOS

HORIZONTES - LUZ Y VIDA - RIO BLANCO


LONGITUD(KM): 07.83 KM ESPESOR(M): 0.075 M
ANCHO(M): 7.200 M
AC20
LONGITUD(M) ANCHO ASF. ESPESOR (M) ESPONJAMIENTO VOLUMEN(M3)
7830 7.20 0.075 20% 5073.84
VOLUMEN(m3) GLN AC20 TOTAL AC20(GL) TOTAL AC20(KG)
5073.84 35 177584.4 672157
COSTO AC20(e=0.075m)
# DE TANQUEROS VALOR U. VALOR TOTAL
$ 291,240.00
20.00 $ 14,562.00 $ 291,240.00

RC250
LONGITUD(m) ANCHO ASF. LITROS X M2 TOTAL GL. TOTAL KG.
7830 7.20 2.20 32768.08 124027

COSTO RC2(e=0.075m)
# DE TANQUEROS VALOR U. VALOR TOTAL
$ 58,248.00
4 $ 14,562.00 $ 58,248.00

DIESEL
VOLUMEN(m3) GL X M3 CANT. DIESEL (GL)
5073.84 10.00 50738.40
TOTAL LT. RC2 25% DIESEL GL. CANT. DIESEL (GL)
84955.50 5611.33 5611.33

TOTAL DIESEL (GL) VALOR U. VALOR TOTAL


56349.73 $ 2.10 $ 118,334.43

COSTO DIESEL(e=0.075m)
TOTAL DIESEL (GL) TRANSP. X GL VALOR TOTAL
$ 124,532.90
56349.73 $ 0.11 $ 6,198.47

COSTO TOTAL(e=0.075m)

$ 474,020.90

SON: CUATROCIENTOS SETENTA Y CUATRO MIL VEINTE DOLARES CON, 90/100


CALCULO DE COSTO DE ASFALTO PARA LA VIA NUEVOS HORIZONTES - LUZ
Y VIDA - RIO BLANCO
LONGITUD(KM): 08 KM

MEJORAMIENTO 9.60M ANCHO X 0.4M ESPESOR


LONGITUD(KM) ANCHO X ESPESOR VOLUMEN C/KM ESPONJAMIENTO VOLUMEN(M3)
07.8 KM 4 4000.00 30% 40716.00
COSTO MEJORAMIENTO
VOLUMEN (M3) VALOR U. VALOR TOTAL
$ 236,152.80
40716 $ 5.80 $ 236,152.80

TRANSPORTE MEJORAMIENTO
VOLUMEN (M3) DISTANCIA PROM. TOTAL M3/KM
40716 10.92 444415.14

COSTO TRANSPORTE MEJORAMIENTO


TOTAL M3/KM VALOR U. VALOR TOTAL
$ 88,883.03
444415.14 $ 0.20 $ 88,883.03

SUBBASE 9.30M ANCHO X 0.15M ESPESOR


LONGITUD(KM) ANCHO X ESPESOR VOLUMEN C/KM ESPONJAMIENTO VOLUMEN(M3)
07.8 KM 1.4175 1417.50 30% 14428.73

COSTO SUBBASE
VOLUMEN (M3) VALOR U. VALOR TOTAL
$ 115,429.86
14428.73 $ 8.00 $ 115,429.86

TRANSPORTE SUBBASE
VOLUMEN (M3) DISTANCIA PROM. TOTAL M3/KM
14428.73 10.92 157489.62

COSTO TRANSPORTE SUBBASE


TOTAL M3/KM VALOR U. VALOR TOTAL
$ 31,497.92
157489.62 $ 0.20 $ 31,497.92

BASE 7.60M ANCHO X 0.15M ESPESOR

LONGITUD(KM) ANCHO X ESPESOR VOLUMEN C/KM ESPONJAMIENTO VOLUMEN(M3)


07.8 KM 1.1625 1162.50 25% 11377.97

COSTO BASE
VOLUMEN (M3) VALOR U. VALOR TOTAL
$ 136,535.63
11377.97 $ 12.00 $ 136,535.63

TRANSPORTE BASE

VOLUMEN (M3) DISTANCIA PROM. TOTAL M3/KM


11377.97 12.97 147515.36

COSTO TRANSPORTE BASE


TOTAL M3/KM VALOR U. VALOR TOTAL
$ 29,503.07
147515.36 $ 0.20 $ 29,503.07
MEZCLA ASFÁLTICA
PRODUCCIÓN

VOLUMEN (M3) PRECIO UNITARIO PRECIO TOTAL COSTO PRODUCCIÓN


5073.8 M3 29.37 149018.68
$ 149,018.68

TENDIDO

VOLUMEN (M3) PRECIO UNITARIO PRECIO TOTAL COSTO TENDIDO


5073.8 M3 25.75 130651.38
$ 130,651.38

TRANSPORTE ASFALTO

VOLUMEN (M3) DISTANCIA PROM. TOTAL M3/KM


5073.84 12.97 65782.34

COSTO TRANSPORTE ASFALTO


TOTAL M3/KM VALOR U. VALOR TOTAL
65782.34 $ 0.20 $ 13,156.47 $ 13,156.47

GEOTEXTIL
LONGITUD (M) ANCHO PROM. AREA (M2) AREA EXC. ALC. M2 AREA GEOT. (M2)
7830 4.00 31320.00 2560.00 2560.00
AREA (M2) TRASLAPES (10%) AREA TOTAL (M2) ROLLOS
33880.00 10% 37268.00 62.11

COSTO GEOTEXTIL
ROLLOS VALOR U. VALOR TOTAL
$ 24,180.00
62.00 $ 390.00 $ 24,180.00

ALCANTARILLAS GALVANIZADAS
LONG. VIA (KM) LONG. DE ALC. TOTAL
08 KM 320.00 320.00

COSTO ALCANTARILLAS GALVANIZADAS


TOTAL ALC. (ML) VALOR U. PROM. VALOR TOTAL
$ 41,600.00
320.00 $ 130.00 $ 41,600.00

EXC. Y RELLENO PARA ESTRUC.


LONG. VIA (KM) LONG. DE ALC. TOTAL ALC. (U)
08 KM 330.00 20.00

TOTAL ALC. (U) EXC. RELLENO (M3) TOTAL (M3)


20.00 402.00 8040.00

COSTO EXC. Y RELLENO PARA ESTRUC.


TOTAL (M3) VALOR U. PROM. VALOR TOTAL
$ 70,752.00
8040.00 $ 8.80 $ 70,752.00

COSTO TOTAL
$ 1,067,360.84

SON: UN MILLON SESENTA Y SIETE MIL TRESCIENTOS SESENTA DOLARES CON, 84/100