REKAP HARGA BERDASARKAN HARGA MATERIAL DAN UPAH

###

NO ITEM SAT
HARGA VOL TOTAL BOBOT

MATERIAL CIVIL WORK


1 Batu Kali M3 500,000 51.14 25,568,400 31.07%
2 Besi Beton £ Ø 12 mm Kg 16,000 632.83 10,125,284 12.30%
3 Kawat Beton/Bendrat Kg 25,000 11.44 285,960 0.35%
4 Kayu Balok 4/6 - 4 m Kelas II (Bekisting/Bowplank) Btg 30,000 47.55 1,426,526 1.73%
5 Paku 2" Kg 24,000 3.39 81,312 0.10%
6 Pasir Beton/Cor M3 250,000 3.26 815,244 0.99%
7 Pasir Pasang M3 225,000 25.57 5,752,890 6.99%
8 Pipa PVC Merk Wavin 2" D - 4 m Btg 100,000 16.00 1,600,000 1.94%
9 Semen PC Type 1 @ 50 Kg Zak 70,000 165.57 11,589,634 14.08%
10 Split M3 450,000 2.31 1,037,945 1.26%
11 Triplek 9 mm m2 65,000 33.88 2,202,200 2.68%

Material Utama ` 0.00%


Material Pendukung 60,485,395 73.49%
Total Material Civil Work 60,485,395 73.49%

UPAH
1 Bekisting Menerus Multiplek m2 30,000 67.76 2,032,800 2.47%
2 Galian Tanah > 1m M3 70,000 85.82 6,007,680 7.30%
3 Pasangan Batu Kali M3 150,000 42.61 6,392,100 7.77%
4 Pembesian £ dia. 12 mm M3 4,000 571.92 2,287,680 2.78%
5 Pembesian £ dia. 12 mm (Tanpa Kawat Beton) M3 2,950 30.78 90,788 0.11%
6 Pengecoran 1:3:5 M3 150,000 - - 0.00%
7 Pengecoran 1 : 2: 3 M3 150,000 3.98 596,520 0.72%
8 Plesteran Kamprot m2 50,000 - - 0.00%
9 Urug Pasir M3 85,000 - - 0.00%
10 Urugan Tanah & Pemadatan M3 85,000 51.85 4,407,420 5.36%
Upah Utama ###
Upah Pendukung 21,814,988 26.51%
Total Upah 21,814,988 26.51%

Total 82,300,383 100.00%

Printed On 11/04/2019
1/3
Prepared by QS
P
a
g
a
r

P
a
ANALISA SATUAN PEKERJAAN n
### - e
harus diisi l

RAP &
NO URAIAN PEKERJAAN SAT Volume
SAT. BAHAN BAHAN SAT. UPAH UPAH JUMLAH s
###
a
l
00 PEKERJAAN PEMBOBOKAN DAN PEMBONGKARAN ###
u
10 PEKERJAAN TANAH & PONDASI ###
r
Pasangan Batu Kali M³ 1.00 963,200 150,000 150,000 1,113,200
### a
Batu Kali M³ 1.20 500,000 600,000 ### n
Semen PC Type 1 @ 50 Kg Zak 3.26 70,000 228,200 ###
Pasir Pasang M³ 0.60 225,000 135,000 ### a
Galian Tanah > 1m M³ 1.00 70,000 70,000 70,000
###
i
r
Urugan Tanah & Pemadatan M³ 1.00 85,000 85,000 85,000
###
- ###
30 PEKERJAAN KONSTRUKSI BETON ###
Bekisting Menerus Multiplek M² 1.00 54,753 30,000 30,000 84,753
###
Triplek 9 mm M² 0.50 65,000 32,500 ###
Kayu Balok 4/6 - 4 m Kelas II (Bekisting/Bowplank) Btg 0.70 30,000 21,053 ###
Paku 2" Kg 0.05 24,000 1,200 ###
Pembesian £ dia. 12 mm Kg 1.00 17,300 4,000 4,000 21,300
###
Besi Beton £ Ø 12 mm Kg 1.05 16,000 16,800 ###
Kawat Beton/Bendrat Kg 0.02 25,000 500 ###
Pembesian £ dia. 12 mm (Tanpa Kawat Beton) Kg 1.00 16,800 2,950 2,950 ###
19,750
Besi Beton £ Ø 12 mm Kg 1.05 16,000 16,800 ###
Pengecoran 1 : 2: 3 M³ 1.00 261,000 150,000 150,000 411,000
###
Semen PC Type 1 @ 50 Kg Zak 6.70 70,000 469,000 ###
Pasir Beton/Cor M³ 0.82 250,000 205,000 ###
Split M³ 0.58 450,000 261,000 ###
Pengecoran 1:3:5 M³ 1.00 867,700 150,000 150,000 ###
1,017,700
Semen PC Type 1 @ 50 Kg Zak 4.36 70,000 305,200 ###
Pasir Beton/Cor M³ 0.63 250,000 157,500 ###
Split M³ 0.90 450,000 405,000 ###
###

Printed On 11/04/2019
2/3
Prepared by QS
###
BANGUNAN : PAGAR PANEL & SALURAN AIR Panjang Pagar : 423.3 M
LOKASI : #REF! Tinggi Pagar : 2.8 M
NO. GBR. : IVM/PGR/PBRO/KTR-PWK/17 Tinggi pondasi batu kali : M
HARGA : Rp 79,620,019
KONTRAKTOR :

Tanggal = 04-Nov-2019
HARGA JUMLAH
NO URAIAN PEKERJAAN SAT. VOL VOL SATUAN HARGA
Estimasi Kontraktor Rp. Rp.

II PEKERJAAN PONDASI BATU KALI PAGAR 60,060,821


II.I PEKERJAAN TANAH DAN PONDASI 60,060,821
II.I.VI Pekerjaan Pagar Sisi Timur (Pot 6) Panjang 59.6 m 60,060,821
Galian Tanah > 1m M³ 85.82 85.82 70,000 6,007,680
Urugan Tanah & Pemadatan M³ 51.85 51.85 85,000 4,407,420
Pipa PVC Merk Wavin 2" D - 4 m Btg 16.00 16.00 100,000 1,600,000
Pasangan Batu Kali M³ 42.61 42.61 1,113,200 47,437,905
PeBesi Beton Ø 10 mm Kg 30.78 30.78 19,750 607,816

III PEKERJAAN PAGAR 19,559,198


III.I PEKERJAAN PAGAR 19,559,198
III.I.IV Pagar Dinding Beton Sisi Timur (Pot 6) Panjang 59.6 m 19,559,198
Sloof uk. 15 x 20 cm
Bekisting Menerus Multiplek m2 23.84 23.84 84,753 2,020,503
Pembesian
PeBesi Beton Ø 10 mm Kg 146.98 146.98 21,300 3,130,728
PeBesi Beton Ø 6 mm Kg 46.45 46.45 21,300 989,489
Pengecoran 1 : 2: 3 M³ 1.79 1.79 411,000 734,868
Kolom Praktis uk. 15 x 20 cm
Bekisting Menerus Multiplek m2 26.04 26.04 84,753 2,206,959
Pembesian
PeBesi Beton Ø 12 mm Kg 132.11 132.11 21,300 2,813,873
PeBesi Beton Ø 8 mm Kg 51.65 51.65 21,300 1,100,167
Pengecoran 1 : 2: 3 M³ 1.12 1.12 411,000 458,676
Ring Balok uk. 12 x 15 cm
Bekisting Menerus Multiplek m2 17.88 17.88 84,753 1,515,377
Pembesian
PeBesi Beton Ø 10 mm Kg 146.98 146.98 21,300 3,130,728
PeBesi Beton Ø 6 mm Kg 47.74 47.74 21,300 1,016,909
Pengecoran 1 : 2: 3 M³ 1.07 1.07 411,000 440,921

TOTAL BANGUNAN 79,620,019