Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PRESUPUESTO
PROYECTO EXAMEN FINAL
FECHA 22 Junio 2016.

ITEM DESCRIPCIÓN UNIDAD METRADO PRECIO PARCIAL SUB TOTAL

01.00.00 OBRAS PRELIMINARES


01.01.00 OFICINAS m2 96.00 144.84 13,904.60
01.02.00 TRAZO Y REPLANTEO m2 2,400.00 4.71 11,293.51
01.03.00 TRAZO DE NIVELES Y REPLANTEO DURANTE EL PROCESO m2 2,400.00 37.35 89,639.11 114,837.23
MOVIMIENTO DE TIERRAS 0.00
01.04.00 EXCAVACION DE ZANJAS m3 960.00 77.66 74,557.22
01.05.00 CORTE MANUAL DE TERRENO m3 1,440.00 22.65 32,618.78
01.06.00 ACARREO DE MATERIAL EXCEDENTE m3 1,920.00 18.25 35,035.97
01.07.00 ELIMINACION DESMONTE CON EQUIPO m3 768.00 30.68 23,561.98
01.08.00 RELLENO CON MATERIAL PROPIO m3 1,440.00 43.86 63,155.38
01.09.00 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 384.00 46.22 17,748.28
01.10.00 NIVELACION INTERIOR Y COMPACTACION m2 2,400.00 7.60 18,229.42 264,907.03
02.00.00 OBRAS DE CONCRETO SIMPLE 0.00
02.01.00 SOLADO DE 2" MEZCLA 1:12 CEMENTO HORMIGON m2 2,880.00 22.44 64,618.34
02.02.00 FALSO CIMIENTO m3 1,152.00 156.12 179,854.49
02.03.00 CONCRETO F'c=100 Kg/cm2 PARA CIMIENTOS m3 1,344.00 141.66 190,395.73
02.04.00 CONCRETO F'c=120 Kg/cm2 PARA SOBRECIMIENTOS m3 1,440.00 204.19 294,029.90
02.05.00 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS m2 3,840.00 45.53 174,826.41
02.06.00 CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGON E=4" m2 3,840.00 24.41 93,746.42 997,471.29
03.00.00 OBRAS DE CONCRETO ARMADO 0.00
03.01.00 SOBRECIMIENTOS 0.00
03.01.01 ACERO EN SOBRECIMIENTO REFORZADO GRADO 60 kg 11,520.00 6.40 73,701.61 73,701.61
03.02.00 PLACAS 0.00
03.02.01 CONCRETO EN MUROS TABIQUES Y PLACAS F'C= 175 KG/CM2 m3 480.00 301.22 144,583.89
03.02.02 ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS kg 19,200.00 6.28 120,611.02
03.02.03 ENCOFRADO Y DESENCOFRADO NORMAL EN MUROS TABIQUES Y PLACAS m2 1,152.00 62.18 71,627.45 336,822.36
03.03.00 VIGAS 0.00
03.03.01 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2 768.00 66.92 51,395.24
03.03.02 ACERO GRADO 60 EN VIGAS kg 19,200.00 6.96 133,581.86
03.03.03 CONCRETO F'c = 175 Kg/CM2 m3 96.00 236.30 22,684.43 207,661.53
03.04.00 LOSAS ALIGERADAS 0.00
03.04.01 CONCRETO PARA VIGAS DE F'c= 280 KG/m2 m3 1,152.00 264.56 304,768.54
03.04.02 CONCRETO DE F'c=175 KG/m2 , CON 10 CM DE ESPESOR m2 1,728.00 183.45 316,993.55
03.04.03 ENCOFRADO Y DESENCOFRADO m2 1,728.00 43.90 75,859.26
03.04.04 ACERO GRADO 60 EN LOSAS ALIGERADAS kg 5,280.00 6.40 33,779.90
03.04.05 CONCRETO F'c = 175 Kg/CM2 m3 480.00 239.29 114,858.75 846,259.99
03.05.00 LOSA MACIZA 0.00
03.05.01 CONCRETO F'C=175 kg/cm2 m3 288.00 184.27 53,070.60
03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS m2 288.00 42.03 12,105.30
03.05.03 ACERO GRADO 60 EN LOSAS MACIZAS kg 1,152.00 6.40 7,370.16 72,546.05
03.06.00 MUROS DE ALBAÑILERIA ARMADA 0.00
03.06.01 ACERO EN MURO DE ALBANILERIA ARMADA kg 3,360.00 6.28 21,106.93
03.06.02 CONCRETO LIQUIDO EN MUROS m3 480.00 181.74 87,234.18
03.06.03 MURO DE LADRILLO KING KONG m2 5,280.00 76.76 405,270.94
03.06.04 MURO DE LADRILLO DE SOGA KING KONG m2 1,920.00 79.36 152,362.02 665,974.07
01.00.00 ARQUITECTURA 0.00
01.01.00 MUROS Y TABIQUES 0.00
01.01.01 MURO CON LADRILLO PANDERETA DE CABEZA m2 960.00 85.16 81,753.00
01.01.02 MURO DE LADRILLO PANDERETA DE SOGA m2 960.00 65.28 62,668.19 144,421.19
01.02.00 REVOQUES ENLUCIDOS Y MOLDURAS 0.00
01.02.01 TARRAJEO PRIMARIO O RAYADO m2 960.00 23.81 22,853.85
01.02.02 TARRAJEO EN INTERIORES m2 1,440.00 18.48 26,604.91 49,458.75
01.03.00 MESAS DE CONCRETO 0.00 0.00
01.03.01 MESAS DE CONCRETO PARA COCINA und 96.00 99.27 9,530.20 9,530.20
01.04.00 PISOS Y PAVIMENTOS 0.00
01.04.01 CONTRAPISO DE 50 mm m2 1,440.00 28.94 41,671.32
01.04.02 CONTRAPISO DE 35 mm m2 1,440.00 18.90 27,212.02
01.04.03 PISO DE CERAMICO 20 x 20 m2 1,248.00 55.24 68,933.53
01.04.04 PISO DE CEMENTO PULIDO Y BRUÑADO m2 1,920.00 58.68 112,661.88 250,478.76
01.05.00 CONTRAZOCALOS 0.00 0.00
01.05.01 CONTRAZOCALO CEMENTO SIN COLOREAR H = 20 cm PULIDO m 2,400.00 17.51 42,032.54 42,032.54

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

01.06.00 ZOCALOS 0.00


01.06.01 ZOCALO DE CERAMICO 20X20 m2 480.00 61.88 29,703.18
01.06.02 ZOCALO DE CEMENTO SIMPLE MEZCLA CEMENTO-ARENA m2 480.00 20.76 9,967.13 39,670.31
01.07.00 CARPINTERIA DE MADERA 0.00
01.07.01 PUERTA PRINCIPAL DE CEDRO DE 0.80 M DE ANCHO und 96.00 199.76 19,176.65
01.07.02 PUERTA POSTERIOR CONTRAPLACADA DE 0.65 M DE ANCHO und 96.00 211.84 20,336.25
01.07.03 PUERTAS INTERIORES CONTRAPLACADAS DE 0.65 M DE ANCHO und 768.00 196.11 150,609.33
01.07.04 PUERTA CORREDIZA DE 1.80 X 1.80 M und 96.00 358.26 34,392.52 224,514.75
01.08.00 CARPINTERIA METALICA 0.00 0.00
01.08.01 ESCALERA METALICA DE 25 PASOS und 96.00 590.91 56,727.40 56,727.40
01.09.00 CARPINTERIA DE ALUMINIO 0.00
01.09.01 VENTANA PRINCIPAL DE 1.80 X 0.90 M DE 2 HOJAS und 96.00 91.60 8,793.21
01.09.02 VENTANA POSTERIOR DE 1.20 X 0.90 M DE 2 HOJAS und 96.00 98.08 9,415.41
01.09.03 VENTANAS EN DORMITORIOS DE 1.50 X .90 M DE 2 HOJAS und 384.00 177.19 68,041.65
01.09.04 VENTANA CORREDIZA DE 1.55 X .90 M DE 2 HOJAS und 384.00 189.76 72,869.15 159,119.41
01.10.00 COLOCACION DE APARATOS 0.00
01.10.01 INODORO COLOR BLANCO ECONOMICO pza 192.00 199.98 38,395.34
01.10.02 LAVATORIO DE PARED BLANCO pza 192.00 206.48 39,643.34
01.10.03 LAVADERO DE ACERO INOXIDABLE pza 192.00 180.73 34,700.51
01.10.04 LAVADERO DE GRANITO pza 96.00 180.73 17,350.25
01.10.05 DUCHA SIMPLE CROMADA 1 LLAVE INCLUYE ACCESORIOS und 192.00 185.29 35,576.03 165,665.47
01.11.00 VARIOS 0.00
01.11.01 JUNTA DE POLIURETANO m 384.00 12.00 4,608.24
01.11.02 BRUÑAS EN MUROS m 768.00 13.59 10,438.01
01.11.03 LIMPIEZA GENERAL DE OBRA m2 9,600.00 2.72 26,095.03 41,141.28
01.01.00 INSTALACION DE AGUA 0.00
01.01.01 RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP m 2,880.00 20.56 59,204.41
01.01.02 SALIDA DE AGUA FRIA DE 1/2" pto 2,400.00 106.78 256,264.80
01.01.03 VALVULAS DE COMPUERTA DE BRONCE DE 1/2" pza 192.00 80.23 15,404.82 330,874.03
01.02.00 INSTALACION DE DESAGUE 0.00
01.02.01 RED DE DESAGUE DE 4" EN PVC m 1,440.00 56.31 81,092.06
01.02.02 RED DE DESAGUE DE 2" EN PVC m 480.00 48.55 23,302.25
01.02.03 TUBERIA DE DESAGUE PVC SAL DE 2" PARA VENTILACION m 4,800.00 48.76 234,024.70
01.02.04 SALIDA DE DESAGUE DE 4" pto 192.00 82.54 15,848.03
01.02.05 SALIDA DE DESAGUE DE 2" pto 192.00 64.79 12,440.03
01.02.06 CAJA DE REGISTRO DE ALBAÑILERIA DE 10" X 20" pza 192.00 31.49 6,045.67
01.02.07 REGISTRO ROSCADO DE BRONCE DE 2" pza 192.00 34.97 6,715.00
01.02.08 REGISTRO ROSCADO DE BRONCE DE 4" pza 192.00 17.87 3,431.80 382,899.53
01.00.00 INSTALACION ELECTRICA 0.00
01.01.01 CENTRO DE LUZ pto 960.00 83.41 80,073.02
01.01.02 SALIDA PARA BRAQUETES pto 480.00 78.62 37,739.71
01.01.03 SALIDA DE INTERRUPTOR SIMPLE pto 960.00 36.59 35,128.06
01.01.04 SALIDA DE INTERRUPTOR DOBLE pto 480.00 91.65 43,991.23
01.01.05 SALIDA DE INTERRUPTOR DE CONMUTACION pto 192.00 90.54 17,384.14
01.01.06 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON LINEA A TIERRA pto 1,440.00 100.86 145,238.96
01.01.07 SALIDA DE TIMBRE pto 96.00 220.15 21,134.25
01.01.08 TABLERO DE DISTRIBUCION und 96.00 103.19 9,906.29
01.01.09 POZO DE CONEXION A TIERRA pza 96.00 476.66 45,759.64
01.01.10 MURETE PARA CONEXIÓN DOMICILIARIA und 96.00 297.26 28,536.67 464,891.97

COSTO DIRECTO S/. 5,941,606.77


GASTOS GENERALES Y DIRECCIÓN TÉCNICA S/. 1,485,401.69

______________
SUB-TOTAL S/. 7,427,008.46
IGV (18%) S/. 1,336,861.52
______________
TOTAL GENERAL S/. 8,763,869.98

$0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

OBRAS PRELIMINARES
PROYECTO: EXAMEN FINAL 1
PRECIO UNITARIO: OFICINAS
RENDIMIENTO EN 8 HRS: 12 M2/DIA
APORTE: 0.6667 HRS/M2 TOTAL P.U. 144.84
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.67 0.00
CAPATAZ H-H 0.10 22.89 0.67 1.53
OPERARIO H-H 1.00 19.18 0.67 12.79
OFICIAL H-H 0.00 15.90 0.67 0.00
PEON H-H 1.00 14.30 0.67 9.53
TOTAL MO 23.85
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 23.85 2.38
CEMENTO TIPO I BLS 3.10 14.83 2.97
HORMIGON M3 0.08 30.00 63.00
AGUA M3 0.08 5.70 3.99
CALAMINA PZA 0.20 14.83 45.97
MADERA TORNILLO P2 2.10 6.50 0.52
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.70 27.00 2.16
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 120.99
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.67 0.00
GRASA KG 0.00 9.39 0.67 0.00
GASOLINA GLN 0.00 11.00 0.67 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.67 0.00
0.67 0.00
0.67 0.00
TOTAL VAR 0.00
TOTAL P.U. 144.84

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 2


PRECIO UNITARIO: TRAZO Y REPLANTEO
RENDIMIENTO EN 8 HRS: 500 M2/DIA
APORTE: 0.0160 HRS/M2 TOTAL P.U. 4.71
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 1.00 25.08 0.02 0.40
CAPATAZ H-H 0.10 22.89 0.02 0.04
OPERARIO H-H 0.00 19.18 0.02 0.00
OFICIAL H-H 0.00 15.90 0.02 0.00
PEON H-H 2.00 14.30 0.02 0.46
TOTAL MO 0.90
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 0.90 0.09
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA TORNILLO P2 0.30 6.50 1.95
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.30 0.50 0.15
CORDEL ML 0.50 2.80 1.40
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 3.59
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.02 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.02 0.00
GRASA KG 0.00 9.39 0.02 0.00
GASOLINA GLN 0.00 11.00 0.02 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TEODOLITO H-M 1.00 8.80 0.02 0.14
SOPORTE H-M 1.00 0.74 0.02 0.01
MIRA DE MADERA H-M 2.00 1.50 0.02 0.05
WINCHA H-M 0.05 20.00 0.02 0.02
TOTAL EQUIP 0.22
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.02 0.00
0.02 0.00
0.02 0.00
TOTAL VAR 0.00
TOTAL P.U. 4.71

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 3


PRECIO UNITARIO: TRAZO DE NIVELES Y REPLANTEO DURANTE EL PROCESO
RENDIMIENTO EN 8 HRS: 500 M2/DIA
APORTE: 0.0160 HRS/M2 TOTAL P.U. 37.35
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 1.00 25.08 0.02 0.40
CAPATAZ H-H 0.10 22.89 0.02 0.04
OPERARIO H-H 0.00 19.18 0.02 0.00
OFICIAL H-H 0.00 15.90 0.02 0.00
PEON H-H 2.00 14.30 0.02 0.46
TOTAL MO 0.90
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 0.90 0.09
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA TORNILLO P2 2.21 6.50 14.37
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.80 27.00 21.60
CAL KG. 0.03 0.50 0.02
CORDEL ML 0.06 2.80 0.17
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 36.24
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.02 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.02 0.00
GRASA KG 0.00 9.39 0.02 0.00
GASOLINA GLN 0.00 11.00 0.02 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TEODOLITO H-M 1.00 8.80 0.02 0.14
SOPORTE H-M 1.00 0.74 0.02 0.01
MIRA DE MADERA H-M 2.00 1.50 0.02 0.05
WINCHA H-M 0.05 20.00 0.02 0.02
TOTAL EQUIP 0.22
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.02 0.00
0.02 0.00
0.02 0.00
TOTAL VAR 0.00
TOTAL P.U. 37.35

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
MOVIMIENTO DE TIERRAS
PROYECTO: EXAMEN FINAL 4
PRECIO UNITARIO: EXCAVACION DE ZANJAS
RENDIMIENTO EN 8 HRS: 3.5 M3/DIA
APORTE: 2.2857 HRS/M3 TOTAL P.U. 77.66
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.29 0.00
CAPATAZ H-H 0.10 22.89 2.29 5.23
OPERARIO H-H 0.00 19.18 2.29 0.00
OFICIAL H-H 0.00 15.90 2.29 0.00
PEON H-H 2.00 14.30 2.29 65.37
TOTAL MO 70.60
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 70.60 7.06
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA TORNILLO P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 7.06
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.29 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.29 0.00
GRASA KG 0.00 9.39 2.29 0.00
GASOLINA GLN 0.00 11.00 2.29 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.29 0.00
H-M 2.29 0.00
H-M 2.29 0.00
H-M 2.29 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.29 0.00
2.29 0.00
2.29 0.00
TOTAL VAR 0.00
TOTAL P.U. 77.66

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 5


PRECIO UNITARIO: CORTE MANUAL DE TERRENO
RENDIMIENTO EN 8 HRS: 12 M3/DIA
APORTE: 0.6667 HRS/M3 TOTAL P.U. 22.65
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.67 0.00
CAPATAZ H-H 0.10 22.89 0.67 1.53
OPERARIO H-H 0.00 19.18 0.67 0.00
OFICIAL H-H 0.00 15.90 0.67 0.00
PEON H-H 2.00 14.30 0.67 19.07
TOTAL MO 20.59
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 20.59 2.06
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA TORNILLO P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 2.06
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.67 0.00
GRASA KG 0.00 9.39 0.67 0.00
GASOLINA GLN 0.00 11.00 0.67 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.67 0.00
0.67 0.00
0.67 0.00
TOTAL VAR 0.00
TOTAL P.U. 22.65

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 6


PRECIO UNITARIO: ACARREO DE MATERIAL EXCEDENTE
RENDIMIENTO EN 8 HRS: 8 M3/DIA
APORTE: 1.0000 HRS/M3 TOTAL P.U. 18.25
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.00 0.00
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 0.00 19.18 1.00 0.00
OFICIAL H-H 0.00 15.90 1.00 0.00
PEON H-H 1.00 14.30 1.00 14.30
TOTAL MO 16.59
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 16.59 1.66
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA TORNILLO P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 1.66
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 0.00 2.14 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
VOLQUETE 210 HP x 6 M3 0.00 213.80 1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 18.25

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 7


PRECIO UNITARIO: ELIMINACION DE DESMONTE CON EQUIPO
RENDIMIENTO EN 8 HRS: 50 M3/DIA
APORTE: 0.1600 HRS/M3 TOTAL P.U. 30.68
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.16 0.00
CAPATAZ H-H 0.10 22.89 0.16 0.37
OPERARIO H-H 0.00 19.18 0.16 0.00
OFICIAL H-H 0.00 15.90 0.16 0.00
PEON H-H 2.00 14.30 0.16 4.58
TOTAL MO 4.94
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 4.94 0.49
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA TORNILLO P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 0.49
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.16 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.16 0.00
GRASA KG 0.00 9.39 0.16 0.00
GASOLINA GLN 1.00 11.00 0.16 1.76

TOTAL COMB 1.76


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
VOLQUETE 6 M3 H-M 1.00 146.77 0.16 23.48
H-M 0.16 0.00
H-M 0.16 0.00
H-M 0.16 0.00
TOTAL EQUIP 23.48
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.16 0.00
0.16 0.00
0.16 0.00
TOTAL VAR 0.00
TOTAL P.U. 30.68

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 8


PRECIO UNITARIO: RELLENO CON MATERIAL PROPIO
RENDIMIENTO EN 8 HRS: 8 M3/DIA
APORTE: 1.0000 HRS/M3 TOTAL P.U. 43.86
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.00 0.00
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 0.00 19.18 1.00 0.00
OFICIAL H-H 0.00 15.90 1.00 0.00
PEON H-H 1.00 14.30 1.00 14.30
TOTAL MO 16.59
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 16.59 1.66
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA TORNILLO P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 1.66
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
COMPACTADORA H-M 1.00 25.61 1.00 25.61
H-M 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
TOTAL EQUIP 25.61
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
VOLQUETE 4X2 H-M 0.00 146.77 1.00 0.00
PISON MANUAL H-M 0.00 7.30 1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 43.86

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 9


PRECIO UNITARIO: RELLENO COMPACTADO CON MATERIAL DE PRESTAMO
RENDIMIENTO EN 8 HRS: 25 M2/DIA
APORTE: 0.3200 HRS/M2 TOTAL P.U. 46.22
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.32 0.00
CAPATAZ H-H 0.10 22.89 0.32 0.73
OPERARIO H-H 1.00 19.18 0.32 6.14
OFICIAL H-H 0.00 15.90 0.32 0.00
PEON H-H 2.00 14.30 0.32 9.15
TOTAL MO 16.02
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 16.02 1.60
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA TORNILLO P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 1.20 17.00 20.40
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 22.00
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.32 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.32 0.00
GRASA KG 0.00 9.39 0.32 0.00
GASOLINA GLN 0.00 11.00 0.32 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
COMPACTADORA H-M 1.00 25.61 0.32 8.20
H-M 0.32 0.00
H-M 0.32 0.00
H-M 0.32 0.00
TOTAL EQUIP 8.20
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PISON MANUAL H-M 0.00 7.30 0.32 0.00
0.32 0.00
0.32 0.00
TOTAL VAR 0.00
TOTAL P.U. 46.22

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 10


PRECIO UNITARIO: NIVELACION INTERIOR Y COMPACTACION
RENDIMIENTO EN 8 HRS: 80 M3/DIA
APORTE: 0.1000 HRS/M3 TOTAL P.U. 7.60
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.10 0.00
CAPATAZ H-H 0.10 22.89 0.10 0.23
OPERARIO H-H 1.00 19.18 0.10 1.92
OFICIAL H-H 0.00 15.90 0.10 0.00
PEON H-H 1.00 14.30 0.10 1.43
TOTAL MO 3.58
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 3.58 0.36
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 0.36
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.10 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.10 0.00
GRASA KG 0.00 9.39 0.10 0.00
GASOLINA GLN 1.00 11.00 0.10 1.10

TOTAL COMB 1.10


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
COMPACTADORA H-M 1.00 25.61 0.10 2.56
H-M 0.10 0.00
H-M 0.10 0.00
H-M 0.10 0.00
TOTAL EQUIP 2.56
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.10 0.00
0.10 0.00
0.10 0.00
TOTAL VAR 0.00
TOTAL P.U. 7.60

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
VARIOS
PROYECTO: EXAMEN FINAL 11
PRECIO UNITARIO: LIMPIEZA GENERAL DE OBRA
RENDIMIENTO EN 8 HRS: 100 M2/DIA
APORTE: 0.0800 HRS/M2 TOTAL P.U. 2.72
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.08 0.00
CAPATAZ H-H 0.10 22.89 0.08 0.18
OPERARIO H-H 0.00 19.18 0.08 0.00
OFICIAL H-H 0.00 15.90 0.08 0.00
PEON H-H 2.00 14.30 0.08 2.29
TOTAL MO 2.47
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 2.47 0.25
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 0.25
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.08 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.08 0.00
GRASA KG 0.00 9.39 0.08 0.00
GASOLINA GLN 0.00 11.00 0.08 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.08 0.00
H-M 0.08 0.00
H-M 0.08 0.00
H-M 0.08 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.08 0.00
0.08 0.00
0.08 0.00
TOTAL VAR 0.00
TOTAL P.U. 2.72

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 12


PRECIO UNITARIO: BRUÑAS EN MUROS
RENDIMIENTO EN 8 HRS: 20 ML/DIA
APORTE: 0.4000 HRS/M TOTAL P.U. 13.59
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.40 0.00
CAPATAZ H-H 0.10 22.89 0.40 0.92
OPERARIO H-H 0.00 19.18 0.40 0.00
OFICIAL H-H 0.00 15.90 0.40 0.00
PEON H-H 2.00 14.30 0.40 11.44
TOTAL MO 12.36
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 12.36 1.24
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0.00
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.00 16.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 1.24
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.40 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.40 0.00
GRASA KG 0.00 9.39 0.40 0.00
GASOLINA GLN 0.00 11.00 0.40 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.40 0.00
H-M 0.40 0.00
H-M 0.40 0.00
H-M 0.40 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.40 0.00
0.40 0.00
0.40 0.00
TOTAL VAR 0.00
TOTAL P.U. 13.59

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 13


PRECIO UNITARIO: JUNTA DE POLIURETANO
RENDIMIENTO EN 8 HRS: 100 M/DIA
APORTE: 0.0800 HRS/M TOTAL P.U. 12.00
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.08 0.00
CAPATAZ H-H 0.10 22.89 0.08 0.18
OPERARIO H-H 0.00 19.18 0.08 0.00
OFICIAL H-H 1.00 15.90 0.08 1.27
PEON H-H 0.00 14.30 0.08 0.00
TOTAL MO 1.46
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 1.46 0.15
CEMENTO TIPO I BLS 0.00 14.83 0.00
HORMIGON M3 0.00 30.00 0.00
AGUA M3 0.00 5.70 0.00
CALAMINA PZA 0.00 14.83 0.00
MADERA P2 0.00 6.50 0.00
TRIPLAY LUPUNA 4´x 8´x 4 mm PZA 0.00 27.00 0
CAL KG. 0.00 0.50 0.00
CORDEL ML 0.00 2.80 0.00
AFIRMADO M3 0.00 17.00 0.00
Sikaflex 300 ml M3 0.65 16.00 10.40
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 10.55
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.08 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.08 0.00
GRASA KG 0.00 9.39 0.08 0.00
GASOLINA GLN 0.00 11.00 0.08 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.08 0.00
H-M 0.08 0.00
H-M 0.08 0.00
H-M 0.08 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.08 0.00
0.08 0.00
0.08 0.00
TOTAL VAR 0.00
TOTAL P.U. 12.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD
DE HERRAM CEMENTO TIPO I AGUA
UNIDAD OBRA MANUALES HORMIGON
OFICINAS 23.85 2.38 2.97 63.00 3.99
METRADO 96 2,289.22 228.92 284.74 6,048.00 383.04

TRAZO Y REPLANTEO 0.90 0.09 0.00 0.00 0.00


METRADO 2400 2,149.21 214.92 0.00 0.00 0.00

TRAZO Y REPLANTEO
DURANTE EL PROCESO 0.90 0.09 0.00 0.00 0.00
METRADO 2400 2,149.21 214.92 0.00 0.00 0.00

EXCAVACION DE ZANJAS 70.60 7.06 0.00 0.00 0.00


METRADO 960 67,779.29 6,777.93 0.00 0.00 0.00

CORTE MANUAL DE TERRENO 20.59 2.06 0.00 0.00 0.00


METRADO 1440 29,653.44 2,965.34 0.00 0.00 0.00

ELIM. DESMONTE CON


EQUIPO 16.59 1.66 0.00 0.00 0.00
METRADO 768 12,740.35 1,274.04 0.00 0.00 0.00

RELLENO CON MATERIAL


PROPIO 4.94 0.49 0.00 0.00 0.00
METRADO 1440 7,116.83 711.68 0.00 0.00 0.00

RELL. COMP. CON MAT. DE


PRESTAMO 16.59 1.66 0.00 0.00 0.00
METRADO 384 6,370.18 637.02 0.00 0.00 0.00

NIV. INT. Y COMPACTACION 16.02 1.60 0.00 0.00 0.00


METRADO 2400 38,452.99 3,845.30 0.00 0.00 0.00

ACARREO DE MAT. EXCED. 3.58 0.36 0.00 0.00 0.00


METRADO 1920 6,867.65 686.76 0.00 0.00 0.00

LIMP. GRAL. DE OBRA 2.47 0.25 0.00 0.00 0.00


METRADO 9600 23,722.75 2,372.28 0.00 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

BRUÑAS EN MUROS 12.36 1.24 0.00 0.00 0.00


METRADO 768 9,489.10 948.91 0.00 0.00 0.00

JUNTA DE POLIURETANO 1.46 0.15 0.00 0.00 0.00


METRADO 384 558.77 55.88 0.00 0.00 0.00

TOTAL 209,338.98 20,933.90 284.74 6,048.00 383.04


PORCENTAJES 0.386 0.039 0.001 0.011 0.001

0.0001620805329

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD
DE HERRAM CLAVOS
UNIDAD OBRA MANUALES
TOTAL 239,187.74 23,918.77 0.00
PORCENTAJES 0.462 0.046 0.000

TRIPLAY
MADERA LUPUNA PLANC.CORRUG
TORNILLO (LARGA) . YESO (20 KG.)
672.38 279.46 430.08 0.00
0.001 0.001 0.001 0.000

ESMALTE SINTET. MATERIAL DE


BLANCO AGUA PREST. MAT9
0.00 0.00 12,960.00 0.00
0.000 0.000 0.025 0.000

COMBUST EQUIPOS
Y
MAT 10 Sikaflex 300 ml  LUBRIC
0.00 5,788.80 36.79 15,565.82
0.000 0.011 0.000 0.030

TOTAL
COSTO
VARIOS 1 VARIOS 2 VARIOS 3 DIRECTO
102,154.24 4,672.00 0.00 405,666.09
0.197 0.009 0.000 0.783

GTO GENERAL GRALES


UTILIDADES PRESUPUESTO
27.85
112,369.51 518,035.60
0.217 1.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MADERA TRIPLEY
CALAMINA TORNILLO LUPUNA CAL CORDEL AFIRMADO Sikaflex 300 ml  MATERIAL 11
45.97 0.52 2.16 0.00 0.00 0.00 0.00 0.00
4,413.41 49.92 207.36 0.00 0.00 0.00 0.00 0.00

0.00 1.95 0.00 0.15 1.40 0.00 0.00 0.00


0.00 4,680.00 0.00 360.00 3,360.00 0.00 0.00 0.00

0.00 14.37 21.60 0.02 0.17 0.00 0.00 0.00


0.00 34,476.00 51,840.00 36.00 403.20 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 20.40 0.00 0.00


0.00 0.00 0.00 0.00 0.00 48,960.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 10.40 0.00


0.00 0.00 0.00 0.00 0.00 0.00 3,993.60 0.00

4,413.41 39,205.92 52,047.36 396.00 3,763.20 48,960.00 3,993.60 0.00


0.008 0.072 0.096 0.001 0.007 0.090 0.007 0.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

COMBUST EQUIPOS TOTAL GTO GENERAL GRALES


Y COSTO UTILIDADES PRESUPUESTO
LUBRIC VARIOS 1 VARIOS 2 VARIOS 3 DIRECTO 18
0.00 0.00 0.00 0.00 0.00 144.84
0.00 0.00 0.00 0.00 0.00 13,904.60

0.00 0.22 0.00 0.00 0.00 4.71


0.00 529.38 0.00 0.00 0.00 11,293.51

0.00 0.22 0.00 0.00 0.00 37.35


0.00 519.78 0.00 0.00 0.00 89,639.11

0.00 0.00 0.00 0.00 0.00 77.66


0.00 0.00 0.00 0.00 0.00 74,557.22

0.00 0.00 0.00 0.00 0.00 22.65


0.00 0.00 0.00 0.00 0.00 32,618.78

0.00 0.00 0.00 0.00 0.00 18.25


0.00 0.00 0.00 0.00 0.00 14,014.39

1.76 23.48 0.00 0.00 0.00 30.68


2,534.40 33,815.81 0.00 0.00 0.00 44,178.72

0.00 25.61 0.00 0.00 0.00 43.86


0.00 9,834.24 0.00 0.00 0.00 16,841.43

0.00 8.20 0.00 0.00 0.00 46.22


0.00 19,668.48 0.00 0.00 0.00 110,926.77

1.10 2.56 0.00 0.00 0.00 7.60


2,112.00 4,917.12 0.00 0.00 0.00 14,583.53

0.00 0.00 0.00 0.00 0.00 2.72


0.00 0.00 0.00 0.00 0.00 26,095.03

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

0.00 0.00 0.00 0.00 0.00 13.59


0.00 0.00 0.00 0.00 0.00 10,438.01

0.00 0.00 0.00 0.00 0.00 12.00


0.00 0.00 0.00 0.00 0.00 4,608.24

0.00 69,284.81 0.00 0.00 0.00 463,699.35 83,465.88 542,518.84


0.000 0.128 0.000 0.000 0.000 0.855 0.153 1.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

OBRAS DE CONCRETO SIMPLE


PROYECTO: EXAMEN FINAL 1
PRECIO UNITARIO: SOLADO DE 2" MEZCLA 1:12 CEMENTO HORMIGON
RENDIMIENTO EN 8 HRS: 80 M2/DIA
APORTE: 0.1000 HRS/M2 TOTAL P.U. 22.44
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.10 0.00
CAPATAZ H-H 0.20 22.89 0.10 0.46
OPERARIO H-H 2.00 19.18 0.10 3.84
OFICIAL H-H 1.00 15.90 0.10 1.59
PEON H-H 6.00 14.30 0.10 8.58
TOTAL MO 14.46
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 14.46 1.45
CEMENTO TIPO 1 BLS 0.15 14.83 2.25
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.12 5.70 0.68
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.07 30.00 2.10
ARENA FINA M3 0.00 37.50 0.00
LADRILLO PANDERETA UND 0.00 0.00 0.00
MADERA TORNILLO P2 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 6.48
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.10 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.10 0.00
GRASA KG 0.00 9.39 0.10 0.00
GASOLINA GLN 1.00 11.00 0.10 1.10
0.00
TOTAL COMB 1.10
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.10 0.40
0.10 0.00
0.10 0.00
0.10 0.00
TOTAL EQUIP 0.40
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.10 0.00
0.10 0.00
0.10 0.00
TOTAL VAR 0.00
2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 22.44

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 2


PRECIO UNITARIO: FALSO CIMIENTO
RENDIMIENTO EN 8 HRS: 25 M2/DIA
APORTE: 0.3200 HRS/M2 TOTAL P.U. 156.12
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.32 0.00
CAPATAZ H-H 0.10 22.89 0.32 0.73
OPERARIO H-H 1.00 19.18 0.32 6.14
OFICIAL H-H 1.00 15.90 0.32 5.09
PEON H-H 1.00 14.30 0.32 4.58
TOTAL MO 16.53
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 16.53 1.65
CEMENTO TIPO I BOL 7.80 14.83 115.67
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.75 5.70 4.28
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.44 30.00 13.20
ARENA FINA M3 0.00 37.50 0.00
LADRILLO UND 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 134.80
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.32 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.32 0.00
GRASA KG 0.00 9.39 0.32 0.00
GASOLINA GLN 1.00 11.00 0.32 3.52

TOTAL COMB 3.52


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.32 1.27
H-M 0.32 0.00
H-M 0.32 0.00
H-M 0.32 0.00
TOTAL EQUIP 1.27
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL

0.32 0.00
0.32 0.00
0.32 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 156.12

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 3


PRECIO UNITARIO: CONCRETO F'c=100 Kg/cm2 PARA CIMIENTOS
RENDIMIENTO EN 8 HRS: 25 M3/DIA
APORTE: 0.3200 HRS/M3 TOTAL P.U. 141.66
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.32 0.00
CAPATAZ H-H 0.10 22.89 0.32 0.73
OPERARIO H-H 1.00 19.18 0.32 6.14
OFICIAL H-H 2.00 15.90 0.32 10.18
PEON H-H 6.00 14.30 0.32 27.46
TOTAL MO 44.50
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 44.50 4.45
CEMENTO TIPO I M2 2.20 14.83 32.63
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.50 55.00 27.50
AGUA M3 0.14 5.70 0.80
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.90 30.00 27.00
ARENA FINA M3 0.00 0.00 0.00
LADRILLO PANDERETA UND 0.00 0.00 0.00
MADERA TORNILLO P2 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 92.37
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.32 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.32 0.00
GRASA KG 0.00 9.39 0.32 0.00
GASOLINA GLN 1.00 11.00 0.32 3.52
0.00
TOTAL COMB 3.52
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.32 1.27
H-M 0.32 0.00
H-M 0.32 0.00
H-M 0.32 0.00
TOTAL EQUIP 1.27
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.32 0.00
0.32 0.00
0.32 0.00
TOTAL VAR 0.00
TOTAL P.U. 141.66
2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 4


PRECIO UNITARIO: CONCRETO F'c=120 Kg/cm2 PARA SOBRECIMIENTOS
RENDIMIENTO EN 8 HRS: 12 M3/DIA
APORTE: 0.6667 HRS/M3 TOTAL P.U. 204.19
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.67 0.00
CAPATAZ H-H 0.10 22.89 0.67 1.53
OPERARIO H-H 1.00 19.18 0.67 12.79
OFICIAL H-H 2.00 15.90 0.67 21.20
PEON H-H 4.00 14.30 0.67 38.13
TOTAL MO 73.65
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 73.65 7.36
CEMENTO TIPO I BOL 4.00 14.83 59.32
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.50 55.00 27.50
AGUA M3 0.16 5.70 0.88
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.85 30.00 25.50
ARENA FINA M3 0.00 37.50 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 120.57
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.67 0.00
GRASA KG 0.00 9.39 0.67 0.00
GASOLINA GLN 1.00 11.00 0.67 7.33
0.00
TOTAL COMB 7.33
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.67 2.64
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
TOTAL EQUIP 2.64
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.67 0.00
0.67 0.00
0.67 0.00
TOTAL VAR 0.00
TOTAL P.U. 204.19

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 5


PRECIO UNITARIO: CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGON E=4"
RENDIMIENTO EN 8 HRS: 110 M2/DIA
APORTE: 0.0727 HRS/M2 TOTAL P.U. 24.41
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.07 0.00
CAPATAZ H-H 0.20 22.89 0.07 0.33
OPERARIO H-H 2.00 19.18 0.07 2.79
OFICIAL H-H 1.00 15.90 0.07 1.16
PEON H-H 6.00 14.30 0.07 6.24
TOTAL MO 10.52
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 10.52 1.05
CEMENTO TIPO I BOL 0.48 14.83 7.16
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.02 5.70 0.09
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.15 30.00 4.50
ARENA FINA M3 0.00 37.50 0.00
CLAVO M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 12.81
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.07 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.07 0.00
GRASA KG 0.00 9.39 0.07 0.00
GASOLINA GLN 1.00 11.00 0.07 0.80
0.00
TOTAL COMB 0.80
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.07 0.29
H-M 0.07 0.00
H-M 0.07 0.00
H-M 0.07 0.00
TOTAL EQUIP 0.29
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.07 0.00
0.07 0.00
0.07 0.00
TOTAL VAR 0.00
TOTAL P.U. 24.41

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 6


PRECIO UNITARIO: CONCRETO EN MUROS TABIQUES Y PLACAS F'C= 175 KG/CM2
RENDIMIENTO EN 8 HRS: 10 M3/DIA
APORTE: 0.8000 HRS/M3 TOTAL P.U. 301.22
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.80 0.00
CAPATAZ H-H 0.20 22.89 0.80 3.66
OPERARIO H-H 2.00 19.18 0.80 30.69
OFICIAL H-H 2.00 15.90 0.80 25.44
PEON H-H 7.00 14.30 0.80 80.08
TOTAL MO 139.87
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 139.87 13.99
CEMENTO TIPO I BOL 7.50 14.83 111.23
ARENA GRUESA M3 0.54 35.00 18.90
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.18 5.70 1.03
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 145.14
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.80 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.80 0.00
GRASA KG 0.00 9.39 0.80 0.00
GASOLINA GLN 1.00 11.00 0.80 8.80
0.00
TOTAL COMB 8.80
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.80 3.17
VIBRADOR 4 HP x 1.50" H-M 1.00 5.30 0.80 4.24
H-M 0.80 0.00
H-M 0.80 0.00
TOTAL EQUIP 7.41
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.80 0.00
0.80 0.00
0.80 0.00
TOTAL VAR 0.00
TOTAL P.U. 301.22

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 7


PRECIO UNITARIO: CONCRETO F'c = 175 Kg/CM2 PARA VIGAS
RENDIMIENTO EN 8 HRS: 20 M3/DIA
APORTE: 0.4000 HRS/M3 TOTAL P.U. 236.30
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.40 0.00
CAPATAZ H-H 0.20 22.89 0.40 1.83
OPERARIO H-H 2.00 19.18 0.40 15.34
OFICIAL H-H 2.00 15.90 0.40 12.72
PEON H-H 8.00 14.30 0.40 45.76
TOTAL MO 75.66
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 75.66 7.57
CEMENTO TIPO I BOL 8.43 14.83 125.02
ARENA GRUESA M3 0.54 35.00 18.90
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.19 5.70 1.05
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 152.54
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.40 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.40 0.00
GRASA KG 0.00 9.39 0.40 0.00
GASOLINA GLN 1.00 11.00 0.40 4.40
0.00
TOTAL COMB 4.40
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.40 1.58
VIBRADOR 4 HP x 1.50" H-M 1.00 5.30 0.40 2.12
0.40 0.00
0.40 0.00
TOTAL EQUIP 3.70
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.40 0.00
0.40 0.00
0.40 0.00
TOTAL VAR 0.00
TOTAL P.U. 236.30

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAAMEN FINAL 8


PRECIO UNITARIO: CONCRETO PARA VIGAS DE F'c= 280 KG/m2
RENDIMIENTO EN 8 HRS: 10 M3/DIA
APORTE: 0.8000 HRS/M3 TOTAL P.U. 264.56
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.80 0.00
CAPATAZ H-H 0.10 22.89 0.80 1.83
OPERARIO H-H 1.00 19.18 0.80 15.34
OFICIAL H-H 1.00 15.90 0.80 12.72
PEON H-H 4.00 14.30 0.80 45.76
TOTAL MO 75.66
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 75.66 7.57
CEMENTO TIPO I BOL 10.00 14.83 148.30
ARENA GRUESA M3 0.45 35.00 15.75
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.19 5.70 1.08
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 172.69
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.80 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.80 0.00
GRASA KG 0.00 9.39 0.80 0.00
GASOLINA GLN 1.00 11.00 0.80 8.80
0.00
TOTAL COMB 8.80
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.80 3.17
VIBRADOR 4 HP x 1.50" H-M 1.00 5.30 0.80 4.24
0.80 0.00
0.80 0.00
TOTAL EQUIP 7.41
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.80 0.00
0.80 0.00
0.80 0.00
TOTAL VAR 0.00
TOTAL P.U. 264.56

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 9


PRECIO UNITARIO: CONCRETO DE F'c=175 KG/m2 , CON 10 CM DE ESPESOR
RENDIMIENTO EN 8 HRS: 40 M2/DIA
APORTE: 0.2000 HRS/M2 TOTAL P.U. 183.45
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.20 0.00
CAPATAZ H-H 0.30 22.89 0.20 1.37
OPERARIO H-H 2.00 19.18 0.20 7.67
OFICIAL H-H 2.00 15.90 0.20 6.36
PEON H-H 6.00 14.30 0.20 17.16
TOTAL MO 32.57
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 32.57 3.26
CEMENTO TIPO I BOL 8.43 14.83 125.02
ARENA GRUESA M3 0.50 35.00 17.50
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.19 5.70 1.05
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 146.83
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.20 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.20 0.00
GRASA KG 0.00 9.39 0.20 0.00
GASOLINA GLN 1.00 11.00 0.20 2.20
0.00
TOTAL COMB 2.20
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 12 P3 H-M 1.00 3.96 0.20 0.79
VIBRADOR 4 HP x 1.50" H-M 1.00 5.30 0.20 1.06
0.20 0.00
0.20 0.00
TOTAL EQUIP 1.85
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.20 0.00
0.20 0.00
0.20 0.00
TOTAL VAR 0.00
TOTAL P.U. 183.45

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN PARCIAL 10


PRECIO UNITARIO: CONCRETO F'c = 175 Kg/CM2 - LOSAS ALIGERADAS
RENDIMIENTO EN 8 HRS: 25 M3/DIA
APORTE: 0.3200 HRS/M3 TOTAL P.U. 239.29
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.32 0.00
CAPATAZ H-H 0.30 22.89 0.32 2.20
OPERARIO H-H 3.00 19.18 0.32 18.41
OFICIAL H-H 2.00 15.90 0.32 10.18
PEON H-H 11.00 14.30 0.32 50.34
TOTAL MO 81.12
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 81.12 8.11
CEMENTO TIPO I BOL 8.43 14.83 125.02
ARENA GRUESA M3 0.50 35.00 17.50
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.19 5.70 1.05
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 151.68
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.32 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.32 0.00
GRASA KG 0.00 9.39 0.32 0.00
GASOLINA GLN 1.00 11.00 0.32 3.52
0.00
TOTAL COMB 3.52
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.32 1.27
VIBRADOR 4 HP x 1.50" H-M 1.00 5.30 0.32 1.70
0.32 0.00
0.32 0.00
TOTAL EQUIP 2.96
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.32 0.00
0.32 0.00
0.32 0.00
TOTAL VAR 0.00
TOTAL P.U. 239.29

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 11


PRECIO UNITARIO: CONCRETO F'C=175 kg/cm2 - LOSA MACIZA
RENDIMIENTO EN 8 HRS: 25 M3/DIA
APORTE: 0.3200 HRS/M3 TOTAL P.U. 184.27
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.32 0.00
CAPATAZ H-H 0.30 22.89 0.32 2.20
OPERARIO H-H 2.00 19.18 0.32 12.28
OFICIAL H-H 1.00 15.90 0.32 5.09
PEON H-H 6.00 14.30 0.32 27.46
TOTAL MO 47.02
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 47.02 4.70
CEMENTO TIPO I BOL 8.43 14.83 125.02
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.19 5.70 1.05
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 130.77
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.32 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.32 0.00
GRASA KG 0.00 9.39 0.32 0.00
GASOLINA GLN 1.00 11.00 0.32 3.52
0.00
TOTAL COMB 3.52
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.32 1.27
VIBRADOR 4 HP x 1.50" H-M 1.00 5.30 0.32 1.70
0.32 0.00
0.32 0.00
TOTAL EQUIP 2.96
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.32 0.00
0.32 0.00
0.32 0.00
TOTAL VAR 0.00
TOTAL P.U. 184.27

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 12


PRECIO UNITARIO: CONCRETO LIQUIDO EN MUROS
RENDIMIENTO EN 8 HRS: 6 M3/DIA
APORTE: 1.3333 HR/M3 TOTAL P.U. 181.74
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.33 0.00
CAPATAZ H-H 0.10 22.89 1.33 3.05
OPERARIO H-H 1.00 19.18 1.33 25.57
OFICIAL H-H 0.00 15.90 1.33 0.00
PEON H-H 2.00 14.30 1.33 38.13
TOTAL MO 66.76
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 66.76 6.68
CEMENTO TIPO I BOL 5.00 14.83 74.15
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.20 5.70 1.14
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.20 30.00 6.00
ARENA FINA M3 0.00 37.50 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 87.97
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.33 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.33 0.00
GRASA KG 0.00 9.39 1.33 0.00
GASOLINA GLN 1.00 11.00 1.33 14.67
0.00
TOTAL COMB 14.67
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1 3.96 1.33 5.28
VIBRADOR 4 HP x 1.50" H-M 1.00 5.30 1.33 7.07
1.33 0.00
1.33 0.00
TOTAL EQUIP 12.35
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.33 0.00
1.33 0.00
1.33 0.00
TOTAL VAR 0.00
TOTAL P.U. 181.74

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 13


PRECIO UNITARIO: MURO DE LADRILLO KING KONG
RENDIMIENTO EN 8 HRS: 8 M2/DIA
APORTE: 1.0000 HRS/M2 TOTAL P.U. 76.76
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.00 0.00
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 1.00 19.18 1.00 19.18
OFICIAL H-H 0.00 15.90 1.00 0.00
PEON H-H 0.50 14.30 1.00 7.15
TOTAL MO 28.62
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 28.62 2.86
CEMENTO TIPO I BOL 0.11 14.83 1.66
ARENA GRUESA M3 0.30 35.00 10.50
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.02 5.70 0.11
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
LADRILLO 24 X 14 X 9 UND 30.00 1.10 33.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 48.14
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 0 3.96 1.00 0.00
VIBRADOR 4 HP x 1.50" H-M 0.00 5.30 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 76.76

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 14


PRECIO UNITARIO: MURO DE LADRILLO DE SOGA KING KONG
RENDIMIENTO EN 8 HRS: 10 M2/DIA
APORTE: 0.8000 HRS/M2 TOTAL P.U. 79.36
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.80 0.00
CAPATAZ H-H 0.10 22.89 0.80 1.83
OPERARIO H-H 1.00 19.18 0.80 15.34
OFICIAL H-H 0.00 15.90 0.80 0.00
PEON H-H 1.00 14.30 0.80 11.44
TOTAL MO 28.62
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 28.62 2.86
CEMENTO TIPO I BOL 0.15 14.83 2.22
ARENA GRUESA M3 0.20 35.00 7.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.02 5.70 0.11
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
LADRILLO 24 X 14 X 9 UND 35.00 1.10 38.50
CLAVO KG 0.01 4.00 0.04
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 50.74
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.80 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.80 0.00
GRASA KG 0.00 9.39 0.80 0.00
GASOLINA GLN 0.00 11.00 0.80 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 0 3.96 0.80 0.00
VIBRADOR 4 HP x 1.50" H-M 0.00 5.30 0.80 0.00
0.80 0.00
0.80 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.80 0.00
0.80 0.00
0.80 0.00
TOTAL VAR 0.00
TOTAL P.U. 79.36

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
ARQUITECTURA
PROYECTO: EXAMEN FINAL 15
PRECIO UNITARIO: MURO CON LADRILLO PANDERETA DE CABEZA
RENDIMIENTO EN 8 HRS: 6.25 M2/DIA
APORTE: 1.2800 HRS/M2 TOTAL P.U. 85.16
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.28 0.00
CAPATAZ H-H 0.10 22.89 1.28 2.93
OPERARIO H-H 1.00 19.18 1.28 24.55
OFICIAL H-H 0.00 15.90 1.28 0.00
PEON H-H 0.55 14.30 1.28 10.07
TOTAL MO 37.55
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 37.55 3.75
CEMENTO TIPO I BOL 0.47 14.83 6.97
ARENA GRUESA M3 0.07 35.00 2.45
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.01 5.70 0.06
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
LADRILLO PANDERETA UND 70.00 0.49 34.30
CLAVO KG 0.02 4.00 0.08
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 47.61
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.28 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.28 0.00
GRASA KG 0.00 9.39 1.28 0.00
GASOLINA GLN 0.00 11.00 1.28 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 0 3.96 1.28 0.00
VIBRADOR 4 HP x 1.50" H-M 0.00 5.30 1.28 0.00
1.28 0.00
1.28 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.28 0.00
1.28 0.00
1.28 0.00
TOTAL VAR 0.00
TOTAL P.U. 85.16
2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 16


PRECIO UNITARIO: MURO DE LADRILLO PANDERETA DE SOGA
RENDIMIENTO EN 8 HRS: 9.9 M2/DIA
APORTE: 0.8081 HRS/M2 TOTAL P.U. 65.28
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.81 0.00
CAPATAZ H-H 0.10 22.89 0.81 1.85
OPERARIO H-H 1.00 19.18 0.81 15.50
OFICIAL H-H 0.00 15.90 0.81 0.00
PEON H-H 1.00 14.30 0.81 11.56
TOTAL MO 28.90
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 28.90 2.89
CEMENTO TIPO I BOL 0.19 14.83 2.82
ARENA GRUESA M3 0.03 35.00 1.05
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.01 5.70 0.06
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.00 37.50 0.00
LADRILLO PANDERETA PZ. 60.00 0.49 29.40
CLAVO M3 0.04 4.00 0.16
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 36.38
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.81 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.81 0.00
GRASA KG 0.00 9.39 0.81 0.00
GASOLINA GLN 0.00 11.00 0.81 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 0 3.96 0.81 0.00
VIBRADOR 4 HP x 1.50" H-M 0.00 5.30 0.81 0.00
0.81 0.00
0.81 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.81 0.00
0.81 0.00
0.81 0.00
TOTAL VAR 0.00
TOTAL P.U. 65.28

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 17


PRECIO UNITARIO: TARRAJEO PRIMARIO O RAYADO
RENDIMIENTO EN 8 HRS: 15 M2/DIA
APORTE: 0.5333 HRS/M2 TOTAL P.U. 23.81
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.53 0.00
CAPATAZ H-H 0.10 22.89 0.53 1.22
OPERARIO H-H 1.00 19.18 0.53 10.23
OFICIAL H-H 0.00 15.90 0.53 0.00
PEON H-H 1.00 14.30 0.53 7.63
TOTAL MO 19.08
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 19.08 1.91
CEMENTO TIPO I BOL 0.12 14.83 1.74
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.05 5.70 0.26
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.02 37.50 0.75
LADRILLO PANDERETA UND 0.00 0.49 0.00
CLAVO KG 0.02 4.00 0.08
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 4.73
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.53 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.53 0.00
GRASA KG 0.00 9.39 0.53 0.00
GASOLINA GLN 0.00 11.00 0.53 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 0 3.96 0.53 0.00
VIBRADOR 4 HP x 1.50" H-M 0.00 5.30 0.53 0.00
REGLA DE MADERA H-M 0.00 3.20 0.53 0.00
0.53 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.53 0.00
0.53 0.00
0.53 0.00
TOTAL VAR 0.00
TOTAL P.U. 23.81

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 18


PRECIO UNITARIO: TARRAJEO EN INTERIORES
RENDIMIENTO EN 8 HRS: 20 M2/DIA
APORTE: 0.4000 HRS/M2 TOTAL P.U. 18.48
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.40 0.00
CAPATAZ H-H 0.10 22.89 0.40 0.92
OPERARIO H-H 1.00 19.18 0.40 7.67
OFICIAL H-H 0.00 15.90 0.40 0.00
PEON H-H 1.00 14.30 0.40 5.72
TOTAL MO 14.31
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 14.31 1.43
CEMENTO TIPO I BOL 0.12 14.83 1.76
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.03 5.70 0.14
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.02 37.50 0.75
LADRILLO PANDERETA UND 0.00 0.49 0.00
CLAVO M3 0.02 4.00 0.08
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 4.17
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.40 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.40 0.00
GRASA KG 0.00 9.39 0.40 0.00
GASOLINA GLN 0.00 11.00 0.40 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 0.00 3.96 0.40 0.00
VIBRADOR 4 HP x 1.50" H-M 0.00 5.30 0.40 0.00
REGLA DE MADERA H-M 0.00 3.20 0.40 0.00
0.40 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.40 0.00
0.40 0.00
0.40 0.00
TOTAL VAR 0.00
TOTAL P.U. 18.48

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 19


PRECIO UNITARIO: MESAS DE CONCRETO PARA COCINA
RENDIMIENTO EN 8 HRS: 50 UND/DIA
APORTE: 0.1600 HRS/UND TOTAL P.U. 99.27
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.16 0.00
CAPATAZ H-H 0.10 22.89 0.16 0.37
OPERARIO H-H 1.00 19.18 0.16 3.07
OFICIAL H-H 0.00 15.90 0.16 0.00
PEON H-H 3.00 14.30 0.16 6.86
TOTAL MO 10.30
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 10.30 1.03
CEMENTO TIPO I BOL 4.22 14.83 62.51
ARENA GRUESA M3 0.27 35.00 9.45
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.06 5.70 0.36
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 35.00 0.00
ARENA FINA M3 0.00 37.50 0.00
LADRILLO UND 27.00 0.49 13.23
CERAMICA PISO-ÁRED 20X20 M3 0.00 24.13 0.00
MATERIAL 10 KG 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 86.58
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.16 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.16 0.00
GRASA KG 0.00 9.39 0.16 0.00
GASOLINA GLN 1.00 11.00 0.16 1.76
0.00
TOTAL COMB 1.76
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.16 0.63
VIBRADOR 4 HP x 1.50" H-M 0.00 5.30 0.16 0.00
REGLA DE MADERA H-M 0.00 3.20 0.16 0.00
H-M 0.16 0.00
TOTAL EQUIP 0.63
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.16 0.00
0.16 0.00
0.16 0.00
TOTAL VAR 0.00
TOTAL P.U. 99.27

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 20


PRECIO UNITARIO: CONTRAPISO DE 50 mm
RENDIMIENTO EN 8 HRS: 80 M2/DIA
APORTE: 0.1000 HRS/M2 TOTAL P.U. 28.94
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.10 0.00
CAPATAZ H-H 0.30 22.89 0.10 0.69
OPERARIO H-H 3.00 19.18 0.10 5.75
OFICIAL H-H 1.00 15.90 0.10 1.59
PEON H-H 6.00 14.30 0.10 8.58
TOTAL MO 16.61
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 16.61 1.66
CEMENTO TIPO I BOL 0.46 14.83 6.75
ARENA GRUESA M3 0.00 30.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.04 5.70 0.23
ADITIVOS GLN 0.00 35.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.05 37.50 1.88
LADRILLO PANDERETA UND 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 10.51
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.10 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.10 0.00
GRASA KG 0.00 9.39 0.10 0.00
GASOLINA GLN 1.00 11.00 0.10 1.10
0.00
TOTAL COMB 1.10
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.10 0.40
REGLA DE MADERA H-M 1.00 3.20 0.10 0.32
0.10 0.00
0.10 0.00
TOTAL EQUIP 0.72
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.10 0.00
0.10 0.00
0.10 0.00
TOTAL VAR 0.00
TOTAL P.U. 28.94

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 21


PRECIO UNITARIO: CONTRAPISO DE 35 mm
RENDIMIENTO EN 8 HRS: 100 M2/DIA
APORTE: 0.0800 HRS/M2 TOTAL P.U. 18.90
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.08 0.00
CAPATAZ H-H 0.30 22.89 0.08 0.55
OPERARIO H-H 1.00 19.18 0.08 1.53
OFICIAL H-H 1.00 15.90 0.08 1.27
PEON H-H 4.00 14.30 0.08 4.58
TOTAL MO 7.93
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 7.93 0.79
CEMENTO TIPO I BOL 0.45 14.83 6.67
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.03 5.70 0.17
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.05 37.50 1.88
LADRILLO PANDERETA UND 0.00 0.49 0.00
M3 0.00 0.00 0.00
M3 0.00 0.00 0.00
M3 0.00 0.00 0.00
TOTAL MAT 9.51
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.08 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.08 0.00
GRASA KG 0.00 9.39 0.08 0.00
GASOLINA GLN 1.00 11.00 0.08 0.88
0.00
TOTAL COMB 0.88
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 1.00 3.96 0.08 0.32
REGLA DE MADERA H-M 1.00 3.20 0.08 0.26
0.08 0.00
0.08 0.00
TOTAL EQUIP 0.57
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.08 0.00
0.08 0.00
0.08 0.00
TOTAL VAR 0.00
TOTAL P.U. 18.90

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 22


PRECIO UNITARIO: PISO DE CERAMICO 20 x 20
RENDIMIENTO EN 8 HRS: 8 M2/DIA
APORTE: 1.0000 TOTAL P.U. 55.24
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.00 0.00
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 1.00 19.18 1.00 19.18
OFICIAL H-H 0.00 15.90 1.00 0.00
PEON H-H 0.50 14.30 1.00 7.15
TOTAL MO 28.62
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 28.62 2.86
CEMENTO TIPO I BOL 0.15 14.83 2.22
ARENA GRUESA M3 0.03 35.00 1.05
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.01 5.70 0.08
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.04 37.50 1.50
LADRILLO PANDERETA UND 0.00 0.49 0.00
CERAMICA PISO-PÁRED 20X2 M2 1.05 18.00 18.90
MATERIAL 10 M2 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 26.62
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 55.24

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 23


PRECIO UNITARIO: PISO DE CEMENTO PULIDO Y BRUÑADO
RENDIMIENTO EN 8 HRS: 100 M2/DIA
APORTE: 0.0800 TOTAL P.U. 58.68
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.08 0.00
CAPATAZ H-H 0.20 22.89 0.08 0.37
OPERARIO H-H 1.00 19.18 0.08 1.53
OFICIAL H-H 1.00 15.90 0.08 1.27
PEON H-H 4.00 14.30 0.08 4.58
TOTAL MO 7.75
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 7.75 0.77
CEMENTO TIPO I BOL 0.48 14.83 7.15
ARENA GRUESA M3 0.45 35.00 15.75
PIEDRA CHANCADA M3 0.45 55.00 24.75
AGUA M3 0.05 5.70 0.26
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.06 37.50 2.25
LADRILLO PANDERETA UND 0.00 0.49 0.00
CERAMICA PISO-ÁRED 20X20 M2 0.00 0.00 0.00
MATERIAL 10 M2 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 50.93
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.08 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.08 0.00
GRASA KG 0.00 9.39 0.08 0.00
GASOLINA GLN 0.00 11.00 0.08 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TROMPO 9 P3 H-M 0.00 3.96 0.08 0.00
REGLA DE MADERA H-M 0.00 3.20 0.08 0.00
0.08 0.00
0.08 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.08 0.00
0.08 0.00
0.08 0.00
TOTAL VAR 0.00
TOTAL P.U. 58.68

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 24


PRECIO UNITARIO: CONTRAZOCALO CEMENTO SIN COLOREAR H = 20 cm PULIDO
RENDIMIENTO EN 8 HRS: 20 ML/DIA
APORTE: 0.4000 HRS/ML TOTAL P.U. 17.51
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.40 0.00
CAPATAZ H-H 0.10 22.89 0.40 0.92
OPERARIO H-H 1.00 19.18 0.40 7.67
OFICIAL H-H 0.00 15.90 0.40 0.00
PEON H-H 1.00 14.30 0.40 5.72
TOTAL MO 14.31
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 14.31 1.43
CEMENTO TIPO I BOL 0.04 14.83 0.59
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.01 5.70 0.06
ADITIVOS GLN 0.00 60.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.03 37.50 1.13
LADRILLO PANDERETA UND 0.00 0.49 0.00
CERAMICA PISO-ÁRED 20X20 M2 0.00 0.00 0.00
MATERIAL 10 M2 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 3.21
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.40 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.40 0.00
GRASA KG 0.00 9.39 0.40 0.00
GASOLINA GLN 0.00 11.00 0.40 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.40 0.00
0.40 0.00
0.40 0.00
0.40 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.40 0.00
0.40 0.00
0.40 0.00
TOTAL VAR 0.00
TOTAL P.U. 17.51

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 25


PRECIO UNITARIO: ZOCALO DE CERAMICO 20X20
RENDIMIENTO EN 8 HRS: 8 M2/DIA
APORTE: 1.0000 HRS/M2 TOTAL P.U. 61.88
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.00 0.00
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 1.00 19.18 1.00 19.18
OFICIAL H-H 0.00 15.90 1.00 0.00
PEON H-H 1.00 14.30 1.00 14.30
TOTAL MO 35.77
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 35.77 3.58
CEMENTO TIPO I BOL 0.19 14.83 2.77
ARENA GRUESA M3 0.00 35.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.02 5.70 0.11
ADITIVOS GLN 0.00 35.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.02 37.50 0.75
LADRILLO PANDERETA UND 0.00 0.49 0.00
CERAMICA PISO-ÁRED 20X20 M2 1.05 18.00 18.90
FRAGUA BLS 0.20 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 26.11
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 61.88

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 26


PRECIO UNITARIO: ZOCALO DE CEMENTO SIMPLE MEZCLA CEMENTO-ARENA
RENDIMIENTO EN 8 HRS: 20 M2/DIA
APORTE: 0.4000 HRS/M2 TOTAL P.U. 20.76
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.40 0.00
CAPATAZ H-H 0.10 22.89 0.40 0.92
OPERARIO H-H 1.00 19.18 0.40 7.67
OFICIAL H-H 0.00 15.90 0.40 0.00
PEON H-H 1.00 14.30 0.40 5.72
TOTAL MO 14.31
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 14.31 1.43
CEMENTO TIPO I BOL 0.25 14.83 3.71
ARENA GRUESA M3 0.00 30.00 0.00
PIEDRA CHANCADA M3 0.00 55.00 0.00
AGUA M3 0.02 5.70 0.11
ADITIVOS GLN 0.00 35.00 0.00
HORMIGON M3 0.00 30.00 0.00
ARENA FINA M3 0.03 37.50 1.13
LADRILLO PANDERETA UND 0.00 0.49 0.00
CERAMICA PISO-ÁRED 20X20 M2 0.00 0.00 0.00
CLAVO M2 0.02 4.00 0.08
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 6.46
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.40 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.40 0.00
GRASA KG 0.00 9.39 0.40 0.00
GASOLINA GLN 0.00 11.00 0.40 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.40 0.00
0.40 0.00
0.40 0.00
0.40 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.40 0.00
0.40 0.00
0.40 0.00
TOTAL VAR 0.00
TOTAL P.U. 20.76

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD
DE HERRAM
CEMENTO ARENA PIEDRA
UNIDAD OBRA MANUALES TIPO I GRUESA CHANCADA
SOLADO DE 2" 14.46 1.45 2.25 0.00 0.00
METRADO 2,880.00 41,655.74 4,165.57 6,470.63 0.00 0.00

FALSO CIMIENTO 16.53 1.65 115.67 0.00 0.00


METRADO 1,152.00 19,047.26 1,904.73 133,256.45 0.00 0.00

CONCRETO PARA
CIMIENTOS 44.50 4.45 32.63 0.00 27.50
METRADO 1,344.00 59,810.80 5,981.08 43,849.34 0.00 36,960.00

CONCRETO PARA
SOBRECIMIENTOS 73.65 7.36 59.32 0.00 27.50
METRADO 1,440.00 106,050.24 10,605.02 85,420.80 0.00 39,600.00

CONCRETO EN
FALSOPISO 10.52 1.05 7.16 0.00 0.00
METRADO 3,840.00 40,393.45 4,039.34 27,505.50 0.00 0.00

Cº EN MUROS TABIQUES
Y PLACAS 139.87 13.99 111.23 18.90 0.00
METRADO 480 67,137.79 6,713.78 53,388.00 9,072.00 0.00

CONCRETO F'c = 175


Kg/CM2 75.66 7.57 125.02 18.90 0.00
METRADO 96 7,262.90 726.29 12,001.62 1,814.40 0.00

CONCRETO PARA VIGAS 75.66 7.57 148.30 15.75 0.00


METRADO 1,152.00 87,154.79 8,715.48 170,841.60 18,144.00 0.00

Cº DE F'c=175 KG/m2
E=10CM 32.57 3.26 125.02 17.50 0.00
METRADO 1,728.00 56,273.01 5,627.30 216,029.20 30,240.00 0.00

CONCRETO LOSAS
ALIGERADAS 81.12 8.11 125.02 17.50 0.00
METRADO 480 38,938.68 3,893.87 60,008.11 8,400.00 0.00

Cº LOSA MACIZA 47.02 4.70 125.02 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
METRADO 288 13,540.79 1,354.08 36,004.87 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

Cº LIQUIDO EN MUROS 66.76 6.68 74.15 0.00 0.00


METRADO 480 32,044.16 3,204.42 35,592.00 0.00 0.00

MURO DE LADRILLO
KING KONG 28.62 2.86 1.66 10.50 0.00
METRADO 5,280.00 151,108.32 15,110.83 8,769.87 55,440.00 0.00

MURO DE LADRILLO DE
SOGA KING KONG 28.62 2.86 2.22 7.00 0.00
METRADO 1,920.00 54,941.18 5,494.12 4,271.04 13,440.00 0.00

MURO C/L. PANDERETA


D/CABEZA 37.55 3.75 6.97 2.45 0.00
METRADO 960 36,045.62 3,604.56 6,691.30 2,352.00 0.00

MURO DE LADRILLO
PANDERETA DE SOGA 28.90 2.89 2.82 1.05 0.00
METRADO 960 27,748.07 2,774.81 2,704.99 1,008.00 0.00

TARRAJEO PRIMARIO O
RAYADO 19.08 1.91 1.74 0.00 0.00
METRADO 960 18,313.73 1,831.37 1,665.71 0.00 0.00

TARRAJEO EN
INTERIORES 14.31 1.43 1.76 0.00 0.00
METRADO 1,440.00 20,602.94 2,060.29 2,541.27 0.00 0.00

MESAS DE CONCRETO
PARA COCINA 10.30 1.03 62.51 9.45 0.00
METRADO 96 988.71 98.87 6,000.81 907.20 0.00

CONTRAPISO DE 50 mm 16.61 1.66 6.75 0.00 0.00


METRADO 1,440.00 23,919.41 2,391.94 9,716.62 0.00 0.00

CONTRAPISO DE 35 mm 7.93 0.79 6.67 0.00 0.00


METRADO 1,440.00 11,421.73 1,142.17 9,609.84 0.00 0.00

PISO DE CERAMICO 20 x
20 28.62 2.86 2.22 1.05 0.00
METRADO 1,248.00 35,716.51 3,571.65 2,776.18 1,310.40 0.00

PISO DE CEMENTO
PULIDO Y BRUÑADO
2011170517
PISO DE CEMENTO Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
PULIDO Y BRUÑADO 7.75 0.77 7.15 15.75 24.75
METRADO 1,920.00 14,877.39 1,487.74 13,724.28 30,240.00 47,520.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

CONTRAZOC. CEM.
S/COLOREAR 14.31 1.43 0.59 0.00 0.00
METRADO 2,400.00 34,338.24 3,433.82 1,423.68 0.00 0.00

ZOCALO DE CERAMICO
20X20 35.77 3.58 2.77 0.00 0.00
METRADO 480 17,169.12 1,716.91 1,330.43 0.00 0.00

ZOCALO DE MEZCLA
CEMENTO-ARENA 14.31 1.43 3.71 0.00 0.00
METRADO 480 6,867.65 686.76 1,779.60 0.00 0.00

TOTAL 1,023,368.24 102,336.82 953,373.72 172,368.00 124,080.00


PORCENTAJES 0.293 0.029 0.273 0.049 0.036

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

AGUA ADITIVOS HORMIGON ARENA FINA LADRILLO


0.68 0.00 2.10 0.00 0.00
1,969.92 0.00 6,048.00 0.00 0.00

4.28 0.00 13.20 0.00 0.00


4,924.80 0.00 15,206.40 0.00 0.00

0.80 0.00 27.00 0.00 0.00


1,072.51 0.00 36,288.00 0.00 0.00

0.88 0.00 25.50 0.00 0.00


1,272.24 0.00 36,720.00 0.00 0.00

0.09 0.00 4.50 0.00 0.00


350.21 0.00 17,280.00 0.00 0.00

1.03 0.00 0.00 0.00 0.00


492.48 0.00 0.00 0.00 0.00

1.05 0.00 0.00 0.00 0.00


101.23 0.00 0.00 0.00 0.00

1.08 0.00 0.00 0.00 0.00


1,241.05 0.00 0.00 0.00 0.00

1.05 0.00 0.00 0.00 0.00


1,822.18 0.00 0.00 0.00 0.00

1.05 0.00 0.00 0.00 0.00


506.16 0.00 0.00 0.00 0.00

1.05 0.00 0.00 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
303.70 0.00 0.00 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

1.14 0.00 6.00 0.00 0.00


547.20 0.00 2,880.00 0.00 0.00

0.11 0.00 0.00 0.00 33.00


601.92 0.00 0.00 0.00 174,240.00

0.11 0.00 0.00 0.00 38.50


218.88 0.00 0.00 0.00 73,920.00

0.06 0.00 0.00 0.00 34.30


54.72 0.00 0.00 0.00 32,928.00

0.06 0.00 0.00 0.00 29.40


54.72 0.00 0.00 0.00 28,224.00

0.26 0.00 0.00 0.75 0.00


246.24 0.00 0.00 720.00 0.00

0.14 0.00 0.00 0.75 0.00


205.20 0.00 0.00 1,080.00 0.00

0.36 0.00 0.00 0.00 13.23


34.75 0.00 0.00 0.00 1,270.08

0.23 0.00 0.00 1.88 0.00


328.32 0.00 0.00 2,700.00 0.00

0.17 0.00 0.00 1.88 0.00


246.24 0.00 0.00 2,700.00 0.00

0.08 0.00 0.00 1.50 0.00


99.59 0.00 0.00 1,872.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
0.26 0.00 0.00 2.25 0.00
492.48 0.00 0.00 4,320.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

0.06 0.00 0.00 1.13 0.00


136.80 0.00 0.00 2,700.00 0.00

0.11 0.00 0.00 0.75 0.00


54.72 0.00 0.00 360.00 0.00

0.11 0.00 0.00 1.13 0.00


54.72 0.00 0.00 540.00 0.00

17,432.97 0.00 114,422.40 16,992.00 310,582.08


0.005 0.000 0.033 0.005 0.089

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

COMBUST EQUIPOS
Y
CERAMICA MAT 10 MAT 11 LUBRIC VARIOS 1 VARIOS 2 VARIOS 3
0.00 0.00 0.00 1.10 0.40 0.00 0.00 0.00
0.00 0.00 0.00 3,168.00 1,140.48 0.00 0.00 0.00

0.00 0.00 0.00 3.52 1.27 0.00 0.00 0.00


0.00 0.00 0.00 4,055.04 1,459.81 0.00 0.00 0.00

0.00 0.00 0.00 3.52 1.27 0.00 0.00 0.00


0.00 0.00 0.00 4,730.88 1,703.12 0.00 0.00 0.00

0.00 0.00 0.00 7.33 2.64 0.00 0.00 0.00


0.00 0.00 0.00 10,560.00 3,801.60 0.00 0.00 0.00

0.00 0.00 0.00 0.80 0.29 0.00 0.00 0.00


0.00 0.00 0.00 3,072.00 1,105.92 0.00 0.00 0.00

0.00 0.00 0.00 8.80 7.41 0.00 0.00 0.00


0.00 0.00 0.00 4,224.00 3,555.84 0.00 0.00 0.00

0.00 0.00 0.00 4.40 3.70 0.00 0.00 0.00


0.00 0.00 0.00 422.40 355.58 0.00 0.00 0.00

0.00 0.00 0.00 8.80 7.41 0.00 0.00 0.00


0.00 0.00 0.00 10,137.60 8,534.02 0.00 0.00 0.00

0.00 0.00 0.00 2.20 1.85 0.00 0.00 0.00


0.00 0.00 0.00 3,801.60 3,200.26 0.00 0.00 0.00

0.00 0.00 0.00 3.52 2.96 0.00 0.00 0.00


0.00 0.00 0.00 1,689.60 1,422.34 0.00 0.00 0.00

0.00 0.00 0.00 3.52 2.96 0.00 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
0.00 0.00 0.00 1,013.76 853.40 0.00 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

0.00 0.00 0.00 14.67 12.35 0.00 0.00 0.00


0.00 0.00 0.00 7,040.00 5,926.40 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00


76.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00


76.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00


153.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00


76.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00


115.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 1.76 0.63 0.00 0.00 0.00


0.00 0.00 0.00 168.96 60.83 0.00 0.00 0.00

0.00 0.00 0.00 1.10 0.72 0.00 0.00 0.00


0.00 0.00 0.00 1,584.00 1,031.04 0.00 0.00 0.00

0.00 0.00 0.00 0.88 0.57 0.00 0.00 0.00


0.00 0.00 0.00 1,267.20 824.83 0.00 0.00 0.00

18.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00


23,587.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

18.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00


9,072.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.08 0.00 0.00 0.00 0.00 0.00 0.00


0.00 38.40 0.00 0.00 0.00 0.00 0.00 0.00

33,158.40 38.40 0.00 56,935.04 34,975.46 0.00 0.00 0.00


0.009 0.000 0.000 0.016 0.010 0.000 0.000 0.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

TOTAL GTO GENERAL GRALES


COSTO UTILIDADES PRESUPUESTO
DIRECTO 18
22.44
64,618.34

156.12
179,854.49

141.66
190,395.73

204.19
294,029.90

24.41
93,746.42

301.22
144,583.89

236.30
22,684.43

264.56
304,768.54

183.45
316,993.55

239.29
114,858.75

184.27

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
53,070.60

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

181.74
87,234.18

76.76
405,270.94

79.36
152,362.02

85.16
81,753.00

65.28
62,668.19

23.81
22,853.85

18.48
26,604.91

99.27
9,530.20

28.94
41,671.32

18.90
27,212.02

55.24
68,933.53

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
58.68
112,661.88

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

17.51
42,032.54

61.88
29,703.18

20.76
9,967.13

2,960,063.53 532,811.44 3,492,874.97


0.847 0.153 1.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

ENCOFRADOS
PROYECTO: EXAMEN FINAL 1
PRECIO UNITARIO: ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS
RENDIMIENTO EN 8 HRS: 14 M2/DIA
APORTE: 0.5714 HRS/M2 TOTAL P.U. 45.53
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.57 0.00
CAPATAZ H-H 0.10 22.89 0.57 1.31
OPERARIO H-H 1.00 19.18 0.57 10.96
OFICIAL H-H 0.00 15.90 0.57 0.00
PEON H-H 2.00 14.30 0.57 16.34
TOTAL MO 28.61
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 28.61 2.86
ALAMBRE NEGRO RECOCIDO N° 8 KG 0.18 2.24 0.40
CLAVOS PARA MADERA C/C 3" KG 0.10 2.88 0.29
MADERA TORNILLO 12' DE LARGO P2 2.70 4.95 13.37
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 M3 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 16.92
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.57 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.57 0.00
GRASA KG 0.00 9.39 0.57 0.00
GASOLINA GLN 0.00 11.00 0.57 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.57 0.00
H-M 0.57 0.00
H-M 0.57 0.00
H-M 0.57 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.57 0.00
0.57 0.00
0.57 0.00
TOTAL VAR 0.00
2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 45.53

PROYECTO: EXAMEN FINAL 2


PRECIO UNITARIO: ENCOFRADO Y DESENCOFRADO NORMAL EN MUROS TABIQUES Y PLACAS
RENDIMIENTO EN 8 HRS: 10 M2/DIA
APORTE: 0.8000 HRS/M2 TOTAL P.U. 62.18
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.80 0.00
CAPATAZ H-H 0.10 22.89 0.80 1.83
OPERARIO H-H 1.00 19.18 0.80 15.34
OFICIAL H-H 0.00 15.90 0.80 0.00
PEON H-H 2.00 14.30 0.80 22.88
TOTAL MO 40.06
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 40.06 4.01
ALAMBRE NEGRO RECOCIDO N° 8 KG 0.07 2.24 0.16
CLAVOS PARA MADERA C/C 3" KG 0.22 2.88 0.63
MADERA TORNILLO 12' DE LARGO P2 3.50 4.95 17.33
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 P2 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 22.12
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.80 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.80 0.00
GRASA KG 0.00 9.39 0.80 0.00
GASOLINA GLN 0.00 11.00 0.80 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.80 0.00
H-M 0.80 0.00
H-M 0.80 0.00
H-M 0.80 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.80 0.00
0.80 0.00
0.80 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL VAR 0.00
TOTAL P.U. 62.18

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 3


PRECIO UNITARIO: ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS
RENDIMIENTO EN 8 HRS: 8 M2/DIA
APORTE: 1.0000 HRS/M2 TOTAL P.U. 66.92
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.00 0.00
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 1.00 19.18 1.00 19.18
OFICIAL H-H 1.00 15.90 1.00 15.90
PEON H-H 0.00 14.30 1.00 0.00
TOTAL MO 37.37
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 37.37 3.74
ALAMBRE NEGRO RECOCIDO N° 8 KG 0.27 2.24 0.60
CLAVOS PARA MADERA C/C 3" KG 0.16 2.88 0.46
MADERA TORNILLO 12' DE LARGO P2 5.00 4.95 24.75
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 M3 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 29.55
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 66.92

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 4


PRECIO UNITARIO: ENCOFRADO Y DESENCOFRADO LOSAS ALIGERADAS
RENDIMIENTO EN 8 HRS: 12 M2/DIA
APORTE: 0.6667 HRS/M2 TOTAL P.U. 43.90
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.67 0.00
CAPATAZ H-H 0.10 22.89 0.67 1.53
OPERARIO H-H 1.00 19.18 0.67 12.79
OFICIAL H-H 1.00 15.90 0.67 10.60
PEON H-H 0.00 14.30 0.67 0.00
TOTAL MO 24.91
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 24.91 2.49
ALAMBRE NEGRO RECOCIDO N° 16 KG 0.10 2.24 0.22
CLAVOS PARA MADERA C/C 3" KG 0.15 2.88 0.43
MADERA TORNILLO 12' DE LARGO P2 3.20 4.95 15.84
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 M3 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 18.99
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.67 0.00
GRASA KG 0.00 9.39 0.67 0.00
GASOLINA GLN 0.00 11.00 0.67 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.67 0.00
0.67 0.00
0.67 0.00
0.67 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.67 0.00
0.67 0.00
0.67 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 43.90

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 5


PRECIO UNITARIO: ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS
RENDIMIENTO EN 8 HRS: 15 M2/DIA
APORTE: 0.5333 HRS/M2 TOTAL P.U. 42.03
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.53 0.00
CAPATAZ H-H 0.10 22.89 0.53 1.22
OPERARIO H-H 1.00 19.18 0.53 10.23
OFICIAL H-H 1.00 15.90 0.53 8.48
PEON H-H 0.00 14.30 0.53 0.00
TOTAL MO 19.93
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 19.93 1.99
ALAMBRE NEGRO RECOCIDO N° 16 KG 0.12 2.24 0.27
CLAVOS PARA MADERA C/C 3" KG 0.10 2.88 0.29
MADERA TORNILLO 12' DE LARGO P2 3.95 4.95 19.55
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 P2 0.06 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 22.10
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.53 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.53 0.00
GRASA KG 0.00 9.39 0.53 0.00
GASOLINA GLN 0.00 11.00 0.53 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.53 0.00
0.53 0.00
0.53 0.00
0.53 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.53 0.00
0.53 0.00
0.53 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 42.03

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD
DE HERRAM
ALAMBRE
UNIDAD OBRA MANUALES NEGRO
ENC./DESEN. SOBREC. 28.61 2.86 0.40
METRADO 3840 109,865.69 10,986.57 1,545.25

ENC./DESEN MUROS TABIQUES


Y PLACAS 40.06 4.01 0.16
METRADO 1152 46,143.59 4,614.36 180.28

ENC./DESEN EN VIGAS 37.37 3.74 0.60


METRADO 768 28,699.39 2,869.94 463.57

ENC./DESEN. LOSAS
ALIGERADAS 24.91 2.49 0.22
METRADO 1728 43,049.09 4,304.91 386.31

ENC./DESEN EN LOSAS
MACIZAS 19.93 1.99 0.27
METRADO 288 5,739.88 573.99 77.26

TOTAL 233,497.64 23,349.76 2,652.67


PORCENTAJES 0.513 0.051 0.006

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD
DE HERRAM
ALAMBRE
UNIDAD OBRA MANUALES NEGRO
TOTAL 202,737.39 20,273.74 4,747.56
PORCENTAJES 0.436 0.044 0.010

CLAVOS PARA
MADERA MADERA TORNILLO- MAT 4 MAT 5
2,876.72 133,353.70 0.00 0.00
0.006 0.287 0.000 0.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

CLAVOS PARA
MADERA MADERA TORNILLO MAT 4 MAT 5 MAT 6 MAT 7 MAT 8
0.29 13.37 0.00 0.00 0.00 0.00 0.00
1,107.30 51,321.60 0.00 0.00 0.00 0.00 0.00

0.63 17.33 0.00 0.00 0.00 0.00 0.00


730.82 19,958.40 0.00 0.00 0.00 0.00 0.00

0.46 24.75 0.00 0.00 0.00 0.00 0.00


354.34 19,008.00 0.00 0.00 0.00 0.00 0.00

0.43 15.84 0.00 0.00 0.00 0.00 0.00


747.43 27,371.52 0.00 0.00 0.00 0.00 0.00

0.29 19.55 0.00 0.00 0.00 0.00 0.00


83.05 5,631.12 0.00 0.00 0.00 0.00 0.00

3,022.94 123,290.64 0.00 0.00 0.00 0.00 0.00


0.007 0.271 0.000 0.000 0.000 0.000 0.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

COMBUST EQUIPOS
Y
MAT9 MAT 10 MAT 11 LUBRIC VARIOS 1 VARIOS 2 VARIOS 3
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

TOTAL GTO GENERAL GRALES


COSTO UTILIDADES PRESUPUESTO
DIRECTO 18
45.53
174,826.41

62.18
71,627.45

66.92
51,395.24

43.90
75,859.26

42.03
12,105.30

385,813.65 69,446.46 455,260.11


0.847 0.153 1.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

OBRAS DE CONCRETO ARMADO


PROYECTO: EXAMEN FINAL 1
PRECIO UNITARIO: ACERO EN SOBRECIMIENTO REFORZADO GRADO 60
RENDIMIENTO EN 8 HRS: 250 KG/DIA
APORTE: 0.0320 HRS/M2 TOTAL P.U. 6.40
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.03 0.00
CAPATAZ H-H 0.10 22.89 0.03 0.07
OPERARIO H-H 1.00 19.18 0.03 0.61
OFICIAL H-H 0.00 15.90 0.03 0.00
PEON H-H 1.00 14.30 0.03 0.46
TOTAL MO 1.14
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 1.14 0.11
ALAMBRE NEGRO RECOCIDO N 16 KG 0.05 2.24 0.11
ACERO CORRUGADO GRADO 60 KG 1.07 4.70 5.03
MATERIAL 3 M3 0.00 0.00 0.00
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 M3 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 5.25
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
GASOLINA GLN 0.00 11.00 0.03 0.00
PETROLEO GLN 0.00 9.39 0.03 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.03 0.00
GRASA KG 0.00 5.00 0.03 0.00
GASOLINA GLN 0.00 9.79 0.03 0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.03 0.00
0.03 0.00
0.03 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 6.40

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN PARCIAL 2


PRECIO UNITARIO: ACERO GRADO 60 EN MUROS TABIQUES Y PLACAS
RENDIMIENTO EN 8 HRS: 300 KG/DIA
APORTE: 0.0267 HRS/KG TOTAL P.U. 6.28
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.03 0.00
CAPATAZ H-H 0.10 22.89 0.03 0.06
OPERARIO H-H 1.00 19.18 0.03 0.51
OFICIAL H-H 0.00 15.90 0.03 0.00
PEON H-H 1.00 14.30 0.03 0.38
TOTAL MO 0.95
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 0.95 0.10
ALAMBRE NEGRO RECOCIDO N 16 KG 0.05 2.24 0.11
ACERO CORRUGADO GRADO 60 KG 1.09 4.70 5.12
MATERIAL 3 M3 0.00 0.00 0.00
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 P2 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 5.33
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
GASOLINA GLN 0.00 11.00 0.03 0.00
PETROLEO GLN 0.00 9.39 0.03 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.03 0.00
GRASA KG 0.00 5.00 0.03 0.00
GASOLINA GLN 0.00 9.79 0.03 0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.03 0.00
0.03 0.00
0.03 0.00
TOTAL VAR 0.00
TOTAL P.U. 6.28

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 3


PRECIO UNITARIO: ACERO GRADO 60 EN VIGAS
RENDIMIENTO EN 8 HRS: 250 KG/DIA
APORTE: 0.0320 HRS/KG TOTAL P.U. 6.96
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.03 0.00
CAPATAZ H-H 0.10 22.89 0.03 0.07
OPERARIO H-H 1.00 19.18 0.03 0.61
OFICIAL H-H 1.00 15.90 0.03 0.51
PEON H-H 1.00 14.30 0.03 0.46
TOTAL MO 1.65
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 1.65 0.17
ALAMBRE NEGRO RECOCIDO N 16 KG 0.05 2.24 0.11
ACERO CORRUGADO GRADO 60 kg 1.07 4.70 5.03
MATERIAL 3 P2 0.00 0.00 0.00
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 M3 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 5.30
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
GASOLINA GLN 0.00 11.00 0.03 0.00
PETROLEO GLN 0.00 9.39 0.03 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.03 0.00
GRASA KG 0.00 5.00 0.03 0.00
GASOLINA GLN 0.00 9.79 0.03 0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.03 0.00
0.03 0.00
0.03 0.00
TOTAL VAR 0.00
TOTAL P.U. 6.96

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 4


PRECIO UNITARIO: ACERO GRADO 60 EN LOSAS ALIGERADAS
RENDIMIENTO EN 8 HRS: 250 M3/DIA
APORTE: 0.0320 HRS/KG TOTAL P.U. 6.40
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.03 0.00
CAPATAZ H-H 0.10 22.89 0.03 0.07
OPERARIO H-H 1.00 19.18 0.03 0.61
OFICIAL H-H 0.00 15.90 0.03 0.00
PEON H-H 1.00 14.30 0.03 0.46
TOTAL MO 1.14
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 1.14 0.11
ALAMBRE NEGRO RECOCIDO N 16 KG 0.05 2.24 0.11
ACERO CORRUGADO GRADO 60 kg 1.07 4.70 5.03
MATERIAL 3 M3 0.00 0.00 0.00
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 M3 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 5.25
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
GASOLINA GLN 0.00 11.00 0.03 0.00
PETROLEO GLN 0.00 9.39 0.03 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.03 0.00
GRASA KG 0.00 5.00 0.03 0.00
GASOLINA GLN 0.00 9.79 0.03 0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.03 0.00
0.03 0.00
0.03 0.00
TOTAL VAR 0.00
TOTAL P.U. 6.40

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 5


PRECIO UNITARIO: ACERO GRADO 60 EN LOSAS MACIZAS
RENDIMIENTO EN 8 HRS: 250 KG/DIA
APORTE: 0.0320 HRS/KG TOTAL P.U. 6.40
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.03 0.00
CAPATAZ H-H 0.10 22.89 0.03 0.07
OPERARIO H-H 1.00 19.18 0.03 0.61
OFICIAL H-H 0.00 15.90 0.03 0.00
PEON H-H 1.00 14.30 0.03 0.46
TOTAL MO 1.14
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 1.14 0.11
ALAMBRE NEGRO RECOCIDO N 16 KG 0.05 2.24 0.11
ACERO CORRUGADO GRADO 60 kg 1.07 4.70 5.03
AGUA M3 0.00 0.00 0.00
GRAVA M3 0.00 0.00 0.00
ARENA M3 0.00 0.00 0.00
MADERA P2 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 5.25
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
GASOLINA GLN 0.00 11.00 0.03 0.00
PETROLEO GLN 0.00 9.39 0.03 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.03 0.00
GRASA KG 0.00 5.00 0.03 0.00
GASOLINA GLN 0.00 9.79 0.03 0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.03 0.00
0.03 0.00
0.03 0.00
TOTAL VAR 0.00
TOTAL P.U. 6.40

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 6


PRECIO UNITARIO: ACERO EN MURO DE ALBANILERIA ARMADA
RENDIMIENTO EN 8 HRS: 300 M3/DIA
APORTE: 0.0267 HRS/KG TOTAL P.U. 6.28
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.03 0.00
CAPATAZ H-H 0.10 22.89 0.03 0.06
OPERARIO H-H 1.00 19.18 0.03 0.51
OFICIAL H-H 0.00 15.90 0.03 0.00
PEON H-H 1.00 14.30 0.03 0.38
TOTAL MO 0.95
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 0.95 0.10
ALAMBRE NEGRO RECOCIDO N 16 KG 0.05 2.24 0.11
ACERO CORRUGADO GRADO 60 kg 1.09 4.70 5.12
MATERIAL 3 P2 0.00 0.00 0.00
MATERIAL 4 M3 0.00 0.00 0.00
MATERIAL 5 M3 0.00 0.00 0.00
MATERIAL 6 P2 0.00 0.00 0.00
MATERIAL 7 M3 0.00 0.00 0.00
MATERIAL 8 M3 0.00 0.00 0.00
MATERIAL 9 M3 0.00 0.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 5.33
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
GASOLINA GLN 0.00 11.00 0.03 0.00
PETROLEO GLN 0.00 9.39 0.03 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.03 0.00
GRASA KG 0.00 5.00 0.03 0.00
GASOLINA GLN 0.00 9.79 0.03 0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
H-M 0.03 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.03 0.00
0.03 0.00
0.03 0.00
TOTAL VAR 0.00
TOTAL P.U. 6.28

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD
DE HERRAM
ACERO
UNIDAD OBRA MANUALES ALAMBRE CORRUGADO
AC. EN SOBREC. 1.14 0.11 0.11 5.03
METRADO 11520 13,185.88 1,318.59 1,287.71 57,909.43

AC. EN MUROS TABIQUES Y


PLACAS 0.95 0.10 0.11 5.12
METRADO 19200 18,313.73 1,831.37 2,146.18 98,319.74

AC. EN VIGAS 1.65 0.17 0.11 5.03


METRADO 19200 31,745.43 3,174.54 2,146.18 96,515.71

AC. EN LOSAS ALIGERADAS 1.14 0.11 0.11 5.03


METRADO 5280 6,043.53 604.35 590.20 26,541.82

AC. EN LOSAS MACIZAS 1.14 0.11 0.11 5.03


METRADO 1152 1,318.59 131.86 128.77 5,790.94

AC. ALBANILERIA ARMADA 0.95 0.10 0.11 5.12


METRADO 3360 3,204.90 320.49 375.58 17,205.96

TOTAL 73,812.07 7,381.21 6,674.61 302,283.60


PORCENTAJES 0.160 0.016 0.014 0.657

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MAT 3 MAT 4 MAT 5 MAT 6 MAT 7 MAT 8 MAT9 MAT 10


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

COMBUST EQUIPOS TOTAL GTO GENERAL


Y COSTO UTILIDADES
MAT 11 LUBRIC VARIOS 1 VARIOS 2 VARIOS 3 DIRECTO 18
0.00 0.00 0.00 0.00 0.00 0.00 6.40
0.00 0.00 0.00 0.00 0.00 0.00 73,701.61

0.00 0.00 0.00 0.00 0.00 0.00 6.28


0.00 0.00 0.00 0.00 0.00 0.00 120,611.02

0.00 0.00 0.00 0.00 0.00 0.00 6.96


0.00 0.00 0.00 0.00 0.00 0.00 133,581.86

0.00 0.00 0.00 0.00 0.00 0.00 6.40


0.00 0.00 0.00 0.00 0.00 0.00 33,779.90

0.00 0.00 0.00 0.00 0.00 0.00 6.40


0.00 0.00 0.00 0.00 0.00 0.00 7,370.16

0.00 0.00 0.00 0.00 0.00 0.00 6.28


0.00 0.00 0.00 0.00 0.00 0.00 21,106.93

0.00 0.00 0.00 0.00 0.00 0.00 390,151.48 70,227.27


0.000 0.000 0.000 0.000 0.000 0.000 0.847 0.153

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

GRALES
PRESUPUESTO

460,378.75
1.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

CARPINTERIA METALICA Y DE MADERA


PROYECTO: EXAMEN FINAL 1
PRECIO UNITARIO: PUERTA PRINCIPAL DE CEDRO DE 0.80 M DE ANCHO
RENDIMIENTO EN 8 HRS: 5 UND/DIA
APORTE: 1.6000 HRS/UND TOTAL P.U. 199.76
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.60 0.00
CAPATAZ H-H 0.00 22.89 1.60 0.00
OPERARIO H-H 1.00 19.18 1.60 30.69
OFICIAL H-H 0.00 15.90 1.60 0.00
PEON H-H 0.00 14.30 1.60 0.00
TOTAL MO 30.69
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 30.69 3.07
VENTANA M2 0.00 19.00 0.00
PERFILES DE ALUMINIO M2 0.00 19.00 0.00
CRISTAL TEMPLADO INCOLORO DE 6mm ML 0.00 93.19 0.00
ACCESORIOS Y CERRAJERIA UND 1.00 6.00 6.00
SILICONA UND 0.00 9.60 0.00
ESCALERA DE CARACOL PZA 0.00 250.00 0.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 1.00 160.00 160.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 169.07
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.60 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.60 0.00
GRASA KG 0.00 9.39 1.60 0.00
GASOLINA GLN 0.00 11.00 1.60 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.60 0.00
1.60 0.00
1.60 0.00
1.60 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.60 0.00
1.60 0.00
1.60 0.00
TOTAL VAR 0.00
TOTAL P.U. 199.76

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 2


PRECIO UNITARIO: PUERTA POSTERIOR CONTRAPLACADA DE 0.65 M DE ANCHO
RENDIMIENTO EN 8 HRS: 8 UND/DIA
APORTE: 1.0000 HRS/UND TOTAL P.U. 211.84
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 1.00 25.08 1.00 25.08
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 0.00 19.18 1.00 0.00
OFICIAL H-H 0.00 15.90 1.00 0.00
PEON H-H 1.00 14.30 1.00 14.30
TOTAL MO 41.67
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 41.67 4.17
VENTANA M2 0.00 19.00 0.00
PERFILES DE ALUMINIO M2 0.00 19.00 0.00
CRISTAL TEMPLADO INCOLORO DE 6mm ML 0.00 93.19 0.00
ACCESORIOS Y CERRAJERIA UND 1.00 6.00 6.00
SILICONA UND 0.00 9.60 0.00
ESCALERA DE CARACOL PZA 0.00 250.00 0.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 1 160.00 160.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 170.17
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
SIERRA CIRCULAR H-M 0.00 2.00 1.00 0.00
CEPILLADORA ELECTRICA H-M 0.00 10.00 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TARUGO P2 0.00 0.50 1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 211.84

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 3


PRECIO UNITARIO: PUERTAS INTERIORES CONTRAPLACADAS DE 0.65 M DE ANCHO
RENDIMIENTO EN 8 HRS: 8 UND/DIA
APORTE: 1.0000 HRS/UND TOTAL P.U. 196.11
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 1.00 25.08 1.00 25.08
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 0.00 19.18 1.00 0.00
OFICIAL H-H 0.00 15.90 1.00 0.00
PEON H-H 0.00 14.30 1.00 0.00
TOTAL MO 27.37
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 27.37 2.74
VENTANA M2 0.00 19.00 0.00
PERFILES DE ALUMINIO M2 0.00 19.00 0.00
CRISTAL TEMPLADO INCOLORO DE 6mm ML 0.00 93.19 0.00
ACCESORIOS Y CERRAJERIA UND 1.00 6.00 6.00
SILICONA UND 0.00 9.60 0.00
ESCALERA DE CARACOL PZA 0.00 250.00 0.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 1.00 160.00 160.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 168.74
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
SIERRA CIRCULAR H-M 0.00 2.00 1.00 0.00
CEPILLADORA ELECTRICA H-M 0.00 10.00 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 196.11

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 4


PRECIO UNITARIO: PUERTA CORREDIZA DE 1.80 X 1.80 M
RENDIMIENTO EN 8 HRS: 8 UND/DIA
APORTE: 1.0000 HRS/UND TOTAL P.U. 358.26
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.00 0.00
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 1.00 19.18 1.00 19.18
OFICIAL H-H 1.00 15.90 1.00 15.90
PEON H-H 0.00 14.30 1.00 0.00
TOTAL MO 37.37
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 37.37 3.74
VENTANA M2 0.00 19.00 0.00
PERFILES DE ALUMINIO M2 2.30 19.00 43.70
CRISTAL TEMPLADO INCOLORO DE 6mm ML 1.05 93.19 97.85
ACCESORIOS Y CERRAJERIA PARA VENTAN UND 1.00 6.00 6.00
SILICONA UND 1.00 9.60 9.60
ESCALERA DE CARACOL PZA 0.00 250.00 0.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 1 160.00 160.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 320.89
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
SIERRA CIRCULAR H-M 0.00 2.00 1.00 0.00
CEPILLADORA ELECTRICA H-M 0.00 10.00 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TARUGO UND 0.00 0.5 1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 358.26

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 5


PRECIO UNITARIO: ESCALERA METALICA DE 25 PASOS
RENDIMIENTO EN 8 HRS: 1 UND/DIA
APORTE: 8.0000 HRS/UND TOTAL P.U. 590.91
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 8.00 0.00
CAPATAZ H-H 0.20 22.89 8.00 36.62
OPERARIO H-H 1.00 19.18 8.00 153.44
OFICIAL H-H 0.00 15.90 8.00 0.00
PEON H-H 1.00 14.30 8.00 114.40
TOTAL MO 304.46
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 304.46 30.45
VENTANA M2 0.00 19.00 0.00
PERFILES DE ALUMINIO M2 0.00 19.00 0.00
CRISTAL TEMPLADO INCOLORO DE 6mm ML 0.00 93.19 0.00
ACCESORIOS Y CERRAJERIA UND 1.00 6.00 6.00
SILICONA UND 0.00 9.60 0.00
ESCALERA DE CARACOL PZA 1.00 250.00 250.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 0 160.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 286.45
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 8.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 8.00 0.00
GRASA KG 0.00 9.39 8.00 0.00
GASOLINA GLN 0.00 11.00 8.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 8.00 0.00
H-M 8.00 0.00
H-M 8.00 0.00
H-M 8.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
8.00 0.00
8.00 0.00
8.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 590.91

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 6


PRECIO UNITARIO: VENTANA PRINCIPAL DE 1.80 X 0.90 M DE 2 HOJAS
RENDIMIENTO EN 8 HRS: 8 UND/DIA
APORTE: 1.0000 HRS/UND TOTAL P.U. 91.60
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 1.00 25.08 1.00 25.08
CAPATAZ H-H 0.10 22.89 1.00 2.29
OPERARIO H-H 0.00 19.18 1.00 0.00
OFICIAL H-H 1.00 15.90 1.00 15.90
PEON H-H 0.00 14.30 1.00 0.00
TOTAL MO 43.27
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 43.27 4.33
VENTANA M2 2.00 19.00 38.00
PERFILES DE ALUMINIO M2 0.00 19.00 0.00
CRISTAL TEMPLADO INCOLORO DE 6mm ML 0.00 93.19 0.00
ACCESORIOS Y CERRAJERIA UND 1.00 6.00 6.00
SILICONA UND 0.00 9.60 0.00
ESCALERA DE CARACOL PZA 0.00 250.00 0.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 0 160.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
MATERIAL 12 M3 0.00 0.00 0.00
TOTAL MAT 48.33
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.00 0.00
GRASA KG 0.00 9.39 1.00 0.00
GASOLINA GLN 0.00 11.00 1.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
H-M 1.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 91.60

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 7


PRECIO UNITARIO: VENTANA POSTERIOR DE 1.20 X 0.90 M DE 2 HOJAS
RENDIMIENTO EN 8 HRS: 4.5 UND/DIA
APORTE: 1.7778 HRS/UND TOTAL P.U. 98.08
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.78 0.00
CAPATAZ H-H 0.10 22.89 1.78 4.07
OPERARIO H-H 1.00 19.18 1.78 34.10
OFICIAL H-H 1.00 15.90 1.78 28.27
PEON H-H 0.00 14.30 1.78 0.00
TOTAL MO 66.43
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 66.43 6.64
VENTANA M2 1.00 19.00 19.00
PERFILES DE ALUMINIO M2 0.00 19.00 0.00
CRISTAL TEMPLADO INCOLORO DE 6mm ML 0.00 93.19 0.00
ACCESORIOS Y CERRAJERIA UND 1.00 6.00 6.00
SILICONA UND 0.00 9.60 0.00
ESCALERA DE CARACOL PZA 0.00 250.00 0.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 0 160.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 31.64
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.78 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.78 0.00
GRASA KG 0.00 9.39 1.78 0.00
GASOLINA GLN 0.00 11.00 1.78 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.78 0.00
H-M 1.78 0.00
H-M 1.78 0.00
H-M 1.78 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.78 0.00
1.78 0.00
1.78 0.00
TOTAL VAR 0.00
TOTAL P.U. 98.08

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAAMEN FINAL 8


PRECIO UNITARIO: VENTANAS EN DORMITORIOS DE 1.50 X .90 M DE 2 HOJAS
RENDIMIENTO EN 8 HRS: 4 M3/DIA
APORTE: 2.0000 TOTAL P.U. 177.19
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 1.00 25.08 2.00 50.16
CAPATAZ H-H 0.10 22.89 2.00 4.58
OPERARIO H-H 0.00 19.18 2.00 0.00
OFICIAL H-H 1.00 15.90 2.00 31.80
PEON H-H 0.00 14.30 2.00 0.00
TOTAL MO 86.54
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 86.54 8.65
VENTANA M2 4.00 19.00 76.00
PERFILES DE ALUMINIO M2 0.00 19.00 0.00
CRISTAL TEMPLADO INCOLORO DE 6mm ML 0.00 93.19 0.00
ACCESORIOS Y CERRAJERIA UND 1.00 6.00 6.00
SILICONA UND 0.00 9.60 0.00
ESCALERA DE CARACOL PZA 0.00 250.00 0.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 0 160.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 90.65
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.00 0.00
GRASA KG 0.00 9.39 2.00 0.00
GASOLINA GLN 0.00 11.00 2.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.00 0.00
2.00 0.00
2.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 177.19

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 9


PRECIO UNITARIO: VENTANA CORREDIZA DE 1.55 X .90 M DE 2 HOJAS
RENDIMIENTO EN 8 HRS: 4 M2/DIA
APORTE: 2.0000 TOTAL P.U. 189.76
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.00 0.00
CAPATAZ H-H 0.30 22.89 2.00 13.73
OPERARIO H-H 1.00 19.18 2.00 38.36
OFICIAL H-H 0.00 15.90 2.00 0.00
PEON H-H 1.00 14.30 2.00 28.60
TOTAL MO 80.69
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 80.69 8.07
VENTANA M2 3.00 19.00 57.00
PERFILES DE ALUMINIO M2 2.00 19.00 38.00
CRISTAL TEMPLADO INCOLORO DE 6mm ML 0.00 93.19 0.00
ACCESORIOS Y CERRAJERIA UND 1.00 6.00 6.00
SILICONA UND 0.00 9.60 0.00
ESCALERA DE CARACOL PZA 0.00 250.00 0.00
CARPINTERIA METALICA M2 0.00 280.69 0.00
PREMARCO ML 0.00 12.45 0.00
PUERTA UND 0.00 160.00 0.00
MATERIAL 10 M3 0.00 0.00 0.00
MATERIAL 11 M3 0.00 0.00 0.00
TOTAL MAT 109.07
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.00 0.00
GRASA KG 0.00 9.39 2.00 0.00
GASOLINA GLN 0.00 11.00 2.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.00 0.00
2.00 0.00
2.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 189.76

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD CRISTAL


DE HERRAM TEMPLADO
PERFILES DE INCOLORO DW
UNIDAD OBRA MANUALES VENTANA ALUMINIO 6 mm
P. PR. 0.80 M. 30.69 3.07 0.00 0.00 0.00
METRADO 96 2,946.05 294.60 0.00 0.00 0.00

P. POST. CONTRAP. 0.65 M 41.67 4.17 0.00 0.00 0.00


METRADO 96 4,000.22 400.02 0.00 0.00 0.00

P. INT. CONTRAP. DE 0.65 M 27.37 2.74 0.00 0.00 0.00


METRADO 768 21,019.39 2,101.94 0.00 0.00 0.00

P. CORRED. DE 1.80 X 1.80 M 37.37 3.74 0.00 43.70 97.85


METRADO 96 3,587.42 358.74 0.00 4,195.20 9,393.55

ESC. MET. DE 25 PASOS 304.46 30.45 0.00 0.00 0.00


METRADO 96 29,228.54 2,922.85 0.00 0.00 0.00

V. PR. DE 1.80 X 0.90 M 2 HOJAS 43.27 4.33 38.00 0.00 0.00


METRADO 96 4,153.82 415.38 3,648.00 0.00 0.00

V. POST. DE 1.20 X 0.90 M . 2


HOJAS 66.43 6.64 19.00 0.00 0.00
METRADO 96 6,377.64 637.76 1,824.00 0.00 0.00

V. EN DORM. DE 1.50 X .90 M. 2


HOJAS 86.54 8.65 76.00 0.00 0.00
METRADO 384 33,230.59 3,323.06 29,184.00 0.00 0.00

V. CORR. 1.55 X .90 M 2 HOJAS 80.69 8.07 57.00 38.00 0.00


METRADO 384 30,986.50 3,098.65 21,888.00 14,592.00 0.00

MANO SEGURIDAD
DE HERRAM
PERFILES DE CRISTAL
UNIDAD OBRA MANUALES VENTANA ALUMINIO TEMPLADO
TOTAL 135,530.19 13,553.02 56,544.00 18,787.20 9,393.55
PORCENTAJES 0.261 0.026 0.109 0.036 0.018

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

COMBUST
Y
ESCALERA DE CARPINTERIA
ACCESORIOS Y CERRAJERIA
SILICONA CARACOL METALICA PREMARCO PUERTA MAT 10 MAT 11 LUBRIC
6.00 0.00 0.00 0.00 0.00 160.00 0.00 0.00 0.00
576.00 0.00 0.00 0.00 0.00 15,360.00 0.00 0.00 0.00

6.00 0.00 0.00 0.00 0.00 160.00 0.00 0.00 0.00


576.00 0.00 0.00 0.00 0.00 15,360.00 0.00 0.00 0.00

6.00 0.00 0.00 0.00 0.00 160.00 0.00 0.00 0.00


4,608.00 0.00 0.00 0.00 0.00 122,880.00 0.00 0.00 0.00

6.00 9.60 0.00 0.00 0.00 160.00 0.00 0.00 0.00


576.00 921.60 0.00 0.00 0.00 15,360.00 0.00 0.00 0.00

6.00 0.00 250.00 0.00 0.00 0.00 0.00 0.00 0.00


576.00 0.00 24,000.00 0.00 0.00 0.00 0.00 0.00 0.00

6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


576.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


576.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


2,304.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


2,304.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

COMBUST
Y
ESCALERA DE CARPINTERIA
ACCESORIOS Y CERRAJERIA
SILICONA CARACOL METALICA PREMARCO PUERTA MAT 10 MAT 11 LUBRIC
12,672.00 921.60 24,000.00 0.00 0.00 168,960.00 0.00 0.00 0.00
0.024 0.002 0.046 0.000 0.000 0.325 0.000 0.000 0.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

EQUIPOS TOTAL GTO GENERAL GRALES


COSTO UTILIDADES PRESUPUESTO
VARIOS 1 VARIOS 2 VARIOS 3 DIRECTO 18
0.00 0.00 0.00 0.00 199.76
0.00 0.00 0.00 0.00 19,176.65

0.00 0.00 0.00 0.00 211.84


0.00 0.00 0.00 0.00 20,336.25

0.00 0.00 0.00 0.00 196.11


0.00 0.00 0.00 0.00 150,609.33

0.00 0.00 0.00 0.00 358.26


0.00 0.00 0.00 0.00 34,392.52

0.00 0.00 0.00 0.00 590.91


0.00 0.00 0.00 0.00 56,727.40

0.00 0.00 0.00 0.00 91.60


0.00 0.00 0.00 0.00 8,793.21

0.00 0.00 0.00 0.00 98.08


0.00 0.00 0.00 0.00 9,415.41

0.00 0.00 0.00 0.00 177.19


0.00 0.00 0.00 0.00 68,041.65

0.00 0.00 0.00 0.00 189.76


0.00 0.00 0.00 0.00 72,869.15

EQUIPOS TOTAL GTO GENERAL GRALES


COSTO UTILIDADES PRESUPUESTO
VARIOS 1 VARIOS 2 VARIOS 3 DIRECTO 28
0.00 0.00 0.00 0.00 440,361.56 79,265.08 519,626.64
0.000 0.000 0.000 0.000 0.847 0.153 1.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

159,119.41

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

INSTALACIONES SANITARIAS
PROYECTO: EXAMEN FINAL 1
PRECIO UNITARIO: INODORO COLOR BLANCO ECONOMICO
RENDIMIENTO EN 8 HRS: 3 PZA./DIA
APORTE: 2.6667 HRS/PZA TOTAL P.U. 199.98
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.67 0.00
CAPATAZ H-H 0.10 22.89 2.67 6.10
OPERARIO H-H 1.00 19.18 2.67 51.15
OFICIAL H-H 0.00 15.90 2.67 0.00
PEON H-H 0.00 14.30 2.67 0.00
TOTAL MO 57.25
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 57.25 5.73
INODORO LOSA COLOR BLANCO UND 1.00 130.50 130.50
PEGAMENTO P/TUBO PVC 1/4GL UND 0.00 21.30 0.00
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 1.00 6.50 6.50
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 142.73
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.67 0.00
GRASA KG 0.00 9.39 2.67 0.00
GASOLINA GLN 0.00 11.00 2.67 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.67 0.00
H-M 2.67 0.00
H-M 2.67 0.00
H-M 2.67 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.67 0.00
2.67 0.00
2.67 0.00
TOTAL VAR 0.00
2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 199.98

PROYECTO: EXAMEN FINAL 2


PRECIO UNITARIO: LAVATORIO DE PARED BLANCO
RENDIMIENTO EN 8 HRS: 3 PZA/DIA
APORTE: 2.6667 HRS/PZA TOTAL P.U. 206.48
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.67 0.00
CAPATAZ H-H 0.10 22.89 2.67 6.10
OPERARIO H-H 1.00 19.18 2.67 51.15
OFICIAL H-H 0.00 15.90 2.67 0.00
PEON H-H 0.00 14.30 2.67 0.00
TOTAL MO 57.25
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 57.25 5.73
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.00 21.30 0.00
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 1.00 133.5 133.50
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 10.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 149.23
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.67 0.00
GRASA KG 0.00 9.39 2.67 0.00
GASOLINA GLN 0.00 11.00 2.67 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.67 0.00
H-M 2.67 0.00
H-M 2.67 0.00
H-M 2.67 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.67 0.00
2.67 0.00
2.67 0.00
2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL VAR 0.00
TOTAL P.U. 206.48

PROYECTO: EXAMEN FINAL 3


PRECIO UNITARIO: LAVADERO DE ACERO INOXIDABLE
RENDIMIENTO EN 8 HRS: 4 UND/DIA
APORTE: 2.0000 HRS/PZA TOTAL P.U. 180.73
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.00 0.00
CAPATAZ H-H 0.10 22.89 2.00 4.58
OPERARIO H-H 1.00 19.18 2.00 38.36
OFICIAL H-H 0.00 15.90 2.00 0.00
PEON H-H 0.00 14.30 2.00 0.00
TOTAL MO 42.94
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 42.94 4.29
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.00 21.30 0.00
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 1.00 133.5 133.50
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 137.79
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.00 0.00
GRASA KG 0.00 9.39 2.00 0.00
GASOLINA GLN 0.00 11.00 2.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.00 0.00
2.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
2.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 180.73

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 4


PRECIO UNITARIO: LAVADERO DE GRANITO
RENDIMIENTO EN 8 HRS: 4 UND/DIA
APORTE: 2.0000 HRS/UND TOTAL P.U. 180.73
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.00 0.00
CAPATAZ H-H 0.10 22.89 2.00 4.58
OPERARIO H-H 1.00 19.18 2.00 38.36
OFICIAL H-H 0.00 15.90 2.00 0.00
PEON H-H 0.00 14.30 2.00 0.00
TOTAL MO 42.94
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 42.94 4.29
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.00 21.30 0.00
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 1.00 133.5 133.50
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 137.79
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.00 0.00
GRASA KG 0.00 9.39 2.00 0.00
GASOLINA GLN 0.00 11.00 2.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.00 0.00
2.00 0.00
2.00 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 180.73

PROYECTO: EXAMEN PARCIAL 5


PRECIO UNITARIO: DUCHA SIMPLE CROMADA 1 LLAVE INCLUYE ACCESORIOS
RENDIMIENTO EN 8 HRS: 4 UND/DIA
APORTE: 2.0000 HRS/UND TOTAL P.U. 185.29
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.00 0.00
CAPATAZ H-H 0.10 22.89 2.00 4.58
OPERARIO H-H 1.00 19.18 2.00 38.36
OFICIAL H-H 0.00 15.90 2.00 0.00
PEON H-H 1.00 14.30 2.00 28.60
TOTAL MO 71.54
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 71.54 7.15
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.00 21.30 0.00
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 1.00 106.60 106.60
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 113.75
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.00 0.00
GRASA KG 0.00 9.39 2.00 0.00
GASOLINA GLN 0.00 11.00 2.00 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.00 0.00
2.00 0.00
2.00 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL VAR 0.00
TOTAL P.U. 185.29

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 6


PRECIO UNITARIO: RED DE DISTRIBUCION TUBERIA DE 1/2" PVC-SAP
RENDIMIENTO EN 8 HRS: 25 ML/DIA
APORTE: 0.3200 HRS/ML TOTAL P.U. 20.56
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.32 0.00
CAPATAZ H-H 0.10 22.89 0.32 0.73
OPERARIO H-H 1.00 19.18 0.32 6.14
OFICIAL H-H 0.00 15.90 0.32 0.00
PEON H-H 0.00 14.30 0.32 0.00
TOTAL MO 6.87
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 6.87 0.69
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.00 21.30 0.00
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 2.00 6.50 13.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 13.69
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.32 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.32 0.00
GRASA KG 0.00 9.39 0.32 0.00
GASOLINA GLN 0.00 11.00 0.32 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.32 0.00
H-M 0.32 0.00
H-M 0.32 0.00
H-M 0.32 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.32 0.00
0.32 0.00
0.32 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 20.56

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 7


PRECIO UNITARIO: SALIDA DE AGUA FRIA DE 1/2"
RENDIMIENTO EN 8 HRS: 4 PTO/DIA
APORTE: 2.0000 HRS/PTO TOTAL P.U. 106.78
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.00 0.00
CAPATAZ H-H 0.10 22.89 2.00 4.58
OPERARIO H-H 1.00 19.18 2.00 38.36
OFICIAL H-H 0.00 15.90 2.00 0.00
PEON H-H 0.00 14.30 2.00 0.00
TOTAL MO 42.94
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 42.94 4.29
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.004 21.30 0.09
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 3.00 6.50 19.50
CODO PVC1/2" Pza 2.00 3.40 6.80
TEE PVC 1/2" Pza 1.00 4.30 4.30
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 28.86
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 63.84
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.00 0.00
GRASA KG 0.00 9.39 2.00 0.00
GASOLINA GLN 0.00 11.00 2.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.00 0.00
2.00 0.00
2.00 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 106.78

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 8


PRECIO UNITARIO: VALVULAS DE COMPUERTA DE BRONCE DE 1/2"
RENDIMIENTO EN 8 HRS: 5 PZA/DIA
APORTE: 1.6000 HRS/PZA TOTAL P.U. 80.23
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.60 0.00
CAPATAZ H-H 0.10 22.89 1.60 3.66
OPERARIO H-H 1.00 19.18 1.60 30.69
OFICIAL H-H 0.00 15.90 1.60 0.00
PEON H-H 1.00 14.30 1.60 22.88
TOTAL MO 57.23
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 57.23 5.72
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.00 21.30 0.00
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 2.00 6.64 13.28
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 4.00 1.00 4.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55
TOTAL MAT 23.00
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.60 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.60 0.00
GRASA KG 0.00 9.39 1.60 0.00
GASOLINA GLN 0.00 11.00 1.60 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.00 0.00
1.00 0.00
1.00 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 80.23

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 9


PRECIO UNITARIO: RED DE DESAGUE DE 4" EN PVC
RENDIMIENTO EN 8 HRS: 12 ML/DIA
APORTE: 0.6667 HRS/ML TOTAL P.U. 56.31
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.67 0.00
CAPATAZ H-H 0.10 22.89 0.67 1.53
OPERARIO H-H 1.00 19.18 0.67 12.79
OFICIAL H-H 0.00 15.90 0.67 0.00
PEON H-H 0.00 14.30 0.67 0.00
TOTAL MO 14.31
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 14.31 1.43
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.10 21.30 2.13
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 2.00 3.40 6.80
TEE PVC 1/2" Pza 0.20 4.30 0.86
UNION UNIVERSAL ACERO GALV. 1/2" UND 2.00 6.64 13.28
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 2.50 7.00 17.50
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 42.00
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.67 0.00
GRASA KG 0.00 9.39 0.67 0.00
GASOLINA GLN 0.00 11.00 0.67 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.67 0.00
0.67 0.00
0.67 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 56.31

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 10


PRECIO UNITARIO: RED DE DESAGUE DE 2" EN PVC
RENDIMIENTO EN 8 HRS: 20 ML/DIA
APORTE: 0.4000 HRS/ML TOTAL P.U. 48.55
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.40 0.00
CAPATAZ H-H 0.10 22.89 0.40 0.92
OPERARIO H-H 1.00 19.18 0.40 7.67
OFICIAL H-H 0.00 15.90 0.40 0.00
PEON H-H 0.00 14.30 0.40 0.00
TOTAL MO 8.59
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 8.59 0.86
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.20 21.30 4.26
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 3.00 3.40 10.20
TEE PVC 1/2" Pza 0.20 4.30 0.86
UNION UNIVERSAL ACERO GALV. 1/2" UND 2.00 6.64 13.28
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 1.50 7.00 10.50
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 39.96
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.40 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.40 0.00
GRASA KG 0.00 9.39 0.40 0.00
GASOLINA GLN 0.00 11.00 0.40 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.40 0.00
H-M 0.40 0.00
H-M 0.40 0.00
H-M 0.40 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.40 0.00
0.40 0.00
0.40 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 48.55

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 11


PRECIO UNITARIO: TUBERIA DE DESAGUE PVC SAL DE 2" PARA VENTILACION
RENDIMIENTO EN 8 HRS: 15 ML/DIA
APORTE: 0.5333 HRS/ML TOTAL P.U. 48.76
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.53 0.00
CAPATAZ H-H 0.10 22.89 0.53 1.22
OPERARIO H-H 1.00 19.18 0.53 10.23
OFICIAL H-H 0.00 15.90 0.53 0.00
PEON H-H 0.00 14.30 0.53 0.00
TOTAL MO 11.45
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 11.45 1.15
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 1.00 21.30 21.30
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.20 4.30 0.86
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 2.00 7.00 14.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 37.31
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.53 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.53 0.00
GRASA KG 0.00 9.39 0.53 0.00
GASOLINA GLN 0.00 11.00 0.53 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.53 0.00
H-M 0.53 0.00
H-M 0.53 0.00
H-M 0.53 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.53 0.00
0.53 0.00
0.53 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 48.76

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN PARCIAL 12


PRECIO UNITARIO: SALIDA DE DESAGUE DE 4"
RENDIMIENTO EN 8 HRS: 4 PTO/DIA
APORTE: 2.0000 HRS/PTO TOTAL P.U. 82.54
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.00 0.00
CAPATAZ H-H 0.10 22.89 2.00 4.58
OPERARIO H-H 1.00 19.18 2.00 38.36
OFICIAL H-H 0.00 15.90 2.00 0.00
PEON H-H 0.00 14.30 2.00 0.00
TOTAL MO 42.94
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 42.94 4.29
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 1.00 21.30 21.30
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 2.00 3.40 6.80
TEE PVC 1/2" Pza 0.70 4.30 3.01
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.60 7.00 4.20
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 39.60
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.00 0.00
GRASA KG 0.00 9.39 2.00 0.00
GASOLINA GLN 0.00 11.00 2.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.00 0.00
2.00 0.00
2.00 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 82.54

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 13


PRECIO UNITARIO: SALIDA DE DESAGUE DE 2"
RENDIMIENTO EN 8 HRS: 4 PTO/DIA
APORTE: 2.0000 HRS/PTO TOTAL P.U. 64.79
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 2.00 0.00
CAPATAZ H-H 0.10 22.89 2.00 4.58
OPERARIO H-H 1.00 19.18 2.00 38.36
OFICIAL H-H 0.00 15.90 2.00 0.00
PEON H-H 0.00 14.30 2.00 0.00
TOTAL MO 42.94
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 42.94 4.29
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.20 21.30 4.26
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 1.00 3.40 3.40
TEE PVC 1/2" Pza 1.00 4.30 4.30
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.80 7.00 5.60
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 21.85
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 2.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 2.00 0.00
GRASA KG 0.00 9.39 2.00 0.00
GASOLINA GLN 0.00 11.00 2.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
H-M 2.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
2.00 0.00
2.00 0.00
2.00 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 64.79

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 14


PRECIO UNITARIO: CAJA DE REGISTRO DE ALBAÑILERIA DE 10" X 20"
RENDIMIENTO EN 8 HRS: 6 UND/DIA
APORTE: 1.3333 HRS/UND TOTAL P.U. 31.49
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 1.33 0.00
CAPATAZ H-H 0.10 22.89 1.33 3.05
OPERARIO H-H 1.00 19.18 1.33 25.57
OFICIAL H-H 0.00 15.90 1.33 0.00
PEON H-H 0.00 14.30 1.33 0.00
TOTAL MO 28.63
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 28.63 2.86
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.00 21.30 0.00
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 0.00 8.55 0.00
TOTAL MAT 2.86
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.33 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.33 0.00
GRASA KG 0.00 9.39 1.33 0.00
GASOLINA GLN 0.00 11.00 1.33 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.33 0.00
H-M 1.33 0.00
H-M 1.33 0.00
H-M 1.33 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
VALVULA COMP. BRONCE 1/2" UND 0.00 27.56 1.33 0.00
1.33 0.00
1.33 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 31.49

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 15


PRECIO UNITARIO: REGISTRO ROSCADO DE BRONCE DE 2"
RENDIMIENTO EN 8 HRS: 12 PZA/DIA
APORTE: 0.6667 HRS/PZA TOTAL P.U. 34.97
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.67 0.00
CAPATAZ H-H 0.10 22.89 0.67 1.53
OPERARIO H-H 1.00 19.18 0.67 12.79
OFICIAL H-H 0.00 15.90 0.67 0.00
PEON H-H 0.00 14.30 0.67 0.00
TOTAL MO 14.31
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 14.31 1.43
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.10 21.30 2.13
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 2" UND 2.00 8.55 17.10
TOTAL MAT 20.66
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.67 0.00
GRASA KG 0.00 9.39 0.67 0.00
GASOLINA GLN 0.00 11.00 0.67 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.67 0.00
0.67 0.00
0.67 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 34.97

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 16


PRECIO UNITARIO: REGISTRO ROSCADO DE BRONCE DE 4"
RENDIMIENTO EN 8 HRS: 12 PZA/DIA
APORTE: 0.6667 HRS/PZA TOTAL P.U. 17.87
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 25.08 0.67 0.00
CAPATAZ H-H 0.10 22.89 0.67 1.53
OPERARIO H-H 1.00 19.18 0.67 12.79
OFICIAL H-H 0.00 15.90 0.67 0.00
PEON H-H 0.00 14.30 0.67 0.00
TOTAL MO 14.31
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 14.31 1.43
INODORO LOSA COLOR BLANCO UND 0.00 130.50 0.00
PEGAMENTO P/TUBO PVC 1/4GL UND 0.10 21.30 2.13
DUCHA SIMPLE C/GRIFERIA Y BRAZO M/VAINSA UND 0.00 106.60 0.00
LAVATORIO UND 0.00 133.5 0.00
TUBERIA PVC 1/2" C-10 Pza 0.00 6.50 0.00
CODO PVC1/2" Pza 0.00 3.40 0.00
TEE PVC 1/2" Pza 0.00 4.30 0.00
UNION UNIVERSAL ACERO GALV. 1/2" UND 0.00 6.64 0.00
TUBO DE PVC P/DESAGUE SAL. 2"X 3m UND 0.00 7.00 0.00
NIPLE ACERO GALV. 1/2" x 1 1/4" UND 0.00 1.00 0.00
REGISTRO ROSCADO DE BRONCE DE 4" UND 2.00 8.55 17.10
TOTAL MAT 3.56
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.67 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.67 0.00
GRASA KG 0.00 9.39 0.67 0.00
GASOLINA GLN 0.00 11.00 0.67 0.00

TOTAL COMB 0.00


EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
H-M 0.67 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.67 0.00
0.67 0.00
0.67 0.00
TOTAL VAR 0.00

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
TOTAL P.U. 17.87

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD PERNO DE


DE HERRAM INODORO SUJECION
COLOR ACCESORIOS TANQUE PARA
UNIDAD OBRA MANUALES BLANCO BAJO INODORO
INODORO C/BLANCO ECON. 57.25 5.73 130.50 0.00 0.00
METRADO 192 10,992.13 1,099.21 25,056.00 0.00 0.00

LAVATORIO DE PARED BLANCO 57.25 5.73 0.00 0.00 0.00


METRADO 192 10,992.13 1,099.21 0.00 0.00 0.00

LAVADERO DE ACERO
INOXIDABLE 42.94 4.29 0.00 0.00 0.00
METRADO 192 8,244.10 824.41 0.00 0.00 0.00

LAVADERO DE GRANITO 42.94 4.29 0.00 0.00 0.00


METRADO 96 4,122.05 412.20 0.00 0.00 0.00

DUCHA SIMP. INC.


ACCESORIOS. 71.54 7.15 0.00 0.00 106.60
METRADO 192 13,735.30 1,373.53 0.00 0.00 20,467.20

RED DE DISTRIB. TUB. 1/2" PVC-


SAP 6.87 0.69 0.00 0.00 0.00
METRADO 2880 19,785.83 1,978.58 0.00 0.00 0.00

SALIDA DE AGUA FRIA DE 1/2" 42.94 4.29 0.00 0.09 0.00


METRADO 2400 103,051.20 10,305.12 0.00 204.48 0.00

VALVULAS DE COMPUERTA DE
BRONCE DE 1/2" 57.23 5.72 0.00 0.00 0.00
METRADO 192 10,988.24 1,098.82 0.00 0.00 0.00

RED DE DESAGUE DE 4" EN PVC 14.31 1.43 0.00 2.13 0.00


METRADO 1440 20,610.24 2,061.02 0.00 3,067.20 0.00

RED DE DESAGUE DE 2" EN PVC 8.59 0.86 0.00 0.00 0.00


METRADO 480 4,122.05 412.20 0.00 0.00 0.00

TUB. DESA. PVC SAL 2" VENT. 11.45 1.15 0.00 21.30 0.00
2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
METRADO 4800 54,960.64 5,496.06 0.00 102,240.00 0.00

SALIDA DE DESAGUE DE 4" 42.94 4.29 4.20 21.30 0.00


METRADO 192 8,244.10 824.41 806.40 4,089.60 0.00

SALIDA DE DESAGUE DE 2" 42.94 4.29 5.60 4.26 0.00


METRADO 192 8,244.10 824.41 1,075.20 817.92 0.00

CAJA DE REGISTRO DE
ALBAÑILERIA DE 10" X 20" 28.63 2.86 0.00 0.00 0.00
METRADO 192 5,496.06 549.61 0.00 0.00 0.00

REGISTRO ROSCADO DE BRONCE


DE 2" 14.31 1.43 0.00 2.13 0.00
METRADO 192 2,748.03 274.80 0.00 408.96 0.00

REGISTRO ROSCADO DE BRONCE


DE 4" 14.31 1.43 0.00 2.13 0.00
METRADO 192 2,748.03 274.80 0.00 408.96 0.00

TOTAL 289,084.21 28,908.42 26,937.60 111,237.12 20,467.20


PORCENTAJES 0.279 0.028 0.026 0.107 0.020

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PERNO DE LAVATORIO
ANCLAJE PARA ARUBA TRAMPA "P" TUBO DE LAVADERO INOX. REGISTRO
INODORO MASILLA BLANCO CROMADA ABASTO Y ACCES. CAJA DE REGISTRO ROSCADO
0.00 6.50 0.00 0.00 0.00 0.00 0.00 0.00
0.00 1,248.00 0.00 0.00 0.00 0.00 0.00 0.00

133.50 0.00 0.00 0.00 10.00 0.00 0.00 0.00


25,632.00 0.00 0.00 0.00 1,920.00 0.00 0.00 0.00

133.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00


25,632.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

133.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00


12,816.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 13.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 37,440.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 19.50 6.80 4.30 0.00 28.86 0.00 0.00


0.00 46,800.00 16,320.00 10,320.00 0.00 69,264.00 0.00 0.00

0.00 0.00 0.00 0.00 13.28 0.00 4.00 0.00


0.00 0.00 0.00 0.00 2,549.76 0.00 768.00 0.00

0.00 0.00 6.80 0.86 13.28 17.50 0.00 0.00


0.00 0.00 9,792.00 1,238.40 19,123.20 25,200.00 0.00 0.00

0.00 0.00 10.20 0.86 13.28 10.50 0.00 0.00


0.00 0.00 4,896.00 412.80 6,374.40 5,040.00 0.00 0.00

0.00 0.00 0.00 0.86 0.00 14.00 0.00 0.00


2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
0.00 0.00 0.00 4,128.00 0.00 67,200.00 0.00 0.00

0.00 0.00 6.80 0.00 0.00 0.00 0.00 0.00


0.00 0.00 1,305.60 0.00 0.00 0.00 0.00 0.00

0.00 0.00 3.40 4.30 0.00 0.00 0.00 0.00


0.00 0.00 652.80 825.60 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 17.10


0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,283.20

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

64,080.00 85,488.00 32,966.40 16,924.80 29,967.36 166,704.00 768.00 3,283.20


0.062 0.083 0.032 0.016 0.029 0.161 0.001 0.003

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

COMBUST EQUIPOS TOTAL GTO GENERAL GRALES


Y COSTO UTILIDADES PRESUPUESTO
LUBRIC VARIOS 1 VARIOS 2 VARIOS 3 DIRECTO 18
0.00 0.00 0.00 0.00 0.00 199.98
0.00 0.00 0.00 0.00 0.00 38,395.34

0.00 0.00 0.00 0.00 0.00 206.48


0.00 0.00 0.00 0.00 0.00 39,643.34

0.00 0.00 0.00 0.00 0.00 180.73


0.00 0.00 0.00 0.00 0.00 34,700.51

0.00 0.00 0.00 0.00 0.00 180.73


0.00 0.00 0.00 0.00 0.00 17,350.25

0.00 0.00 0.00 0.00 0.00 185.29


0.00 0.00 0.00 0.00 0.00 35,576.03

0.00 0.00 0.00 0.00 0.00 20.56


0.00 0.00 0.00 0.00 0.00 59,204.41

0.00 0.00 0.00 0.00 0.00 106.78


0.00 0.00 0.00 0.00 0.00 256,264.80

0.00 0.00 0.00 0.00 0.00 80.23


0.00 0.00 0.00 0.00 0.00 15,404.82

0.00 0.00 0.00 0.00 0.00 56.31


0.00 0.00 0.00 0.00 0.00 81,092.06

0.00 0.00 0.00 0.00 0.00 48.55


0.00 0.00 0.00 0.00 0.00 23,302.25

0.00 0.00 0.00 0.00 0.00 48.76


2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS
0.00 0.00 0.00 0.00 0.00 234,024.70

0.00 0.00 0.00 0.00 0.00 82.54


0.00 0.00 0.00 0.00 0.00 15,848.03

0.00 0.00 0.00 0.00 0.00 64.79


0.00 0.00 0.00 0.00 0.00 12,440.03

0.00 0.00 0.00 0.00 0.00 31.49


0.00 0.00 0.00 0.00 0.00 6,045.67

0.00 0.00 0.00 0.00 0.00 34.97


0.00 0.00 0.00 0.00 0.00 6,715.00

0.00 0.00 0.00 0.00 0.00 17.87


0.00 0.00 0.00 0.00 0.00 3,431.80

0.00 0.00 0.00 0.00 0.00 879,439.03 158,299.03 1,035,115.34


0.000 0.000 0.000 0.000 0.000 0.850 0.153 1.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

INSTALACIONES ELECTRICAS
PROYECTO: EXAMEN FINAL 1
PRECIO UNITARIO: CENTRO DE LUZ
RENDIMIENTO EN 8 HRS: 5 PTO/DIA
APORTE: 1.6000 HRS/PTO TOTAL P.U. 83.41
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 1.60 0.00
CAPATAZ H-H 0.10 20.79 1.60 3.33
OPERARIO H-H 1.00 18.08 1.60 28.93
OFICIAL H-H 0.00 14.81 1.60 0.00
PEON H-H 1.00 13.62 1.60 21.79
TOTAL MO 54.05
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 54.05 5.40
CABLE TW N 14 AWG 2.5 MM2 M 8.50 0.988 8.40
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 1.00 2.50 2.50
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 1.00 2.50 2.50
INTERRUPTOR 250V -15 A PZA 1.00 7.50 7.50
TUBO PVC 5/8" PZA 1.50 0.40 0.60
CURVA LIVIANA PVC 5/8" UND 3.00 0.70 2.10
CONEXIÓN A CAJA PVC 5/8" UND 2.00 0.18 0.36
TUBO PVC 3/4" UND 0.00 1.35 0.00
CURVA PESADA 3/4" UND 0.00 1.37 0.00
CURVA LIVIANA 3/4" UND 0.00 0.46 0.00
UNION UNIVERSAL 3/4" UND 0.00 4.24 0.00
TOTAL MAT 29.36
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.60 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.60 0.00
GRASA KG 0.00 9.39 1.60 0.00
GASOLINA GLN 0.00 11.00 1.60 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
INTERRUPTO DOBLE UND 0.00 8.00 1.60 0.00
INTERRUPTOR CONMUTABLE SIMPLE UND 0.00 9.00 1.60 0.00
TOMACORRIENTE DOBLE BIPOLAR UND 0.00 8.00 1.60 0.00
TOTAL VAR 0.00
TOTAL P.U. 83.41

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 2


PRECIO UNITARIO: SALIDA PARA BRAQUETES
RENDIMIENTO EN 8 HRS: 5 PTO/DIA
APORTE: 1.6000 HRS/PTO TOTAL P.U. 78.62
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 1.60 0.00
CAPATAZ H-H 0.10 20.79 1.60 3.33
OPERARIO H-H 1.00 18.08 1.60 28.93
OFICIAL H-H 0.00 14.81 1.60 0.00
PEON H-H 1.00 13.62 1.60 21.79
TOTAL MO 54.05
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 54.05 5.40
CABLE TW N 14 AWG 2.5 MM2 M 8.50 0.988 8.40
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 2.50 2.50 6.25
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 1.00 2.50 2.50
INTERRUPTOR 250V -15 A PZA 0.00 7.50 0.00
TUBO PVC 5/8" PZA 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" UND 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" UND 0.00 0.18 0.00
TUBO PVC 3/4" UND 1.50 1.35 2.03
CURVA PESADA 3/4" UND 0.00 1.37 0.00
CURVA LIVIANA 3/4" UND 0.00 0.46 0.00
UNION UNIVERSAL 3/4" UND 0.00 4.24 0.00
TOTAL MAT 24.58
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.60 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.60 0.00
GRASA KG 0.00 9.39 1.60 0.00
GASOLINA GLN 0.00 11.00 1.60 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.60 0.00
1.60 0.00
1.60 0.00
TOTAL VAR 0.00
TOTAL P.U. 78.62

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 3


PRECIO UNITARIO: SALIDA DE INTERRUPTOR SIMPLE
RENDIMIENTO EN 8 HRS: 15 M3/DIA
APORTE: 0.5333 TOTAL P.U. 36.59
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 0.53 0.00
CAPATAZ H-H 0.10 20.79 0.53 1.11
OPERARIO H-H 1.00 18.08 0.53 9.64
OFICIAL H-H 0.00 14.81 0.53 0.00
PEON H-H 0.00 13.62 0.53 0.00
TOTAL MO 10.75
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 10.75 1.08
CABLE TW N 14 AWG 2.5 MM2 M 10.00 0.988 9.88
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 1.00 2.50 2.50
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 1.00 2.50 2.50
INTERRUPTOR 250V -15 A PZA 1.00 7.50 7.50
TUBO PVC 5/8" PZA 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" UND 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" UND 2.00 0.18 0.36
TUBO PVC 3/4" UND 1.50 1.35 2.03
CURVA PESADA 3/4" UND 0.00 1.37 0.00
CURVA LIVIANA 3/4" UND 0.00 0.46 0.00
UNION UNIVERSAL 3/4" UND 0.00 4.24 0.00
TOTAL MAT 25.84
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 0.53 0.00
ACEITE Y FILTROS GLN 0.00 80.00 0.53 0.00
GRASA KG 0.00 9.39 0.53 0.00
GASOLINA GLN 0.00 11.00 0.53 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 0.53 0.00
H-M 0.53 0.00
H-M 0.53 0.00
H-M 0.53 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
0.53 0.00
0.53 0.00
0.53 0.00
TOTAL VAR 0.00
TOTAL P.U. 36.59

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 4


PRECIO UNITARIO: SALIDA DE INTERRUPTOR DOBLE
RENDIMIENTO EN 8 HRS: 5 PTO/DIA
APORTE: 1.6000 HRS/PTO TOTAL P.U. 91.65
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 1.60 0.00
CAPATAZ H-H 0.10 20.79 1.60 3.33
OPERARIO H-H 1.00 18.08 1.60 28.93
OFICIAL H-H 0.00 14.81 1.60 0.00
PEON H-H 1.00 13.62 1.60 21.79
TOTAL MO 54.05
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 54.05 5.40
CABLE TW N 14 AWG 2.5 MM2 M 9.00 0.988 8.89
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 1.00 2.50 2.50
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 0.00 2.50 0.00
INTERRUPTOR 250V -15 A PZA 0.00 7.50 0.00
TUBO PVC 5/8" PZA 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" UND 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" UND 2.00 0.18 0.36
TUBO PVC 3/4" UND 1.50 1.35 2.03
CURVA PESADA 3/4" UND 0.00 1.37 0.00
CURVA LIVIANA 3/4" UND 3.00 0.46 1.38
UNION UNIVERSAL 3/4" UND 1.00 4.24 4.24
TOTAL MAT 24.80
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.60 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.60 0.00
GRASA KG 0.00 9.39 1.60 0.00
GASOLINA GLN 0.00 11.00 1.60 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
INTERRUPTO DOBLE UND 1.00 8.00 1.6000 12.80
1.60 0.00
1.60 0.00
TOTAL VAR 12.80
TOTAL P.U. 91.65

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 5


PRECIO UNITARIO: SALIDA DE INTERRUPTOR DE CONMUTACION
RENDIMIENTO EN 8 HRS: 5 PTO/DIA
APORTE: 1.6000 HRS/PTO TOTAL P.U. 90.54
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 1.60 0.00
CAPATAZ H-H 0.10 20.79 1.60 3.33
OPERARIO H-H 1.00 18.08 1.60 28.93
OFICIAL H-H 0.00 14.81 1.60 0.00
PEON H-H 1.00 13.62 1.60 21.79
TOTAL MO 54.05
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 54.05 5.40
CABLE TW #12 AWG - 4 mm2 M 9.00 1.454 13.09
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 2.00 2.50 5.00
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 2.00 2.50 5.00
INTERRUPTOR 250V -15 A PZA 0.00 7.50 0.00
TUBO PVC 5/8" PZA 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" UND 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" UND 2.00 0.18 0.36
TUBO PVC 3/4" UND 1.50 1.35 2.03
CURVA PESADA 3/4" UND 0.00 1.37 0.00
CURVA LIVIANA 3/4" UND 3.00 0.46 1.38
UNION UNIVERSAL 3/4" UND 1.00 4.24 4.24
TOTAL MAT 36.50
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.60 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.60 0.00
GRASA KG 0.00 9.39 1.60 0.00
GASOLINA GLN 0.00 11.00 1.60 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
1.60 0.00
1.60 0.00
1.60 0.00
TOTAL VAR 0.00
TOTAL P.U. 90.54

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 6


PRECIO UNITARIO: SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE CON LINEA A TIERRA
RENDIMIENTO EN 8 HRS: 5 PTO/DIA
APORTE: 1.6000 HRS/PTO TOTAL P.U. 100.86
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 1.60 0.00
CAPATAZ H-H 0.10 20.79 1.60 3.33
OPERARIO H-H 1.00 18.08 1.60 28.93
OFICIAL H-H 0.00 14.81 1.60 0.00
PEON H-H 1.00 13.62 1.60 21.79
TOTAL MO 54.05
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 54.05 5.40
CABLE TW #12 AWG - 4 mm2 M 16.00 1.454 23.26
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 1.00 2.50 2.50
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 0.00 2.50 0.00
INTERRUPTOR 250V -15 A PZA 0.00 7.50 0.00
TUBO PVC 5/8" PZA 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" UND 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" UND 2.00 0.18 0.36
TUBO PVC 3/4" UND 1.50 1.35 2.03
CURVA PESADA 3/4" UND 0.00 1.37 0.00
CURVA LIVIANA 3/4" UND 1.00 0.46 0.46
UNION UNIVERSAL 3/4" UND 0.00 4.24 0.00
TOTAL MAT 34.01
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 1.60 0.00
ACEITE Y FILTROS GLN 0.00 80.00 1.60 0.00
GRASA KG 0.00 9.39 1.60 0.00
GASOLINA GLN 0.00 11.00 1.60 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
H-M 1.60 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TOMACORRIENTE DOBLE BIPOLAR UND 1.00 8.00 1.60 12.80
1.60 0.00
1.60 0.00
TOTAL VAR 12.80
TOTAL P.U. 100.86

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 7


PRECIO UNITARIO: SALIDA DE TIMBRE
RENDIMIENTO EN 8 HRS: 2 PTO/DIA
APORTE: 4.0000 HRS/PTO TOTAL P.U. 220.15
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 4.00 0.00
CAPATAZ H-H 0.10 20.79 4.00 8.32
OPERARIO H-H 1.00 18.08 4.00 72.32
OFICIAL H-H 0.00 14.81 4.00 0.00
PEON H-H 1.00 13.62 4.00 54.48
TOTAL MO 135.12
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 135.12 13.51
CABLE TW #14 AWG - 2.5 mm² M 16 3.64 58.16
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 1.00 2.50 2.50
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 0.00 2.50 0.00
INTERRUPTOR 250V -15 A PZA 1.00 7.50 7.50
TUBO PVC 5/8" PZA 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" UND 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" UND 1.00 0.18 0.18
TUBO PVC 3/4" UND 1.00 1.35 1.35
CURVA PESADA 3/4" UND 1.00 1.37 1.37
CURVA LIVIANA 3/4" UND 1.00 0.46 0.46
UNION UNIVERSAL 3/4" UND 0.00 4.24 0.00
TOTAL MAT 85.03
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 4.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 4.00 0.00
GRASA KG 0.00 9.39 4.00 0.00
GASOLINA GLN 0.00 11.00 4.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 4.00 0.00
H-M 4.00 0.00
H-M 4.00 0.00
H-M 4.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
4.00 0.00
4.00 0.00
4.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 220.15

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 8


PRECIO UNITARIO: TABLERO DE DISTRIBUCION
RENDIMIENTO EN 8 HRS: 2 UND/DIA
APORTE: 4.0000 HRS/UND TOTAL P.U. 103.19
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 4.00 0.00
CAPATAZ H-H 0.10 20.79 4.00 8.32
OPERARIO H-H 1.00 18.08 4.00 72.32
OFICIAL H-H 0.00 14.81 4.00 0.00
PEON H-H 0.00 13.62 4.00 0.00
TOTAL MO 80.64
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 80.64 8.06
CABLE TW #14 AWG - 2.5 mm² M 0.00 3.64 0.00
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 1.00 2.50 2.50
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 1.00 2.50 2.50
INTERRUPTOR 250V -15 A PZA 1.00 7.50 7.50
TUBO PVC 5/8" PZA 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" UND 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" UND 1.00 0.18 0.18
TUBO PVC 3/4" UND 1.00 1.35 1.35
CURVA PESADA 3/4" UND 0.00 1.37 0.00
CURVA LIVIANA 3/4" UND 1.00 0.46 0.46
UNION UNIVERSAL 3/4" UND 0.00 4.24 0.00
TOTAL MAT 22.55
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 4.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 4.00 0.00
GRASA KG 0.00 9.39 4.00 0.00
GASOLINA GLN 0.00 11.00 4.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 4.00 0.00
H-M 4.00 0.00
H-M 4.00 0.00
H-M 4.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
4.00 0.00
4.00 0.00
4.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 103.19

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 9


PRECIO UNITARIO: POZO DE CONEXION A TIERRA
RENDIMIENTO EN 8 HRS: 1 PTO/DIA
APORTE: 8.0000 HRS/PTO TOTAL P.U. 476.66
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 8.00 0.00
CAPATAZ H-H 0.10 20.79 8.00 16.63
OPERARIO H-H 1.00 18.08 8.00 144.64
OFICIAL H-H 0.00 14.81 8.00 0.00
PEON H-H 2.00 13.62 8.00 217.92
TOTAL MO 379.19
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 379.19 37.92
CABLE TW #14 AWG - 2.5 mm² M 14.00 3.64 50.89
CAJA RECTANGULAR GALV. 4" x 2 1/8" UND 1.00 2.50 2.50
CAJA ORTOGONAL GALV 4" x 2 1/8" UND 1.00 2.50 2.50
INTERRUPTOR 250V -15 A PZA 0.00 7.50 0.00
TUBO PVC 5/8" PZA 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" UND 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" UND 0.00 0.18 0.00
TUBO PVC 3/4" UND 0.00 1.35 0.00
CURVA PESADA 3/4" UND 2.00 1.37 2.74
CURVA LIVIANA 3/4" UND 2.00 0.46 0.92
UNION UNIVERSAL 3/4" UND 0.00 4.24 0.00
TOTAL MAT 97.47
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 8.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 8.00 0.00
GRASA KG 0.00 9.39 8.00 0.00
GASOLINA GLN 0.00 11.00 8.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
H-M 8.00 0.00
H-M 8.00 0.00
H-M 8.00 0.00
H-M 8.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
8.00 0.00
8.00 0.00
8.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 476.66

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

PROYECTO: EXAMEN FINAL 10


PRECIO UNITARIO: MURETE PARA CONEXIÓN DOMICILIARIA
RENDIMIENTO EN 8 HRS: 1 UND/DIA
APORTE: 8.0000 HRS/UND TOTAL P.U. 297.26
MANO DE OBRA UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
ESPECIALISTA H-H 0.00 23.91 8.00 0.00
CAPATAZ H-H 0.10 20.79 8.00 16.63
OPERARIO H-H 1.00 18.08 8.00 144.64
OFICIAL H-H 0.00 14.81 8.00 0.00
PEON H-H 1.00 13.62 8.00 108.96
TOTAL MO 270.23
MATERIALES UNIDAD CANTIDAD COSTO SUBTOTAL
SEG. Y HERR.MAN. %MO 10 0.10 270.23 27.02
CABLE TW N 14 AWG 2.5 MM2 M2 0.00 0.988 0.00
CAJA RECTANGULAR GALV. 4" x 2 1/8" KG 0.00 2.50 0.00
CAJA ORTOGONAL GALV 4" x 2 1/8" P2 0.00 2.50 0.00
INTERRUPTOR 250V -15 A M3 0.00 7.50 0.00
TUBO PVC 5/8" M3 0.00 0.40 0.00
CURVA LIVIANA PVC 5/8" M3 0.00 0.70 0.00
CONEXIÓN A CAJA PVC 5/8" M3 0.00 0.18 0.00
TUBO PVC 3/4" M3 0.00 1.35 0.00
CURVA PESADA 3/4" M3 0.00 1.37 0.00
CURVA LIVIANA 3/4" M3 0.00 0.46 0.00
UNION UNIVERSAL 3/4" M3 0.00 4.24 0.00
TOTAL MAT 27.02
COMB. Y LUB. UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
PETROLEO GLN 0.00 5.00 8.00 0.00
ACEITE Y FILTROS GLN 0.00 80.00 8.00 0.00
GRASA KG 0.00 9.39 8.00 0.00
GASOLINA GLN 0.00 11.00 8.00 0.00
0.00
TOTAL COMB 0.00
EQUIPOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
TAMBOR 12 P3 H-M 0.00 18.84 8.00 0.00
H-M 8.00 0.00
H-M 8.00 0.00
H-M 8.00 0.00
TOTAL EQUIP 0.00
VARIOS UNIDAD CANTIDAD COSTO APORTE SUBTOTAL
8.00 0.00
8.00 0.00
8.00 0.00
TOTAL VAR 0.00
TOTAL P.U. 297.26

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

MANO SEGURIDAD
DE HERRAM
CAJA CAJA
UNIDAD OBRA MANUALES CABLE TW RECTANGULAR ORTOGONAL
CENTRO DE LUZ 54.05 5.40 8.40 2.50 2.50
METRADO 960 51,884.85 5,188.49 8,062.08 2,400.00 2,400.00

SALIDA PARA BRAQUETES 54.05 5.40 8.40 6.25 2.50


METRADO 480 25,942.43 2,594.24 4,031.04 3,000.00 1,200.00

SALIDA DE INTERRUPTOR
SIMPLE 10.75 1.08 9.88 2.50 2.50
METRADO 960 10,321.51 1,032.15 9,484.80 2,400.00 2,400.00

SALIDA DE INTERRUPTOR DOBLE 54.05 5.40 8.89 2.50 0.00


METRADO 480 25,942.43 2,594.24 4,268.16 1,200.00 0.00

SALIDA DE INTERRUP. CONMUT. 54.05 5.40 13.09 5.00 5.00


METRADO 192 10,376.97 1,037.70 2,512.51 960.00 960.00

SALIDA PARA TOMAC. DOBLE


C/L.TIERRA 54.05 5.40 23.26 2.50 0.00
METRADO 1440 77,827.28 7,782.73 33,500.16 3,600.00 0.00

SALIDA DE TIMBRE 135.12 13.51 58.16 2.50 0.00


METRADO 96 12,971.21 1,297.12 5,583.36 240.00 0.00

TABLERO DE DISTRIBUCION 80.64 8.06 0.00 2.50 2.50


METRADO 96 7,741.13 774.11 0.00 240.00 240.00

POZO DE CONEXION A TIERRA 379.19 37.92 50.89 2.50 2.50


METRADO 96 36,402.59 3,640.26 4,885.44 240.00 240.00

MURETE PARA CONEXIÓN DOM. 270.23 27.02 0.00 0.00 0.00


METRADO 96 25,942.43 2,594.24 0.00 0.00 0.00

TOTAL 285,352.82 28,535.28 72,327.55 14,280.00 7,440.00


PORCENTAJES 0.520 0.052 0.132 0.026 0.014

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

COMBUST
Y
INTERRUCTOR
DE 250V TUBO PVC 5/8"
CURVA LIVIANA PVC
CONEXIÓN
5/8" A CAJA PVC
TUBO PVC 3/4"CURVA PESADA 3/4"
CURVA LIVIANAUNION
3/4" UNIVERSAL 3/4" LUBRIC
7.50 0.60 2.10 0.36 0.00 0.00 0.00 0.00 0.00
7,200.00 576.00 2,016.00 345.60 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 2.03 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 972.00 0.00 0.00 0.00 0.00

7.50 0.00 0.00 0.36 2.03 0.00 0.00 0.00 0.00


7,200.00 0.00 0.00 345.60 1,944.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.36 2.03 0.00 1.38 4.24 0.00


0.00 0.00 0.00 172.80 972.00 0.00 662.40 2,035.20 0.00

0.00 0.00 0.00 0.36 2.03 0.00 1.38 4.24 0.00


0.00 0.00 0.00 69.12 388.80 0.00 264.96 814.08 0.00

0.00 0.00 0.00 0.36 2.03 0.00 0.46 0.00 0.00


0.00 0.00 0.00 518.40 2,916.00 0.00 662.40 0.00 0.00

7.50 0.00 0.00 0.18 1.35 1.37 0.46 0.00 0.00


720.00 0.00 0.00 17.28 129.60 131.52 44.16 0.00 0.00

7.50 0.00 0.00 0.18 1.35 0.00 0.46 0.00 0.00


720.00 0.00 0.00 17.28 129.60 0.00 44.16 0.00 0.00

0.00 0.00 0.00 0.00 0.00 2.74 0.92 0.00 0.00


0.00 0.00 0.00 0.00 0.00 263.04 88.32 0.00 0.00

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00


0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

15,840.00 576.00 2,016.00 1,486.08 7,452.00 394.56 1,766.40 2,849.28 0.00


0.029 0.001 0.004 0.003 0.014 0.001 0.003 0.005 0.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

EQUIPOS TOTAL GTO GENERAL GRALES


COSTO UTILIDADES PRESUPUESTO
VARIOS 1 VARIOS 2 VARIOS 3 DIRECTO 18
0.00 0.00 0.00 0.00 83.41
0.00 0.00 0.00 0.00 80,073.02

0.00 0.00 0.00 0.00 78.62


0.00 0.00 0.00 0.00 37,739.71

0.00 0.00 0.00 0.00 36.59


0.00 0.00 0.00 0.00 35,128.06

0.00 12.80 0.00 0.00 91.65


0.00 6,144.00 0.00 0.00 43,991.23

0.00 0.00 0.00 0.00 90.54


0.00 0.00 0.00 0.00 17,384.14

0.00 12.80 0.00 0.00 100.86


0.00 18,432.00 0.00 0.00 145,238.96

0.00 0.00 0.00 0.00 220.15


0.00 0.00 0.00 0.00 21,134.25

0.00 0.00 0.00 0.00 103.19


0.00 0.00 0.00 0.00 9,906.29

0.00 0.00 0.00 0.00 476.66


0.00 0.00 0.00 0.00 45,759.64

0.00 0.00 0.00 0.00 297.26


0.00 0.00 0.00 0.00 28,536.67

0.00 24,576.00 0.00 0.00 464,891.97 83,680.55 548,572.52


0.000 0.045 0.000 0.000 0.847 0.153 1.000

2011170517
Marco Miguel Montalvo Pizan COSTOS Y PRESUPUESTOS

2011170517

También podría gustarte