DEPARTAMENTO DE AYACUCHO
Supervisor Externo: ING. RUBEN A. BEDRIÑANA BAÑICO Jefe de Supervisión: ING. RUBEN A. BEDRIÑANA BAÑICO
Monto del Contrato: S/. 214,118.55 Con IGV S/. 181,355.93 Sin IGV
Monto del Adelanto: S/. 214,118.55 Con IGV S/. 181,355.93 Sin IGV
Nombre de Proyecto:
" INSTALACION DE RESIDENCIA ESTUDIANTIL EN LA I.E. AGROPECUARIO SAN ESTEBAN DE APONGO DEL DISTRITO DE APONGO
PRESUPUESTO CONTRACTUAL
AVANCE ACTUAL
ÍTEM DESCRIPCION PRECIO
UND CANTIDAD UNITARIO COSTO PARCIAL (S/.)
VALORIZADO
(S/.) METRADO
(S/.)
VALORIZACION CANAL
COSTO DIRECTO 163,474.23 49,974.39
GASTOS GENERALES (6.00%) 9,808.45 2,998.46
UTILIDAD (5.00%) 8,173.71 2,498.72
RESUMEN GENERAL
COSTO DIRECTO S/. 163,474.23 49,974.39
GASTOS GENERALES (6.00%) S/. 9,808.45 2,998.46
Región: AYACUCHO
Departamento: AYACUCHO
Distrito: APONGO
AVANCES
SALDOS POR VALORIZAR
NCE ACTUAL AVANCE ACUMULADO ANTERIOR AVANCE ACUMULADO ACTUAL
Nº
30.57% S/. 55,440.86 30.57% S/. 55,440.86 30.57% S/. 125,915.07
S/. 55,440.86 S/. 55,440.86 S/. 125,915.07
9,979.36 9,979.36 22,664.71
30.57% S/. 65,420.22 30.57% S/. 65,420.22 30.57% S/. 148,579.78
Nº 025-2016-MPA/A
APONGO
69.43%
SALDOS POR VALORIZAR
69.43%
69.43%
RESUMEN DE VALORIZACIÓN DE EJECUCIÓN DE OBRA N
Nombre de Proyecto:
" INSTALACION DE RESISDENCIA ESTUDIANTIL EN LA I.E. AGROPECUARIO SAN ESTEBAN DE APONGO DEL DISTRITO D
DE VICTOR FAJARDO-AYACUCHO"
1.00 S/. 55,440.86 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 55,440.86
2.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
3.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
PARCIAL S/. 55,440.86 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 55,440.86
ADICIONALES:
1.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
2.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
PARCIAL S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
ADELANTO DIRECTO EN EFECTIVO ADELANTO EN MATERIALES RETENCIÓN
REINTEGRO
VALORIZACIÓN FIEL
N° REAJUSTE PPTT SUB TOTAL
BRUTA CUMPLIMIENTO
PRINCIPAL ADELANTO AMORTIZACION ADELANTO AMORTIZACION (10%)
TOTAL
GENERA S/. 55,440.86 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 55,440.86
L
OBSERVACIONES:
ECUCIÓN DE OBRA Nº 01
REAJUSTES (R)
FORMULA UNICA 0.00 0.00 0.00
-------------------------------- ---------------------------- ----------------------------------
TOTAL REAJUSTES 0.00 0.00 0.00
AMORTIZACIONES (A)
AMORTIZACION DE ADEL. EFECTIVO 0.00 0.00 0.00 0.00 0.00
AMORTIZACION DE MATERIALES 0.00 0.00 0.00 0.00 0.00
-------------------------- -------------------------------- ---------------------------- ---------------------------------- --------------------------
TOTAL DE AMORTIZACIONES 0.00 0.00 0.00 0.00 0.00