CALENDARIO DE ADQUISICION DE MATERIALES E INSUMOS

OBRA
ENTIDAD
LUGAR

PLAZO DE EJECUCION (120 DIAS CALENDARIOS)

CÓDIGO DESCRIPCION UNIDAD CANTIDAD PRECIO S/. PARCIAL S/. TOTAL


31 OCTUBRE AL 30 DEL 01 AL 31 DE DEL 01 AL 31 DE DEL 01 AL 27 DE DEL 09 AL 31 DE DEL 1 AL 17 DE
NOVIEMBRE DICIEMBRE ENERO FEBRERO MAYO JUNIO

101010003 OPERARIO hh 373.29 21.01 7,842.81 1,319.94 1,024.27 2,246.97 3,251.63 7,842.81
101010004 OFICIAL hh 1,013.12 17.03 17,253.39 2,746.74 747.07 3,804.37 5,079.40 241.55 4,634.26 17,253.39
101010005 PEON hh 6,036.71 15.34 92,603.14 16,483.36 3,000.34 18,150.22 27,503.13 851.95 26,614.14 92,603.14
101030000 TOPOGRAFO hh 54.26 15.50 841.03 709.24 131.79 841.03
1010300081 CONTROLADOR OFICIAL hh 245.42 15.50 3,804.08 1,867.04 503.66 1,262.19 171.18 3,804.08
2010500011 ASFALTO RC-250 gal 5.62 9.50 53.40 26.70 26.70 53.40
201050006 AFIRMADO m3 13.41 112.00 1,501.38 270.10 120.11 1,005.47 105.70 1,501.38
203020002 FLETE TERRESTRE glb 1.00 20,745.19 20,745.19 10,372.60 5,186.30 4,149.04 1,037.26 20,745.19
2040100012 ALAMBRE NEGRO RECOCIDO N° 16 kg 73.42 3.75 275.33 122.19 153.14 275.33
204030005 ACERO DE REFUERZO fy = 4200 kg/cm2 GRADO 60 kg 69.02 3.98 274.68 274.68 274.68
2041200010 CLAVOS PARA MADERA CON CABEZA PROMEDIO " kg 200.27 3.50 700.93 280.58 186.52 233.83 700.93
2041600013 PLATINA DE FIERRO 3/16" und 41.88 7.80 326.66 326.66 326.66
2042900018 ALCANTARILLA TMC D=36" m 54.40 272.01 14,797.34 14,797.34 14,797.34
2042900019 ALCANTARILLA TMC D=48" m 8.00 424.79 3,398.32 3,398.32 3,398.32
20429000112 ALCANTARILLA TMC D=60" m 39.20 624.25 24,470.60 24,470.60 24,470.60
207010005 PIEDRA MEDIANA m3 20.27 130.00 2,635.10 1,054.04 1,581.06 2,635.10
207010011 GRAVILLA 1/2" - 3/4" m3 104.46 120.00 12,535.00 2,933.19 7,094.81 2,507.00 12,535.00
2070200012 ARENA GRUESA m3 100.21 112.00 11,223.43 1,459.05 6,023.61 3,740.77 11,223.43
207030001 HORMIGON m3 3.92 110.00 431.38 143.78 287.60 431.38
20704000101 MATERIAL GRANULAR PARA SUB-BASE m3 6,252.66 35.00 218,843.01 78,783.48 35,014.88 74,406.62 30,638.02 218,843.01
20704000102 MATERIAL GRANULAR PARA BASE m3 5,999.30 145.00 869,898.14 252,270.46 200,598.51 417,029.17 869,898.14
210020003 GIGANTOGRAFIA m2 10.00 19.00 190.00 190.00 190.00
213010001 CEMENTO PORTLAND TIPO I (42.5 kg) bol 1,566.44 19.50 30,545.53 3,054.55 3,573.83 11,698.94 12,218.21 30,545.53
21303000104 YESO BOLSA 18 kg bol 34.67 5.00 173.36 132.62 40.74 173.36
219030002 CONCRETO f'c=175 KG/cm2 m3 1,266.80 315.35 399,483.80 48,377.49 8,548.95 342,557.36 399,483.80
219030003 JUNTAS ASFALTICAS e=1" m 4,222.65 2.71 11,443.38 2,975.28 457.74 8,010.37 11,443.38
219030004 ENCOFRADO Y DESENCOFRADO PARA ESTRUCTURAS m2 2,871.40 25.98 74,599.02 18,649.76 3,729.95 52,219.31 74,599.02
219030005 EXCAVACION PARA ESTRUCTURAS m3 1,055.66 13.14 13,871.41 1,679.83 298.24 11,893.35 13,871.41
231010001 MADERA TORNILLO p2 2,652.85 5.10 13,529.53 5,415.87 3,601.56 4,512.10 13,529.53
231040004 ESTACA DE MADERA pza 253.20 0.20 50.64 50.64 50.64
2310500017 TRIPLAY DE 4'x8'x4 mm pln 49.20 50.85 2,501.82 2,501.82 2,501.82
2310500018 CALAMINA pln 24.00 18.25 438.00 438.00 438.00
238010005 LIJA und 32.00 1.50 47.99 47.99 47.99
240020017 PINTURA ESMALTE SINTETICO gal 30.20 38.14 1,151.79 728.51 135.34 287.95 1,151.79
240020018 PINTURA IMPRIMANTE RETROREFLECTIVA gal 0.31 85.50 26.47 26.47 26.47
240020019 PINTURA ESMALTE EPOXICA gal 0.72 85.00 61.41 61.41 61.41
240070001 PINTURA ANTICORROSIVA gal 0.72 62.15 44.90 44.90 44.90
240080022 DISOLVENTE EPOXICO gal 2.89 22.50 65.03 65.03 65.03
240080023 ADITIVO ESTABILIZACION DE SUELOS gal 81.59 820.00 66,904.13 19,402.20 15,428.09 32,073.84 66,904.13
24607000104 PERNOS HEXAGONALES DE 3/4" X 6" INC. TUER und 12.00 2.50 30.00 30.00 30.00
255080015 SOLDADURA kg 28.66 11.50 329.53 329.53 329.53
263120001 POSTE DE CONCRETO PARA SEÑALES, INC. PINTURA und 13.00 130.00 1,690.00 1,690.00 1,690.00
2650100010 TUBO DE FIERRO NEGRO DE 3" m 28.90 36.00 1,040.40 1,040.40 1,040.40
26711000407 SEÑAL PREVENTIVA, EN FIBRA DE VIDRIO DE 4MM DE 60 X60 und 9.00 125.00 1,125.00 1,125.00 1,125.00
2671100049 CM INC.REGLAMENTARIA,
SEÑAL PERNOS EN FIBRA DE VIDRIO DE 4MM DE 60 und 4.00 160.00 640.00 640.00 640.00
26711000400 X90 CMINFORMATIVA,
SEÑAL INC. PERNOS PANEL EN FIBRA DE VIDRIO DE 4MM INC. PINTURA Y PERNOS m2 2.51 278.00 698.56 698.56 698.56
272040053 MOVILIZACION Y DESMOVILIZACION glb 1.00 20,833.56 20,833.56 10,416.78 10,416.78 20,833.56
279010048 HITO KILOMETRICO DE CONCRETO ARMADO und 5.00 110.00 550.00 550.00 550.00
290130022 AGUA m3 40.56 6.00 243.36 32.44 13.77 59.60 77.66 4.67 55.22 243.36
290130023 PLANTON DE EUCALIPTO und 30.00 0.40 12.00 12.00 12.00
290130024 ICHU m2 4,090.50 0.25 1,022.63 1,022.63 1,022.63
292010006 PLAN DE MONITOREO AMBIENTAL glb 1.00 15,000.00 15,000.00 7,500.00 1,500.00 2,250.00 3,000.00 300.00 450.00 15,000.00
292010008 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DE PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 14,400.00 14,400.00 7,200.00 1,440.00 2,160.00 2,880.00 288.00 432.00 14,400.00
292010010 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 15,500.00 15,500.00 7,750.00 1,550.00 2,325.00 3,100.00 310.00 465.00 15,500.00

COSTO DIRECTO 1,992,697.59 158,418.10 315,562.50 195,192.73 134,842.36 218,022.77 970,659.14 1,992,697.59