CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

PROYECTO: MEJORAMIENTO DEL CAMINO VECINAL LA CONGA-LA LAGUNA-EL CARDON-CARHUALLO, DISTRITO DE LA RAMADA-CUTERVO-CAJAMARCA
ENTIDAD: MUNICIPALIDAD DISTRITAL DE LA RAMADA
UBICACIÓN: LA RAMADA, CUTERVO-CAJAMARCA
FECHA: ENERO 2019

MES -01 MES -02 MES -03 MES -04 MES -05 MES -06
Parcial Total
Item Descripción Und Metrado
S/. Parcial Parcial Parcial Parcial Parcial Parcial S/.

01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 198,833.54 198,833.54


01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES, 172,310.32 172,310.32
01.01.01 OBRAS PROVISIONALES 153,962.84 153,962.84
01.01.01.01 INSTALACION DE CARTEL DE IDENTIFICACION DE OBRA 4.80X2.40M und 1.00 1,329.97 1,329.97 1,329.97
01.01.01.02 CASETA DE GUARDIANIA m2 15.00 1,176.00 1,176.00 1,176.00
01.01.01.03 CAMPAMENTO Y ALMACEN PROVISIONAL m2 400.00 22,048.00 22,048.00 22,048.00
01.01.01.04 VESTUARIO DEL PERSONAL OBRERO m2 20.00 588.40 588.40 588.40
01.01.01.05 SERVICIOS HIGIENICOS PORTATILES mes 6.00 6,000.00 6,000.00 6,000.00
01.01.01.06 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA, EQUIPOS Y HERRAMIENTAS GLB 1.00 59,131.01 59,131.01 59,131.01
01.01.01.07 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL mes 6.00 37,301.46 37,301.46 37,301.46
01.01.01.08 FLETE TERRESTRE GLB 1.00 26,388.00 26,388.00 26,388.00
01.01.02 TRABAJOS PRELIMINARES 18,347.48 18,347.48
01.01.02.01 DESBROCE Y LIMPIEZA EL TERRENO HA 1.17 6,616.78 6,616.78 6,616.78
01.01.02.02 TRAZOS, NIVELES Y REPLANTEO KM 9.22 11,730.70 11,730.70 11,730.70
01.02 SEGURIDAD Y SALUD 26,523.22 26,523.22
01.02.01 ELABORACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO-PSST GLB 1.00 1,600.00 1,600.00 1,600.00
01.02.02 EQUIPOS DE PROTECCION INDIVIDUAL GLB 1.00 12,519.60 12,519.60 12,519.60
01.02.03 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 2,120.40 2,120.40 2,120.40
01.02.04 CAPACITACION EN SEGURIDAD Y SALUD mes 6.00 8,580.00 8,580.00 8,580.00
01.02.05 RECURSOS PARA RESPUESTA ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJ GLB 1.00 1,703.22 1,703.22 1,703.22
02 MOVIMIENTO DE TIERRAS 847,280.23 847,280.23
02.01 EXCAVACION EN MATERIAL SUELTO m3 64,585.18 381,698.41 64,433.11 76,828.20 76,829.64 74,349.64 76,829.62 12,428.20 381,698.41
02.02 EXCAVACION EN ROCA SUELTA m3 8,211.42 163,982.06 76,190.54 87,791.52 163,982.06
02.03 EXCAVACION EN ROCA FIJA m3 712.85 21,471.04 21,471.04 21,471.04
02.04 PERFILADO Y COMPACTACION DE SUBRASANTE m2 41,445.00 69,627.60 36,363.16 33,264.44 69,627.60
02.05 TERRAPLEN CON MATERIAL PROPIO m3 2,695.59 17,979.59 17,979.56 0.03 17,979.59
02.06 TERRAPLEN CON MATERIAL PROPIO TRANSPORTADO m3 1,456.51 9,714.92 9,714.92 9,714.92
02.07 TERRAPLEN CON MATERIAL DE CANTERA m3 4,020.34 118,037.18 118,037.18 118,037.18
02.08 CONFORMACION Y ACOMODO DMEs m3 72,774.64 64,769.43 39,889.80 24,879.63 64,769.43
03 PAVIMENTOS 312,515.38 312,515.38
03.01 AFIRMADO GRANULAR PARA BASE m3 9,750.87 312,515.38 265,372.45 47,142.93 312,515.38
04 DRENAJE 614,151.02 614,151.02
04.01 BADENES (06 UNID) 102,971.35 102,971.35
04.01.01 OBRAS PRELIMINARES 1,525.50 1,525.50
04.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 450.00 553.50 553.50 553.50
04.01.01.02 TRAZO Y REPLANTEO DE OBRAS DE ARTE m2 450.00 972.00 972.00 972.00
04.01.02 MOVIMIENTO DE TIERRAS 22,169.03 22,169.03
04.01.02.01 EXCAVACION EN MATERIAL SUELTO m3 937.50 5,540.63 5,540.63 5,540.63
04.01.02.02 RELLENO PARA ESTRUCTURAS m3 360.00 16,628.40 12,744.39 3,884.01 16,628.40
04.01.03 CONCRETO ARMADO 79,276.82 79,276.82
04.01.03.01 CONCRETO ARMADO F'c=210 KG/CM2 m3 78.00 37,132.68 37,132.68 37,132.68
04.01.03.02 ENCOFRADO Y DESENCOFRADO-BADEN m2 26.00 1,658.54 1,167.02 491.52 1,658.54
04.01.03.03 ACERO DE REFUERZO GRADO 60 FY=4200 KG/CM2 kg 6,822.27 36,158.03 26,884.60 9,273.43 36,158.03
04.01.03.04 EMBOQUILLADO DE PIEDRA E=0.30M m2 32.18 4,327.57 4,327.57 4,327.57
04.02 ALCANTARILLAS TMC DIAM. 36" - TUBERIA DE METAL CORRUGADO (35 UNID) 499,962.60 499,962.60
04.02.01 LIMPIEZA Y DESCOLMATADO m 192.00 3,129.60 3,129.60 3,129.60
04.02.02 EXCAVACION PARA ESTRUCTURAS C/MAQUINA m3 2,355.86 9,682.58 9,682.58 9,682.58
04.02.03 RELLENO PARA ESTRUCTURAS m3 1,149.53 53,096.79 28,360.34 24,736.45 53,096.79
04.02.04 CONCRETO F'C=175 KG/CM2 m3 90.82 39,036.25 39,036.25 39,036.25
04.02.05 CONCRETO F'C=100 KG/CM2 m3 15.90 5,393.28 5,393.28 5,393.28
04.02.06 CONCRETO CICLOPEO F'C=140 KG/CM2 + 30%P.M m3 265.35 74,672.14 64,624.06 10,048.08 74,672.14
04.02.07 ACERO DE REFUERZO GRADO 60 FY=4200 KG/CM2 kg 3,665.83 19,428.90 18,282.89 1,146.01 19,428.90
04.02.08 TUBERIA CORRUGADA DE ACERO GALVANIZADO CIRCULAR, DIAM.=36" m 242.19 120,407.18 102,816.68 17,590.50 120,407.18
04.02.09 MAMPOSTERIA DE PIEDRA EMBOQUILLADA m3 169.53 70,007.41 62,160.27 7,847.14 70,007.41
04.02.10 ENCOFRADO Y DESENCOFRADO m2 1,865.61 105,108.47 79,960.78 25,147.69 105,108.47
04.03 CUNETAS (NO REVESTIDAS) 11,217.07 11,217.07
04.03.01 TRAZOS, NIVELES Y REPLANTEO EN CUNETAS NO REVESTIDAS KM 9.72 3,538.27 3,538.27 3,538.27
04.03.02 CONFORMACION DE CUNETAS (NO REVESTIDAS) m 9,720.00 7,678.80 7,678.80 7,678.80
05 TRANSPORTE 679,807.16 679,807.16
05.01 TRANSPORTE DE MATERIAL GRANULAR (ENTRE 120M Y 1000M) M3K 14,329.00 38,831.59 38,831.59 38,831.59
05.02 TRANSPORTE DE MATERIAL GRANULAR (MAS DE 1000M) M3K 45,553.00 189,044.95 63,014.72 126,030.23 189,044.95
05.03 TRANSPORTE DE MATERIAL EXCEDENTE (ENTRE 120M Y 1000M) M3K 72,774.64 155,009.98 155,009.98 155,009.98
05.04 TRANSPORTE DE MATERIAL EXCEDENTE (MAS DE 1000M) M3K 92,787.70 296,920.64 212,019.34 84,901.30 296,920.64
06 SEÑALIZACION Y SEGURIDAD VIAL 39,887.81 39,887.81
06.01 SEÑALIZACION VERTICAL PREVENTIVA und 43.00 25,424.18 25,424.18 25,424.18
06.02 SEÑAL REGLAMENTARIA und 4.00 1,833.76 1,833.76 1,833.76
06.03 SEÑAL INFORMATIVA und 13.00 9,842.69 9,842.69 9,842.69
06.04 POSTES DE KILOMETRAJE und 11.00 2,787.18 2,787.18 2,787.18
07 MITIGACION AL IMPACTO AMBIENTAL 56,174.08 56,174.08
07.01 PROGRAMA DE MEDIDAS PREVENTIVAS, MITIGADORAS Y CORRECTIVAS 27,103.05 27,103.05
07.01.01 SUB PROGRAMA DE MANEJO DE RESIDUOS SOLIDOS Y EFLUENTES 3,868.00 3,868.00
07.01.01.01 CONSTRUCCION DE MICRO-RELLENO día 1.00 1,856.80 1,856.80 1,856.80
07.01.01.02 DISPOSICION FINAL DE LOS RESIDUOS GLB 1.00 2,011.20 2,011.20 2,011.20
07.01.02 SUB PROGRAMA DE SEÑALIZACION Y SEGURIDAD 2,299.98 2,299.98
07.01.02.01 SUB PROGRAMA DE SEÑALIZACION Y SEGURIDAD mes 6.00 2,299.98 2,299.98 2,299.98
07.01.03 SUB PROGRAMA DE MANEJO DE CANTERAS 5,228.00 5,228.00
07.01.03.01 SUB PROGRAMA DE MANEJO DE CANTERAS GLB 1.00 5,228.00 5,228.00 5,228.00
07.01.04 SUB PROGRAMA DE DEPOSITOS DE MATERIAL EXCEDENTE (DMEs) 5,948.00 5,948.00
07.01.04.01 SUB PROGRAMA DE DEPOSITOS DE MATERIAL EXCEDENTE (DMEs) mes 1.00 5,948.00 5,948.00 5,948.00
07.01.05 SUB PROGRAMA DE ALMACENAMIENTO DE COMBUSTIBLES Y LUBRICANTES 3,200.00 3,200.00
07.01.05.01 SUB PROGRAMA DE ALMACENAMIENTO DE COMBUSTIBLES Y LUBRICANTES GLB 1.00 3,200.00 3,200.00 3,200.00
07.01.06 SUB PROGRAMA DE PARTICIPACION CIUDADANA 6,559.07 6,559.07
07.01.06.01 CHARLAS DE SOCIALIZACION DEL PROYECTO A POBLACION BENEFICIARIA mes 6.00 6,559.07 6,559.07 6,559.07
07.02 PROGRAMA DE BIOSEGURIDAD EN PERSONAL 4,705.00 4,705.00
07.02.01 PROGRAMA DE BIOSEGURIDAD EN PERSONAL GLB 1.00 4,705.00 4,705.00 4,705.00
07.03 PROGRAMA DE CONTINGENCIAS 3,200.00 3,200.00
07.03.01 PROGRAMA DE CONTINGENCIAS mes 5.00 3,200.00 3,200.00 3,200.00
07.04 PROGRAMA DE COMPENSACION SOCIAL 11,766.03 11,766.03
07.04.01 PROGRAMA DE COMPENSACION SOCIAL GLB 1.00 11,766.03 11,766.03 11,766.03
07.05 PROGRAMA DE ABANDONO 3,900.00 3,900.00
07.05.01 PROGRAMA DE ABANDONO mes 1.00 3,900.00 3,900.00 3,900.00
07.06 SUPERVISION Y ELABORACION DEL INFORME DE CIERRE DEL PROYECTO 5,500.00 5,500.00
07.06.01 SUPERVISION Y ELABORACION DEL INFORME DE CIERRE DEL PROYECTO GLB 1.00 5,500.00 5,500.00 5,500.00

COSTO DIRECTO 2,748,649.22 410,858.36 571,429.74 451,594.70 483,043.81 585,453.94 246,268.67 2,748,649.22

Gastos Generales 10% 10.00% 274,864.92 41,085.84 57,142.97 45,159.47 48,304.38 58,545.39 24,626.87 274,864.92

Utilidad 5% 5.00% 137,432.46 20,542.92 28,571.49 22,579.74 24,152.19 29,272.70 12,313.43 137,432.46

SUB TOTAL 3,160,946.60 472,487.11 657,144.20 519,333.91 555,500.38 673,272.03 283,208.96 3,160,946.60

I.G.V 18% 18.00% 568,970.39 85,047.68 118,285.96 93,480.10 99,990.07 121,188.97 50,977.61 568,970.39

VALOR REFERENCIAL 3,729,916.99 557,534.79 775,430.16 612,814.01 655,490.45 794,461.00 334,186.58 3,729,916.99

Supervision 4.85% 181,029.00 27,059.57 37,634.98 29,742.51 31,813.79 38,558.63 16,219.52 181,029.00

PRESUPUESTO DE OBRA 3,910,946.00 584,594.37 813,065.14 642,556.52 687,304.24 833,019.62 350,406.10 3,910,946.00
CALENDARIO DE UTILIZACION DE EQUIPO

Cantidad PLAZO DE EJECUCION


Item Descripción
Und Semana 1 Semana 2 Semana 3 Semana 4

MANO DE OBRA

1.1 CAPATAZ 1 1 1 1

1.2 OPERARIO 1 1 1 1

1.3 OFICIAL 1 1 1 1

1.4 PEON 1 1 1 1

1.5 TOPOGRAFO 1 1 1 1 1
1.6 MANO DE OBRA - T 2 2 2 2 2
1.7 MANO DE OBRA - LT 1 1 1 1 1
1.8 MANO DE OBRA-A 1 1 1 1 1
1.9 MANO DE OBRA - SEÑALIZACION 2 2 2
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y
1.10 1 1 1 1 1
SALUD EN EL TRABAJO
1.11 MANO DE OBRA - PROTECCION COLECTIVA 1 1 1
1.12 CHARLAS DE CAPACITACION EN SEGURIDAD AL PERSONAL 1 1 1 1 1
1.13 MANO DE OBRA - CAPACITACION EN SEGURIDAD 1 1 1 1 1
MATERIALES
2.1 ALAMBRE NEGRO Nro. 8 1 1 1 1 1
2.2 ALAMBRE NEGRO Nro.16 1 1 1 1
2.3 CLAVOS CON CABEZA DE 2 1/2", 3", 4" 1 1 1 1 1
2.4 CLAVOS CON CABEZA DE 3" 1 1 1 1 1
2.5 CLAVOS CON CABEZA DE 4" 1 1 1
2.6 ACERO 1 1 1
2.7 ARENA GRUESA 1 1 1
2.8 ARENA FINA 1 1 1 1
2.9 PIEDRA CHANCADA DE 1/2” Y 3/4" 1 1 1
2.10 AGUA 1 1 1 1 1
2.11 AGUA 1 1 1 1
2.12 ASFALTO LIQUIDO RC-250 1 1 1 1
2.13 MEZCLA ASFALTICA EN CALIENTE 1 1 1
2.14 TRANSPORTE DE MEZCLA ASFALTICA C/VOLQUETE 10M3 1 1 1 1
2.15 LADRILLO KK TIPO IV 24X13X09 CM 1 1 1 1
2.16 CEMENTO PORTLAND TIPO I (42.5kg) 1 1 1 1
2.17 PEGAMENTO PARA TUBERIA PVC 1 1 1 1
2.18 CAL (BOLSA X 20 kg) 1 1 1 1
2.19 CORDEL 1 1 1 1
2.20 IMPERMEABILIZANTE LIQUIDO PARA CONCRETO 1 1 1 1
2.21 EXTINTOR DE POLVO SECO 1 1 1 1
2.22 DISCO DE CORTE DE 16" 1 1
2.23 CASCO DE PROTECCION 1 1
2.24 BOTINES DE CUERO 1 1
2.25 TAPONES AUDITIVOS 1 1
2.26 GUANTES DE CUERO 1 1
2.27 RESPIRADOR CONTRA POLVO 1 1
2.28 CHALECOS REFLECTIVOS 1 1
2.29 LENTES DE PROTECCION 1 1
2.30 MATERIALES - PROTECCION COLECTIVA 1 1
2.31 MATERIALES - SEÑALIZACION SEGURIDAD 1 1
2.32 CAMILLA 1 1
2.33 BOTIQUIN CON MEDICINA 1
2.34 CILINDRO VACIO 1
2.35 TAPA DE CONCRETO C/MARCO F°F PARA BUZON ø 0.60m 1
2.36 GASOLINA 95 OCTANOS 1
2.37 HORMIGON 1
2.38 AFIRMADO 1
2.39 MADERA TORNILLO 1
2.40 MADERA TORNILLO-A 1
2.41 KEROSENE INDUSTRIAL 1
2.42 TUBO PVC-SAP - 8" (5M) 1
2.43 TUBO PVC-SAP-4" (3M) 1
2.44 TUBO PVC-SAP - 6" (5M) 1
2.45 TAPON PVC SAL P/DESAGUE 08” 1
EQUIPOS 1
3.1 HERRAMIENTA 1
3.2 HERRAMIENTA-T 1
3.3 HERRAMIENTA - LT 1
3.4 COMP. NEUMATICA - 93 HP - 335/375 PCM 1
3.5 MARTILLO NEUMATICO - 25/29 KG 1
3.6 RETROEXCAVADORA S/LLANT. 62 HP -1 YD3 1
3.7 TRACTOR DE TIRO DE 60HP 1
3.8 PLANCHA COMPACTADORA VIBRAT. 4.0 HP 1
3.9 RODILLO NEUMATICO AUTOP. 81-100HP 5.5-20T 1
3.10 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T 1
3.11 MEZCLADORA DE CONC.(TAMBOR) 11 P3,18 HP 1
3.12 VIBRADOR A GASOLINA Y 1 3/4", 4 HP 1
3.13 CORTADORA DE CONCRETO 13 HP 1
3.14 CAMION VOLQUETE 4x2, 210/280 HP, 8 M3 1
3.15 TEODOLITO Y MIRA 1
3.16 BARREDORA MECANICA 10-20HP
3.17 PAVIMENTADORA SOBRE ORUGAS 105HP 10-16'
3.18 CAMION IMPRIMADOR 6x2 178-210HP 2000 GLN
CRONOGRAMA DE ADQUISICION DE MATERIALES

Descripción P. Unit. Parcial PLAZO DE EJECUCION


Item Und Cant.
S/. S/. Semana 1 Semana 2 Semana 3 Semana 4

MANO DE OBRA

1.1 CAPATAZ H-H 85.53 20.06 1715.73

1.2 OPERARIO H-H 486.37 18.24 8871.40

1.3 OFICIAL H-H 147.67 15.28 2256.36

1.4 PEON H-H 1101.79 13.74 15138.61

1.5 TOPOGRAFO H-H 2.99 21.07 63.03

1.6 MANO DE OBRA - T GLB 1.00 70.00 70.00

1.7 MANO DE OBRA - LT GLB 1.00 315.00 315.00

1.8 MANO DE OBRA-A GLB 1.00 360.00 360.00

1.9 MANO DE OBRA - SEÑALIZACION GLB 1.00 102.95 102.95


ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE
1.10 GLB 1.00 500.00 500.00
SEGURIDAD Y SALUD EN EL TRABAJO
1.11 MANO DE OBRA - PROTECCION COLECTIVA GLB 1.00 118.15 118.15

1.12 CHARLAS DE CAPACITACION EN SEGURIDAD AL PERSONAL GLB 26.00 30.00 780.00

1.13 MANO DE OBRA - CAPACITACION EN SEGURIDAD GLB 260.00 0.30 78.00

30369.23

MATERIALES

2.1 ALAMBRE NEGRO Nro. 8 kg 9.79 2.47 24.18

2.2 ALAMBRE NEGRO Nro.16 kg 28.91 2.47 71.40

2.3 CLAVOS CON CABEZA DE 2 1/2", 3", 4" kg 2.32 2.80 6.49

2.4 CLAVOS CON CABEZA DE 3" kg 0.77 2.80 2.15

2.5 CLAVOS CON CABEZA DE 4" kg 6.55 2.80 18.35

2.6 ACERO kg 622.06 2.40 1492.94

2.7 ARENA GRUESA m3 28.10 58.60 1646.83

2.8 ARENA FINA m3 1.31 102.50 134.48

2.9 PIEDRA CHANCADA DE 1/2” Y 3/4" m3 10.47 70.64 739.74

2.10 AGUA m3 27.87 5.68 158.30

2.11 AGUA GLB 1.00 300.00 300.00

2.12 ASFALTO LIQUIDO RC-250 gal 39.46 9.51 375.29

2.13 MEZCLA ASFALTICA EN CALIENTE m3 16.03 320.00 5130.11

2.14 TRANSPORTE DE MEZCLA ASFALTICA C/VOLQUETE 10M3 m3 16.03 46.64 747.71

2.15 LADRILLO KK TIPO IV 24X13X09 CM und 50.00 0.85 42.50

2.16 CEMENTO PORTLAND TIPO I (42.5kg) bl 182.43 16.95 3092.22

2.17 PEGAMENTO PARA TUBERIA PVC gal 4.11 97.71 401.44

2.18 CAL (BOLSA X 20 kg) bl 16.81 8.43 141.69

2.19 CORDEL M 63.87 0.15 9.58

2.20 IMPERMEABILIZANTE LIQUIDO PARA CONCRETO gal 2.50 13.56 33.85

2.21 EXTINTOR DE POLVO SECO und 1.00 129.80 129.80

2.22 DISCO DE CORTE DE 16" und 0.88 550.85 487.12

2.23 CASCO DE PROTECCION und 10.00 9.24 92.40

2.24 BOTINES DE CUERO par 10.00 44.83 448.30


CRONOGRAMA DE ADQUISICION DE MATERIALES

Descripción P. Unit. Parcial PLAZO DE EJECUCION


Item Und Cant.
S/. S/. Semana 1 Semana 2 Semana 3 Semana 4

2.25 TAPONES AUDITIVOS par 10.00 2.12 21.20

2.26 GUANTES DE CUERO par 10.00 12.63 126.30

2.27 RESPIRADOR CONTRA POLVO und 10.00 2.46 24.60

2.28 CHALECOS REFLECTIVOS und 10.00 7.54 75.40

2.29 LENTES DE PROTECCION und 10.00 5.34 53.40

2.30 MATERIALES - PROTECCION COLECTIVA GLB 1.00 1181.52 1181.52

2.31 MATERIALES - SEÑALIZACION SEGURIDAD GLB 1.00 1029.48 1029.48

2.32 CAMILLA und 1.00 250.00 250.00

2.33 BOTIQUIN CON MEDICINA und 1.00 296.61 296.61

2.34 CILINDRO VACIO und 1.00 67.80 67.80

2.35 TAPA DE CONCRETO C/MARCO F°F PARA BUZON ø 0.60m und 5.00 300.00 1500.00

2.36 GASOLINA 95 OCTANOS gal 88.43 11.02 974.52

2.37 HORMIGON m3 0.02 40.14 0.80

2.38 AFIRMADO m3 53.92 33.60 1811.68

2.39 MADERA TORNILLO p2 252.66 4.40 1111.69

2.40 MADERA TORNILLO-A GLB 1.00 240.00 240.00

2.41 KEROSENE INDUSTRIAL gal 9.87 9.55 94.22

2.42 TUBO PVC-SAP - 8" (5M) M 193.20 23.19 4480.26

2.43 TUBO PVC-SAP-4" (3M) M 18.49 7.42 137.18

2.44 TUBO PVC-SAP - 6" (5M) M 17.03 15.40 262.20

2.45 TAPON PVC SAL P/DESAGUE 08” und 4.42 36.76 162.54

29628.27

EQUIPOS

3.1 HERRAMIENTA %MO 958.30

3.2 HERRAMIENTA-T GLB 1.00 280.00 280.00

3.3 HERRAMIENTA - LT GLB 1.00 35.00 35.00

3.4 COMP. NEUMATICA - 93 HP - 335/375 PCM h-m 2.71 99.81 270.11

3.5 MARTILLO NEUMATICO - 25/29 KG h-m 2.71 4.49 12.16

3.6 RETROEXCAVADORA S/LLANT. 62 HP -1 YD3 h-m 6.85 124.08 849.87

3.7 TRACTOR DE TIRO DE 60HP h-m 0.25 57.69 14.23

3.8 PLANCHA COMPACTADORA VIBRAT. 4.0 HP h-m 78.60 24.16 1898.92

3.9 RODILLO NEUMATICO AUTOP. 81-100HP 5.5-20T h-m 1.21 127.67 154.29

3.10 RODILLO TANDEM ESTATIC AUT 58-70HP 8-10T h-m 1.21 93.28 112.73

3.11 MEZCLADORA DE CONC.(TAMBOR) 11 P3,18 HP h-m 14.31 10.65 152.39

3.12 VIBRADOR A GASOLINA Y 1 3/4", 4 HP h-m 12.48 4.95 61.78

3.13 CORTADORA DE CONCRETO 13 HP h-m 60.78 10.00 607.82

3.14 CAMION VOLQUETE 4x2, 210/280 HP, 8 M3 h-m 3.87 196.77 760.75

3.15 TEODOLITO Y MIRA h-m 2.99 13.46 40.27

3.16 BARREDORA MECANICA 10-20HP h-m 0.25 46.79 11.54

3.17 PAVIMENTADORA SOBRE ORUGAS 105HP 10-16' h-m 1.21 133.17 160.94
CRONOGRAMA DE ADQUISICION DE MATERIALES

Descripción P. Unit. Parcial PLAZO DE EJECUCION


Item Und Cant.
S/. S/. Semana 1 Semana 2 Semana 3 Semana 4

3.18 CAMION IMPRIMADOR 6x2 178-210HP 2000 GLN h-m 0.25 122.29 30.16

6411.24