TOTAL DE VALORIZACION S/. 2,349,697.16 S/. 471,926.17 S/. 556,128.64 S/. 1,028,054.81 S/. 1,321,642.29
20.08% 23.67% 43.75% 56.25%
2 DE 71
INFORME DE VALORIZACION MENSUAL DE OBRA N° 001 ( CORRESPONDIENTE AL MES DE AGOSTO DEL 2,018)
DATOS GENERALES
FUNCION 019 VIVIENDA Y DESARROLLO URBANO PRESUPUESTO S/. 2,349,697.16 UBICACIÓN
PROGRAMA 041 DESARROLLO URBANO FECHA INICIO 8/1/2018 DEPARTAMENTO AYACUCHO
SUB-PROG. 010 INFRAESTRUCTURA Y EQUIPAMIENTO FECHA TERMINO 12/29/2018 PROVINCIA HUAMANGA
PROYECTO 2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE ANDRÉS AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910) MES EVALUADO AGOSTO DEL 2018 LUGAR AV. ANDRES AVELINO CACERES
FECHA 22 DE AGOSTO 2018
COSTO DIRECTO S/. 2,100,550.58 S/. 0.00 S/. 164,424.97 S/. 164,424.97 S/. 1,936,125.56
GASTOS GENERALES (10% C.D.) S/. 210,055.06 S/. 0.00 S/. 16,442.50 S/. 16,442.50 S/. 193,612.56
PRESUPUESTO DE OBRA S/. 2,310,605.64 S/. 0.00 S/. 180,867.47 S/. 180,867.47 S/. 2,129,738.12
SUPERVISION (1.86 % C.D.) S/. 39,091.52 S/. 0.00 S/. 3,059.97 S/. 3,059.97 S/. 36,031.55
PRESUPUESTO TOTAL S/. 2,349,697.16 S/. 0.00 S/. 183,927.44 S/. 183,927.44 S/. 2,165,769.67
3 DE 71
VALORIZACION N° 02 - OBRA PRINCIPAL
INFORME DE VALORIZACION MENSUAL DE OBRA N° 002 ( CORRESPONDIENTE AL MES DE SEPTIEMBRE DEL 2,018)
DATOS GENERALES
FUNCION 019 VIVIENDA Y DESARROLLO URBANO PRESUPUESTO S/. 2,349,697.16 UBICACIÓN
PROGRAMA 041 DESARROLLO URBANO FECHA INICIO 8/1/2018 DEPARTAMENTO AYACUCHO
SUB-PROG. 010 INFRAESTRUCTURA Y EQUIPAMIENTO FECHA TERMINO 12/29/2018 PROVINCIA HUAMANGA
PROYECTO 2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE ANDRÉS AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910) MES EVALUADO SEPTIEMBRE DEL 2018 LUGAR AV. ANDRES AVELINO CACERES
FECHA 30 DE SEPTIEMBRE 2018
4 DE 71
INFORME DE VALORIZACION MENSUAL DE OBRA N° 002 ( CORRESPONDIENTE AL MES DE SEPTIEMBRE DEL 2,018)
DATOS GENERALES
FUNCION 019 VIVIENDA Y DESARROLLO URBANO PRESUPUESTO S/. 2,349,697.16 UBICACIÓN
PROGRAMA 041 DESARROLLO URBANO FECHA INICIO 8/1/2018 DEPARTAMENTO AYACUCHO
SUB-PROG. 010 INFRAESTRUCTURA Y EQUIPAMIENTO FECHA TERMINO 12/29/2018 PROVINCIA HUAMANGA
PROYECTO 2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE ANDRÉS AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910) MES EVALUADO SEPTIEMBRE DEL 2018 LUGAR AV. ANDRES AVELINO CACERES
FECHA 30 DE SEPTIEMBRE 2018
COSTO DIRECTO S/. 2,100,550.58 S/. 164,424.97 S/. 254,656.55 S/. 419,081.52 S/. 1,681,469.01
GASTOS GENERALES (10% C.D.) S/. 210,055.06 S/. 16,442.50 S/. 25,465.66 S/. 41,908.15 S/. 168,146.90
PRESUPUESTO DE OBRA S/. 2,310,605.64 S/. 180,867.47 S/. 280,122.21 S/. 460,989.67 S/. 1,849,615.91
SUPERVISION (1.86 % C.D.) S/. 39,091.52 S/. 3,059.97 S/. 4,739.19 S/. 7,799.16 S/. 31,292.36
PRESUPUESTO TOTAL S/. 2,349,697.16 S/. 183,927.44 S/. 284,861.40 S/. 468,788.83 S/. 1,880,908.27
5 DE 71
VALORIZACION N° 02 - MA
INFORME DE VALORIZACION MENSUAL DE OBRA N° 002 ( CO
DATOS GENERALES
FUNCION 019 VIVIENDA Y DESARROLLO URBANO
PROGRAMA 041 DESARROLLO URBANO
SUB-PROG. 010 INFRAESTRUCTURA Y EQUIPAMIENTO
PROYECTO 2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE ANDRÉS AVELINO CÁCERES - HUAMANGA
FECHA 30 DE SEPTIEMBRE 2018
03 MOVIMIENTO DE TIERRAS
03.05 RELLENO CON MATERIAL PROPIO M3 11.08 27.08
05 VEREDAS Y RAMPAS
05.01 MOVIMIENTO DE TIERRAS
05.01.01 DEMOLICION DE VEREDAS EXISTENTES M2 1,291.00 3.41
COSTO DIRECTO
GASTOS GENERALES (10% C.D.)
PRESUPUESTO DE OBRA
SUPERVISION (1.86 % C.D.)
PRESUPUESTO TOTAL
PORCENTAJE DE AVANCE
RIZACION N° 02 - MAYORES METRADOS
DE OBRA N° 002 ( CORRESPONDIENTE AL MES DE SEPTIEMBRE DEL 2,018)
PRESUPUESTOS/. 2,349,697.16
FECHA INICIO 8/1/2018
FECHA TERMI 12/29/2018
S AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910) MES EVALUAD SEPTIEMBRE DEL 2018
AVANCE ACUMULADO
TOTAL %
404.03 134.66%
2,400.64 54.53%
S/. 2,804.67
S/. 280.47
S/. 3,085.14
S/. 52.20
S/. 3,137.34
0.13%
CRONOGRAMA VALORIZADO
OBRA : 2DA ETAPA DE "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CACERES, DISTRITO DE ANDRES AVELINO
AV. ANDRES AVELINO CACERES DORREGARAY SEM 01 SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04 SEM 01
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA UND 1.00 883.00 S/. 883.00 S/. 883.00
01.02 ALQUILER DE LOCAL PARA OBRA MES 5.00 1,350.00 S/. 6,750.00 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50
02 TRABAJOS PRELIMINARES
02.01 LIMPIEZA DE TERRENO NORMAL M2 10,613.29 0.46 S/. 4,882.11 S/. 2,441.06 S/. 2,441.06
02.02 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS Y EQUIPOS GLB 1.00 4,661.74 S/. 4,661.74 S/. 2,330.87 S/. 2,330.87
02.03 TRAZO Y REPLANTEO PRELIMINAR M2 10,613.29 1.40 S/. 14,858.61 S/. 4,952.87 S/. 4,952.87 S/. 4,952.87
02.04 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA M2 10,613.29 1.92 S/. 20,377.52 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88
03 MOVIMIENTO DE TIERRAS
03.01 CORTE EN MATERIAL COMPACTO A NIVEL DE SUBRASANTE M3 6,535.55 8.31 S/. 54,310.42 S/. 18,103.47 S/. 18,103.47 S/. 18,103.47
03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 8,481.81 11.39 S/. 96,607.82 S/. 19,321.56 S/. 19,321.56 S/. 19,321.56 S/. 19,321.56 S/. 19,321.56
03.03 PERFILADO Y COMPACTADO DE SUB-RASANTE M2 10,613.29 5.49 S/. 58,266.96 S/. 19,422.32 S/. 19,422.32 S/. 19,422.32
03.04 CONFORMACION Y COMPACTACION DE BASE GRANULAR E=0.25M M2 10,613.29 29.29 S/. 310,863.26 S/. 77,715.82 S/. 77,715.82 S/. 77,715.82
03.05 RELLENO CON MATERIAL PROPIO M3 11.08 27.08 S/. 300.05 S/. 300.05
04 PAVIMENTO
04.01 DEMOLICION DE PAVIMENTO DE CONCRETO M2 10,385.00 3.41 S/. 35,412.85 S/. 17,706.43 S/. 17,706.43
04.02 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO M2 1,503.78 38.17 S/. 57,399.28 S/. 19,133.09 S/. 19,133.09
04.03 CONCRETO F´CR=245KG/CM2 M2 7,437.85 116.63 S/. 867,476.45 S/. 216,869.11
04.04 CURADO DE CONCRETO M2 7,437.85 1.13 S/. 8,404.77
04.05 JUNTAS ASFALTICAS M 4,501.20 5.27 S/. 23,721.32
05 VEREDAS Y RAMPAS
05.01 MOVIMIENTO DE TIERRAS
05.01.01 DEMOLICION DE VEREDAS EXISTENTES M2 1,291.00 3.41 S/. 4,402.31 S/. 2,201.16 S/. 2,201.16
05.01.02 EXCAVACION MANUAL DE TERRENO A NIVEL DE SUBRASANTE M3 206.74 21.75 S/. 4,496.60
05.01.03 ACARREO DE MATERIAL EXCEDENTE M3 268.77 8.88 S/. 2,386.68
NIVELACION Y COMPACTACION DE SUBRASANTE CON EQUIPO
05.01.04 M2 2,067.44 1.40 S/. 2,894.42
LIVIANO
05.01.05 CONFORMACION Y COMPACTACION DE BASE E=0.10M M2 2,067.44 9.40 S/. 19,433.94
05.01.06 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 268.77 11.39 S/. 3,061.29
05.02 OBRAS DE CONCRETO
05.02.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS M2 347.39 35.54 S/. 12,346.24
05.02.02 CONCRETO F´CR=175 KG/CM2 EN VEREDAS E=0.10m M2 2,067.44 40.21 S/. 83,131.76
05.02.03 JUNTAS ASFALTICAS M 651.00 5.27 S/. 3,430.77
05.02.04 CURADO DE CONCRETO M2 2,067.44 1.13 S/. 2,336.21
06 SARDINEL DE CONCRETO
06.01 MOVIMIENTO DE TIERRAS
06.01.01 EXCAVACION DE ZANJA PARA SARDINEL M3 163.11 15.44 S/. 2,518.42
06.01.02 ACARREO DE MATERIAL EXCEDENTE M3 212.04 8.88 S/. 1,882.92
06.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 212.04 11.39 S/. 2,415.14
06.02 CONCRETO SIMPLE
06.02.01 ENCOFRADO Y DESENCOFRADO DE SARDINEL M2 1,087.37 38.59 S/. 41,961.61
06.02.02 CONCRETO F´CR=175 KG/CM2 EN SARDINEL M3 163.11 402.14 S/. 65,593.06
06.02.03 CURADO DE CONCRETO M2 810.46 1.13 S/. 915.82
06.02.04 JUNTAS ASFALTICAS ML 248.60 5.27 S/. 1,310.12
07 CUNETA DE CONCRETO
07.01 MOVIMIENTO DE TIERRAS
07.01.01 EXCAVACION DE ZANJA PARA SARDINEL M3 226.93 15.44 S/. 3,503.80
07.01.02 ACARREO DE MATERIAL EXCEDENTE M3 309.76 8.88 S/. 2,750.67
07.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 309.76 11.39 S/. 3,528.17
07.02 CONCRETO SIMPLE
07.02.01 ENCOFRADO Y DESENCOFRADO DE SARDINEL M2 1,742.49 38.59 S/. 67,242.69
07.02.02 CONCRETO F´CR=175 KG/CM2 EN SARDINEL M3 238.28 407.96 S/. 97,208.71
CRONOGRAMA VALORIZADO
OBRA : 2DA ETAPA DE "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CACERES, DISTRITO DE ANDRES AVELINO
AV. ANDRES AVELINO CACERES DORREGARAY SEM 01 SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04 SEM 01
07.02.03 CURADO DE CONCRETO M2 1,588.51 1.13 S/. 1,795.02
07.02.04 JUNTAS ASFALTICAS M 542.40 5.27 S/. 2,858.45
08 SEÑALIZACION
08.01 SEÑAL PREVENTIVA UND 8.00 383.51 S/. 3,068.08
08.02 SEÑALES DE INFORMACION UND 10.00 406.42 S/. 4,064.20
08.03 PINTURA DE TRANSITO PARA PASO PEATONAL M2 132.00 5.35 S/. 706.20
08.04 SEÑALES HORIZONTALES (MARCAS EN EL PAVIMENTO) M2 56.76 12.29 S/. 697.58
09 MITIGACION E IMPACTO AMBIENTAL
09.01 PROGRAMA DE PREVENCION Y MITIGACION GLB 1.00 161.56 S/. 161.56 S/. 161.56
09.02 PROGRAMA DE EDUCACION AMBIENTAL GLB 1.00 241.56 S/. 241.56
09.03 PROGRAMA DE MANEJO DE RESIDUOS LIQUIDOS Y SOLIDOS MES 5.00 222.26 S/. 1,111.30 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57
09.04 PROGRAMA DE MANEJO DE CAMPAMENTO Y PATIO DE MAQUINAS HA 0.30 1,543.30 S/. 462.99 S/. 231.50
09.05 PROGRAMA DE CANTERAS Y BOTADEROS HA 0.90 1,929.13 S/. 1,736.22 S/. 868.11
09.06 PROGRAMA DE SEÑALIZACION AMBIENTAL Y SEGURIDAD UND 3.00 197.60 S/. 592.80 S/. 592.80
09.07 PROGRAMA DE REFORESTACION M2 2,299.96 1.00 S/. 2,299.96
09.08 PROGRAMA DE CONTINGENCIAS MES 5.00 399.96 S/. 1,999.80 S/. 99.99 S/. 99.99 S/. 99.99 S/. 99.99 S/. 99.99 S/. 99.99 S/. 99.99 S/. 99.99 S/. 99.99
09.09 PROGRAMA DE MONITOREO AMBIENTAL GLB 1.00 24,000.00 S/. 24,000.00 S/. 8,000.00
09.10 PROGRAMA DE MONITOREO ARQUEOLOGICO GLB 1.00 10,000.00 S/. 10,000.00 S/. 5,000.00 S/. 5,000.00
10 VARIOS
10.01 SEGURIDAD Y SALUD
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN
10.01.01 GLB 1.00 2,500.00 S/. 2,500.00 S/. 625.00 S/. 625.00
DE SEGURIDAD Y SALUD
10.01.02 EQUIPOS DE SEGURIDAD INDIVIDUAL UND 95.00 402.50 S/. 38,237.50 S/. 19,118.75 S/. 19,118.75
10.01.03 EQUIPOS DE SEGURIDAD COLECTIVA GLB 1.00 2,045.00 S/. 2,045.00 S/. 1,022.50 S/. 1,022.50
10.01.04 SEÑALIZACION TEMPORAL GLB 1.00 2,155.00 S/. 2,155.00 S/. 1,077.50 S/. 1,077.50
10.01.05 CAPACITACION DE SEGURIDAD Y SALUD GLB 1.00 1,220.00 S/. 1,220.00 S/. 610.00 S/. 610.00
10.02 LIMPIEZA GENERAL
10.02.01 LIMPIEZA FINAL DE OBRA M2 10,613.29 0.44 S/. 4,669.85
S/. 36,427.44 S/. 37,438.44 S/. 44,475.85 S/. 38,936.97 S/. 43,936.97 S/. 45,555.87 S/. 117,971.63 S/. 137,104.72 S/. 339,389.57
COSTO DIRECTO S/. 2,100,550.58 S/. 157,278.70 S/. 344,569.19 S
GASTOS GENERALES (10%) S/. 210,055.06 S/. 15,727.87 S/. 34,456.92
PRESUPUESTO DE OBRA S/. 2,310,605.64 S/. 173,006.57 S/. 379,026.11 S
GASTOS DE SUPERVISION (1.86%) S/. 39,091.52 S/. 2,926.98 S/. 6,412.48
PRESUPUESTO TOTAL S/. 2,349,697.16 S/. 175,933.55 S/. 385,438.58 S
PORCENTAJE AVANCE % 7.49% 16.40%
PORCENTAJE ACUMULADO % 7.49% 23.89%
AMA VALORIZADO
O CACERES, DISTRITO DE ANDRES AVELINO CACERES DORREGARAY - HUAMANGA - AYACUCHO"
SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04
S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50 S/. 337.50
S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88 S/. 1,018.88
S/. 77,715.82
S/. 19,133.09
S/. 216,869.11 S/. 216,869.11 S/. 216,869.11
S/. 1,680.95 S/. 1,680.95 S/. 1,680.95 S/. 1,680.95 S/. 1,680.95
S/. 11,860.66 S/. 11,860.66
S/. 4,496.60
S/. 2,386.68
S/. 2,518.42
S/. 1,882.92
S/. 2,415.14
S/. 3,503.80
S/. 2,750.67
S/. 3,528.17
SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04 SEM 01 SEM 02 SEM 03 SEM 04
S/. 598.34 S/. 598.34 S/. 598.34
S/. 1,429.23 S/. 1,429.23
S/. 241.56
S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57 S/. 55.57
S/. 231.50
S/. 868.11
S/. 4,669.85
S/. 331,794.19 S/. 222,134.21 S/. 231,851.18 S/. 80,309.27 S/. 122,413.00 S/. 157,309.69 S/. 87,186.66 S/. 5,432.67 S/. 11,182.20 S/. 2,278.58 S/. 7,421.49
S/. 1,125,169.14 S/. 447,218.61 S/. 26,314.94
S/. 112,516.91 S/. 44,721.86 S/. 2,631.49
S/. 1,237,686.06 S/. 491,940.47 S/. 28,946.44
S/. 20,939.54 S/. 8,322.80 S/. 489.72
S/. 1,258,625.60 S/. 500,263.27 S/. 29,436.16
53.57% 21.29% 1.25%
77.46% 98.75% 100.00%
VALORIZACION N° 03 - OBRA PRINCI
INFORME DE VALORIZACION MENSUAL DE OBRA N° 003 ( CORRESPOND
DATOS GENERALES
FUNCION 019 VIVIENDA Y DESARROLLO URBANO
PROGRAMA 041 DESARROLLO URBANO
SUB-PROG. 010 INFRAESTRUCTURA Y EQUIPAMIENTO
PROYECTO 2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE ANDRÉS AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
FECHA 15 DE OCTUBRE 2018
AVANCE ANTERIOR
Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
CANT. TOTAL
01 OBRAS PROVISIONALES S/. 7,633.00
01.01 CARTEL DE OBRA UND 1.00 883.00 S/. 883.00 1.00 883.00
01.02 ALQUILER DE LOCAL PARA OBRA MES 5.00 1,350.00 S/. 6,750.00 2.00 2,700.00
02 TRABAJOS PRELIMINARES S/. 44,779.98
02.01 LIMPIEZA DE TERRENO NORMAL M2 10,613.29 0.46 S/. 4,882.11 10,613.29 4,882.11
02.02 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIAS Y EQUIPOS GLB 1.00 4,661.74 S/. 4,661.74 0.50 2,330.87
02.03 TRAZO Y REPLANTEO PRELIMINAR M2 10,613.29 1.40 S/. 14,858.61 10,613.29 14,858.61
02.04 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE LA OBRA M2 10,613.29 1.92 S/. 20,377.52 10,613.29 20,377.52
03 MOVIMIENTO DE TIERRAS S/. 520,348.51
03.01 CORTE EN MATERIAL COMPACTO A NIVEL DE SUBRASANTE M3 6,535.55 8.31 S/. 54,310.42 6,535.55 54,310.42
03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 8,481.81 11.39 S/. 96,607.82 8,481.81 96,607.82
03.03 PERFILADO Y COMPACTADO DE SUB-RASANTE M2 10,613.29 5.49 S/. 58,266.96 10,613.29 58,266.96
03.04 CONFORMACION Y COMPACTACION DE BASE GRANULAR E=0.25M M2 10,613.29 29.29 S/. 310,863.26 5,434.00 159,161.86
03.05 RELLENO CON MATERIAL PROPIO M3 11.08 27.08 S/. 300.05 11.08 300.05
04 PAVIMENTO S/. 992,414.67
04.01 DEMOLICION DE PAVIMENTO DE CONCRETO M2 10,385.00 3.41 S/. 35,412.85 -
04.02 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO M2 1,503.78 38.17 S/. 57,399.28 -
04.03 CONCRETO F´CR=245KG/CM2 M2 7,437.85 116.63 S/. 867,476.45 -
04.04 CURADO DE CONCRETO M2 7,437.85 1.13 S/. 8,404.77 -
04.05 JUNTAS ASFALTICAS M 4,501.20 5.27 S/. 23,721.32 -
05 VEREDAS Y RAMPAS S/. 137,920.22
05.01 MOVIMIENTO DE TIERRAS S/. 36,675.24
05.01.01 DEMOLICION DE VEREDAS EXISTENTES M2 1,291.00 3.41 S/. 4,402.31 1,291.00 4,402.31
05.01.02 EXCAVACION MANUAL DE TERRENO A NIVEL DE SUBRASANTE M3 206.74 21.75 S/. 4,496.60 -
05.01.03 ACARREO DE MATERIAL EXCEDENTE M3 268.77 8.88 S/. 2,386.68 -
05.01.04 NIVELACION Y COMPACTACION DE SUBRASANTE CON EQUIPO LIVIANO M2 2,067.44 1.40 S/. 2,894.42 -
120%
80%
77.5%
60%
43.8%
40%
23.9%
20% 20.1%
7.8%
7.5%
0% 0.0%
MONTOS TOTAL (Inc/ IGV) PORCENTAJES MONTOS TOTAL (Inc/ IGV) PORCENTAJES
Items AÑO MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
0.00 0.00 0.00% 0.00% DEL 14 DICIEMBRE 2016 0.00 0.00 0.00% 0.00%
001 2018 AL 31 AGOSTO 175,933.55 175,933.55 7.49% 7.49% AL 31 AGOSTO 183,927.44 183,927.44 7.83% 7.83%
002 2018 AL 30 SETIEMBRE 385,438.58 561,372.13 16.40% 23.89% AL 30 SETIEMBRE 556,128.64 740,056.08 12.26% 20.08%
003 2018 AL 31 OCTUBRE 1,258,625.60 1,819,997.73 53.57% 77.46% AL 31 OCTUBRE 556,128.64 1,296,184.72 23.67% 43.75%
004 2018 AL 30 NOVIEMBRE 500,263.27 2,320,261.00 21.29% 98.75% AL 30 NOVIEMBRE
005 2018 AL 29 DICIEMBRE 29,436.16 2,349,697.16 1.25% 100.00% AL 29 DICIEMBRE
245 GLB 0.08 20.08% 23.67% 43.75% 2,346,697.00 148,426.00 0.00 515,183.42 1,683,087.58 0 0.00 0.00 0.00
TOTAL
STOS
SALDO MES
SIGUIENTE
0
FORMATO N° 03
TOTAL AVANCE
EJECUCION REAL
ANALITICA (%)
(6)=(4)+(5)
107724.96 19.07%
340358.46 22.46%
67100 25.20%
515,183.42 21.95%
FUNCION : VIVIENDA
019 019 VIVIENDA Y DESARROLLO
Y DESARROLLO URBANO
URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE AN
PROYECTO
AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE
041 DESARROLLO URBANO
META 245
FECHA 31 DE OCTUBRE 2018
CONSUMO (EGRESO)
CODIGO PRECIO
DESCRIPCION UND COSTO DIRECTO GASTOS GENERALES
ANALITICO UNITARIO Cantidad Parcial Cantidad Parcial
COMBUSTIBLE
1 PETROLEO GALON 12.50 1185 14812.50
2 PETROLEO DEV. HUANTA LURICOCHA GALON 12.50 400 5000.00
3 GASOLINA GALON 12.99 126 1636.74
MATERIALES DE CONSTRUCCION
4 MATERIAL AFIRMADO M3 36.0 900 32400.00
5 MATERIAL AFIRMADO M3 36.0 900 32400.00
6 MATERIAL AFIRMADO M3 36.00 900 32400.00
7 MATERIAL AFIRMADO M3 36.00 759 27324.00
8 PIEDRA CHANCADA DE 3/4" M3 49.00 457 22393.00
9 PIEDRA CHANCADA DE 3/4" M3 49.00 398 19502.00
10 PIEDRA CHANCADA DE 3/4" M3 49.00 0 0.00
11 ARENA GRUESA M3 48.00 382 18336.00
12 ARENA GRUESA M3 48.00 321.5 15432.00
13 ARENA GRUESA M3 48.00 0 0.00
14 CEMENTO BOLSA 15.00 6143 92145.00
15 CEMENTO BOLSA 15.00 5657 84855.00
16 CEMENTO BOLSA 15.00 0 0.00
17 CLAVO DE 4" KILO 4.50 20 90.00
18 CLAVO DE 4" KILO 4.50 23 103.50
19 CLAVO DE 3" KILO 4.50 23 103.50
20 CLAVO DE 3" KILO 4.50 90 405.00
21 CLAVO DE 2 1/2" KILO 4.50 26 117.00
22 CLAVO DE 2 1/2" KILO 4.50 22 99.00
23 CLAVO DE 2" KILO 4.50 17 76.50
24 CLAVO DE 2" KILO 4.50 0 0.00
25 CLAVO DE 1" KILO 6.50 8 52.00
26 CLAVO DE CALAMINA KILO 6.50 15 97.50
27 ALAMBRE NEGRO N°16 KILO 5.00 42 210.00
28 ALAMBRE NEGRO N° 16 KILO 5.00 0 0.00
29 ALAMBRE NEGRO N°8 KILO 5.00 20 100.00
30 ALAMBRE NEGRO N°8 KILO 5.00 170 850.00
31 ABRAZADERA PVC DE 6" A 1/2" CONSY UNIDAD 45.00 0 0.00
32 ADAPTADOR PVC DE 3/4" C-10 UNIDAD 3.50 0 0.00
33 ADAPTADOR DE PVC DE 1/2"C-10 UNIDAD 2.00 0 0.00
34 ALDABA GALVANIZADA 3 1/2" OYUSTU UNIDAD 5.00 0 0.00
35 COSTALES UNIDAD 1.00 0 0.00
36 CABEZA DE DUCHA CROMADA UNIDAD 28.00 0 0.00
FORMATO N° 05
FUNCION : VIVIENDA
019 019 VIVIENDA Y DESARROLLO
Y DESARROLLO URBANO
URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE AN
PROYECTO
AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE
041 DESARROLLO URBANO
META 245
FECHA 31 DE OCTUBRE 2018
CONSUMO (EGRESO)
CODIGO PRECIO
DESCRIPCION UND COSTO DIRECTO GASTOS GENERALES
ANALITICO UNITARIO Cantidad Parcial Cantidad Parcial
37 CABLE THW 7 HILOS X 100 MT N°12 ROLLO 180.00 0 0.00
38 CABLE THW 7 HILOS X 100 MT N°14 ROLLO 120.00 0 0.00
39 CADENA DE 3/8" PRODAC METRO 25.00 0 0.00
40 LLAVE TERMOMAGNETICA DE 32 AMP UNIDAD 45.00 0 0.00
41 CAJA PVC PARA LLAVE TERMOMAGNETI UNIDAD 15.00 0 0.00
42 CANDADO N° 40 CANTOL UNIDAD 38.00 0 0.00
43 CANDADO N° 50 CANTOL UNIDAD 48.00 0 0.00
44 CAÑO ESFERICO UNIDAD 10.00 0 0.00
45 PUNTA DE FIERRO CORRUGADO UNIDAD 10.00 0 0.00
46 CINTA AISLANTE 3M UNIDAD 4.00 2 8.00
47 CINTA TEFLON UNIDAD 1.50 4 6.00
48 CODO MIXTO DE PVC SAP DE 1/2" PAV UNIDAD 2.00 0 0.00
49 CODO DE PVC SAL DE 2" X 90° PAVCO UNIDAD 2.50 0 0.00
50 CODO DE PVC SAL DE 4" X 90° PAVCO UNIDAD 8.50 0 0.00
51 CORTAVIENTO EN TELA DRILL UNIDAD 10.00 0 0.00
52 CUELLO DE CERA PARA INODORO MET UNIDAD 12.00 0 0.00
53 CURVA DE 1/2" PVC PAVCO C-10 UNIDAD 2.50 0 0.00
54 ENGRASADORA DE METAL TRUPER UNIDAD 50.00 0 0.00
55 FOCO AHORRADOR LET DE 15 WATS UNIDAD 18.00 0 0.00
56 GUANTES DE CUERO BADANA - CLUTE UNIDAD 14.00 0 0.00
57 HOJA DE SIERRA UNIDAD 5.50 1 5.50
58 INFLADOR TRUPER UNIDAD 25.00 0 0.00
59 INTERRUTOR DOBLE SPARK UNIDAD 25.00 0 0.00
60 REFLECTOR LED DE 200 W NOVALAMP UNIDAD 480.00 0 0.00
61 LINTERNA RECARGABLE PROFIELD UNIDAD 28.00 0 0.00
62 LLAVE CORPORATION DE PVC DE 1/2" UNIDAD 15.00 1 15.00
63 LLAVE DE PASO DE PVC DE 1/2" JET UNIDAD 10.00 2 20.00
64 MANGUERA DE 3/4" X 100 MT ROLLO 140.00 0 0.00
65 MANTA ARPILLERA X 2 MT DE ANCHO X UNIDAD 750.00 0 0.00
66 PEGAMENTO PVC OATEY GALON 120.00 0 0.00
67 PLASTICO DOBLE ANCHO X100 METRO ROLLO 700.00 1 700.00
68 PONCHO PVC PARA LLUVIA C/AMARILL UNIDAD 32.00 0 0.00
69 REDUCCION PVC DE 3/ 4" A 1/ 2" PAVC UNIDAD 5.00 0 0.00
70 REDUCCION PVC DE 4" X 2" PAVCO UNIDAD 5.00 0 0.00
71 SILBATO PARA VIGILANTE TIPO POLICI UNIDAD 1.50 0 0.00
72 SOQUETE COLGANTE SPARK UNIDAD 2.00 0 0.00
73 TEE PVC DE 4" UNIDAD 8.50 0 0.00
74 TEE PVC DE 4" A 2" UNIDAD 8.50 0 0.00
FORMATO N° 05
FUNCION : VIVIENDA
019 019 VIVIENDA Y DESARROLLO
Y DESARROLLO URBANO
URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE AN
PROYECTO
AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE
041 DESARROLLO URBANO
META 245
FECHA 31 DE OCTUBRE 2018
CONSUMO (EGRESO)
CODIGO PRECIO
DESCRIPCION UND COSTO DIRECTO GASTOS GENERALES
ANALITICO UNITARIO Cantidad Parcial Cantidad Parcial
75 TEE PVC DE 3/4" UNIDAD 3.50 0 0.00
76 TOMACORRIENTE DOBLE SPARK UNIDAD 8.00 0 0.00
77 TUBO PVC DE 3/4" CON ROSCA C-10 UNIDAD 22.00 0 0.00
78 TUBO PVC SAL DE 2" UNIDAD 12.00 0 0.00
79 TUBO PVC SAL DE 4" UNIDAD 25.00 0 0.00
80 TUBO PVC DE 1/2" C/R C-10 UNIDAD 16.00 3 48.00
81 WINCHA DE METAL TRUPER DE 50 MT UNIDAD 55.00 1 55.00
82 YEE PVC SAL 4" X 4" UNIDAD 12.00 0 0.00
83 YEE PVC SAL 4" X 2" UNIDAD 8.50 0 0.00
84 BOLSA DE YESO X 25 KG UNIDAD 10.00 2 20.00
85 BARRETA DE ACERO 1" X 1.80 MT ORE UNIDAD 60.00 0 0.00
86 CILINDROS METALICOS UNIDAD 60.00 10 600.00
87 TIMBOS DE PLASTICO X 55 GL UNIDAD 110.00 0 0.00
88 PUNTAS DE 1" X 12" EXAGONAL UNIDAD 15.00 3 45.00
89 CINTA DE SEÑALIZACION C/ROJO Y AM UNIDAD 40.00 1 40.00
90 COMBA DE 12 LIBRAS ORE UNIDAD 70.00 0 0.00
91 COMBA DE 6 LIBRAS ORE UNIDAD 44.00 9 396.00
92 CONO DE SEÑALIZACION NARANJA DE UNIDAD 40.00 0 0.00
93 DISCO DE CORTE DE METAL DE 7" UNIDAD 9.00 10 90.00
94 AMOLADORA ANGULAR DE 7" UNIDAD 490 1 490.00
95 DISCO DE CORTE DE MADERA DE 7" UNIDAD 19.00 5 95.00
96 HOJA DE SIERRA SANDFLEX UNIDAD 5.50 14 77.00
97 CUBO DE 250 GALONES DE PVC UNIDAD 440.00 6 2640.00
98 NIVEL DE MANO DE 18" UNIDAD 34.00 2 68.00
99 REGLA DE ALUMINIO 1 1/2" X 4" X 6 M UNIDAD 120.00 2 240.00
100 BIDON DE AGUA DE 2O LITROS ANGEL UNIDAD 39.00 33 1287.00
101 CILINDROS METALICOS RECICLABLES UNIDAD 110.00 0 0.00
102 SURTIDOR DE AGUA PARA BIDON DE 2 UNIDAD 37.00 0 0.00
103 MALLA DE SEGURIDAD L = 45 MT X 1 UNIDAD 55.00 5 275.00
104 PALETAS DE MADERA PARE Y SIGA UNIDAD 16.00 0 0.00
105 EXTINTOR DE POLVO QUIMICO SECO D UNIDAD 80.00 1 80.00
106 TEKNOPORT DE 1.2 X 2.40 X 1" UNIDAD 17.50 57 997.50
107 MANTA ARPILLERA X 2 MT DE ANCHO X UNIDAD 600.00 1 600.00
108 TELA YUTE DE 1 DE ANCHO X 100MT D UNIDAD 450.00 0 0.00
109 VARILLA DE FIERRO CORRUGADO DE 1 VARILLA 29.50 90 2655.00
110 CALAMINA GALVANIZADA DE 0.30 X 3.6 UNIDAD 38.00 61 2318.00
111 CALAMINA GALVANIZADA DE 1.80 X 0.8 UNIDAD 15.90 40 636.00
112 TRIPLAY DE 18 MM M/LUPUNA UNIDAD 129.00 43 5547.00
FORMATO N° 05
FUNCION : VIVIENDA
019 019 VIVIENDA Y DESARROLLO
Y DESARROLLO URBANO
URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE AN
PROYECTO
AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE
041 DESARROLLO URBANO
META 245
FECHA 31 DE OCTUBRE 2018
CONSUMO (EGRESO)
CODIGO PRECIO
DESCRIPCION UND COSTO DIRECTO GASTOS GENERALES
ANALITICO UNITARIO Cantidad Parcial Cantidad Parcial
113 TRIPLAY DE 4 MM M /LUPUNA UNIDAD 36.50 50 1825.00
114 TRIPLAY DE 6MM M/LUPUNA UNIDAD 49.60 34 1686.40
115 MADERA TORNILLO DE 1" X 8" X 10P UNIDAD 36.00 264 9504.00
116 MADERA TORNILLO DE 1" X 10" X 10P UNIDAD 45.00 350 15750.00
117 MADERA TORNILLO DE 2" X 2" X 10P UNIDAD 18.00 300 5400.00
118 MADERA TORNILLO DE 3" X 2" X 10P UNIDAD 27.00 250 6750.00
119 MADERA TORNILLO DE 1" X 8" X 10P UNIDAD 36.00 0 0.00
120 MADERA TORNILLO DE 1" X 10" X 10P UNIDAD 45.00 87 3915.00
121 MADERA TORNILLO DE 2" X 2" X 10P UNIDAD 18.00 300 5400.00
122 MADERA TORNILLO DE 3" X 2" X 10P UNIDAD 27.00 200 5400.00
123 ESCOBILLON HUDE UNIDAD 20.00 6 120.00
124 BOLSA DE YESO X 25 KG UNIDAD 10.00 0 0.00
125 TELA FRANELA NACIONAL UNIDAD 6.00 10 60.00
REPUESTOS, ACSESORIOS DE MAQUINARIAS, VESTUARIO Y UTILES
RODILLO VIBRATORIO LISO CS - 533E
126 BALDE DE ACEITE DE MOTOR 15 W 40 BALDE 400.00 1 400.00
127 FILTRO DE ACEITE DE MOTOR 7W - 23 UNIDAD 120.00 1 120.00
128 FILTRO DE AIRE SECUNDARIO 206 - 56 UNIDAD 380.00 1 380.00
129 FILTRO DE AIRE PRIMARIO 206 - 5234 UNIDAD 390.00 1 390.00
130 FILTRO DE COMBUSTIBLE 1R - 1804 UNIDAD 130.00 1 130.00
131 FILTRO PRIMARIO DE COMBUSTIBLE 36UNIDAD 420.00 1 420.00
132 BALDE DE GRASA CAT EP2 UNIDAD 890.00 1 890.00
MOTONIVELADORA CAT 140K
133 SWITCH AS - ROCKET (24 VOLT)COD. 3 UNIDAD 950.00 1 950.00
134 LINK - CONMECTING COD.6G-1631 UNIDAD 5200.00 4 20800.00
135 RETEN SEAL O RING COD 8H - 2046 UNIDAD 75.00 1 75.00
136 CHAIN GP (TANDEM) COD. 6G 1633 UNIDAD 350.00 4 1400.00
CAMION CISTERNA EGG - 876
137 BALDE DE ACEITE DE MOTOR 15 W 40 BALDE 310.00 2 620.00
138 FILTRO DE ACEITE DE MOTOR LF-367 UNIDAD 180.00 1 180.00
139 FILTRO DE AIRE SECUNDARIO AFL-25 UNIDAD 380.00 1 380.00
140 FILTRO DE AIRE PRIMARIO AFL -2501 UNIDAD 490.00 1 490.00
141 FILTRO DE COMBUSTIBLE FF5269 FLE UNIDAD 140.00 1 140.00
142 FILTRO SEPARADOR DE AGUA COD.FS-1UNIDAD 180.00 1 180.00
143 UNA LATA DE SOLDADURA SELLOCOR UNIDAD 480.00 1 480.00
VOLQUETE VOLVO XQ - 1598
144 BALDE DE ACEITE DE MOTOR 25 W 50 UNIDAD 320.00 2 640.00
145 FILTRO DE ACEITE DE MOTOR LF 4666 UNIDAD 75.00 2 150.00
FORMATO N° 05
FUNCION : VIVIENDA
019 019 VIVIENDA Y DESARROLLO
Y DESARROLLO URBANO
URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE AN
PROYECTO
AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE
041 DESARROLLO URBANO
META 245
FECHA 31 DE OCTUBRE 2018
CONSUMO (EGRESO)
CODIGO PRECIO
DESCRIPCION UND COSTO DIRECTO GASTOS GENERALES
ANALITICO UNITARIO Cantidad Parcial Cantidad Parcial
146 FILTRO DE AIRE PRIMARIO Y SECUNDA UNIDAD 980.00 1 980.00
147 FILTRO DE COMBUSTIBLE FF5018 UNIDAD 48.00 2 96.00
148 FILTRO SEPARADOR DE AGUA LFWP90 UNIDAD 210.00 1 210.00
149 JUEGO DE PINES Y BOCINAS DE MUEL UNIDAD 260.00 6 1560.00
VESTUARIO
150 CASACA PARA PERSONAL TEC. GZUCK. UNIDAD 300.00 9 2700.00
151 CHALECO PARA PERSONAL TEC. LOGO UNIDAD 120.00 12 1440.00
152 CORTAVIENTO DE DRIL PARA USO DEB UNIDAD 10.00 38 380.00
153 UNIFORME PARA PERSONAL OBRERO 2 UNIDAD 68.00 37 2516.00
154 ZAPATOS PUNTA DE ACERO CAT UNIDAD 450.00 10 4500.00
155 BARBIQUEJO DE PLASTICO PARA CASC UNIDAD 2.50 33 82.50
156 BOTAS DE JEBE CAÑA ALTA RAMBO PAR 40.00 6 240.00
157 CASCO DE DE SEGURIDAD DE PLASTIC UNIDAD 14.00 29 406.00
158 CASCO DE SEGURIDAD COLOR BLANCO UNIDAD 50.00 5 250.00
159 GUANTES DE CUERO BADANA CLUTE PAR 14.00 60 840.00
160 GUANTES DE JEBE C-35 PROTEX PAR 15.00 14 210.00
161 LENTES DE PROTECCION TRANSPAREN UNIDAD 15.00 16 240.00
162 LENTES DE PROTECCION PARA PERSONUNIDAD 40.00 7 280.00
163 CAPOTIN IMPERMEABLE DE PLASTICO UNIDAD 32.00 48 1536.00
164 RESPIRADOR CONTRA POLVO 3M UNIDAD 15.00 26 390.00
165 TAPON DE OIDO CON PORTA ESTUCHE UNIDAD 10.00 0 0.00
166 ZAPATO DE SEGURIDAD PUNTA DE AC PAR 70.00 37 2590.00
UTILES DE ESCRITORIO
167 MEMORIA PORTATILUSB DE 32 GB - K UNIDAD 70.00
168 PIZARRA ACRILICA DE 2M DE LARGO X UNIDAD 190.00
169 PERFORADOR DE 2 ESPIGAS PARA 100 UNIDAD 136.00
170 ARCHIVADOR PLASTIFICADO PALANCA UNIDAD 3.52
171 LAPICERO PUNTA FINA FABER CASTELL UNIDAD 0.32
172 LAPICERO PUNTA FINA FABER CASTEL UNIDAD 0.32
173 LAPICERO PUNTA FINA FABER CASTELL UNIDAD 0.32
174 BORRADOR PARA LAPIZ ARTESCO UNIDAD 0.45
175 CORRECTOR LIQUIDO FABER CASTELL UNIDAD 1.12
176 ENGRAPADOR DE METAL T/ALICATE P-1UNIDAD 15.00
177 FOLDER MANILA T/A-4 GALLO EMPX 25 4.72
178 GOMA EN BARRA X 20 G APROX. CONT. UNIDAD 1.73
179 GRAPA 26/6 X 5000 ARTESCO UNIDAD 1.77
180 LAPIZ NEGRO GRADO 28 FABER CASTE UNIDAD 0.43
181 PAPEL BOND 80 GR TAMAÑO A/4 ATLASEMPX 500 12.60
FORMATO N° 05
FUNCION : VIVIENDA
019 019 VIVIENDA Y DESARROLLO
Y DESARROLLO URBANO
URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE AN
PROYECTO
AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE
041 DESARROLLO URBANO
META 245
FECHA 31 DE OCTUBRE 2018
CONSUMO (EGRESO)
CODIGO PRECIO
DESCRIPCION UND COSTO DIRECTO GASTOS GENERALES
ANALITICO UNITARIO Cantidad Parcial Cantidad Parcial
182 PLUMON PARA PIZARRA ACRILICA C/AZ UNIDAD 2.60
183 PLUMON PARA PIZARRA ACRILICA C/ROUNIDAD 2.60
184 PLUMON PARA PIZARRA ACRILICA C/NE UNIDAD 2.60
185 PLUMON RESALTADOR PUNTA FINA C/AUNIDAD 1.70
186 SUJETADOR FASTENER ARTESCO EMPX 50 2.57
187 TAMPON CON CUBIERTA TAMAÑO GRANUNIDAD 2.35
188 CUADERNO CUADRICULADO T/A4 100 HUNIDAD 3.16 4 12.64
189 CUADERNO DE OBRA T/A4 100H CONT UNIDAD 11.69
PRESTAMO DE MATERIALES DE LA OBRA TACNA
190 PAQUETES DE ESPONJA X 36 UND C/U UNIDAD 1
191 LACA SELLADORA DUCOLAC GALON 5
192 NYLON VIKINGO X 100 MT UNIDAD 1
193 BROCHAS DE 2" TUMI UNIDAD 2
194 LLANTAS DE BUGUI TRUPER UNIDAD 0
195 COMBA DE 18 LIBRAS UNIDAD 0
196 EXTINTORES DE 6KG C/UNO UNIDAD 0
197 ACEITE SHELL 20 W 50 X 1 LITRO C/U UNIDAD 2
198 LIJA DE FIERRO N°40 UNIDAD 7
199 ESCOBA DE CERDA PLASTICA UNIDAD 0
200 SOGA DE NYLON DE 1/2" METRO 0
201 PEGAMENTO PVC OATEY GALON 0
202 CAPUCHONES DE SEGURIDAD UNIDAD 0
203 PALAS TIPO CUCHARA FOR GROUP UNIDAD 9
204 PICOS FOR GROUP UNIDAD 17
205 PLASTICO DOBLE ANCHO X10 METROS METRO 5
206 CARRETILLAS TIPO BUGUI UNIDAD 3
207 CLAVO CON CABEZA DE 2 1/2" KILO 0
208 CLAVO CON CABEZA DE 2" KILO 0
209 PINTURAS EN SPRAY X 400 ML C/UNO UNIDAD 2
210 TECNOPORT DE 1" UNIDAD 7
211 ASFALTO RC - 250 GALON 0
212 TRIPLAY DE 6MM UNIDAD 9
213 ARCHIVADORES A-4 ARTESCO UNIDAD 0
214 PLUMONES MARCADORES FABER CASTEUNIDAD 2
215 PERFORADOR ARTESCO M 73 UNIDAD 0
216 TIZAS DE C/BLANCO X 50 UNIDADES CAJITA 1
217 CINTA MASKING DE 2" UNIDAD 0
218 GRAPAS ARTESCO CAJITA 1
FORMATO N° 05
FUNCION : VIVIENDA
019 019 VIVIENDA Y DESARROLLO
Y DESARROLLO URBANO
URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE AN
PROYECTO
AVELINO CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE
041 DESARROLLO URBANO
META 245
FECHA 31 DE OCTUBRE 2018
CONSUMO (EGRESO)
CODIGO PRECIO
DESCRIPCION UND COSTO DIRECTO GASTOS GENERALES
ANALITICO UNITARIO Cantidad Parcial Cantidad Parcial
219 MASCARILLA CON FILTRO UNIDAD 7
220 CASCOS DE COLOR UNIDAD 2
221 PONCHO PVC PARA LLUVIA C/AMARILL UNIDAD 0
222 BOTAS DE JEBE PAR 0
223 ZAPATO PUNTA DE ACERO NACIONAL PAR 0
224 LENTES DE PROTECCION CLUTE UNIDAD 20
225 PROTECTORES AUDITIVOS UNIDAD 1
226 CURE BAND VENDITAS X 100 UND UNIDAD 0
227 GEL DICLOFENACO UNIDAD 1
228 SULFACREM UNIDAD 1
229 ALCOHOL DE 1000 ML UNIDAD 1
230 AGUA OXIGENADA DE 500 ML UNIDAD 1
TOTAL
S, DISTRITO DE ANDRÉS
CONSUMO
TOTAL
S/. 21,449.24
S/. 14,812.50
S/. 5,000.00
S/. 1,636.74
S/. 455,355.40
S/. 32,400.00
S/. 32,400.00
S/. 32,400.00
S/. 27,324.00
S/. 22,393.00
S/. 19,502.00
S/. 0.00
S/. 18,336.00
S/. 15,432.00
S/. 0.00
S/. 92,145.00
S/. 84,855.00
S/. 0.00
S/. 90.00
S/. 103.50
S/. 103.50
S/. 405.00
S/. 117.00
S/. 99.00
S/. 76.50
S/. 0.00
S/. 52.00
S/. 97.50
S/. 210.00
S/. 0.00
S/. 100.00
S/. 850.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO
S, DISTRITO DE ANDRÉS
CONSUMO
TOTAL
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 8.00
S/. 6.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 5.50
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 15.00
S/. 20.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 700.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO
S, DISTRITO DE ANDRÉS
CONSUMO
TOTAL
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 48.00
S/. 55.00
S/. 0.00
S/. 0.00
S/. 20.00
S/. 0.00
S/. 600.00
S/. 0.00
S/. 45.00
S/. 40.00
S/. 0.00
S/. 396.00
S/. 0.00
S/. 90.00
S/. 490.00
S/. 95.00
S/. 77.00
S/. 2,640.00
S/. 68.00
S/. 240.00
S/. 1,287.00
S/. 0.00
S/. 0.00
S/. 275.00
S/. 0.00
S/. 80.00
S/. 997.50
S/. 600.00
S/. 0.00
S/. 2,655.00
S/. 2,318.00
S/. 636.00
S/. 5,547.00
ADO
S, DISTRITO DE ANDRÉS
CONSUMO
TOTAL
S/. 1,825.00
S/. 1,686.40
S/. 9,504.00
S/. 15,750.00
S/. 5,400.00
S/. 6,750.00
S/. 0.00
S/. 3,915.00
S/. 5,400.00
S/. 5,400.00
S/. 120.00
S/. 0.00
S/. 60.00
S/. 50,674.14
S/. 2,730.00
S/. 400.00
S/. 120.00
S/. 380.00
S/. 390.00
S/. 130.00
S/. 420.00
S/. 890.00
S/. 23,225.00
S/. 950.00
S/. 20,800.00
S/. 75.00
S/. 1,400.00
S/. 2,470.00
S/. 620.00
S/. 180.00
S/. 380.00
S/. 490.00
S/. 140.00
S/. 180.00
S/. 480.00
S/. 3,636.00
S/. 640.00
S/. 150.00
ADO
S, DISTRITO DE ANDRÉS
CONSUMO
TOTAL
S/. 980.00
S/. 96.00
S/. 210.00
S/. 1,560.00
S/. 18,600.50
S/. 2,700.00
S/. 1,440.00
S/. 380.00
S/. 2,516.00
S/. 4,500.00
S/. 82.50
S/. 240.00
S/. 406.00
S/. 250.00
S/. 840.00
S/. 210.00
S/. 240.00
S/. 280.00
S/. 1,536.00
S/. 390.00
S/. 0.00
S/. 2,590.00
S/. 12.64
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO
S, DISTRITO DE ANDRÉS
CONSUMO
TOTAL
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
12.64
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
ADO
S, DISTRITO DE ANDRÉS
CONSUMO
TOTAL
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 0.00
S/. 527,478.78
ALMACENERO
Firma y Sello
FORMATO N° 06
HOJA DE TAREO
No VALOR
DESCRIPCION O/C UNID. CANT.
Ord. UNID.
COMBUSTIBLE
1 PETROLEO PRESTAMO GALON 215 12.5
2 PETROLEO DEV. HUANTA LURICOCHA DEVOLUCION GALON 0 12.5
3 GASOLINA PRESTAMO GALON 4 12.99
MATERIALES DE CONSTRUCCION
4 MATERIAL AFIRMADO 2091 M3 0 36
5 MATERIAL AFIRMADO 2061 M3 0 36
6 MATERIAL AFIRMADO 1986 M3 0 36.00
7 MATERIAL AFIRMADO M3 150 36.00
8 PIEDRA CHANCADA DE 3/4" 2112 M3 0 49.00
9 PIEDRA CHANCADA DE 3/4" 2084 M3 59 49.00
10 PIEDRA CHANCADA DE 3/4" 2015 M3 457 49.00
11 ARENA GRUESA 2111 M3 0 48.00
12 ARENA GRUESA 2085 M3 60.5 48.00
13 ARENA GRUESA 2012 M3 382 48.00
14 CEMENTO 2005 BOLSA 0 15.00
15 CEMENTO 2016 BOLSA 486 15.00
16 CEMENTO 2093 BOLSA 6143 15.00
17 CLAVO DE 4" 1711 KILO 0 4.50
18 CLAVO DE 4" 1675 KILO 7 4.50
19 CLAVO DE 3" 1711 KILO 0 4.50
20 CLAVO DE 3" 1675 KILO 0 4.50
21 CLAVO DE 2 1/2" 1711 KILO 0 4.50
22 CLAVO DE 2 1/2" 1675 KILO 98 4.50
23 CLAVO DE 2" 1711 KILO 7 4.50
24 CLAVO DE 2" 1675 KILO 120 4.50
25 CLAVO DE 1" 1711 KILO 18 6.50
26 CLAVO DE CALAMINA 1711 KILO 6 6.50
27 ALAMBRE NEGRO N°16 1711 KILO 53 5.00
28 ALAMBRE NEGRO N° 16 1675 KILO 200 5.00
29 ALAMBRE NEGRO N°8 1711 KILO 0 5.00
30 ALAMBRE NEGRO N°8 1675 KILO 130 5.00
31 ABRAZADERA PVC DE 6" A 1/2" CONSYSA 1711 UNIDAD 6 45.00
32 ADAPTADOR PVC DE 3/4" C-10 1711 UNIDAD 0 3.50
33 ADAPTADOR DE PVC DE 1/2"C-10 1711 UNIDAD 1 2.00
34 ALDABA GALVANIZADA 3 1/2" OYUSTUL 1711 UNIDAD 0 5.00
35 COSTALES 1711 UNIDAD 0 1.00
36 CABEZA DE DUCHA CROMADA 1711 UNIDAD 0 28.00
37 CABLE THW 7 HILOS X 100 MT N°12 1711 ROLLO 0 180.00
38 CABLE THW 7 HILOS X 100 MT N°14 1711 ROLLO 4 120.00
39 CADENA DE 3/8" PRODAC 1711 METRO 0 25.00
40 LLAVE TERMOMAGNETICA DE 32 AMP 1711 UNIDAD 0 45.00
41 CAJA PVC PARA LLAVE TERMOMAGNETICA KBA 1711 UNIDAD 0 15.00
42 CANDADO N° 40 CANTOL 1711 UNIDAD 0 38.00
43 CANDADO N° 50 CANTOL 1711 UNIDAD 0 48.00
FORMATO N° 09
SALDO DE MATERIALES VALORIZADOS DE OBRA
FUNCION : 019 VIVIENDA Y DESARROLLO URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE A
PROYECTO :
CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE041 DESARROLLO URBANO
META : 245
FECHA : 31 DE OCTUBRE 2018
No VALOR
DESCRIPCION O/C UNID. CANT.
Ord. UNID.
44 CAÑO ESFERICO 1711 UNIDAD 1 10.00
45 PUNTA DE FIERRO CORRUGADO 1711 UNIDAD 0 10.00
46 CINTA AISLANTE 3M 1711 UNIDAD 1 4.00
47 CINTA TEFLON 1711 UNIDAD 4 1.50
48 CODO MIXTO DE PVC SAP DE 1/2" PAVCO 1711 UNIDAD 2 2.00
49 CODO DE PVC SAL DE 2" X 90° PAVCO 1711 UNIDAD 0 2.50
50 CODO DE PVC SAL DE 4" X 90° PAVCO 1711 UNIDAD 0 8.50
51 CORTAVIENTO EN TELA DRILL 1711 UNIDAD 0 10.00
52 CUELLO DE CERA PARA INODORO METUSA 1711 UNIDAD 0 12.00
53 CURVA DE 1/2" PVC PAVCO C-10 1711 UNIDAD 0 2.50
54 ENGRASADORA DE METAL TRUPER 1711 UNIDAD 0 50.00
55 FOCO AHORRADOR LET DE 15 WATS 1711 UNIDAD 0 18.00
56 GUANTES DE CUERO BADANA - CLUTE 1711 UNIDAD 0 14.00
57 HOJA DE SIERRA 1711 UNIDAD 0 5.50
58 INFLADOR TRUPER 1711 UNIDAD 1 25.00
59 INTERRUTOR DOBLE SPARK 1711 UNIDAD 0 25.00
60 REFLECTOR LED DE 200 W NOVALAMPS 1711 UNIDAD 0 480.00
61 LINTERNA RECARGABLE PROFIELD 1711 UNIDAD 0 28.00
62 LLAVE CORPORATION DE PVC DE 1/2"CONSYSA 1711 UNIDAD 5 15.00
63 LLAVE DE PASO DE PVC DE 1/2" JET 1711 UNIDAD 3 10.00
64 MANGUERA DE 3/4" X 100 MT 1711 ROLLO 0 140.00
65 MANTA ARPILLERA X 2 MT DE ANCHO X 200 LARGO 1711 UNIDAD 0 750.00
66 PEGAMENTO PVC OATEY 1711 GALON 0 120.00
67 PLASTICO DOBLE ANCHO X100 METROS 1711 ROLLO 0 700.00
68 PONCHO PVC PARA LLUVIA C/AMARILLO 1711 UNIDAD 10 32.00
69 REDUCCION PVC DE 3/ 4" A 1/ 2" PAVCO 1711 UNIDAD 0 5.00
70 REDUCCION PVC DE 4" X 2" PAVCO 1711 UNIDAD 0 5.00
71 SILBATO PARA VIGILANTE TIPO POLICIA 1711 UNIDAD 0 1.50
72 SOQUETE COLGANTE SPARK 1711 UNIDAD 0 2.00
73 TEE PVC DE 4" 1711 UNIDAD 1 8.50
74 TEE PVC DE 4" A 2" 1711 UNIDAD 0 8.50
75 TEE PVC DE 3/4" 1711 UNIDAD 0 3.50
76 TOMACORRIENTE DOBLE SPARK 1711 UNIDAD 0 8.00
77 TUBO PVC DE 3/4" CON ROSCA C-10 1711 UNIDAD 0 22.00
78 TUBO PVC SAL DE 2" 1711 UNIDAD 1 12.00
79 TUBO PVC SAL DE 4" 1711 UNIDAD 5 25.00
80 TUBO PVC DE 1/2" C/R C-10 1711 UNIDAD 13 16.00
81 WINCHA DE METAL TRUPER DE 50 MT 1711 UNIDAD 0 55.00
82 YEE PVC SAL 4" X 4" 1711 UNIDAD 0 12.00
83 YEE PVC SAL 4" X 2" 1711 UNIDAD 2 8.50
84 BOLSA DE YESO X 25 KG 1711 UNIDAD 0 10.00
85 BARRETA DE ACERO 1" X 1.80 MT ORE 1695 UNIDAD 0 60.00
86 CILINDROS METALICOS 1695 UNIDAD 0 60.00
87 TIMBOS DE PLASTICO X 55 GL 1695 UNIDAD 6 110.00
FORMATO N° 09
SALDO DE MATERIALES VALORIZADOS DE OBRA
FUNCION : 019 VIVIENDA Y DESARROLLO URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE A
PROYECTO :
CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE041 DESARROLLO URBANO
META : 245
FECHA : 31 DE OCTUBRE 2018
No VALOR
DESCRIPCION O/C UNID. CANT.
Ord. UNID.
88 PUNTAS DE 1" X 12" EXAGONAL 1695 UNIDAD 13 15.00
89 CINTA DE SEÑALIZACION C/ROJO Y AMRILLO 1695 UNIDAD 4 40.00
90 COMBA DE 12 LIBRAS ORE 1695 UNIDAD 6 70.00
91 COMBA DE 6 LIBRAS ORE 1695 UNIDAD 1 44.00
92 CONO DE SEÑALIZACION NARANJA DE 28" ALTURA 1695 UNIDAD 5 40.00
93 DISCO DE CORTE DE METAL DE 7" 1695 UNIDAD 0 9.00
94 AMOLADORA ANGULAR DE 7" 1695 UNIDAD 0 490.00
95 DISCO DE CORTE DE MADERA DE 7" 1695 UNIDAD 10 19.00
96 HOJA DE SIERRA SANDFLEX 1695 UNIDAD 6 5.50
97 CUBO DE 250 GALONES DE PVC 1695 UNIDAD 0 440.00
98 NIVEL DE MANO DE 18" 1695 UNIDAD 4 34.00
99 REGLA DE ALUMINIO 1 1/2" X 4" X 6 MT 1695 UNIDAD 4 120.00
100 BIDON DE AGUA DE 2O LITROS ANGEL 1696 UNIDAD 12 39.00
101 CILINDROS METALICOS RECICLABLES DE COLORES 1696 UNIDAD 0 110.00
102 SURTIDOR DE AGUA PARA BIDON DE 20 LITROS 1696 UNIDAD 0 37.00
103 MALLA DE SEGURIDAD L = 45 MT X 1 MT DE ALTO 1696 UNIDAD 0 55.00
104 PALETAS DE MADERA PARE Y SIGA 1696 UNIDAD 4 16.00
105 EXTINTOR DE POLVO QUIMICO SECO DE 6 KG 1696 UNIDAD 1 80.00
106 TEKNOPORT DE 1.2 X 2.40 X 1" 1722 UNIDAD 242 17.50
107 MANTA ARPILLERA X 2 MT DE ANCHO X 200 LARGO 1722 UNIDAD 1 600.00
108 TELA YUTE DE 1 DE ANCHO X 100MT DE LARGO 1722 UNIDAD 15 450.00
109 VARILLA DE FIERRO CORRUGADO DE 1/2" 1722 VARILLA 9 29.50
110 CALAMINA GALVANIZADA DE 0.30 X 3.60 X 0.80 M/I 2003 UNIDAD 11 38.00
111 CALAMINA GALVANIZADA DE 1.80 X 0.80 X 0.22 M/I 2003 UNIDAD 0 15.90
112 TRIPLAY DE 18 MM M/LUPUNA 1994 UNIDAD 37 129.00
113 TRIPLAY DE 4 MM M /LUPUNA 1994 UNIDAD 0 36.50
114 TRIPLAY DE 6MM M/LUPUNA 1994 UNIDAD 0 49.60
115 MADERA TORNILLO DE 1" X 8" X 10P 2013 UNIDAD 36 36.00
116 MADERA TORNILLO DE 1" X 10" X 10P 2013 UNIDAD 0 45.00
117 MADERA TORNILLO DE 2" X 2" X 10P 2013 UNIDAD 0 18.00
118 MADERA TORNILLO DE 3" X 2" X 10P 2013 UNIDAD 0 27.00
119 MADERA TORNILLO DE 1" X 8" X 10P 2062 UNIDAD 300 36.00
120 MADERA TORNILLO DE 1" X 10" X 10P 2062 UNIDAD 263 45.00
121 MADERA TORNILLO DE 2" X 2" X 10P 2062 UNIDAD 0 18.00
122 MADERA TORNILLO DE 3" X 2" X 10P 2062 UNIDAD 0 27.00
123 ESCOBILLON HUDE 1675 UNIDAD 10 20.00
124 BOLSA DE YESO X 25 KG 1675 UNIDAD 50 10.00
125 TELA FRANELA NACIONAL 2089 UNIDAD 0 6.00
REPUESTOS Y ACSESORIOS DE MAQUINARIAS
RODILLO VIBRATORIO LISO CS - 533E
126 BALDE DE ACEITE DE MOTOR 15 W 40 3E-9713 1957 BALDE 0 400.00
127 FILTRO DE ACEITE DE MOTOR 7W - 2326 1957 UNIDAD 0 120.00
128 FILTRO DE AIRE SECUNDARIO 206 - 5635 1957 UNIDAD 0 380.00
129 FILTRO DE AIRE PRIMARIO 206 - 5234 1957 UNIDAD 0 390.00
FORMATO N° 09
SALDO DE MATERIALES VALORIZADOS DE OBRA
FUNCION : 019 VIVIENDA Y DESARROLLO URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE A
PROYECTO :
CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE041 DESARROLLO URBANO
META : 245
FECHA : 31 DE OCTUBRE 2018
No VALOR
DESCRIPCION O/C UNID. CANT.
Ord. UNID.
130 FILTRO DE COMBUSTIBLE 1R - 1804 1957 UNIDAD 0 130.00
131 FILTRO PRIMARIO DE COMBUSTIBLE 368-3973/4794 1957 UNIDAD 0 420.00
132 BALDE DE GRASA CAT EP2 1957 UNIDAD 0 890.00
MOTONIVELADORA CAT 140K UNIDAD
133 SWITCH AS - ROCKET (24 VOLT)COD. 3E-9317 1698 UNIDAD 0 950.00
134 LINK - CONMECTING COD.6G-1631 1698 UNIDAD 0 5,200.00
135 RETEN SEAL O RING COD 8H - 2046 1698 UNIDAD 0 75.00
136 CHAIN GP (TANDEM) COD. 6G 1633 1698 UNIDAD 0 350.00
CAMION CISTERNA EGG - 876
137 BALDE DE ACEITE DE MOTOR 15 W 40 1958 BALDE 0 310.00
138 FILTRO DE ACEITE DE MOTOR LF-3670 FLEETGUAR 1958 UNIDAD 0 180.00
139 FILTRO DE AIRE SECUNDARIO AFL-25732 FLEETGU 1958 UNIDAD 0 380.00
140 FILTRO DE AIRE PRIMARIO AFL -2501HD FLEETGUA 1958 UNIDAD 0 490.00
141 FILTRO DE COMBUSTIBLE FF5269 FLEETGUARD 1958 UNIDAD 0 140.00
142 FILTRO SEPARADOR DE AGUA COD.FS-19547 FLEET. 1958 UNIDAD 0 180.00
143 UNA LATA DE SOLDADURA SELLOCOR - SOLDADURA 1958 UNIDAD 0 480.00
VOLQUETE VOLVO XQ - 1598
144 BALDE DE ACEITE DE MOTOR 25 W 50 1988 UNIDAD 0 320.00
145 FILTRO DE ACEITE DE MOTOR LF 466634 1988 UNIDAD 0 75.00
146 FILTRO DE AIRE PRIMARIO Y SECUNDARIO 1988 UNIDAD 0 980.00
147 FILTRO DE COMBUSTIBLE FF5018 1988 UNIDAD 0 48.00
148 FILTRO SEPARADOR DE AGUA LFWP9000 1988 UNIDAD 0 210.00
149 JUEGO DE PINES Y BOCINAS DE MUELLE DELANTER 1988 UNIDAD 0 260.00
VESTUARIO
150 CASACA PARA PERSONAL TEC. GZUCK. LOGO GRA 1713 UNIDAD 0 300.00
151 CHALECO PARA PERSONAL TEC. LOGO GRA 1713 UNIDAD 0 120.00
152 CORTAVIENTO DE DRIL PARA USO DEBAJO DEL CAS 1713 UNIDAD 22 10.00
153 UNIFORME PARA PERSONAL OBRERO 2 CUERPOS 1713 UNIDAD 33 68.00
154 ZAPATOS PUNTA DE ACERO CAT 1732 UNIDAD 0 450.00
155 BARBIQUEJO DE PLASTICO PARA CASCO TRIDENTE 1697 UNIDAD 37 2.50
156 BOTAS DE JEBE CAÑA ALTA RAMBO 1697 PAR 64 40.00
157 CASCO DE DE SEGURIDAD DE PLASTICO NACIONAL 1697 UNIDAD 41 14.00
158 CASCO DE SEGURIDAD COLOR BLANCO 3M 1697 UNIDAD 5 50.00
159 GUANTES DE CUERO BADANA CLUTE 1697 PAR 0 14.00
160 GUANTES DE JEBE C-35 PROTEX 1697 PAR 56 15.00
161 LENTES DE PROTECCION TRANSPARENTE CLUTE 1697 UNIDAD 54 15.00
162 LENTES DE PROTECCION PARA PERSONAL TEC.3M 1697 UNIDAD 3 40.00
163 CAPOTIN IMPERMEABLE DE PLASTICO NACIONAL 1697 UNIDAD 0 32.00
164 RESPIRADOR CONTRA POLVO 3M 1697 UNIDAD 44 15.00
165 TAPON DE OIDO CON PORTA ESTUCHE CLUTE 1697 UNIDAD 70 10.00
166 ZAPATO DE SEGURIDAD PUNTA DE ACERO NACIONA 1697 PAR 33 70.00
UTILES DE ESCRITORIO
167 MEMORIA PORTATILUSB DE 32 GB - KINGSTON 1790 UNIDAD 10 70.00
168 PIZARRA ACRILICA DE 2M DE LARGO X 1.5 ALTURA 1790 UNIDAD 2 190.00
169 PERFORADOR DE 2 ESPIGAS PARA 100 HOJAS KW T 1977 UNIDAD 1 136.00
170 ARCHIVADOR PLASTIFICADO PALANCA L/A ARTESC 1978 UNIDAD 26 3.52
171 LAPICERO PUNTA FINA FABER CASTELL AZUL 1978 UNIDAD 16 0.32
172 LAPICERO PUNTA FINA FABER CASTELL NEGRO 1978 UNIDAD 16 0.32
173 LAPICERO PUNTA FINA FABER CASTELL ROJO 1978 UNIDAD 18 0.32
FORMATO N° 09
SALDO DE MATERIALES VALORIZADOS DE OBRA
FUNCION : 019 VIVIENDA Y DESARROLLO URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE A
PROYECTO :
CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE041 DESARROLLO URBANO
META : 245
FECHA : 31 DE OCTUBRE 2018
No VALOR
DESCRIPCION O/C UNID. CANT.
Ord. UNID.
174 BORRADOR PARA LAPIZ ARTESCO 1978 UNIDAD 10 0.45
175 CORRECTOR LIQUIDO FABER CASTELL 1978 UNIDAD 11 1.12
176 ENGRAPADOR DE METAL T/ALICATE P-101 FABER CA 1978 UNIDAD 1 15.00
177 FOLDER MANILA T/A-4 GALLO 1978 EMPX 25 4 4.72
178 GOMA EN BARRA X 20 G APROX. CONT.22GR. FABER 1978 UNIDAD 5 1.73
179 GRAPA 26/6 X 5000 ARTESCO 1978 UNIDAD 12 1.77
180 LAPIZ NEGRO GRADO 28 FABER CASTELL 1978 UNIDAD 24 0.43
181 PAPEL BOND 80 GR TAMAÑO A/4 ATLAS OFFICE 1978 EMPX 500 30 12.60
182 PLUMON PARA PIZARRA ACRILICA C/AZUL FABER C. 1978 UNIDAD 5 2.60
183 PLUMON PARA PIZARRA ACRILICA C/ROJO FABER C. 1978 UNIDAD 5 2.60
184 PLUMON PARA PIZARRA ACRILICA C/NEGRO FABER C 1978 UNIDAD 5 2.60
185 PLUMON RESALTADOR PUNTA FINA C/AMARILLO F.C 1978 UNIDAD 8 1.70
186 SUJETADOR FASTENER ARTESCO 1978 EMPX 50 2 2.57
187 TAMPON CON CUBIERTA TAMAÑO GRANDE C /AZUL 1978 UNIDAD 4 2.35
188 CUADERNO CUADRICULADO T/A4 100 H ALPHA 1976 UNIDAD 10 3.16
189 CUADERNO DE OBRA T/A4 100H CONT 25 FOLIOS D 1976 UNIDAD 6 11.69
PRESTAMO DE MATERIALES DE LA OBRA TACNA
190 PAQUETES DE ESPONJA X 36 UND C/UNO PRESTAMO UNIDAD 8
191 LACA SELLADORA DUCOLAC PRESTAMO GALON 0
192 NYLON VIKINGO X 100 MT PRESTAMO UNIDAD 1
193 BROCHAS DE 2" TUMI PRESTAMO UNIDAD 0
194 LLANTAS DE BUGUI TRUPER PRESTAMO UNIDAD 8
195 COMBA DE 18 LIBRAS PRESTAMO UNIDAD 0
196 EXTINTORES DE 6KG C/UNO PRESTAMO UNIDAD 0
197 ACEITE SHELL 20 W 50 X 1 LITRO C/UNO PRESTAMO UNIDAD 0
198 LIJA DE FIERRO N°40 PRESTAMO UNIDAD 4
199 ESCOBA DE CERDA PLASTICA PRESTAMO UNIDAD 0
200 SOGA DE NYLON DE 1/2" PRESTAMO METRO 0
201 PEGAMENTO PVC OATEY PRESTAMO GALON 1
202 CAPUCHONES DE SEGURIDAD PRESTAMO UNIDAD 152
203 PALAS TIPO CUCHARA FOR GROUP PRESTAMO UNIDAD 20
204 PICOS FOR GROUP PRESTAMO UNIDAD 8
205 PLASTICO DOBLE ANCHO X10 METROS PRESTAMO METRO 0
206 CARRETILLAS TIPO BUGUI PRESTAMO UNIDAD 10
207 CLAVO CON CABEZA DE 2 1/2" PRESTAMO KILO 0
208 CLAVO CON CABEZA DE 2" PRESTAMO KILO 0
209 PINTURAS EN SPRAY X 400 ML C/UNO PRESTAMO UNIDAD 0
210 TECNOPORT DE 1" PRESTAMO UNIDAD 0
211 ASFALTO RC - 250 PRESTAMO GALON 15
212 TRIPLAY DE 6MM PRESTAMO UNIDAD 4
213 ARCHIVADORES A-4 ARTESCO PRESTAMO UNIDAD 0
214 PLUMONES MARCADORES FABER CASTELL PRESTAMO UNIDAD 10
215 PERFORADOR ARTESCO M 73 PRESTAMO UNIDAD 0
216 TIZAS DE C/BLANCO X 50 UNIDADES PRESTAMO CAJITA 0
217 CINTA MASKING DE 2" PRESTAMO UNIDAD 2
218 GRAPAS ARTESCO PRESTAMO CAJITA 0
219 MASCARILLA CON FILTRO PRESTAMO UNIDAD 12
220 CASCOS DE COLOR PRESTAMO UNIDAD 0
221 PONCHO PVC PARA LLUVIA C/AMARILLO PRESTAMO UNIDAD 7
222 BOTAS DE JEBE PRESTAMO PAR 15
FORMATO N° 09
SALDO DE MATERIALES VALORIZADOS DE OBRA
FUNCION : 019 VIVIENDA Y DESARROLLO URBANO
2340036: "CREACION DE PISTAS Y VEREDAS EN LA AV. ANDRES AVELINO CÁCERES, DISTRITO DE A
PROYECTO :
CÁCERES - HUAMANGA - AYACUCHO" TRAMO II (0+240 Al 0+910)
COMPONENTE041 DESARROLLO URBANO
META : 245
FECHA : 31 DE OCTUBRE 2018
No VALOR
DESCRIPCION O/C UNID. CANT.
Ord. UNID.
223 ZAPATO PUNTA DE ACERO NACIONAL PRESTAMO PAR 0
224 LENTES DE PROTECCION CLUTE PRESTAMO UNIDAD 16
225 PROTECTORES AUDITIVOS PRESTAMO UNIDAD 3
226 CURE BAND VENDITAS X 100 UND PRESTAMO UNIDAD 1
227 GEL DICLOFENACO PRESTAMO UNIDAD 0
228 SULFACREM PRESTAMO UNIDAD 0
229 ALCOHOL DE 1000 ML PRESTAMO UNIDAD 0
230 AGUA OXIGENADA DE 500 ML PRESTAMO UNIDAD 0
VALOR
OBSERVACIONES
CANT.
VALOR
OBSERVACIONES
CANT.
10.00 ALMACEN DE OBRA
0.00 SIN SALDO
4.00 ALMACEN DE OBRA
6.00 ALMACEN DE OBRA
4.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
25.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
75.00 ALMACEN DE OBRA
30.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
30.00 SIN SALDO
0.00 SIN SALDO
320.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
8.50 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
12.00 ALMACEN DE OBRA
125.00 ALMACEN DE OBRA
208.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
17.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
660.00 ALMACEN DE OBRA
S DE OBRA
VALOR
OBSERVACIONES
CANT.
195.00 ALMACEN DE OBRA
160.00 ALMACEN DE OBRA
420.00 ALMACEN DE OBRA
44.00 ALMACEN DE OBRA
200.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
190.00 ALMACEN DE OBRA
33.00 ALMACEN DE OBRA
0.00 SIN SALDO
136.00 ALMACEN DE OBRA
480.00 ALMACEN DE OBRA
468.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
64.00 ALMACEN DE OBRA
80.00 ALMACEN DE OBRA
4,235.00 ALMACEN DE OBRA
600.00 ALMACEN DE OBRA
6,750.00 ALMACEN DE OBRA
265.50 ALMACEN DE OBRA
418.00 ALMACEN DE OBRA
0.00 SIN SALDO
4,773.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
1,296.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
10,800.00 ALMACEN DE OBRA
11,835.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
200.00 ALMACEN DE OBRA
500.00 ALMACEN DE OBRA
0.00 SIN SALDO
VALOR
OBSERVACIONES
CANT.
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
VALOR
OBSERVACIONES
CANT.
4.50 ALMACEN DE OBRA
12.32 ALMACEN DE OBRA
15.00 ALMACEN DE OBRA
18.88 ALMACEN DE OBRA
8.65 ALMACEN DE OBRA
21.24 ALMACEN DE OBRA
10.32 ALMACEN DE OBRA
378.00 ALMACEN DE OBRA
13.00 ALMACEN DE OBRA
13.00 ALMACEN DE OBRA
13.00 ALMACEN DE OBRA
13.60 ALMACEN DE OBRA
5.14 ALMACEN DE OBRA
9.40 ALMACEN DE OBRA
31.60 ALMACEN DE OBRA
70.14 ALMACEN DE OBRA
VALOR
OBSERVACIONES
CANT.
0.00 SIN SALDO
0.00 ALMACEN DE OBRA
0.00 ALMACEN DE OBRA
0.00 ALMACEN DE OBRA
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
0.00 SIN SALDO
216,984.27
FORMATO N° 10
MATERIALES TRASFERIDOS Y/O DONADOS
No PRESTADOS ADEUDADOS
DESCRIPCION UNID. OBSERVACIONES
Ord. P.U. CANT. S/. CANT. S/.
SIN ACTIVIDAD EN EL
MES DE OCTUBRE
8:00 10/9/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 10 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 10:00 2
8:00 10/10/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 10 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 10:00 1.6
8:00 10/11/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 20 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 14:00 4.9
8:00 10/12/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 30 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 14:00 4.5
8:00 10/15/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 15 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 12:00 3.3
8:00 10/18/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 10 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 11:00 2.2
8:00 10/20/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 10 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 11:00 2.4
8:00 10/22/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 20 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 14:00 4.7
8:00 10/24/2018 CARGADOR FRONTAL CAT 950-H LLAJARUNA MENDEZ SANTOS 15 CORTE Y CARGUILLO DE MATERIAL EXCEDENTE 12:00 3.3
TOTAL = 140 28.9
MOTONIVELADORA CAR 140-K
8:00 10/1/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 15 PERFILADO DE SUB-RAZANTE 12:00 3.17
8:00 10/2/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 10 PERFILADO DE SUB-RAZANTE 15:00 4.75
8:00 10/9/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 40 PERFILADO DE SUB-RAZANTE 16:00 8
8:00 10/10/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 40 PERFILADO DE SUB-RAZANTE 12:00 5.17
8:00 10/11/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 20 PERFILADO DE SUB-RAZANTE 11:00 2
8:00 10/20/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 25 BATIDO DE MATERIAL BASE 17:00 2.42
8:00 10/22/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 0 BATIDO DE MATERIAL BASE 9:00 1
8:00 10/23/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 15 PLANTILLADO DE MATERIAL BASE 14:00 5
8:00 10/24/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 30 BATIDO DE MATERIAL BASE 12:00 4
8:00 10/25/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 25 PLANTILLADO DE MATERIAL BASE 12:00 4
8:00 10/26/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 20 BATIDO DE MATERIAL BASE 14:00 5
8:00 10/27/2018 MOTONIVELADORA CAT 140 - K LLIMPE HUAMAN PREX 5 BATIDO DE MATERIAL BASE 12:00 4
TOTAL = 245 48.51
CAMION CISTERNA INTERNATIONAL EGG-876
66 DE 71
FORMATO N° 11
MAQUINARIA PROPIA
9:00 10/25/2018 CAMION CISTERNA INTERNATIONAL EGG - 871 ORIUNDO ESCALANTE WILFREDO 5 RIEGO DE MATERIAL BASE PARA BATIDO DEL AFIRMADO 10:00 2
10:00 10/26/2018 CAMION CISTERNA INTERNATIONAL EGG - 871 ORIUNDO ESCALANTE WILFREDO 10 RIEGO DE MATERIAL BASE PARA BATIDO DEL AFIRMADO 11:00 3
TOTAL = 35 11
RODILLO VIBRATORIO CAT CS 533-E
9:00 10/1/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH COMPACTACION A NIVEL DE SUB-RASANTE 12:00 1.3
9:00 10/2/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 10 COMPACTACION A NIVEL DE SUB-RASANTE 12:00 5.3
8:00 10/3/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 15 COMPACTACION DE MATERIAL BASE 12:00 2.8
9:00 10/9/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 10 COMPACTACION DE MATERIAL BASE 11:00 4.2
8:00 10/10/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH COMPACTACION DE MATERIAL BASE 17:00 2.8
9:00 10/11/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 10 COMPACTACION DE MATERIAL BASE 15:00 1.9
9:00 20/102018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 10 COMPACTACION DE MATERIAL BASE 16:00 2.3
8:00 10/22/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH COMPACTACION DE MATERIAL BASE 9:00 3.3
9:00 10/23/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 10 COMPACTACION DE MATERIAL BASE 12:00 1.12
8:00 10/24/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 15 COMPACTACION DE MATERIAL BASE 12:00 4.42
67 DE 71
FORMATO N° 11
MAQUINARIA PROPIA
8:00 10/25/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 5 COMPACTACION DE MATERIAL BASE 12:00 3.8
8:00 10/26/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 10 COMPACTACION DE MATERIAL BASE 12:00 3.8
8:00 10/29/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 10 COMPACTACION DE MATERIAL BASE 12:00 3.5
8:00 10/30/2018 RODILLO VIBRATORIO CAT CS 533 - E HINOSTROZA ALARCON EDITH 10 COMPACTACION DE MATERIAL BASE 12:00 2.1
TOTAL = 115 42.64
CARMIX 3.5 TT MODELO N25T51
9:00 10/11/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 7.2
9:00 10/12/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 7.4
9:00 10/13/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 7.3
10:00 10/15/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 25 PREPARADO Y TRASLADO DE CONCRETO 17:00 6.17
9:00 10/16/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 7.33
9:00 10/17/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 7.17
9:00 10/18/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 7.5
8:00 10/19/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 8
9:00 10/20/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 15 PREPARADO Y TRASLADO DE CONCRETO 17:00 7
8:00 10/22/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 8
8:00 10/23/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 6.5
8:00 10/24/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 25 PREPARADO Y TRASLADO DE CONCRETO 17:00 7.5
8:00 10/25/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 25 PREPARADO Y TRASLADO DE CONCRETO 17:00 8
10:00 10/26/2018 CARMIX AUTOHORMIGUERA CARMIX N25T52 HUAYHUA QUISPE JORGE 25 PREPARADO Y TRASLADO DE CONCRETO 17:00 6
11:00 10/27/2018 CARMIX AUTOHORMIGUERA CARMIX N25T53 HUAYHUA QUISPE JORGE 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 5
8:00 10/29/2018 CARMIX AUTOHORMIGUERA CARMIX N25T54 HUAYHUA QUISPE JORGE 25 PREPARADO Y TRASLADO DE CONCRETO 17:00 6
8:00 10/30/2018 CARMIX AUTOHORMIGUERA CARMIX N25T55 HUAYHUA QUISPE JORGE 30 PREPARADO Y TRASLADO DE CONCRETO 17:00 7.5
8:00 10/31/2018 CARMIX AUTOHORMIGUERA CARMIX N25T51 HUAYHUA QUISPE JORGE 25 PREPARADO Y TRASLADO DE CONCRETO 17:00 6.17
TOTAL = 395 125.74
CARMIX 3.5 TT MODELO N28T51
11:00 10/16/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 15 PREPARADO Y TRASLADO DE CONCRETO 15:30 3.5
13:00 10/17/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 10 PREPARADO Y TRASLADO DE CONCRETO 17:00 3.5
9:00 10/18/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 20 PREPARADO Y TRASLADO DE CONCRETO 15:30 6
14:00 10/19/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 10 PREPARADO Y TRASLADO DE CONCRETO 17:00 1.5
10:00 10/22/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 20 PREPARADO Y TRASLADO DE CONCRETO 17:00 5
9:00 10/23/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 20 PREPARADO Y TRASLADO DE CONCRETO 16:00 6.5
8:00 10/24/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 20 PREPARADO Y TRASLADO DE CONCRETO 12:30 4.5
9:00 10/25/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 25 PREPARADO Y TRASLADO DE CONCRETO 15:30 5
11:00 10/30/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 15 PREPARADO Y TRASLADO DE CONCRETO 14:30 2.5
6:00 10/31/2018 CARMIX AUTOHORMIGUERA CARMIX N28T51 COTRINA DAMIAN JUAN 20 PREPARADO Y TRASLADO DE CONCRETO 12:00 6
TOTAL = 175 44
CAMIONCITO NISSAN VANETTE
8:00 10/1/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/2/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/3/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 12:00 4
8:00 10/4/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/5/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/6/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 3 TRASLADO DE MATERIALES A LA OBRA 13:00 5
8:00 10/8/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/9/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/10/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/11/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/12/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/13/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 3 TRASLADO DE MATERIALES A LA OBRA 13:00 5
8:00 10/15/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/16/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/17/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/18/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/19/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/20/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 13:00 5
68 DE 71
FORMATO N° 11
MAQUINARIA PROPIA
8:00 10/22/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/23/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/24/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/25/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/26/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/27/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 13:00 5
8:00 10/29/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 5 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/30/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
8:00 10/31/2018 CAMIONCITO NISSAN TRAMITE QUISPE OZAITA DIOGENES CARLIN 0 TRASLADO DE MATERIALES A LA OBRA 17:00 8
TOTAL = 51 184
CAMIONETA TOYOTA HILUX F8G-906
8:00 10/1/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 10 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/2/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/3/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 12:00 4
8:00 10/4/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 10 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/5/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/6/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 13:00 5
8:00 10/8/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/9/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 10 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/10/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/11/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/12/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/13/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 10 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 13:00 5
8:00 10/15/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/16/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/17/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/18/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 10 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/19/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/20/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 13:00 5
8:00 10/22/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/23/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/24/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/25/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 10 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/26/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/27/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 13:00 5
8:00 10/29/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 10 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/30/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
8:00 10/31/2018 CAMIONETA HILUX F8G - 905 CHUCHON PAREJA JHUNIOR 0 MOVILIZACION DE PERSONAL OBRERO Y TRASLADO DE MATERIAL 17:00 8
TOTAL = 70 200
69 DE 71
FORMATO N° 12