PRESUPUESTO CONTENEDORES

SAN LUIS

ITEM DESCRIPCION UND CANT VR UNIT TOTAL

1.0 CONTENEDORES
1.1 CONTENEDORES HIGH CUBE 40' UND 15 $ 11,543,000 $ 173,145,000
1.2 CONTENEDORES HIGH CUBE 10' UND 1 $ 11,543,000 $ 11,543,000
1.3 ADECUACION ESTRUCTURAL POR CONTENEDOR UND 16 $ 2,000,000 $ 32,000,000
SUB - TOTAL $ 216,688,000

2.0 PUERTAS
2.1 PUERTAS DE ACERO 32"x78" CON CHAPA UND 18 $ 280,000 $ 5,040,000
2.2 PUERTA DE METAL TIPO GARAJE 10' x 7' UND 11 $ 1,677,500 $ 18,452,500
SUB - TOTAL $ 23,492,500

3.0 VENTANAS
3.1 VENTANA METALICA ABATIBLES DE 2 HOJAS 1,50 x1,20 UND 30 $ 270,000 $ 8,100,000
SUB - TOTAL $ 8,100,000

4.0 ESCALERA
4.1 ESCALERA DE ACERO UND 4 $ 3,250,000 $ 13,000,000
SUB - TOTAL $ 13,000,000

5.0 PINTURA
5.1 PINTURA BLANCA EXTERIOR GL 320 $ 47,000 $ 15,040,000
5.2 PINTURA EPOXICA COLOR GRIS MAS DISOLVENTE GL 96 $ 120,000 $ 11,520,000
5.3 MANO DE OBRA PINTURA EXTERIOR 16 $ 500,000 $ 8,000,000
5.4 MANO DE OBRA PINTURA PISO 16 $ 150,000 $ 2,400,000
SUB - TOTAL $ 36,960,000

6.0 MADERA - REVESTIMIENTO EN MADERA CONTRACHAPADA


6.1 MADERA MELAMINICO 18MM RH UND 15 $ 10,660,000 $ 159,900,000
6.2 ESTRUCTURA SOPORTE LAMINA DE MADERA UND 1 $ 5,330,000 $ 5,330,000
6.3 MANO DE OBRA INSTALACION MADERA ND 16 $ 3,000,000 $ 48,000,000
SUB - TOTAL $ 213,230,000

7.0 TRANSPORTE
7.1 SITIO DE COMPRA AL SITIO DE ADECUACION VJ $ 16,000,000
7.2 SITIO DE ADECUACION A SITIO DE OBRA VJ $ 7,200,000
7.3 DESCARGUE Y UBICACIÓN DE EQUIPOS DIA 5 $ 1,200,000 $ 6,000,000
SUB - TOTAL $ 29,200,000

8.0 LAMPARAS
8.1 LAMPARAS LED 40W UND 4 $ 850,000 $ 3,400,000
SUB - TOTAL $ 3,400,000

9.0 ASEO
9.1 ASEO GENERAL UND 15 $ 100,000 $ 1,500,000
SUB - TOTAL $ 1,500,000

TOTAL COSTOS DIRECTOS $ 545,570,500


IMPREVISTOS 3% $ 10,911,410
ADMINSTRACION 7% $ 27,278,525
UTILIDAD 8% $ 16,367,115
TOTAL COSTO GENERAL DE OBRA $ 600,127,550
DURACION EN
ACTIVIDADES FECHA DE INICIO DIAS
TRANSPORTE DE CONTENEDORES 15-May 5
INSTALACION EQUIPOS EN OBRA Y ACABADOS 20-May 5
LIMPIEZA Y PINTURA BASE 25-Jun 10
ADECUACION CONTENEDORES 4-Jun 10
INSTALACION Y FABRICACION PUERTAS Y VENTANAS 14-Jun 8
INSTALACION Y FABRICACION DE ESCALERAS 22-Jun 8
PINTURA EXTERIOR 30-Jun 10
PINTURA PISO 10-Jul 3
ESTRUCTURA DE MADERA 13-Jul 12
INSTALACIONA DE LAMPARAS 25-Jul 1
ASEO GENERAL 27-Jul 3
75
INICIO PROYECTO 43600
FIN PROYECTO 43675
FECHA FINAL
DIAGRAMA GANTT
19-May
24-May 15-May 25-May 4-Jun 14-Jun 24-Jun 4-Jul 14-Jul 24-Jul
3-Jun TRANSPORTE DE CONTENEDORES
13-Jun INSTALACION EQUIPOS EN OBRA Y ACABADOS
21-Jun
LIMPIEZA Y PINTURA BASE
29-Jun
9-Jul ADECUACION CONTENEDORES
12-Jul INSTALACION Y FABRICACION PUERTAS Y VENTANAS
24-Jul
INSTALACION Y FABRICACION DE ESCALERAS
26-Jul
29-Jul PINTURA EXTERIOR

PINTURA PISO

ESTRUCTURA DE MADERA

INSTALACIONA DE LAMPARAS

ASEO GENERAL
n 4-Jul 14-Jul 24-Jul 3-Aug