RESUMEN DE METRADOS TRAMO 1

Item Descripción Und. Metrado

Descripción
01 OBRAS PRELIMINARES 01
01.01 CARTEL DE IDENTIFICACION DE LA OBRA 4.80M X 2.40M u 1.00
01.02 CAMPAMENTO Y ALMACEN DE OBRA glb 1.00
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO_I glb 1.00
01.04 TRAZO Y REPLANTEO km 70.98
01.05 ROCE Y LIMPIEZA m2 241,343.61
02 MOVIMIENTO DE TIERRAS 02
02.01 CORTE PARA MEJORAMIENTO m3 144,088.58
02.02 MEJORAMIENTO DE SUELOS A NIVEL DE SUBRASANTE m3 184,920.15
02.03 ESCARIFICADO DE AFIRMADO m2 177,147.12
02.04 PERFILADO Y COMPACTADO m2 177,147.12
03 SUB BASESY BASES 03
03.02 SUB BASE GRANULAR m3 73,381.88
03.03 BASE GRANULAR m3 61,755.57
04 PAVIMENTOS 04
04.01 IMPRIMACION ASFALTICA m2 393,070.66
04.02 MEJORAMIENTO DE LA SUPERFICIE DE RODADURA C/ SOLUCION BASICA m2 393,070.66
05 TRANSPORTE 05
05.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1KM m3k 245,718.90
05.02 TRANSPORTE DE MATERIAL GRANULAR DESPUES DE 1KM m3k 6,420,538.70
05.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1KM m3k 118,622.01
05.04 TRANSPORTE DE MATERIAL EXCEDENTE DESPUES DE 1KM m3k 827,813.50
06 OBRAS DE ARTE Y DRENAJE 06
06.01 CUNETAS 06.01
06.01.01 CUNETA TRIANGULAR REVESTIDA TIPO I m 20,475.00
06.01.03 LIMPIEZA Y ENCAUZAMIENTO CUNETAS m 3,492.00
06.01.04 DEMOLICION DE CUNETAS m3 6.26
06.01.04 REPOSICION DE CUNETAS m 591.90
06.01.05 ELIMINACION DE MATERIAL EXCEDENTE m3 144.27
06.02 ALCANTARILLAS TMC -
06.02.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN m3 517.50
06.02.02 RELLENOS PARA ESTRUCTURAS m3 261.97
06.02.03 CONCRETO CLASE E (F'C=175 KG/CM2) m3 188.09
06.02.04 ENCOFRADO Y DESENCOFRADO m2 857.51
06.02.05 TUBERIA METALICA CORRUGADA CIRCULAR D=0.90 m m 173.65
06.02.09 TUBERIA METALICA CORRUGADA CIRCULAR D=0.90 m m 713.00
06.02.10 LIMPIEZA DE ALCANTARILLAS TMC EXISTENTES und 157.00
06.02.08 ELIMINACION DE MATERIAL EXCEDENTE m3 1,309.47
06.04 BADENES -
06.04.11 LIMPIEZA DE BADENES u 3.00
06.07 PONTONES 06.07
06.07.01 INSTALACION DE BARANDAS m 206.80
06.07.02 LIMPIEZA DE SUPERFICIES DE PUENTES DE CONCRETO m2 2,907.32
06.07.03 PINTADO DE ELEMENTOS DE PUENTES DE CONCRETO m2 2,907.32
06.07.04 REPARACION DE SUPERESTRUCTURAS DE CONCRETO m2 65.90
06.08 PUENTES -
06.08.01 INSTALACION DE BARANDAS m 462.00
RESUMEN DE METRADOS TRAMO 1

Item Descripción Und. Metrado

Descripción
06.08.02 LIMPIEZA DE SUPERFICIE DE PUENTES DE CONCRETO m2 3,057.30
06.08.03 PINTADO DE ELEMENTOS DE PUENTES DE CONCRETO m2 3,057.30
06.08.04 REPARACION SUPERFICIAL DE ELEMENTOS DE COCNRETO m2 78.00
06.08.05 LIMPIEZA DE SUPERFICIE DE DE PUENTES METALICOS m2 237.00
06.08.06 CONSERVACION DE LA PINTURA DE PUENTES METALICOS m2 237.00
06.08.07 LOSAS DE APROXIMACION m2 166.00
06.08.08 LIMPIEZA Y ENCAUZAMIENTO EN PUENTES Y PONTONES m3 1,308.35
06.08.09 ELIMINACION DE MATERIAL EXCEDENTE m3 1,308.35
07 SEÑALIZACION 07
07.01 MANTENIMIENTO DE SEÑALES u 31.00
07.02 RETIRO DE SEÑALES u 5.00
07.03 MARCAS EN EL PAVIMENTO m2 14,196.68
07.04 HITOS KILOMETRICOS u 70.00
07.05 POSTES DE SOPORTE DE SEÑALES DE CONCRETO u 372.00
07.06 SEÑAL PREVENTIVA 0.60m x 0.60m u 312.00
07.07 SEÑAL REGLAMENTARIA 0.90m x 0.60m u 60.00
07.08 POSTES DELINEADORES u 3,840.00
07.09 SEÑAL INFORMATIVA m2 38.99
07.10 ESTRUCTURA DE SOPORTE DE SEÑALES TIPO E-I u 14.00
07.11 ESTRUCTURA DE SOPORTE DE SEÑALES TIPO E-II u 18.00
07.12 GIBAS u 10.00
07.13 PINTADO DE PARAPETOS DE ALCANTARILLAS m2 164.84
07.14 GUARDAVIAS METALICAS m 2,403.00
08 PROTECCION AMBIENTAL 08
08.01 PROGRAMA DE SEÑALIZACION AMBIENTAL 08.01
08.01.01 SEÑALIZACION AMBIENTAL TEMPORAL u 100.00
08.01.02 SEÑALIZACION AMBIENTAL PERMANENTE m2 10.00
08.01.03 ESTRUCTURAS DE SOPORTE DE SEÑALES TIPO E-1 u 20.00
08.02 PROGRAMA DE MONITOREO AMBIENTAL 08.02
08.02.01 MONITOREO DE LA CALIDAD DEL AGUA pto 12.00
08.02.02 MONITOREO DE LA CALIDAD DEL AIRE pto 12.00
08.02.03 MONITOREO DE RUIDOS pto 12.00
08.03 PLAN DE CIERRE 08.03
08.03.01 ACONDICIONAMIENTO DE DEPOSITOS DE MATERIAL EXCEDENTE m3 150,995.00
08.03.02 READECUACION AMBIENTAL DEL DME m2 50,000.00
08.03.03 READECUACION AMBIENTAL DE CANTERAS DE RIO m2 5,000.00
08.03.04 READECUACION AMBIENTAL DE CANTERAS DE CERRO m2 5,000.00
08.03.05 REVEGETACION DE INSTALACIONES AUXILIARES, CAMPAMENTO, PLAN m2 80,000.00
RELACIÓN DE EQUIPO MÍNIMO

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

ÍTEM RELACIÓN DE EQUIPO MÍNIMO Nº EQUIPOS COSTO HH

01 Camión Plataforma 1.00 176.40


02 Camión Cisterna 4 X 2 (Agua) 2,000 Gln 1.00 133.56
03 Camión Volquete 10m3. 3.00 128.88
04 Rodillo Liso Vib. Auto Prop. 101-135 HP, 10-12 Ton. 1.00 132.48
05 Cargador S/Llantas 160 - 195 HP 3.5 YD3. 1.00 163.44
06 Tractor D6 1.00 210.24
07 Motoniveladora de 125 HP 1.00 189.72
08 Teodolito 1.00 28.50
09 Motobomba 10 HP 4" 1.00 22.65
10 Miras y Jalones 1.00 5.00
11 Zaranda Manual 1.00 5.00
JUSTIFICACIÓN DE METRADOS

01.00.00 OBRAS PRELIMINARES


01.01.00 Cartel de Identificación de la Obra 4.80M X 2.40M. Und 1.00

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"
TRAMO : Ruta N° SM-105, Emp. 5NB (P. de Caynarachi) - Barranquita - Pelejo-Papaplaya
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

DESCRIPCIÓN UNIDAD CANTIDAD


Cartel de Identificación de la Obra 4.80M X 2.40M. UND 1.00
JUSTIFICACIÓN DE METRADOS

01.00.00 OBRAS PRELIMINARES


01.02.00 Campamento y Almacen de la Obra Und 1.00

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial


OBRA
Regional Alto Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

DESCRIPCIÓN UNIDAD CANTIDAD


Campamento y Almacen de la Obra UND 1.00
MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPOS
VICTOR RAUL HAYA DE LA TORRE

A.- MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO TRANSPORTADO

Nº VIAJES
PESO (TON) PESO Cama Cama Camion Semi-
EQUIPO CANTIDAD
UND TOTAL Baja Baja Plataforma Trailer
25 Ton. 18 Ton. 19 Ton. 35 Ton.

COMPACTADORA VIBRATORIA TIPO PLANCHA 7HP 0.13 1.00 0.13 0.01


ROTO MARTILLO ELECTRICO DE 1500W 0.03 1.00 0.03 0.03
CARGADOR FRONTAL 938F-CAT 16.70 1.00 16.70 1 1
VIBRADOR DE CONCRETO 4HP 1.25" 0.02 2.00 0.04 0
VIBRADOR DE CONCRETO 4HP 2.40" 0.03 2.00 0.05 1
RETROEXCAVADORA SOBRE LLANTAS 96 HP 9.00 1.00 9.00 1
MEZCLADOR DE CONCRETO TAMBOR 18HP 11P3 0.37 2.00 0.73 1
WINCHE ELECTRICO DE DOS BALDES 350 KG TRIFASICO 0.30 2.00 0.60 1
Total de viajes 0.00 0.00 5.06 1.00
Duración del viaje IDA (HM) 1.00 1.00 1.00 1.00
FRV : Factor de Retorno al Vacío (D.S. N° 010-2006-MTC) 1.40 1.40 1.40 1.40
Costo de alquiler de Equipo (S/. / HM) 120.33 116.39
MOVILIZACIÓN DE EQUIPO TRANSPORTADO (S/.) 0.00 0.00 852.92 162.95
DESMOVILIZACIÓN DE EQUIPO TRANSPORTADO (S/.) 0.00 0.00 852.92 162.95
SEGUROS DE TRANSPORTE 0.00 0.00 85.29 16.29

MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO TRANSPORTADO (S/.) 2,133.33

(*) D.S Nº 010-2006/MTC del 26.03.06

Distancia Velocidad Tiempo


Origen / Destino
(Km.) (Km./h) (Horas)
Trujillo - Casa Grande 45.00 45.00 1
Casa Grande - Centro Poblado Roma 7.5 45.00 0
TOTAL 52.5 1

B.- MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO AUTOTRANSPORTADO

Distancia Velocidad
EQUIPO AUTOTRANSPORTADO CANTIDAD HM (S/.) HORAS PARCIAL (S/.)
(Km.) (Km./h)

CAMION VOLQUETE 15 m3 1 274.06 52.50 60.0 1 274.06


CAMION VOLQUETE 10 m3 1 140.42 52.50 60.0 1 140.42
CAMION GRUA (BRAZO ARTICULADO) 1 160.88 52.50 60.0 1 160.88
MOVILIZACIÓN DE EQUIPO AUTOTRANSPORTADO (S/.) 575.36
DESMOVILIZACIÓN DE EQUIPO AUTOTRANSPORTADO (S/.) 575.36
SEGUROS DE TRANSPORTE 57.54

MOVILIZACIÓN Y DESMOVILIZACIÓN DE EQUIPO AUTOTRANSPORTADO (S/.) 1,208.26

COSTO DE MOVILIZACION Y DESMOVILIZACION DE EQUIPO S/. 3,341.58

NOTA :
El resto de Equipos sera transportado en los Volquetes o remolcado por los mismos.
Esta relación no es limitativa, debiendo el Contratista compatibilizarla con la de su propuesta, de tal manera de poder terminar la obra en el plazo planteado
El Seguro de Transporte cubre la movilizacion y desmovilizacion de los equipos transportados.
El Equipo de Topografia sera transportado en las camionetas.
JUSTIFICACIÓN DE METRADOS

01.00.00 OBRAS PRELIMINARES


01.04.00 Trazo y Replanteo Km 70.98

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga,
OBRA
Bajo Mayo Y Bajo Huallaga – San Martin"
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

UBICACIÓN LONGITUD LONGITUD


Del Km. Al Km. ML KM
0+000 70+983 70,983.42 70.98
TOTAL 70,983.42 70.98
JUSTIFICACIÓN DE METRADOS

01.00.00 OBRAS PRELIMINARES


01.05.00 Roce y Limpieza m2 241,343.61

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y
OBRA
Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

PROGRESIVA
LARGO ANCHO AREA M2 AREA Ha
DEL Km AL Km
0+000 1+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
1+000 2+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
2+000 3+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
3+000 4+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
4+000 5+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
5+000 6+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
6+000 7+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
7+000 8+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
8+000 9+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
9+000 10+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
10+000 11+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
11+000 12+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
12+000 13+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
13+000 14+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
14+000 15+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
15+000 16+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
16+000 17+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
17+000 18+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
18+000 19+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
19+000 20+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
20+000 21+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
21+000 22+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
22+000 23+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
23+000 24+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
24+000 25+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
25+000 26+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
26+000 27+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
27+000 28+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
28+000 29+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
29+000 30+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
30+000 31+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
31+000 32+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
32+000 33+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
33+000 34+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
34+000 35+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
35+000 36+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
JUSTIFICACIÓN DE METRADOS

01.00.00 OBRAS PRELIMINARES


01.05.00 Roce y Limpieza m2 241,343.61

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y
OBRA
Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

PROGRESIVA
LARGO ANCHO AREA M2 AREA Ha
DEL Km AL Km
36+000 37+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
37+000 38+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
38+000 39+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
39+000 40+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
40+000 41+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
41+000 42+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
42+000 43+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
43+000 44+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
44+000 45+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
45+000 46+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
46+000 47+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
47+000 48+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
48+000 49+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
49+000 50+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
50+000 51+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
51+000 52+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
52+000 53+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
53+000 54+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
54+000 55+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
55+000 56+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
56+000 57+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
57+000 58+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
58+000 59+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
59+000 60+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
60+000 61+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
61+000 62+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
62+000 63+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
63+000 64+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
64+000 65+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
65+000 66+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
66+000 67+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
67+000 68+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
68+000 69+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
69+000 70+000 1,000.00 2.00 A/L x 85 % 3,400.00 0.340
70+000 70+983 983.41 2.00 A/L x 85 % 3,343.61 0.334
JUSTIFICACIÓN DE METRADOS

01.00.00 OBRAS PRELIMINARES


01.05.00 Roce y Limpieza m2 241,343.61

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y
OBRA
Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

PROGRESIVA
LARGO ANCHO AREA M2 AREA Ha
DEL Km AL Km
TOTAL 241,343.61 24.13
JUSTIFICACIÓN DE METRADOS

03.00.00 SUB BASES Y BASES


03.01.00 Mejoramiento con Material Granular m3 14,000.00

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional


OBRA
Alto Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

TRAMO LONGITUD ANCHO ESPESOR AREA VOLUMEN


DE A ML ML ML M2 M3

0+000 39+000 39000 5.60 0.10 218400.00 21840.00


39+000 53+000 14000 -5.60 0.10 -78400.00 -7840.00
53+000 0+000 -53000 0.00 0.10 0.00 0.00

TOTALES 0.00 14,000.00


JUSTIFICACIÓN DE METRADOS

02.00.00 MOVIMIENTO DE TIERRAS


02.01.00 Corte para Mejoramiento m3 144,088.58
02.02.00 Mejoramiento de Suelos a nivel de subrasante m3 184,920.15

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional


OBRA
Alto Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"

DEPARTAMEN: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

ESP. VOLUMEN VOLUMEN MATERIAL DE


LONG. ANCHO ESP. AREA
EXIST. DE CORTE MEJORAMIENTO CANTERA
TRAMO
DE A ML ML ML ML M2 M3 M4 M3

0+250 0+750 500 6.33 0.55 1.15 3,165.00 1,740.75 5,380.50 1,740.75
0+750 1+200 450 6.33 0.55 0.15 2,848.50 1,566.68 1,993.95 1,566.68
2+250 3+250 1000 6.33 0.55 0.15 6,330.00 3,481.50 4,431.00 3,481.50
4+750 5+750 1000 6.33 0.55 0.15 6,330.00 3,481.50 4,431.00 3,481.50
7+250 7+750 500 6.33 0.55 0.15 3,165.00 1,740.75 2,215.50 1,740.75
7+750 8+750 1000 6.33 0.55 0.15 6,330.00 3,481.50 4,431.00 3,481.50
9+750 10+750 1000 6.33 0.55 0.15 6,330.00 3,481.50 4,431.00 3,481.50
11+750 12+250 500 6.33 0.55 0.15 3,165.00 1,740.75 2,215.50 1,740.75
14+250 17+250 3000 6.33 0.55 0.15 18,990.00 10,444.50 13,293.00 10,444.50
18+750 19+250 500 6.33 0.55 0.15 3,165.00 1,740.75 2,215.50 1,740.75
19+750 20+750 1000 6.33 0.55 0.15 6,330.00 3,481.50 4,431.00 3,481.50
21+250 23+250 2000 6.33 0.55 0.15 12,660.00 6,963.00 8,862.00 6,963.00
24+250 25+750 1500 6.33 0.55 0.15 9,495.00 5,222.25 6,646.50 5,222.25
26+250 27+250 1000 6.33 0.55 0.15 6,330.00 3,481.50 4,431.00 3,481.50
28+250 29+250 1000 6.33 0.55 0.15 6,330.00 3,481.50 4,431.00 3,481.50
29+250 29+750 500 6.33 0.55 0.15 3,165.00 1,740.75 2,215.50 1,740.75
31+250 32+250 1000 6.33 0.55 0.15 6,330.00 3,481.50 4,431.00 3,481.50
32+750 35+750 3000 6.33 0.55 0.15 18,990.00 10,444.50 13,293.00 10,444.50
36+250 37+750 1500 6.33 0.45 0.15 9,495.00 4,272.75 5,697.00 4,272.75
38+800 39+200 400 6.33 0.45 0.15 2,532.00 1,139.40 1,519.20 1,139.40
41+250 41+750 500 6.33 0.45 0.15 3,165.00 1,424.25 1,899.00 1,424.25
43+750 44+750 1000 6.03 0.45 0.15 6,030.00 2,713.50 3,618.00 2,713.50
45+250 46+250 1000 6.48 0.45 0.15 6,480.00 2,916.00 3,888.00 2,916.00
50+750 51+250 500 6.48 0.45 0.15 3,240.00 1,458.00 1,944.00 1,458.00
53+250 60+750 7500 6.48 0.65 0.15 48,600.00 31,590.00 38,880.00 31,590.00
61+750 62+250 500 6.48 0.65 0.15 3,240.00 2,106.00 2,592.00 2,106.00
63+250 68+750 5500 6.48 0.65 0.15 35,640.00 23,166.00 28,512.00 23,166.00
70+750 71+250 500.00 6.48 0.65 0.15 3,240.00 2,106.00 2,592.00 2,106.00
TOTALES 39,350.00 251,110.50 144,088.58 184,920.15 144,088.58
JUSTIFICACIÓN DE METRADOS

02.00.00 MOVIMIENTO DE TIERRAS


02.03.00 Escarificado de Afirmado m2 177,147.12

“Contrato De Gestión Vial Por Niveles De Servicio De La Red


OBRA Vial Regional Alto Huallaga, Bajo Mayo Y Bajo Huallaga –
San Martin"

DEPARTAMENTO: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

TRAMO LONGITUD ANCHO AREA OBS.


DE A ML ML M2

0+000 70+983 70983 5.60 397,507.12


0+000 70+983 39350 -5.60 -220,360.00 Zonas de Mejoramiento

TOTALES 31,633.42 177,147.12


JUSTIFICACIÓN DE METRADOS

02.00.00 MOVIMIENTO DE TIERRAS


02.04.00 Perfilado y Compactado m2 177,147.12

“Contrato De Gestión Vial Por Niveles De Servicio De La Red


OBRA Vial Regional Alto Huallaga, Bajo Mayo Y Bajo Huallaga –
San Martin"

DEPARTAMENTO: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

TRAMO LONGITUD ANCHO AREA


DE A ML ML M2

0+000 70+983 70983 5.60 397,507.12


0+000 70+983 39350 -5.60 -220,360.00 Zonas de Mejoramiento

TOTALES 31,633.42 177,147.12


JUSTIFICACIÓN DE METRADOS

03.00.00 SUB BASES Y BASES


03.01.00 Sub Base Granular m3 73,381.88

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"

DEPARTAM : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

TRAMO LONGITUD ANCHO SUP. ANCHO INF. ESP. AREA VOLUMEN


DE A ML ML ML ML M2 M3

0+000 35+900 35,900.00 6.03 6.48 0.150 224,375.00 33,656.25


35+900 53+000 17,100.00 6.03 6.63 0.200 108,157.50 21,631.50
53+000 63+400 10,400.00 6.03 6.48 0.150 65,000.00 9,750.00
63+400 70+983 7,583.42 6.03 6.55 0.175 47,680.72 8,344.13

TOTALES 70,983.42 73,381.88


JUSTIFICACIÓN DE METRADOS

03.00.00 SUB BASES Y BASES


03.02.00 Base Granular m3 61,755.57
.

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

ANCHO ANCHO
TRAMO LONGITUD ESPESOR AREA VOLUMEN
SUP. INF.
DE A ML ML ML ML M2 M3

0+000 35+900 35900 5.58 6.03 0.15 208220.00 31233.00


35+900 53+000 17100 5.58 6.03 0.15 99180.00 14877.00
53+000 63+400 10400 5.58 6.03 0.15 60320.00 9048.00
63+400 70+983 7583 5.58 6.03 0.15 43983.81 6597.57

TOTALES 70,983.42 61,755.57


JUSTIFICACIÓN DE METRADOS
04.00.00 PAVIMENTOS
04.01.00 Imprimacion Asfaltica m2 393,070.66

Mejoramiento de Superficie de Rodadura


04.02.00 con Solucion Basica m2 393,070.66

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga,
OBRA
Bajo Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
TRAMO : 01

TRAMO LONGITUD ANCHO SUP. ANCHO INF. ESPESOR AREA


DE A ML ML ML ML M2

0+000 35+900 35,900.00 5.50 5.58 0.025 198,796.25


35+900 53+000 17,100.00 5.50 5.58 0.025 94,691.25
53+000 63+400 10,400.00 5.50 5.58 0.025 57,590.00
63+400 70+983 7,583.42 5.50 5.58 0.025 41,993.16

TOTALES 70,983.42 393,070.66


JUSTIFICACIÓN DE METRADOS
05.00.00 OBRAS DE ARTE Y DRENAJE

05.01.00 CUNETAS
05.01.01 Limpieza y Encauzamiento de Cunetas sin Revestir

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y
OBRA
Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

IZQUIERDA DERECHA
PROGRESIVA LONGITUD PROGRESIVA LONGITUD
KM KM ML KM KM ML
0+820 - 0+890 70.00 54+120 - 54+185 65.00
62+120 - 62+150 30.00

PARCIAL (I) 70.00 PARCIAL (D) 95.00

TOTAL (ML.) 165.00


JUSTIFICACIÓN DE METRADOS
05.00.00 OBRAS DE ARTE Y DRENAJE

05.01.00 CUNETAS
05.01.02 Limpieza y Encauzamiento de Cunetas Revestidas 9810.00
05.01.03 Reparacion de Cunetas 2943.00
05.01.05 Eliminación de mat. prov. de limpieza y encauzamiento de cunetas 185.00

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo
OBRA
Y Bajo Huallaga – San Martin"

DEPARTAMEN: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

VOL.
COORDENADAS INICIO COORDENADAS FIN LONGITUD PRGRESIVAS LADO LONGITUD LONGITUD
ELIMINACION
Y X Y X ML DE A ML 30% M3
-84.75146 -7.01037 -84.7507 -7.0101 90.00 0+501 0+578 D 77.00 23.10 8.00
-84.75103 -7.01020 -84.7505 -7.0100 53.00 0+547 0+604 I 57.00 17.10 5.00
-84.74270 -7.01252 -84.7425 -7.0127 30.00 1+516 1+544 D 28.00 8.40 3.00
-84.73821 -7.01298 -84.7378 -7.0128 45.00 1+978 2+024 D 46.00 13.80 3.00
-84.73336 -7.01248 -84.7327 -7.0125 70.00 2+476 2+546 I 70.00 21.00 8.00
-84.73055 -7.01317 -84.7293 -7.0127 130.00 2+770 2+898 I 128.00 38.40 5.00
-84.73076 -7.01316 -84.7302 -7.0131 60.00 2+748 2+807 D 59.00 17.70 9.00
-84.72875 -7.01256 -84.7281 -7.0123 65.00 2+959 3+030 D 71.00 21.30 7.00
-84.72844 -7.01240 -84.7281 -7.0122 40.00 2+994 3+030 I 36.00 10.80 2.00
-84.71959 -7.01124 -84.7189 -7.0111 75.00 3+997 4+066 I 69.00 20.70 2.00
-84.71666 -7.00885 -84.7167 -7.0079 108.00 4+479 4+597 D 118.00 35.40 4.00
-84.70776 -7.00173 -84.7077 -7.0016 25.00 5+753 5+769 I 16.00 4.80 2.00
-84.70780 -7.00183 -84.7077 -7.0016 22.00 5+742 5+769 D 27.00 8.10 4.00
-84.70726 -7.00108 -84.7068 -7.0009 47.00 5+837 5+881 D 44.00 13.20 2.00
-84.70715 -7.00103 -84.7069 -7.0009 33.00 5+848 5+881 I 33.00 9.90 2.00
-84.70041 -6.99318 -84.7005 -6.9929 32.00 6+927 6+960 D 33.00 9.90 2.00
-84.67772 -6.99614 -84.6774 -6.9961 37.00 9+956 9+985 D 29.00 8.70 2.00
-84.47892 -6.94040 -84.4788 -6.9400 40.00 36+105 36+143 D 38.00 11.40 7.00
-84.44107 -6.90700 -84.4407 -6.9068 45.00 41+753 41+796 D 43.00 12.90 2.00
-84.44107 -6.90700 -84.4407 -6.9068 45.00 49+710 49+812 I 102.00 30.60 2.00
-84.37622 -6.91957 -84.3759 -6.9205 105.00 50+608 50+795 I 187.00 56.10 15.00
-84.37622 -6.91957 -84.3759 -6.9205 105.00 50+615 50+803 D 188.00 56.40 10.00
-84.37000 -6.92458 -84.3689 -6.9261 185.00 53+550 53+761 D 211.00 63.30 20.00
-84.36996 -6.92464 -84.3689 -6.9262 186.00 53+587 53+827 I 240.00 72.00 10.00
-84.34640 -6.93169 -84.3455 -6.9320 80.00 53+776 54+029 D 253.00 75.90 13.00
-84.34605 -6.93180 -84.3444 -6.9323 240.00 54+000 54+325 I 325.00 97.50 13.00
-84.34423 -6.93236 -84.3440 -6.9327 45.00 54+167 55+504 D 1337.00 401.10
-84.34371 -6.93438 -84.3435 -6.9345 34.00 55+216 56+059 I 843.00 252.90
-84.34221 -6.93510 -84.3407 -6.9352 150.00 55+940 60+207 I 4267.00 1280.10
-84.33228 -6.93563 -84.3295 -6.9359 260.00 59+999 60+207 D 208.00 62.40 3.00
-84.32520 -6.93641 -84.3240 -6.9365 115.00 61+255 61+320 D 65.00 19.50 5.00
-84.28839 -6.92557 -84.2883 -6.9274 195.00 61+392 61+928 I 536.00 160.80 5.00
-84.28839 -6.92557 -84.2883 -6.9274 195.00 61+596 61+622 D 26.00 7.80 5.00
-84.27883 -6.93073 -84.2782 -6.9310 65.00 I 0.00 0.00 2.00
-84.27760 -6.93134 -84.2765 -6.9294 520.00 I 0.00 0.00
-84.27618 -6.93236 -84.2758 -6.9322 50.00 D 0.00 0.00 3.00
9810.00 2943.00 185.00
JUSTIFICACIÓN DE METRADOS
05.00.00 OBRAS DE ARTE Y DRENAJE

05.01.00 CUNETAS
05.01.04 Cunetas Triangulares tipo I 45,320.00

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y
OBRA
Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

IZQUIERDA DERECHA
PROGRESIVA LONGITUD PROGRESIVA LONGITUD
KM KM ML KM KM ML
3+600 - 3+640 40.00
2+150 - 2+220 70.00 6+760 - 6+820 60.00
5+550 - 5+585 35.00 15+120 - 15+185 65.00
55+940 - 55+975 35.00 54+120 - 54+185 65.00
63+750 - 63+795 45.00 60+875 - 60+915 40.00
62+120 - 62+150 30.00

PARCIAL (I) 185.00 PARCIAL (D) 300.00

TOTAL (ML.) 45,320.00


JUSTIFICACIÓN DE METRADOS
05.02.00 ALCANTARILLAS
05.02.01 Limpieza y Encauzamiento de Alcantarillas 114.00
05.02.02 Demolicion de Estructuras 6.54
05.02.03 Elimnacion de Mat. Proveniente de Limp. Y encauz. De alcantarillas 175.70

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y Bajo
OBRA
Huallaga – San Martin"

DEPARTAM: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA: LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01
RELACIÓN ALCANTARILLAS
DIAM. /
DESCRIPCION COORDENADAS UBICACIÓN TIPO ALTURA METRADO DEMOLICION ELIMINACION
ANCHO
(UND.) (M3) (M3)
Nº Obra de Arte X Y Progr. Km. ALC. (m) (m)

1 Alcantarilla -84.75426333 -7.00856559 0+165 TMC 0.80 1.00 2.00


2 Alcantarilla -84.75201884 -7.01019112 0+442 TMC 1.13 1.00
3 Alcantarilla -84.74762775 -7.009195537 0+901 TMC 1.18 1.00
4 Alcantarilla -84.74559002 -7.009926624 01+126 TMC 2.90 1.00 4.00
5 Alcantarilla -84.74304331 -7.012119982 01+463 TMC 2.15 1.00 4.50
6 Alcantarilla -84.73963225 -7.013205532 01+833 TMC 0.90 1.00 2.90
7 Alcantarilla -84.73723112 -7.012652233 02+081 MC 4.40 3.45 1.00
8 Alcantarilla -84.72890556 -7.012616657 02+942 TMC 2.22 1.00 6.80
9 Alcantarilla -84.72519107 -7.0112844 03+350 TMC 1.07 1.00
10 Alcantarilla -84.71557004 -7.007540018 04+717 TMC 0.75 1.00
11 Alcantarilla -84.71171334 -7.003731094 05+268 TMC 1.75 1.00
12 Alcantarilla -84.70574552 -6.998911128 06+112 TMC 1.80 1.00
13 Alcantarilla -84.70073668 -6.993594487 06+871 TMC 2.88 1.00 9.50
14 Alcantarilla -84.68530774 -6.992784422 09+071 TMC 3.20 1.00
15 Alcantarilla -84.68168443 -6.995793339 09+558 TMC 2.80 1.00 28.00
16 Alcantarilla -84.68003776 -6.996048893 09+725 TMC 1.18 1.00
17 Alcantarilla -84.66940671 -6.997284479 10+803 TMC 1.18 1.00 3.50
18 Alcantarilla -84.65739004 -6.994020008 12+095 TMC 1.20 1.00 5.00
19 Alcantarilla -84.65432227 -6.995217781 12+431 TMC 1.20 1.00 2.50
20 Alcantarilla -84.64214774 -7.000831142 13+859 TMC 1.20 1.00
21 Alcantarilla -84.63891558 -7.000836637 14+196 TMC 1.20 1.00 7.00
22 Alcantarilla -84.63577554 -7.000712212 14+541 TMC 1.20 1.00 6.50
23 Alcantarilla -84.63470554 -6.99877115 14+808 TMC 1.75 1.00
24 Alcantarilla -84.63599663 -6.995404419 15+170 TMC 1.20 1.00
25 Alcantarilla -84.63600557 -6.992929988 15+421 TMC 1.20 1.00
26 Alcantarilla -84.63563891 -6.988328881 15+899 TMC 1.20 1.00
27 Alcantarilla -84.63120777 -6.983718928 16+535 ABOVEDADA 3.00 2.40 1.00
28 Alcantarilla -84.62981442 -6.981225591 16+822 TMC 1.20 1.00
29 Alcantarilla -84.62730441 -6.97870329 17+181 TMC 1.20 1.00 6.00
30 Alcantarilla -84.6241978 -6.976813358 17+547 TMC 1.20 1.00 2.00
31 Alcantarilla -84.62134004 -6.974222231 17+945 ABOVEDADA 3.00 2.90 1.00
32 Alcantarilla -84.62006226 -6.972251088 18+179 TMC 1.20 1.00 6.54 5.00
33 Alcantarilla -84.61531 -6.969430018 18+734 TMC 1.20 1.00
34 Alcantarilla -84.6145656 -6.967685558 18+923 TMC 1.20 1.00 6.50
35 Alcantarilla -84.61223776 -6.964864489 19+291 TMC 1.20 1.00
36 Alcantarilla -84.60080111 -6.956810039 20+750 TMC 1.10 1.00
37 Alcantarilla -84.59951775 -6.955000013 20+971 TMC 1.20 1.00 7.50
38 Alcantarilla -84.59771108 -6.953038927 21+243 TMC 1.20 1.00
39 Alcantarilla -84.59659889 -6.951153371 21+471 TMC 1.20 1.00 13.00
40 Alcantarilla -84.5899011 -6.94904998 22+203 TMC 1.20 1.00
41 Alcantarilla -84.58851669 -6.948372256 22+356 TMC 1.80 1.00
42 Alcantarilla -84.5860878 -6.949201133 22+618 TMC 1.20 1.00
43 Alcantarilla -84.58079109 -6.951205526 23+191 TMC 1.20 1.00 4.50
44 Alcantarilla -84.5755389 -6.950488873 23+759 TMC 1.20 1.00 10.00
45 Alcantarilla -84.57235778 -6.951046642 24+088 TMC 1.20 1.00
46 Alcantarilla -84.56831332 -6.948550046 24+620 TMC 1.32 1.00
47 Alcantarilla -84.55916997 -6.945741083 25+866 TMC 0.80 1.00
48 Alcantarilla -84.55788447 -6.947336626 26+073 TMC 1.20 1.00
49 Alcantarilla -84.55511779 -6.949548889 26+455 TMC 1.43 1.00
50 Alcantarilla -84.55342557 -6.949575524 26+624 TMC 0.90 1.00
51 Alcantarilla -84.55092441 -6.946703326 27+050 TMC 1.20 1.00
52 Alcantarilla -84.54357004 -6.948323361 27+918 TMC 0.80 1.00 1.00
53 Alcantarilla -84.54021225 -6.947858911 28+255 TMC 0.90 1.00 2.00
54 Alcantarilla -84.53852218 -6.947912182 28+425 TMC 1.20 1.00
55 Alcantarilla -84.53633552 -6.94762338 28+647 TMC 0.90 1.00 6.00
56 Alcantarilla -84.53495447 -6.94706114 28+799 TMC 0.90 1.00
57 Alcantarilla -84.53250779 -6.944453343 29+163 TMC 0.90 1.00 5.50
58 Alcantarilla -84.52835223 -6.941667758 29+673 TMC 1.20 1.00
JUSTIFICACIÓN DE METRADOS
05.02.00 ALCANTARILLAS
05.02.01 Limpieza y Encauzamiento de Alcantarillas 114.00
05.02.02 Demolicion de Estructuras 6.54
05.02.03 Elimnacion de Mat. Proveniente de Limp. Y encauz. De alcantarillas 175.70

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y Bajo
OBRA
Huallaga – San Martin"

DEPARTAM: SAN MARTIN


REGION : SAN MARTIN
PROVINCIA: LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01
RELACIÓN ALCANTARILLAS
DIAM. /
DESCRIPCION COORDENADAS UBICACIÓN TIPO ALTURA METRADO DEMOLICION ELIMINACION
ANCHO
(UND.) (M3) (M3)
Nº Obra de Arte X Y Progr. Km. ALC. (m) (m)
59 Alcantarilla -84.52669 -6.941648852 29+840 TMC 1.20 1.00
60 Alcantarilla -84.52013554 -6.940165534 30+530 TMC 1.20 1.00 4.00
61 Alcantarilla -84.51773664 -6.934492197 31+187 TMC 1.80 1.00
62 Alcantarilla -84.51293558 -6.932916679 31+746 TMC 0.90 1.00
63 Alcantarilla -84.50639332 -6.930648908 32+499 TMC 0.90 1.00
64 Alcantarilla -84.50341225 -6.932404451 32+848 TMC 1.80 1.00
65 Alcantarilla -84.49790329 -6.936884486 33+599 TMC 0.90 1.00 6.00
66 Alcantarilla -84.48296003 -6.945326644 35+365 TMC 1.50 1.00
67 Alcantarilla -84.47985891 -6.942741107 35+853 TMC 0.90 1.00 4.00
68 Alcantarilla -84.47861224 -6.93541225 36+611 TMC 1.20 1.00
69 Alcantarilla -84.47781336 -6.934503372 36+743 TMC 0.90 1.00
70 Alcantarilla -84.47106332 -6.931254454 37+501 TMC 1.80 1.00
71 Alcantarilla -84.46946777 -6.930659991 37+671 TMC 0.90 1.00
72 Alcantarilla -84.46442112 -6.930666697 38+201 TMC 1.20 1.00
73 Alcantarilla -84.46297441 -6.929682196 38+382 TMC 0.90 1.00
74 Alcantarilla -84.45372777 -6.920106709 39+855 TMC 1.00 1.00
75 Alcantarilla -84.44408113 -6.911985577 41+161 TMC 0.90 1.00
76 Alcantarilla -84.44167115 -6.907504424 41+675 TMC 0.90 1.00
77 Alcantarilla -84.43289446 -6.905138866 42+589 TMC 1.75 1.00
78 Alcantarilla -84.42971893 -6.903598923 42+955 TMC 1.20 1.00
79 Alcantarilla -84.42544779 -6.900676712 43+494 TMC 1.20 1.00
80 Alcantarilla -84.42379776 -6.899745576 43+683 TMC 0.90 1.00
81 Alcantarilla -84.41488557 -6.899813377 44+599 TMC 0.90 1.00
82 Alcantarilla -84.41100447 -6.900705583 44+995 TMC 0.90 1.00 6.50
83 Alcantarilla -84.4060244 -6.901782192 45+516 TMC 1.80 1.00
84 Alcantarilla -84.3944422 -6.90758666 46+856 TMC 1.20 1.00
85 Alcantarilla -84.38283559 -6.906797737 48+161 TMC 0.90 1.00
86 Alcantarilla -84.37478337 -6.921935547 49+988 TMC 1.50 1.00
87 Alcantarilla -84.37040336 -6.924025528 50+540 MC 3.00 1.88 1.00
88 Alcantarilla -84.36808335 -6.927041151 50+920 TMC 1.20 1.00
89 Alcantarilla -84.36444886 -6.928771082 51+358 TMC 1.20 1.00
90 Alcantarilla -84.36271669 -6.930113304 51+595 TMC 1.20 1.00
91 Alcantarilla -84.35944775 -6.93057999 51+949 TMC 1.20 1.00
92 Alcantarilla -84.35725775 -6.931640021 52+197 TMC 1.20 1.00
93 Alcantarilla -84.35540553 -6.933149974 52+442 MC 1.10 1.10 1.00
94 Alcantarilla -84.35217552 -6.934188866 52+829 MC 2.00 2.10 1.00
95 Alcantarilla -84.32907332 -6.935940031 55+544 MC 3.00 1.80 1.00
96 Alcantarilla -84.31901112 -6.93552997 56+568 TMC 0.90 1.00
97 Alcantarilla -84.29934001 -6.928205583 58+823 MC 1.20 1.50 1.00
98 Alcantarilla -84.2971433 -6.928368844 59+044 MC 0.94 0.94 1.00
99 Alcantarilla -84.29626664 -6.927968934 59+140 MC 1.50 1.50 1.00
100 Alcantarilla -84.29114558 -6.926346663 59+679 MC 0.94 0.95 1.00
101 Alcantarilla -84.26114107 -6.928226631 63+605 MC 1.30 1.30 1.00
102 Alcantarilla -84.25920997 -6.925556622 63+938 MC 1.12 1.12 1.00
103 Alcantarilla -84.25571891 -6.923142262 64+361 MC 1.30 1.30 1.00
104 Alcantarilla -84.25066555 -6.919626706 64+973 MC 3.00 1.80 1.00
105 Alcantarilla -84.24868891 -6.918256637 65+213 MC 1.30 1.30 1.00
106 Alcantarilla -84.24416892 -6.91796001 65+672 MC 1.30 1.30 1.00
107 Alcantarilla -84.23591107 -6.918954477 66+510 MC 3.00 1.70 1.00
108 Alcantarilla -84.23092663 -6.916784402 67+059 MC 3.00 1.90 1.00
109 Alcantarilla -84.22646774 -6.914725527 67+598 MC 3.00 1.90 1.00
110 Alcantarilla -84.22621777 -6.911675539 67+919 MC 1.50 1.50 1.00
111 Alcantarilla -84.22623891 -6.90898113 68+214 MC 1.10 1.10 1.00 4.00
112 Alcantarilla -84.21376776 -6.901021116 68+843 MC 0.90 0.90 1.00
113 Alcantarilla -84.20389555 -6.903933361 70+876 MC 0.90 0.90 1.00
114 Alcantarilla -84.20301443 -6.904453319 70+920 MC 1.20 1.20 1.00
114.00 6.54 175.70
JUSTIFICACIÓN DE METRADOS
05.02.00 ALCANTARILLAS
05.02.04 Alcantarilla TMC Ø=48" C=12 7.20
05.02.05 Cabezal Alero Concreto (TMC 48" Y MC DE 1.20x1.20) 1.00

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo
OBRA
Mayo Y Bajo Huallaga – San Martin"

DEPARTAM : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01
RELACIÓN ALCANTARILLAS
DESCRIPCION UBICACIÓN COORDENADAS TIPO DIMENSIÓN LONGITUD CANTIDAD
LONGITUD
Nº Obra de Arte Y X ALC. (Pulg) (Ml.) (UND.)

1 Alcantarilla -84.6817 -6.9958 TMC 48 11.00 7.20 1.00

7.20 1.00
JUSTIFICACIÓN DE METRADOS
05.03.00 BADENES
05.03.01 Limpieza de Badenes 3.00

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo
OBRA
Y Bajo Huallaga – San Martin"

DEPARTAME : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01
RELACIÓN BADENES
DESCRIPCION UBICACIÓN COORDENADAS Prog. TIPO METRADO
LONGITUD ANCHO
Nº Obra de Arte Y X Km Bad. (UND.)

1 Badén -84.6673 -6.9974 11+015 Conc. 6.40 8.00 1.00


2 Badén -84.4796 -6.9423 35+903 Conc. 6.00 5.20 1.00
3 Badén -84.3865 -6.9051 47+736 Conc. 8 7.00 1.00
3.00
JUSTIFICACIÓN DE METRADOS
05.04.00 PONTONES
05.04.01 Limpieza y Encauzamiento de Pontones
05.04.02 Eliminacion de Mat. Prov. De Limpieza y Encauzamiento de Pontones

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y Bajo Huallaga –
OBRA
San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN PONTONES
DESCRIPCION UBICACIÓN COORDENADAS PROG. LUZ ANCHO ALTURA CANTIDAD
Nº Obra de Arte Y X (Km) (ML) (ML) (ML) (UND.)

1 Ponton -84.6927 -6.9888 8+161 6.15 1.00


2 Ponton -84.6616 -6.9953 11+629 6.00 1.00
3 Ponton -84.6042 -6.9595 20+302 4.80 1.00
4 Ponton -84.5846 -6.9499 22+782 4.00 1.00
5 Ponton -84.5767 -6.9501 23+631 4.00 1.00
6 Ponton -84.5675 -6.9462 24+882 4.40 1.00
7 Ponton -84.5467 -6.9458 27+488 6.00 1.00
8 Ponton -84.5189 -6.9371 30+883 6.00 1.00
9 Ponton -84.4872 -6.9418 34+810 6.00 1.00
10 Ponton -84.4503 -6.9167 40+338 6.00 1.00
11 Ponton -84.4199 -6.8989 44+087 9.50 1.00
12 Ponton -84.4007 -6.9057 46+174 5.00 1.00
13 Ponton -84.3605 -6.9299 51+821 6.40 1.00
14 Ponton -84.3144 -6.9317 57+178 3.00 1.00
15 Ponton -84.3022 -6.9280 58+541 6.50 1.00
16 Ponton -84.2396 -6.9190 66+145 6.80 1.00
17 Ponton -84.2338 -6.9181 66+741 5.00 1.00
18 Ponton -84.2282 -6.9163 67+335 4.00 1.00
18.00
18.00
34.00

ELIMININACIO
N (UND.)

6.00

5.00

5.00

10.00

8.00
34.00
JUSTIFICACIÓN DE METRADOS
03.04.00 PONTONES
03.04.03 Madera Rolliza

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo
OBRA
Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN PONTONES
DESCRIPCION UBICACIÓN LUZ ANCHO ALTURA METRADO
Nº Obra de Arte Progr. Km. (ML) (ML) (ML) (ML.)

1 Ponton 08+430 8.00 5.00 - 20.00


2 Ponton 13+330 4.00 4.00 - 12.00
3 Ponton 15+200 4.00 5.00 - 20.00
4 Ponton 15+960 4.00 6.00 - 24.00
5 Ponton 16+630 4.00 6.00 - 24.00
6 Ponton 17+320 4.00 5.00 - 20.00
7 Ponton 18+320 5.00 6.00 - 24.00
8 Ponton 18+690 5.00 6.00 - 24.00
9 Ponton 19+560 4.00 6.00 - 24.00
10 Ponton 20+330 4.00 6.00 - 24.00
11 Ponton 20+550 8.00 6.00 - 24.00
12 Ponton 23+800 4.00 4.00 - 12.00
13 Ponton 31+950 6.00 6.00 - 24.00

276.00
JUSTIFICACIÓN DE METRADOS
05.05.00 PUENTES
05.05.01 Limpieza y Encauzamiento de Puentes 4.00
05.05.03 Eliminacion de Mat. Prov. De Limpieza y Encauzamiento de Puentes 632.55

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y Bajo
OBRA
Huallaga – San Martin"

DEPARTA : SAN MARTIN


REGION : SAN MARTIN
PROVINCI : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN PONTONES
DESCRIPCION UBICACIÓN COORDENADAS PROG. LUZ ANCHO ALTURA CANTIDAD ELIMININACIO
Nº Obra de Arte Y X (Km) (ML) (ML) (ML) (UND.) N (UND.)

1 Puente -84.5943 -6.9502 21+739 30.35 1.00 91.05


2 Puente -84.4406 -6.9069 41+798 130.00 1.00 390.00
3 Puente -84.2644 -6.9302 63+197 5.50 1.00 16.50
4 Puente -84.2208 -6.9040 69+009 45.00 1.00 135.00
4.00 632.55
JUSTIFICACIÓN DE METRADOS
05.05.00 PUENTES
05.05.02 Repintado de Barandas

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo
OBRA
Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN PUENTES
DESCRIPCION UBICACIÓN LUZ ALTURA METRADO
FACTOR X ML
Nº Obra de Arte Progr. Km. (ML) (ML) (M2.)

1 Puente 63+500 16.00 - 1.40 44.80


2 Puente 69+900 45.00 - 1.40 126.00

170.80
JUSTIFICACIÓN DE METRADOS
03.06.00 ENCAUZAMIENTO DE CURSOS DE AGUA
03.06.01 Encauzamiento de cursos de agua.

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo
OBRA
Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

DESCRIPCIÓN UNIDAD CANTIDAD


Encauzamiento de cursos de agua. M3 0
JUSTIFICACIÓN DE METRADOS
03.07.00 DEMOLICION DE ESTRUCTURAS DE CONCRETO
03.07.02 Demolición de Badenes de Concreto

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y
OBRA
Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01
RELACIÓN BADENES
DESCRIPCION UBICACIÓN TIPO ESPESOR METRADO
LONGITUD ANCHO
Nº Obra de Arte Progr. Km. Bad. PROM. (M3.)

1 Badén 09+742 Conc. 4 0.00 0.30 0.00


2 Badén 01+112 Conc. 8 0.00 0.30 0.00
3 Badén 01+866 Conc. 8 0.00 0.30 0.00
4 Badén 10+100 Conc. 7 0.00 0.30 0.00
5 Badén 12+967 Conc. 8 0.00 0.30 0.00
6 Badén 25+505 Conc. 8 0.00 0.30 0.00
7 Badén 30+029 Conc. 8 0.00 0.30 0.00
8 Badén 31+165 Conc. 8 0.00 0.30 0.00
9 Badén 01+074 Conc. 10 0.00 0.30 0.00
10 Badén 01+470 Conc. 9 0.00 0.30 0.00
11 Badén 02+582 Conc. 10 0.00 0.30 0.00
12 Badén 03+656 Conc. 10 0.00 0.30 0.00
13 Badén 05+088 Conc. 10 0.00 0.30 0.00
14 Badén 06+162 Conc. 10 0.00 0.30 0.00
15 Badén 07+236 Conc. 10 0.00 0.30 0.00
16 Badén 05+446 Conc. 12 0.00 0.30 0.00
0.00
JUSTIFICACIÓN DE METRADOS
03.08.00 OBRAS DE CONCRETO
03.08.01 Concreto Fc'=175 Kg/cm2

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo
OBRA
Mayo Y Bajo Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN PUENTES Y PONTONES


DESCRIPCION UBICACIÓN LUZ ANCHO ALTURA METRADO
Nº Obra de Arte Progr. Km. (ML) (ML) (ML) (UND.)

1 Ponton 08+430 8.00 5.30 3.00 1.00


2 Ponton 09+980 4.00 6.30 3.00 1.00
3 Ponton 11+340 5.00 5.20 4.00 1.00
4 Puente 12+980 50.00 6.30 8.00 1.00
5 Ponton 15+740 6.00 5.30 3.00 1.00
6 Puente 20+850 54.00 6.70 8.00 1.00

6.00
JUSTIFICACIÓN DE METRADOS

06.00.00 SEÑALIZACION
06.01.01 Mantenimiento de Señales
06.01.02 Marcas en el pavimento
06.01.03 Reparación / repos. de postes kilométricos
06.01.04 Señal preventiva 0.75m x 0.75m
06.01.05 Señal Reglamentaria
06.01.06 Señal informativa 0.75m x 0.60m

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN DE SEÑALES DE TRANSITO


UBICACIÓN DESCRIPCION
LADO METRADO (UND)
Nº Progr. Km. Tipo

1 00+122 INFORMATIVA I 1.00


2 04+800 PREVENTIVAS D 1.00
3 05+180 PREVENTIVAS D 1.00
4 10+930 INFORMATIVA D 1.00
5 11+040 PREVENTIVAS D 1.00
6 11+180 PREVENTIVAS I 1.00
7 11+230 PREVENTIVAS D 1.00
8 11+580 PREVENTIVAS I 1.00
9 14+960 PREVENTIVAS I 1.00
10 20+700 PREVENTIVAS D 1.00
11 20+950 PREVENTIVAS I 1.00
12 27+990 INFORMATIVA D 1.00
13 41+120 INFORMATIVA D 1.00
14 42+200 INFORMATIVA D 1.00
15 42+300 INFORMATIVA I 1.00
16 42+400 REGLAMENTARIA I 1.00
17 42+900 INFORMATIVA I 1.00
18 42+990 REGLAMENTARIA I 1.00
19 48+070 PREVENTIVAS D 1.00
20 52+470 PREVENTIVAS D 1.00
21 53+250 PREVENTIVAS D 1.00
22 53+500 PREVENTIVAS I 1.00
23 60+500 PREVENTIVAS D 1.00
24 60+750 PREVENTIVAS I 1.00
25 61+950 PREVENTIVAS D 1.00
26 62+000 PREVENTIVAS I 1.00
27 62+950 INFORMATIVA D 1.00
28 63+200 INFORMATIVA D 1.00
JUSTIFICACIÓN DE METRADOS

06.00.00 SEÑALIZACION
29 68+900 INFORMATIVA I 1.00
30 69+800 INFORMATIVA D 1.00
30.00
JUSTIFICACIÓN DE METRADOS

06.00.00 SEÑALIZACION
06.02.00 Marcas en el Pavimento

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

MARCAS EN EL PAVIMENTO
TRAMO LONGITUD SUPERFICIE METRADO
KM KM ML M2/KM M2
0+000 1+000 1000.00 0.2913 291.30
1+000 2+000 1000.00 0.2913 291.30
2+000 3+000 1000.00 0.2913 291.30
3+000 4+000 1000.00 0.2913 291.30
4+000 5+000 1000.00 0.2913 291.30
5+000 6+000 1000.00 0.2913 291.30
6+000 7+000 1000.00 0.2913 291.30
7+000 8+000 1000.00 0.2913 291.30
8+000 9+000 1000.00 0.2913 291.30
9+000 10+000 1000.00 0.2913 291.30
10+000 11+000 1000.00 0.2913 291.30
11+000 12+000 1000.00 0.2913 291.30
12+000 13+000 1000.00 0.2913 291.30
13+000 14+000 1000.00 0.2913 291.30
14+000 15+000 1000.00 0.2913 291.30
15+000 16+000 1000.00 0.2913 291.30
16+000 17+000 1000.00 0.2913 291.30
17+000 18+000 1000.00 0.2913 291.30
18+000 19+000 1000.00 0.2913 291.30
19+000 20+000 1000.00 0.2913 291.30
20+000 21+000 1000.00 0.2913 291.30
21+000 22+000 1000.00 0.2913 291.30
22+000 23+000 1000.00 0.2913 291.30
23+000 24+000 1000.00 0.2913 291.30
24+000 25+000 1000.00 0.2913 291.30
25+000 26+000 1000.00 0.2913 291.30
26+000 27+000 1000.00 0.2913 291.30
27+000 28+000 1000.00 0.2913 291.30
28+000 29+000 1000.00 0.2913 291.30
29+000 30+000 1000.00 0.2913 291.30
30+000 31+000 1000.00 0.2913 291.30
31+000 32+000 1000.00 0.2913 291.30
32+000 33+000 1000.00 0.2913 291.30
33+000 34+000 1000.00 0.2913 291.30
JUSTIFICACIÓN DE METRADOS

06.00.00 SEÑALIZACION
34+000 35+000 1000.00 0.2913 291.30
35+000 36+000 1000.00 0.2913 291.30
36+000 37+000 1000.00 0.2913 291.30
37+000 38+000 1000.00 0.2913 291.30
38+000 39+000 1000.00 0.2913 291.30
39+000 40+000 1000.00 0.2913 291.30
40+000 41+000 1000.00 0.2913 291.30
41+000 42+000 1000.00 0.2913 291.30
42+000 43+000 1000.00 0.2913 291.30
43+000 44+000 1000.00 0.2913 291.30
44+000 45+000 1000.00 0.2913 291.30
45+000 46+000 1000.00 0.2913 291.30
46+000 47+000 1000.00 0.2913 291.30
47+000 48+000 1000.00 0.2913 291.30
48+000 49+000 1000.00 0.2913 291.30
49+000 50+000 1000.00 0.2913 291.30
50+000 51+000 1000.00 0.2913 291.30
51+000 52+000 1000.00 0.2913 291.30
52+000 53+000 1000.00 0.2913 291.30
53+000 54+000 1000.00 0.2913 291.30
54+000 55+000 1000.00 0.2913 291.30
55+000 56+000 1000.00 0.2913 291.30
56+000 57+000 1000.00 0.2913 291.30
57+000 58+000 1000.00 0.2913 291.30
58+000 59+000 1000.00 0.2913 291.30
59+000 60+000 1000.00 0.2913 291.30
60+000 61+000 1000.00 0.2913 291.30
61+000 62+000 1000.00 0.2913 291.30
62+000 63+000 1000.00 0.2913 291.30
63+000 64+000 1000.00 0.2913 291.30
64+000 65+000 1000.00 0.2913 291.30
65+000 66+000 1000.00 0.2913 291.30
66+000 67+000 1000.00 0.2913 291.30
67+000 68+000 1000.00 0.2913 291.30
68+000 69+000 1000.00 0.2913 291.30
69+000 70+000 1000.00 0.2913 291.30
70+000 71+000 1000.00 0.2913 291.30
20682.30
JUSTIFICACIÓN DE METRADOS

06.00.00 SEÑALIZACION
06.03.00 Repración/Reposic. Postes Kilométricos

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN DE SEÑALES DE TRANSITO


UBICACIÓN DESCRIPCION
LADO METRADO (UND)
Nº Progr. Km. Tipo

1 7+000 Poste Kilométrico I 1.00


2 8+000 Poste Kilométrico I 1.00
3 9+000 Poste Kilométrico I 1.00
4 10+000 Poste Kilométrico I 1.00
5 16+000 Poste Kilométrico D 1.00
6 17+000 Poste Kilométrico D 1.00
7 18+000 Poste Kilométrico D 1.00
8 20+000 Poste Kilométrico D 1.00
9 22+000 Poste Kilométrico D 1.00
10 23+000 Poste Kilométrico D 1.00
11 26+000 Poste Kilométrico D 1.00
12 27+000 Poste Kilométrico D 1.00
13 28+000 Poste Kilométrico D 1.00
14 29+000 Poste Kilométrico D 1.00
15 32+000 Poste Kilométrico D 1.00
16 33+000 Poste Kilométrico D 1.00
17 34+000 Poste Kilométrico D 1.00
18 35+000 Poste Kilométrico D 1.00
19 36+000 Poste Kilométrico D 1.00
20 38+000 Poste Kilométrico D 1.00
21 43+000 Poste Kilométrico D 1.00
22 44+000 Poste Kilométrico D 1.00
23 51+000 Poste Kilométrico D 1.00
24 52+000 Poste Kilométrico D 1.00
25 54+000 Poste Kilométrico D 1.00
26 56+000 Poste Kilométrico D 1.00
27 57+000 Poste Kilométrico D 1.00
28 58+000 Poste Kilométrico D 1.00
29 59+000 Poste Kilométrico D 1.00
30 60+000 Poste Kilométrico D 1.00
31 62+000 Poste Kilométrico D 1.00
32 63+000 Poste Kilométrico D 1.00
33 69+000 Poste Kilométrico D 1.00
33.00
JUSTIFICACIÓN DE METRADOS

06.00.00 SEÑALIZACION
05.04.00 Señal Preventiva

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN DE SEÑALES DE TRANSITO


UBICACIÓN DESCRIPCION
LADO METRADO (UND)
Nº Progr. Km. Tipo

1 -- PREVENTIVAS -- 428.00

428.00
JUSTIFICACIÓN DE METRADOS

06.00.00 SEÑALIZACION

05.05.00 Señal Reglamentaria

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN DE SEÑALES DE TRANSITO


UBICACIÓN DESCRIPCION
LADO METRADO (UND)
Nº Progr. Km. Tipo

1 -- REGLAMENTARIA -- 212.00

212.00

05.06.00 Señal Informativa

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto
OBRA
Huallaga, Bajo Mayo Y Bajo Huallaga – San Martin"
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

RELACIÓN DE SEÑALES DE TRANSITO


UBICACIÓN DESCRIPCION
LADO METRADO (UND)
Nº Progr. Km. Tipo

1 -- INFORMATIVA -- 24.00

24.00
"Mantenimiento Periódico de la Carretera Departamental Emp. PE-5NB (Pongo de Caynarachi) - Barraquita; Tramo: Km. 00+000 - Km. 27+000"

FECHA : Marzo 2011 Plazo de Ejecución: 120 Días Calenadarios


Costo a Marzo del 2,011

MESES
ITEM DESCRIPCION PARCIAL MES 1 MES 2 MES 3 MES 4
S/. SEM 1 SEM 2 SEM 3 SEM 4 SEM 5 SEM 6 SEM 7 SEM 8 SEM 9 SEM 10 SEM 11 SEM 12 SEM 13 SEM 14 SEM 15 SEM 16

#REF! #REF!
01.01.00 Movilización y Desmovilización de Equipo 6,834.60 3,417.30 3,417.30
01.02.00 Campamento Provisional de la Obra 1,200.00 1,200.00
#REF! #REF! 633.84 633.84
#REF! #REF! 5,625.72 5,625.72
#REF! #REF! 7,220.62 1,805.16 1,805.16 1,805.16 1,805.16
#REF! #REF! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
#REF! #REF! 16,013.89 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85 1,143.85
#REF! #REF! 294,492.00 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14 21,035.14
#REF! #REF! 127,523.09 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54 8,501.54
#REF! #REF!
#REF! #REF!
#REF! #REF! 938.69 67.05 67.05 67.05 67.05 67.05 67.05 67.05 67.05 67.05 67.05 67.05 67.05 67.05 67.05
#REF! #REF!
#REF! #REF! 11,823.30 2,955.83 2,955.83 2,955.83 2,955.83
#REF! #REF!
#REF! #REF! 1,970.55 492.64 492.64 492.64 492.64
#REF! #REF!
#REF! #REF! 867.41 867.41
#REF! #REF! 1,044.52 522.26 522.26
#REF! #REF!
#REF! #REF! 1,542.50 385.63 385.63 385.63 385.63
#REF! #REF! 4,176.23 1,044.06 1,044.06 1,044.06 1,044.06
#REF! #REF! 696.04 174.01 174.01 174.01 174.01

COSTO DIRECTO 482,603.00 16,130.48 36,001.20 36,001.20 36,001.20 31,269.84 31,269.84 32,351.27 32,351.27 32,351.27 32,351.27 30,747.58 30,747.58 30,747.58 30,747.58 30,747.58 12,786.25
GASTOS GENERALES (11.064373% CD) 53,397.00 1,784.74 3,983.31 3,983.31 3,983.31 3,459.81 3,459.81 3,579.47 3,579.47 3,579.47 3,579.47 3,402.03 3,402.03 3,402.03 3,402.03 3,402.03 1,414.72
SUPERVISIÓN 14,000.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00 875.00
TOTAL PRESUPUESTO 550,000.00 18,790.21 40,859.51 40,859.51 40,859.51 35,604.65 35,604.65 36,805.74 36,805.74 36,805.74 36,805.74 35,024.61 35,024.61 35,024.61 35,024.61 35,024.61 15,075.97
% DE AVANCE DE OBRA 100.00 3.42 7.43 7.43 7.43 6.47 6.47 6.69 6.69 6.69 6.69 6.37 6.37 6.37 6.37 6.37 2.74
% ACUM. DE AVANCE DE OBRA 100.00 3.42 10.85 18.27 25.70 6.47 12.95 19.64 26.33 6.69 13.38 19.75 26.12 6.37 12.74 19.10 21.85
% ACUM. MENSUAL DE AVANCE DE OBRA 100.00 25.70 26.33 26.12 21.85
CALCULO DE LA DISTANCIA MEDIA DE TRANSPORTE DE MATERIAL LIGANTE 20%
TRAMO: KM. 27+000 - KM. 32+000
“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y Bajo
OBRA
Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

Cantera Ligante FIN DE TRAMO


INICIO DE TRAMO
Nº01 KM. 10+000 Km 32+000
Km 27+000

CANTERA PTOS. DE INFLUENCIA d1 ACCESO dm VOLUMEN dmx VOLUMEN


10+000 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
10+000 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
10+000 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
10+000 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
10+000 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
#REF! #REF!

D= #REF! / #REF! #REF! KM

CALCULO DEL RENDIMIENTO DEL CAMION VOLQUETE PARA TRANSPORTE DE MATERIAL DE AFIRMADO

Velocidad cargado : 20 km/h


Velocidad descargado : 30 km/h
Tiempo carga y descarga : 5'
Tiempo de recorrido descargado : (60/20) d= 3 d
Tiempo de recorrido cargado : (60/30) d= 2 d
-------------------
Ciclo = 5+5d

Tiempo Util : 8 h x 60 min. x 0.90 = 432 min.


Nº de viajes : 432*10/(5+5d)

Rendimiento dm= #REF! : #REF! m³/día (para un camión volquete)

Rendimiento para cuatro camiones = #REF! m³/día

CALCULO DE LA DISTANCIA MEDIA DE TRANSPORTE DE MATERIAL RIO 80%


TRAMO: KM. 27+000 - KM. 32+000

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y Bajo
OBRA
Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

INICIO DE TRAMO FIN DE TRAMO


Km 27+000 Km 32+000

Cantera Río
Nº02 KM. 16+200

CANTERA PTOS. DE INFLUENCIA d1 ACCESO dm VOLUMEN dmx VOLUMEN


16+200 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
16+200 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
16+200 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
16+200 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
16+200 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
#REF! #REF!

D= #REF! / #REF! #REF! KM

CALCULO DEL RENDIMIENTO DEL CAMION VOLQUETE PARA TRANSPORTE DE MATERIAL DE AFIRMADO

Velocidad cargado : 20 km/h


Velocidad descargado : 30 km/h
Tiempo carga y descarga : 5'
Tiempo de recorrido descargado : (60/20) d= 3 d
Tiempo de recorrido cargado : (60/30) d= 2 d
-------------------
Ciclo = 5+5d

Tiempo Util : 8 h x 60 min. x 0.90 = 432 min.


Nº de viajes : 432*10/(5+5d)

Rendimiento dm= #REF! : #REF! m³/día (para un camión volquete)

Rendimiento para cuatro camiones = #REF! m³/día


CALCULO DE LA DISTANCIA MEDIA DE TRANSPORTE DE MATERIAL LIGANTE 20%
TRAMO: KM. 27+000 - KM. 32+000
“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y Bajo
OBRA
Huallaga – San Martin"

DEPARTAMENTO : SAN MARTIN


REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

Cantera Ligante FIN DE TRAMO


INICIO DE TRAMO
Nº01 KM. 10+000 Km 32+000
Km 27+000

CALCULO DE LA DISTANCIA MEDIA DE TRANSPORTE DE MATERIAL DE AFIRMADO


TRAMO: KM. 32+000 - KM. 53+300

“Contrato De Gestión Vial Por Niveles De Servicio De La Red Vial Regional Alto Huallaga, Bajo Mayo Y Bajo
OBRA
Huallaga – San Martin"
DEPARTAMENTO : SAN MARTIN
REGION : SAN MARTIN
PROVINCIA : LAMAS
DISTRITO : PONGO DE CAYNARACHI, BARRANQUITA, PELEJO Y PAPLAYA
FECHA : 01

INICIO DE TRAMO FIN DE TRAMO


Km 27+000 Km 53+300

Cantera Nº01
KM. 53+300

CANTERA PTOS. DE INFLUENCIA d1 ACCESO dm VOLUMEN dmx VOLUMEN


53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
53+300 #REF! #REF! #REF! 0.00 #REF! #REF! #REF!
#REF! #REF!

D= #REF! / #REF! #REF! KM

CALCULO DEL RENDIMIENTO DEL CAMION VOLQUETE PARA TRANSPORTE DE MATERIAL DE AFIRMADO

Velocidad cargado : 20 km/h


Velocidad descargado : 30 km/h
Tiempo carga y descarga : 5'
Tiempo de recorrido descargado : (60/20) d= 3 d
Tiempo de recorrido cargado : (60/30) d= 2 d
-------------------
Ciclo = 5+5d

Tiempo Util : 8 h x 60 min. x 0.90 = 432 min.


Nº de viajes : 432*10/(5+5d)

Rendimiento dm= #REF! : #REF! m³/día (para un camión volquete)

Rendimiento para cuatro camiones = #REF! m³/día