s/ Mes 1 Mes 2 Mes 3 Mes 4 Mes 5
Parcial % Parcial % Parcial % Parcial % Parcial %

1 MODULO DE AULAS Y SS.HH. S834,638.40 S87,028.60 10.43% S228,387.79 27.36% S390,481.28 46.78% S128,740.74 15.42%
1.1 OBRAS PROVISIONALES S17,542.26 S17,542.26
1.1.1 ALMACEN DE OBRA S2,500.00 S2,500.00
1.1.2 CARTEL DE OBRA S818.26 S818.26
1.1.3 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA S12,224.00 S12,224.00
1.1.4 PLAN DE SEGURIDAD Y SALUD OCUPACIONAL S2,000.00 S2,000.00
1.2 OBRAS PRELIMINARES S2,684.29 S2,684.29
1.2.1 LIMPIEZA DE TERRENO S312.80 S312.80
1.2.2 TRAZO Y REPLANTEO S680.29 S680.29
1.2.3 CINTA PARA SEÑAL DE PELIGRO S1,691.20 S1,691.20
1.3 MOVIMIENTO DE TIERRAS S72,262.90 S66,802.05 S5,460.85
1.3.1 CORTE A NIVEL DE SUBRASANTE CON MAQUINARIA S1,756.65 S1,756.65
1.3.2 NIVELACION MANUAL DE TERRENO S571.92 S571.92

1.3.3 EXCAVACION PARA CIMIENTOS HASTA 1.00 m. EN TERRENO NORMAL S937.78


S937.78
1.3.4 EXCAVACION PARA ZAPATAS S5,709.21 S5,709.21
1.3.5 RELLENO CON MATERIAL PROPIO SELECCIONADO S1,401.99 S1,401.99

1.3.6 RELLENO CON MAT. DE PRESTAMO E = 0.20 m. EN BASE DE ZAPATAS S1,814.24


S1,814.24

1.3.7 MEJORAMIENTO DE SUBRASANTE EN ZAPATAS CON OVER, E = 0.20 m. S2,825.25


S2,825.25
1.3.8 ELIMINACION .MAT.EXCED. EN CARRETILLA D = 30 max. S15,222.43 S15,222.43
1.3.9 ELIMINACION DE DESMONTE C/VOLQUETE, CARGUIO A MANO S35,764.17 S35,764.17
1.3.10 NIVELACION INT.Y APISONADO PARA FALSO PISO S798.41 S798.41
1.3.11 AFIRMADO DE 4" PARA PATIOS Y VEREDAS S5,460.85 S5,460.85
1.4 OBRAS DE CONCRETO SIMPLE S23,929.33 S23,929.33
1.4.1 CIMIENTOS CORRIDOS 1:10 + 30% P.G. S4,028.13 S4,028.13
1.4.2 SOLADO PARA ZAPATAS E=4" , 1:10 CEMENTO-HORMIGON S4,311.31 S4,311.31
1.4.3 CONCRETO SOBRECIMIENTO DE 1:8 C:H 25% P.M. S3,000.15 S3,000.15
1.4.4 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO S3,934.21 S3,934.21

1.4.5 CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGON E=4" S7,733.10


S7,733.10
1.4.6 RAMPA DE CONCRETO F´c = 175 Kg/cm2 E = 4" S922.43 S922.43
1.5 OBRAS DE CONCRETO ARMADO S262,539.14 S143,119.43 S118,900.27 S519.45
1.5.1 ZAPATAS S38,723.38 S38,723.38
1.5.2 VIGAS DE CIMENTACION S12,825.31 S12,825.31
1.5.3 COLUMNAS S69,152.35 S69,152.35
1.5.4 VIGAS S59,782.38 S22,418.39 S37,363.99
1.5.5 LOSAS ALIGERADAS S73,633.77 S73,633.77
1.5.6 LOSAS MACIZAS S4,266.39 S4,266.39
1.5.7 ESCALERAS S4,155.56 S3,636.12 S519.45
1.6 ALBAÑILERIA S41,424.62 S41,424.62
1.7 REVOQUES ENLUCIDOS Y MOLDURAS S55,279.06 S55,279.06
1.8 CIELORRASOS S49,401.01 S37,050.76 S12,350.25
1.9 JUNTAS S2,301.61 S2,301.61
1.1 PISOS, VEREDAS Y PAVIMENTOS S49,020.39 S49,020.39
1.11 ZOCALOS S2,996.85 S2,996.85
1.12 CONTRAZOCALOS S7,755.68 S7,755.68
1.13 REVESTIMIENTO DE GRADAS Y ESCALERA S2,361.77 S2,361.77
1.14 CUBIERTAS S35,604.02 S35,604.02
1.15 CARPINTERIA DE MADERA S23,666.70 S23,666.70
1.16 CARPINTERIA METALICA S13,959.36 S13,959.36
1.17 CERRAJERIA S3,385.86 S3,385.86
1.18 VIDRIOS, CRISTALES Y SIMILARES S8,870.81 S8,870.81
1.19 PINTURA S32,450.45 S32,450.45
1.2 APARATOS SANITARIOS Y ACCESORIOS S6,696.64 S2,678.66 S4,017.98
1.21 INSTALACIONES SANITARIAS S5,238.04 S5,238.04
1.22 SISTEMA DE AGUA FRIA S1,738.49 S1,738.49
1.23 TRATAMIENTO DE AGUAS RESIDUALES CON BIODIGESTOR S28,338.76 S21,335.70 S7,003.06
1.23.1 TRABAJOS PRELIMINARES S133.76 S133.76
1.23.2 MOVIMIENTO DE TIERRAS S20,538.79 S20,538.79
1.23.3 OBRAS DE CONCRETO SIMPLE S773.68 S663.15 S110.53
1.23.4 REVOQUES ENLUCIDOS Y MOLDURAS S67.56 S67.56
1.23.5 TUBERIAS Y ACCESORIOS S493.97 S493.97
1.23.6 VARIOS S6,331.00 S6,331.00
1.24 SISTEMA DE DRENAJE PLUVIAL S19,880.59 S19,880.59
1.25 INSTALACIONES ELECTRICAS S33,046.61 S5,006.70 S20,211.17 S7,828.74
1.25.1 SALIDA PARA ALUMBRADO S5,006.70 S5,006.70
1.25.2 SALIDA PARA INTERRUPTORES S460.88 S460.88
1.25.3 SALIDA PARA TOMACORRIENTES S5,055.75 S5,055.75
1.25.4 SALIDA PARA COMUNICACIONES Y SEÑALES S134.00 S134.00
1.25.5 CANALIZACIONES Y/O TUBERIAS S2,964.04 S2,964.04
1.25.6 CONDUCTORES Y/O CABLES S9,325.98 S9,325.98
1.25.7 TABLEROS Y LLAVES TERMOMAGNETICAS S965.61 S965.61
1.25.8 ARTEFACTOS PARA ILUMINACION S7,828.74 S7,828.74
1.25.9 SISTEMA DE PUESTA A TIERRA S1,304.91 S1,304.91
1.26 EQUIPAMIENTO S32,263.16 S32,263.16
2 INGRESO PRINCIPAL S25,636.44 S2,932.45 11.44% S4,319.76 16.85% S5,456.49 21.28%
2.1 TRABAJOS PRELIMINARES S319.01 S319.01
2.2 MOVIMIENTO DE TIERRAS S2,909.04 S2,909.04
2.3 OBRAS DE CONCRETO SIMPLE S1,195.00 S1,045.63 S149.38
2.4 OBRAS DE CONCRETO ARMADO S6,465.45 S46.08 S5,307.11
2.4.1 ZAPATAS S368.61 S46.08 S322.53
2.4.2 VIGAS DE CIMENTACION S301.71 S301.71
2.4.3 COLUMNAS S2,458.20 S2,458.20
2.4.4 VIGAS S1,112.41 S1,112.41
2.4.5 LOSAS MACIZAS S2,224.52 S1,112.26
2.5 ALBAÑILERIA S1,730.31
2.6 REVOQUES ENLUCIDOS Y MOLDURAS S1,970.88
2.7 CIELORRASOS S385.47
2.8 PISOS, VEREDAS Y PAVIMENTOS S889.78
2.9 VEREDAS S2,932.45 S2,932.45
2.1 CUBIERTAS S1,181.84
2.11 CARPINTERIA METALICA S4,796.93
2.12 CERRAJERIA S104.44
2.13 PINTURA S755.84
3 CERCO PERIMETRICO S392,697.07 S211,683.09 53.90% S2,850.36 0.73% S3,271.44 0.83% S43,919.89 11.18% S120,937.36 30.80%
3.1 MURO DE CONTENCION S88,769.37 S36,416.47 S52,352.90
3.1.1 TRABAJOS PRELIMINARES S598.50 S598.50
3.1.2 MOVIMIENTO DE TIERRAS S26,067.88 S26,067.88
3.1.3 OBRAS DE CONCRETO ARMADO S62,102.99 S9,750.09 S52,352.90
3.1.3.1 ZAPATAS S15,600.15 S9,750.09 S5,850.06
3.1.3.2 MURO - PANTALLA S42,560.50 S42,560.50
3.1.3.3 REVOQUES ENLUCIDOS Y MOLDURAS S2,823.00 S2,823.00
3.1.3.4 PINTURA S1,119.34 S1,119.34
3.2 MURO PERIMETRICO I S42,129.62 S5,635.85 S27,537.01
3.2.1 OBRAS PRELIMINARES S32.82 S32.82
3.2.2 MOVIMIENTO DE TIERRAS S1,936.83 S1,936.83
3.2.3 OBRAS DE CONCRETO SIMPLE S5,865.92 S3,666.20 S2,199.72
3.2.4 OBRAS DE CONCRETO ARMADO S11,086.33 S11,086.33
3.2.4.1 COLUMNAS S7,281.79 S7,281.79
3.2.4.2 VIGAS S3,804.54 S3,804.54
3.2.5 ALBAÑILERIA S14,178.15 S14,178.15
3.2.6 JUNTAS S72.81 S72.81
3.2.7 REVOQUES ENLUCIDOS Y MOLDURAS S7,681.97

3.2.8 PINTURA S1,274.79

3.3 MURO PERIMETRICO II S41,268.82 S922.67 S40,346.15


3.3.1 OBRAS PRELIMINARES S55.74 S55.74
3.3.2 MOVIMIENTO DE TIERRAS S417.32 S417.32
3.3.3 OBRAS DE CONCRETO SIMPLE S719.38 S449.61 S269.77
3.3.4 CARPINTERIA METALICA S35,777.97 S35,777.97
3.3.5 PINTURA S4,298.41 S4,298.41
3.4 CONTROL DE CALIDAD DEL CONCRETO S5,971.23 S826.60 S2,226.98 S2,596.12 S321.52
3.4.1 DISEÑO DE MEZCLAS DE CONCRETO S750.00 S353.77 S339.62 S56.60
3.4.2 ENSAYO A LA COMPRESION DE PROBETAS DE CONCRETO S1,740.00 S472.83 S453.91 S491.74 S321.52
3.4.3 CURADO DE CONCRETO CON EMULSION S3,481.23 S1,433.45 S2,047.78
3.5 TRABAJOS VARIOS S214,558.03 S210,856.49 S623.38 S675.32 S623.38 S701.30
3.5.1 PLACA RECORDATORIA DE BRONCE S350.89

3.5.2 MITIGACION DE IMPACTO AMBIENTAL S4,000.00 S649.35 S623.38 S675.32 S623.38 S701.30
3.5.3 FLETE TERRESTRE S208,978.06 S208,978.06
3.5.4 LIMPIEZA FINAL DE OBRA S1,229.08 S1,229.08

Costo Directo S1,252,971.91 S301,644.14 S231,238.15 S393,752.72 S176,980.39 S126,393.85

Gastos Generales S117,152.87 S28,203.73 S21,620.77 S36,815.88 S16,547.67 S11,817.82

Utilidades S62,648.60 S15,082.21 S11,561.91 S19,687.64 S8,849.02 S6,319.69


Sub- Total S1,432,773.38 S344,930.07 S264,420.82 S450,256.24 S202,377.08 S144,531.37

Impuesto General a las Ventas S257,899.21 S62,087.41 S47,595.75 S81,046.12 S36,427.87 S26,015.65
Valor Referencial (V.R.) S1,690,672.59 S407,017.49 24.07% S312,016.57 18.46% S531,302.36 31.43% S238,804.95 14.12% S170,547.01 10.09%
Mes 6 Mes 7
Parcial % Parcial %
S12,171.91 47.48% S755.84 2.95%

S1,112.26

S1,112.26
S1,730.31
S1,970.88
S385.47
S889.78

S1,181.84
S4,796.93
S104.44
S755.84
S9,580.14 2.44% S454.79 0.12%

S8,956.76

S7,681.97
S1,274.79

S623.38 S454.79
S350.89
S623.38 S103.90

S21,752.05 S1,210.63

S2,033.82 S113.19

S1,087.60 S60.53
S24,873.47 S1,384.36

S4,477.22 S249.18
S29,350.69 1.74% S1,633.54 0.10%