RESUMEN DE METRADOS GENERALES: I.E.

Nº 80565 SEÑOR DE
LOS MILAGROS PICHINCHUCO
ITEM DESCRIPCION UND METRADO
ESTRUCTURAS
1.00 OBRAS PROVICIONALES
1.01 CARTEL DE OBRA DE 3.60 X 2.40 m CON GIGANTOGRAFIA und 2.00
1.02 CASETA DE GUARDIANIA Y ALMACEN DE OBRA m2 60.00
1.03 TRANSPORTE DE EQUIPO, HERRAMIENTAS Y MATERIALES A OBRA GLB 1.00
1.04 INSTALACION PROV. Y DOTACION DE AGUA glb 1.00
1.05 ACARREO DE AGREGADOS D>100m m3 377.45
1.06 ACARREO DE CEMENTO DMAX>=100m bols 2238.33
1.07 DESMONTAJE DE PUERTAS m2 13.20
1.08 DESMONTAJE DE VENTANAS m2 3.60
1.09 DESMONTAJE DE TECHO DE TEJA ANDINA m2 315.00
1.01 DEMOLICION DE MUROS DE ADOBE m2 344.25
1.11 DEMOLICION DE CONTRAPISO m2 315.00
1.12 DEMOLICION DE VEREDAS m2 12.00
1.13 DEMOLICION DE CIMIENTO CORRIDO m3 59.40
1.14 ELIMINACION DE DESMONTE m3 367.13
2.00 TRABAJOS PRELIMINARES
2.01 LIMPIEZA DE TERRENO MANUAL M2 763.16
2.02 TRAZO Y REPLANTEO M2 763.16
3.00 MOVIMIENTO DE TIERRAS
3.01 CORTE EN MATERIAL SUELTO, (PERFILADO GENERAL) M3 95.40
3.02 EXCAVACION DE ZANJAS Y ZAPATAS (MATERIAL SUELTO) M3 117.07
3.03 EXCAVACION MASIVA EN TERRENO SUELTO, MANUAL M3 92.52
3.04 ELIMINACION MATERIAL EXCEDENTE + 25% EXPONJAMIENTO M3 193.31
3.05 NIVELACION Y APISONADO INT. / EXT. PARA FALSO PISO Y VEREDAS M2 778.19
3.06 HORMIGON DE 4" PARA LOSA DEPORTIVA M2 766.62
3.07 RELLENO CON MATERIAL PROPIO M3 114.79
4.00 OBRAS DE CONCRETO SIMPLE
4.01 SOLADO PARA ZAPATAS C:H 1:12 + 30%P:G. E=4" M2 39.62
4.02 FALSO PISO E=4" (1:8) M2 139.31
4.03 VEREDA DE CONCRETO f´c = 175 kg/cm2 e = 4" M2 77.29
4.04 CIMIENTO CORRIDO C:H 1/10 + 30% P.G. M3 25.61
4.05 LOSA DEPORTIVA: CONCRETO FC=175KG/CM2 M2 383.31
4.06 LOSA DEPORTIVA: ENCOFRADO Y DESENCOFRADO M2 120.24
5.00 OBRAS DE CONCRETO ARMADO
5.01 ZAPATAS
5.01.01 ZAPATAS:CONCRETO F'c=210 Kg/cm2 M3 21.68
5.01.02 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 477.15
5.02 VIGAS DE CIMENTACION
5.02.01 VIGAS DE CIMENTACION:CONCRETO f'c=210 Kg/cm2 M3 1.68
5.02.02 VIGAS DE CIMENTACION:ENCOFRADO Y DESENCOFRADO NORMAL M2 11.20
5.03.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 308.83
5.03 SOBRECIMIENTO REFORZADO
5.03.01 SOBRECIMIENTO REFORZADO:CONCRETO f'c=175 Kg/cm2 M3 13.46
5.03.02 SOBRECIMIENTO REFORZADO:ENCOFRADO Y DESENCOFRADO NORMAL M2 153.66
5.03.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 450.76
5.04 COLUMNAS Y COLUMNETAS
5.04.01 COLUMNAS Y COLUMNETAS:CONCRETO F'c=210 Kg/cm2 M3 21.69
5.04.02 COLUMNAS Y COLUMNETAS:ENCOFRADO Y DESENCOFRADO NORMAL M2 239.72
5.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 7,335.98
5.05.00 VIGAS Y VIGUETAS
5.05.01 VIGAS Y VIGUETAS:CONCRETO F'c=210 Kg/cm2 M3 18.48
5.05.02 VIGAS Y VIGUETAS:ENCOFRADO Y DESENCOFRADO NORMAL M2 149.13
5.05.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 2,747.77
5.06.00 LOSA ALIGERADA
5.06.01 LOSA ALIGERADA:CONCRETO F'c=210 Kg/cm2 M3 22.65
5.06.02 LOSA ALIGERADA:ENCOFRADO Y DESENCOFRADO NORMAL M2 241.10
5.06.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 1,461.75
5.06.04 LADRILLO PARA TECHO DE ARCILLA 30x30x15cm UND 2,354.67
5.07.00 LOSAS MACIZAS
5.07.01 LOSAS MACIZAS:CONCRETO F'c=210 Kg/cm2 M3 0.42
5.07.02 LOSAS MACIZAS:ENCOFRADO Y DESENCOFRADO NORMAL M2 4.19
5.07.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 34.36
5.08.00 ESCALERAS Y GRADERIAS
5.08.01 ESCALERA Y GRADERIAS:CONCRETO F'c=210 Kg/cm2 M3 2.80
5.08.02 ESCALERA Y GRADERIAS:ENCOFRADO Y DESENCOFRADO NORMAL M2 16.43
5.08.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 235.25
5.09 CANAL CON REJILLA
5.09.01 CANAL CON REJILLA:CONCRETO F'c=210 Kg/cm2 M3 23.91
5.09.02 CANAL CON REJILLA:ENCOFRADO Y DESENCOFRADO NORMAL M2 32.98
5.09.03 REJILLA CON PLATINA M 41.23
5.09.04 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 214.11

ARQUITECTURA
1.00 + DE ALBAÑILERIA
MUROS Y TABIQUES
1.01 MURO DE LADRILLO K.K. TIPO IV APAREJO DE SOGA M2 81.32
1.02 MURO DE LADRILLO K.K. DE CABEZA M2 137.93
2.00 REVOQUES ENLUCIDOS Y MOLDURAS
2.01 TARRAJEO EN MUROS INTERIORES M2 219.25
2.02 TARRAJEO EN MUROS EXTERIORES M2 196.50
2.03 TARRAJEO DE COLUMNAS M2 39.95
2.04 TARRAJEO DE VIGAS M2 134.22
2.05 VESTIDURA DE DERRAMES M 148.12
3.00 CIELOS RASOS
3.01 CIELO RASO CON MEZCLA C: 1:5 M2 245.29
4.00 CUBIERTAS Y ESTRUCTURA DE MADERA
4.01 COBERTURA DE TEJA ANDINA 1.14m x 0.72m X 5 mm M2 234.32
4.02 TIJETAL DE ESTRUCTURA DE MADERA Nº 01 UND 2.00
4.03 CORREAS DE MADERA TORNILLO 3"X5" ML 195.80
4.04 CUMBRERAS ARTICULADAS DE TEJA ANDINA ML 20.43
5.00 REVESTIMIENTO ESCALERAS
5.01 REVESTIMIENTO DE ESCALERAS M2 16.43
6.00 PISOS Y PAVIMENTOS
6.01 CONTRAPISOS 40 mm M2 139.31
6.02 PISO CERAMICO DE ALTO TRANSITO DE 30 x 30 cm M2 7.26
6.03 PISO CONCRETO COLOREADO, ACABADO FROTACHADO M2 132.05
7.00 CONTRAZOCALOS
7.01 CONTRAZOCALO SANITARIO DE LOSETA H=0.10M . M 4.00
7.02 CONTRAZOCALO DE CEMENTO PULIDO H=0.30M e=1.5 cm. M 165.70
8.00 ZOCALOS Y ENCHAPES
8.01 REVESTIMIENTO DE ESCALERAS M2 32.60
9.00 CARPINTERIA DE MADERA
9.01 PUERTA DE MADERA CON MARCOS Y BASTIDORES M2 18.56
9.02 PUERTA CONTRAPLACADA CON MARCOS Y BASTIDORES DE TORNILLO M2 9.60
9.03 VENTANA DE MADERA C/CEDRO SEGUN DISEÑO, INCLUIDO PROTECTOR DE M2 54.56
10.00 CARPINTERIA METALICA Y HERRERIA
10.01 BARANDA PASAMANO TUBO DE F° DIAM. 2" INCLUYE PINTADO M 15.90
10.02 CANTONERA DE PLANCHA ESTRIADA EN GRADAS DE ESCALERAS M 27.00
11.00 CERRAJERIA
11.01 BISAGRA ALUMIN. 4" , PESADA EN PUERTAS Pz. 80.00
11.02 JALADORES CROMADOS UND 20.00
11.03 CERRADURA DE SEGURIDAD DE SOBREPONER TRES GOLPES UND 12.00
11.04 CERRADURA DE SEGURIDAD DE EMBUTIR DE PERILLA UND 8.00
12.00 VIDRIOS, CRISTALES Y SIMILARES
12.01 VIDRIO 6 MM, PROVISION Y COLOCACION EN VENTANAS P2 270.47
13.00 PINTURA
13.01 PINTURA LATEX 2 MANOS EN CIELO RASO Y VIGAS M2 379.50
13.02 PINTURA AL LATEX EN MUROS INTERIORES Y EXTERIORES M2 415.75
13.03 PINTURA AL LATEX EN COLUMNAS M2 39.95
13.04 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALOS M2 165.70
13.05 PINTURA PARA DEMARCACION DE LOSA DEPORTIVA M 458.40
14.00 VARIOS
14.01 ARCO DE FULBITO CON TABLERO DE BASQUET BALL (METAL-MADERA), INC UND 2.00
14.02 RED DE VOLEY PARA LOSA DEPORTIVA UND 1.00
14.03 JUNTA DE CONSTRUCCION CON TEKNOPORT M2 3.30
14.04 JUNTA DE ASFALTICAS ML 440.00
14.05 PIZARRA ACRILICA UND 3.00
INSTALACIONES SANITARIAS
1.00 DESAGUE
1.01 SUMINISTRO E INSTALACION DE TUBERÍA SAL DIAM. 2" ML 40
1.02 SUMINISTRO E INSTALACION DE TUBERÍA SAL DIAM. 4" ML 12
1.03 SUMINISTRO E INSTALACION DE TUBERÍA SAL DIAM. 6" ML 26.2
1.04 SALIDA PARA VENTILACION DE 2" PVC INC. SOMBRERO EN TECHO PTO 2.00
1.05 REDUCCION PVC SAL DE 4" x 2" UND 3.00
1.06 REGISTRO ROSCADO DE 4" UND 2.00
1.07 CAJA DE REGISTRO DE 12" x 24" C/TAPA DE CONCRETO UND 3.00
2.00 SISTEMA DE AGUA FRIA
2.01 SALIDA DE AGUA FRIA, PVC PTO 5.00
2.02 TUBERIA PVC CLASE 10 - Ø 1/2" M 8.00
2.03 TEE 1/2 " PVC P/ AGUA UND 3.00
2.04 CODO DE 90º 1/2" PVC P/ AGUA UND 2.00
2.05 VALVULA COMPUERTA DE BRONCE Ø 1/2" UND 1.00
2.06 SUM. E INSTAL. DE TANQUE ELEVADO DE POLIETILENO CAP. 1,100 Lts. GLB 1.00
2.07 SISTEMA DE REBOCE Y LIMPIEZA UND 1.00
3.00 APARATOS Y ACCESORIOS SANITARIOS
3.01 INODORO VITRIFICADO TANQUE BAJO COLOR BLANCO UND 2.00
3.02 OVALIN LOSA SONET UND 2.00
3.03 URINARIOS UND 1.00
3.04 LLAVE CUELLO DE GANZO SIMPLE PARA LAVADERO UND 2.00
4.00 SISTEMA DE EVACUACION DE AGUAS PLUVIALES
4.01 CANALETA DE EVACUACION DE AGUAS PLUVIALES ML 72.00
4.02 TUBERIA DE DRENAJE PVC SAL 4"/PLUVIAL ML 32
5.00 TANQUE SÉPTICO
5.01 TRABAJOS PRELIMINARES
5.01.01 LIMPIEZA DE TERRENO MANUAL M2 0.98
5.01.02 TRAZO Y REPLANTEO M2 0.98
5.02 MOVIMIENTO DE TIERRAS
5.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 1.64
5.02.02 CORTE EN MATERIAL SUELTO (PERFILADO GENERAL) M2 0.98
5.02.03 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m MANUAL M3 1.97
5.03 OBRAS DE CONCRETO SIMPLE
5.03.01 SOLADO DE CONCRETO C:H 1:10 E=10CM M2 0.98
5.04 OBRAS DE CONCRETO ARMADO
5.04.01 TANQUE SEPTICO:CONCRETO f'c=175kg/cm2 M3 0.97
5.04.02 ENCOFRADO Y DESENCOFRADO EN TANQUE SEPTICO M2 6.66
5.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 16.97
5.05 TARRAJEOS
5.05.01 TARRAJEO INT. CON IMPERMEA 1:2 M2 5.33
5.05.02 TARRAJEO EN MUROS EXTERIORES M2 1.02
5.06 ACCESORIOS TANQUE SÉPTICO
5.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS TANQUE SEPTICO GLB 1.00
5.06.02 PRUEBA DE ABSORCIÓN GLB 1.00
5.06.03 TEST DE PERCOLACIÓN GLB 1.00
5.06.04 PRUEBA HIDRÁULICA MAS ESCORRENTÍA PARA DESAGÜE GLB 1.00
6.00 CÁMARA DE SECADO
6.01 TRABAJOS PRELIMINARES
6.01.01 LIMPIEZA DE TERRENO MANUAL M2 1.00
6.01.02 TRAZO Y REPLANTEO M2 1.00
6.02 MOVIMIENTO DE TIERRAS
6.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 1.60
6.02.02 RELLENO CON MATERIAL PROPIO M3 0.13
6.02.03 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m MANUAL M3 1.77
6.03 OBRAS DE CONCRETO SIMPLE
6.03.01 SOLADO DE CONCRETO C:H 1:10 E=10CM M2 1.00
6.03.02 CONCRETO C:H 1:10 +30% P.G. M3 0.72
6.04 OBRAS DE CONCRETO ARMADO
6.04.01 CAMARA SECA:CONCRETO f'c=175 Kg/cm2 M3 0.58
6.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA DE SECADO M2 3.84
6.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 4.48
6.05 REVOQUES, ENLUCIDOS Y MOLDURAS
6.05.01 TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZCLA 1:1 M2 7.04
6.05.02 TARRAJEO EN MUROS EXTERIOR IORES 1:4 M2 1.80
6.06 FILTRO DE GRAVA
6.06.01 FILTRO DE GRAVA UND 1.00
6.07 ACCESORIOS TANQUE SÉPTICO 0 0.00
6.07.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS TANQUE SEPTICO GLB 1.00
7.00 POZO DE PERCOLACIÓN
7.01 TRABAJOS PRELIMINARES
7.01.01 LIMPIEZA DE TERRENO MANUAL M2 1.77
7.01.02 TRAZO Y REPLANTEO M2 1.77
7.02 MOVIMIENTO DE TIERRAS
7.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 2.45
7.02.02 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m MANUAL M3 2.94
7.03 MUROS Y TABIQUES 0 0.00
7.03.01 MURO DE CABEZA LADRILLO CORRIENTE M2 6.91
7.04 OBRAS DE CONCRETO SIMPLE
7.04.01 SOLADO DE CONCRETO C:H 1:10 E=10CM M2 1.77
7.05 OBRAS DE CONCRETO ARMADO
7.05.01 POZO DE PERCOLACION:CONCRETO f'c=175 Kg/cm2 M3 0.36
7.05.02 ENCOFRADO Y DESENCOFRADO EN POZO DE PERCOLACION M2 2.11
7.05.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 19.96
7.06 FILTROS
7.06.01 FILTRO DE GRAVA M3 1.01
7.07 ACCESORIOS DE POZO DE PERCOLACIÓN
7.07.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS POZO DE PERCOLACION GLB 1.00
8.00 CAJA DE REGISTRO
8.01 TRABAJOS PRELIMINARES
8.01.01 LIMPIEZA DE TERRENO MANUAL M2 0.37
8.01.02 TRAZO Y REPLANTEO M2 0.37
8.02 MOVIMIENTO DE TIERRAS
8.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 0.35
8.02.02 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m MANUAL M3 0.42
8.03 OBRAS DE CONCRETO SIMPLE
8.03.01 SOLADO DE CONCRETO C:H 1:10 E=10CM M2 0.37
8.04 OBRAS DE CONCRETO ARMADO
8.04.01 CAJA DE REGISTRO:CONCRETO f'c=175 Kg/cm2 M3 0.46
8.04.02 ENCOFRADO Y DESENCOFRADO EN CAJA DE REGISTRO M2 3.66
8.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 14.92
8.05 REVOQUES, ENLUCIDOS Y MOLDURAS
8.05.01 TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZCLA 1:1 M2 1.82
8.06 ACCESORIOS CAJA REGISTRO
8.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS EN CAJA DE REGISTRO GLB 2.00
9.00 CAJA DE VÁLVULA
9.01 TRABAJOS PRELIMINARES
9.01.01 LIMPIEZA DE TERRENO MANUAL M2 0.16
9.01.02 TRAZO Y REPLANTEO M2 0.16
9.02 MOVIMIENTO DE TIERRAS
9.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 0.06
9.02.02 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m MANUAL M3 0.08
9.03 OBRAS DE CONCRETO SIMPLE
9.03.01 SOLADO DE CONCRETO C:H 1:10 E=10cm M2 0.16
9.04 OBRAS DE CONCRETO ARMADO
9.04.01 CAJA DE VALVULA:CONCRETO f'c=175 Kg/cm2 M3 0.14
9.04.02 ENCOFRADO Y DESENCOFRADO EN CAJA DE VALVULA M2 1.02
9.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 3.58
9.05 REVOQUES, ENLUCIDOS Y MOLDURAS
9.05.01 TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZCLA 1:1 M2 0.40
9.06 ACCESORIOS CAJA DE VÁLVULA
9.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS EN CAJA DE VALVULA GLB 1.00
INSTALACIONES ELECTRICAS
1.00 ALIMENTADOR PRINCIPAL
1.01 TUBERIA PVC-SAP DE 40mm INCLUYE ACCESORIOS M 20.00
1.02 CABLE 3*10mm2 WP+1*10MM2(N)WP(CPI) M 20.00
1.03 CAJA DE FG CUADRADA DE DISTRIBUCION Y PASO DE 350X350X100mm UND 1.00
1.04 POZO DE PUESTA A TIERRA UND 1.00
2.00 COMPONENTES GENERALES DE LA INSTALACION
2.01 CAJA DE FG CUADRADA DE DISTRIBUCIONY PASO DE100mm UND 2.00
2.02 CAJA DE FG OCTOGONAL DE DISTRIBUCIONY PASO DE100mm UND 2.00
3.00 TABLEROS Y SUB TABLEROS ELECTRICOS
3.01 TABLEROS GENERAL(TG) PZA 1.00
3.02 SUBTABLERO DE DISTRIBUCION: PRIMER NIVEL PZA 1.00
3.03 SUBTABLERO DE DISTRIBUCION: SEGUNDO NIVEL PZA 1.00
4.00 ALIMENTADORES SECUNDARIOS
4.01 TUBERIA PVC SAP D=25mm M 208.00
4.02 CABLE TW 6mm2 M 208.00
4.03 CABLE DE COBRE DESNUDO DE 10mm2 M 208.00
5.00 CIRCUITOS DERIVADOS
5.01 CABLE TW 6mm2 M 15.00
5.02 CABLE TW 4mm2 M 15.00
5.03 CABLE TW 2.5mm2 M 624.00
5.04 TUBERIA PVC SAP D= 20mm M 162.00
5.05 TUBERIA PVC SAP D= 25mm M 462.00
5.06 SALIDA PARA CENTRO DE LUZ PTO 22.00
5.07 WALL SOCKET O BRAQUETE PTO 8.00
5.08 SALIDA PARA TOMACORRIENTE USO NORMAL H=1.1 PTO 8.00
5.09 SALIDA PARA ARTEFACTO FLUORESECENTE 2x40 W UND 4.00
5.10 INTERRUPTOR SIMPLE UND 2.00
5.11 INTERRUPTOR DOBLE UND 4.00
5.12 INTERRUPTOR TRIPLE UND 2.00
MOBILIARIO Y EQUIPAMIENTO
1.00 MOBILIARIO Y EQUIPAMIENTO
1.01 SILLA DE METAL CON AMDERA PRIMARIA GLB 90
1.02 MESA DE METAL CON AMDERA PRIMARIA GLB 90
1.03 SILLA DE METAL CON AMDERA PROFESORES GLB 7
1.04 MESA DE METAL CON AMDERA PROFESORES GLB 7
HOJA DE METRADOS ESTRUCTURAS : I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO
1.0 OBRAS PROVICIONALES UND CANT. LONG ANCHO ALTURA PARCIAL SUB TOTAL
1.01 CARTEL DE OBRA DE 3.60 X 2.40 m CON GIGANTOGRAFIA und 2 - - - 2.00 2.00
1.02 CASETA DE GUARDIANIA Y ALMACEN DE OBRA m2 CANT. LONG ANCHO ALTURA PARCIAL 60.00 60.00
CASETA m2 10.00 6.00 60.00
1.03 TRANSPORTE DE EQUIPO, HERRAMIENTAS Y MATERIALES A OBRA GLB 1 1.00 - - - 1.00 1.00
1.04 INSTALACION PROV. Y DOTACION DE AGUA glb 1 1.00 - - - 1.00 1.00
1.05 ACARREO DE AGREGADOS D>100m m3 377.45 377.45
ARENA GRUESA Y FINA m3 143.38
PIEDRA CHANCADA Y GRAVILLA m3 147.83
HORMIGON m3 86.24
1.06 ACARREO DE CEMENTO DMAX>=100m bols 2,238.33 2,238.33
LA TOTALIDAD DE CEMENTO SEGÚN EXPEDIENTE TECNICO, DESDE FIO CARRETERA 2238.33
1.07 DESMONTAJE DE PUERTAS CANT. LONG AREA ALTURA PARCIAL SUB TOTAL 13.20
m2 6 1.00 2.20 13.20
1.08 DESMONTAJE DE VENTANAS m2 CANT. LONG AREA ALTURA PARCIAL SUB TOTAL 3.60
m2 6 0.50 1.20 3.60
1.09 DESMONTAJE DE TECHO DE TEJA ANDINA m2 CANT. LONG AREA ALTURA PARCIAL SUB TOTAL 315.00
m2 1 - 315.00 - 315.00
1.01 DEMOLICION DE MUROS DE ADOBE m2 CANT. LONG ESPESOR ALTURA PARCIAL SUB TOTAL 344.25
m2 1 255.00 0.60 2.25 344.25
1.11 DEMOLICION DE CONTRAPISO m2 CANT. LONG AREA ALTURA PARCIAL SUB TOTAL 315.00
PISO DE AULAS + PISO DE PATIO EXISTENTE m2 1 - 315.00 315.00
1.12 DEMOLICION DE VEREDAS m2 CANT. LONG AREA ALTURA PARCIAL SUB TOTAL 12.00
m2 1 15.00 0.80 12.00
1.13 DEMOLICION DE CIMIENTO CORRIDO m3 CANT. LONG ANCHO ALTURA PARCIAL SUB TOTAL 59.40
m3 1 165.00 0.60 0.60 59.40
1.14 ELIMINACION DE DESMONTE m3 CANT. ACUMULADO ANCHO ANCHO PARCIAL SUB TOTAL 367.13
m3 1 734.25 0.50 367.13

2.0 TRABAJOS PRELIMINARES


2.01 LIMPIEZA DE TERRENO MANUAL M2 CANT. AREA ANCHO AREA PARCIAL SUB TOTAL 763.16
AREA DE TERRENO M2 1 713.71 713.71 763.16
SSHH 1 49.45 49.45
2.02 TRAZO Y REPLANTEO M2 CANT. LONG ANCHO AREA PARCIAL SUB TOTAL 763.16
AREA DE TERRENO M2 1 713.71 713.71 763.16
SSHH 1 49.45 49.45
3.0 MOVIMIENTO DE TIERRAS
3.01 CORTE EN MATERIAL SUELTO, (PERFILADO GENERAL) M3 AREA F.E. PROMEDIO PARCIAL SUB TOTAL 95.40
AREA DE TERRENO M3 1 713.71 1.25 0.10 89.21
SSHH M3 1 49.45 1.25 0.10 6.18
3.02 EXCAVACION DE ZANJAS Y ZAPATAS (MATERIAL SUELTO) M3 CANT. LONG ANCHO ALTURA PARCIAL SUB TOTAL 117.07
ZAPATAS M3 57.82
Z-1 2 1.25 1.25 1.60 5.00
Z-2 2 2.20 1.60 1.60 11.26
Z-3 1 1.70 1.30 1.60 3.54
Z-4 8 1.00 1.00 1.60 12.80
Z-5 2 1.20 1.20 1.60 4.61
Z-6 2 1.10 1.10 1.60 3.87
Z-7 2 2.20 1.40 1.60 9.86
Z-8 1 1.70 1.10 1.60 2.99
Z-9 1 2.70 0.90 1.60 3.89
VIGA DE CIMENTACION M3 CANT. LONG ANCHO ALTURA PARCIAL 2.94
VC1 30X80 2 3.50 0.30 1.40 2.94
CORTES M3 CANT. LONG ANCHO ALTURA PARCIAL 27.66
C 1-1 1 18.20 0.50 1.30 11.83
C 2-2 1 0.75 0.50 1.30 0.49
C 3-3 1 6.30 0.60 1.30 4.91
C 4-4 1 2.90 0.80 1.30 3.02
C 5-5 1 7.00 0.50 1.30 4.55
C 6-6 1 4.40 0.50 1.30 2.86
VEREDA EXTERNA M3 CANT. LONG ANCHO ALTURA PARCIAL 8.76
VEREDA EXTERIOR 1 22.23 1.50 0.15 5.00
1 22.23 0.60 0.15 2.00
1 6.50 1.20 0.15 1.17
1 6.50 0.60 0.15 0.59
SSHH
ZAPATAS M3 CANT. LONG ANCHO ALTURA PARCIAL 12.17
Z-1 4 1.20 1.30 1.30 8.11
Z-2 2 1.20 1.30 1.30 4.06
CORTES M3 CANT. LONG ANCHO ALTURA PARCIAL 6.35
C 1-1 2 2.80 0.50 1.00 2.80
C 2-2 1 2.80 0.50 1.00 1.40
C 3-3 4 1.08 0.50 1.00 2.15
VEREDA EXTERNA M3 CANT. AREA ANCHO ALTURA PARCIAL 1.38
VEREDA EXTERIOR 1 9.23 0.15 1.38
3.03 EXCAVACION MASIVA EN TERRENO SUELTO, MANUAL M3 CANT. LONG AREA PARCIAL SUB TOTAL 92.52
SEGÚN CORTE LONGITUDINAL M3 92.52
AREA DE CORTE DE PERFIL EN LOSA 1 26.40 2.45 64.68
AREA DE CORTE EN AULAS 1 32.00 1.45 0.60 27.84
3.04 ELIMINACION MATERIAL EXCEDENTE + 25% EXPONJAMIENTO M3 V.Exc. V. Rell Volumen Esp.25% Parcial
212.47 57.82 154.65 38.66 193.31 193.31 193.31
3.05 NIVELACION Y APISONADO INT. / EXT. PARA FALSO PISO Y VEREDAS M2 CANT. LONG ANCHO ALTURA PARCIAL SUB TOTAL 778.19
PARA FALSO PISO 778.19
Aula 1 M2 1 8.00 6.20 49.60
Aula 2 M2 1 8.00 6.20 49.60
Baños M2 2 3.30 1.10 7.26
Escalera M2 2 3.90 1.50 11.70
PARA LOSA DEPORTIVA M2 1 30.00 20.00 600.00
M2 2 1.48 0.56 1.66
PARA VEREDAS EXTERNA M2 1 22.23 1.50 33.34
M2 1 22.23 0.60 13.34
HOJA DE METRADOS ESTRUCTURAS : I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO
M2 1 6.50 1.20 7.80
M2 1 6.50 0.60 3.90
SSHH 89.31
PARA FALSO PISO M2 CANT. LONG ANCHO ALTURA PARCIAL
para ss.hh M2 2 10.58 21.15
para vereda externa M2 1 68.16 68.16
3.06 HORMIGON DE 4" PARA LOSA DEPORTIVA M2 CANT. AREA ANCHO ALTURA PARCIAL SUB TOTAL 766.62
SE CONSIDERA DOS CAPAS DE 4", Patio de Formacion 2 383.31 766.62 766.62
3.07 RELLENO CON MATERIAL PROPIO M3 CANT. AREA F.E ALTURA PARCIAL SUB TOTAL 114.79
ZAPATAS 39.74
Z-1 M3 2 1.44 1.35 0.90 3.50
Z-2 2 3.22 1.35 0.90 7.82
Z-3 1 2.09 1.35 0.90 2.54
Z-4 8 0.91 1.35 0.90 8.85
Z-5 2 1.35 1.35 0.90 3.28
Z-6 2 1.09 1.35 0.90 2.65
Z-7 2 2.72 1.35 0.90 6.61
Z-8 1 1.75 1.35 0.90 2.13
Z-9 1 1.95 1.35 0.90 2.37
VIGA DE CIMENTACION M3 5.67
VC1 30X80 2 3.50 1.35 0.60 5.67
CORTES M3 11.21
C 1-1 1 6.37 1.35 0.60 5.16
C 2-2 1 0.38 1.35 0.60 0.30
C 3-3 1 2.21 1.35 0.60 1.79
C 4-4 1 1.60 1.35 0.60 1.29
C 5-5 1 1.75 1.35 0.60 1.42
C 6-6 1 1.54 1.35 0.60 1.25
SSHH
zapatas M3 F.E AREA LONG ANCHO PARCIAL 58.17
Z-1 M3 1.35 1.59 0.60 1.29
Z-2 M3 1.35 1.65 0.55 1.22
cortes
C 1-1 M3 1.35 4.76 0.30 1.93
C 2-2 M3 1.35 2.38 0.30 0.96
C 3-3 M3 1.35 3.67 0.30 1.49
RELLENO EN LOSA DEPORTIVA, SEGÚN CORTE DE LONGITUDINAL M2 1.35 1.45 26.20 51.29
4 OBRAS DE CONCRETO SIMPLE
4.01 SOLADO PARA ZAPATAS C:H 1:12 + 30%P:G. E=4" M2 CANT. LONG ANCHO ALTURA PARCIAL SUB TOTAL 39.62
Zapatas M2 39.62
Z-1 2 1.25 1.25 - 3.13
Z-2 2 2.20 1.60 - 7.04
Z-3 1 1.70 1.30 - 2.21
Z-4 8 1.00 1.00 - 8.00
Z-5 2 1.20 1.20 - 2.88
Z-6 2 1.10 1.10 - 2.42
Z-7 2 2.20 1.40 - 6.16
Z-8 1 1.70 1.10 - 1.87
Z-9 1 2.70 0.90 - 2.43
SSHH
Zapatas M2 CANT. LONG ANCHO ALTURA PARCIAL
C 2-2 1 0.38 1.35 - 0.51
C 3-3 1 2.21 1.35 - 2.98
4.02 FALSO PISO E=4" (1:8) M2 CANT. LONG ANCHO ALTURA PARCIAL SUB TOTAL 139.31
Aula 1 M2 1 8.00 6.20 49.60 118.16
Aula 2 M2 1 8.00 6.20 49.60
Baños M2 2 3.30 1.10 7.26
Escalera M2 2 3.90 1.50 11.70
SSHH M2 CANT. AREA ANCHO ALTURA PARCIAL 21.15
FALSO PISO M2 2 10.58 21.15
4.03 VEREDA DE CONCRETO f´c = 175 kg/cm2 e = 4" M2 CANT. LONG ANCHO ALTURA PARCIAL SUB TOTAL 77.29
Veredas Exterior m2 1 22.23 1.50 33.34 58.37
m2 1 22.23 0.60 13.34
m2 1 6.50 1.20 7.80
m2 1 6.50 0.60 3.90
SSHH M2 CANT. LONG ANCHO AREA PARCIAL 18.92
Veredas Exterior 1 18.92 18.92
4.04 CIMIENTO CORRIDO C:H 1/10 + 30% P.G. M3 CANT. LONG ANCHO ALTURA PARCIAL SUB TOTAL 25.61
C 1-1 1 18.20 0.50 0.70 6.37 18.30
C 2-2 1 0.75 0.50 0.70 0.26
C 3-3 1 6.30 0.60 0.70 2.65
C 4-4 1 8.20 0.80 0.70 4.59
C 5-5 1 7.00 0.50 0.70 2.45
C 6-6 1 4.40 0.50 0.70 1.54
CIMIENTOS PARA ESCALERAS 1 1.45 0.50 0.60 0.44
SSHH M3 CANT. LONG ANCHO ALTURA PARCIAL
Z-6 2 1.10 1.10 0.70 1.69 7.32
Z-7 2 2.20 1.40 0.70 4.31
Z-8 1 1.70 1.10 0.70 1.31
4.05 LOSA DEPORTIVA: CONCRETO FC=175KG/CM2 M2 CANT. LONG ESPESOR AREA PARCIAL 383.31 383.31
TODA EL AREA DE PARTIO Y LOSA 1 383.31 383.31
4.06 LOSA DEPORTIVA: ENCOFRADO Y DESENCOFRADO M2 CANT. LONG ANCHO AREA PARCIAL 120.24 120.24
TODAS LAS JUNTAS ANCHO 9.00 0.30 26.20 70.74
TODAS LAS JUNTAS LARGO 11 0.30 15.00 49.50
5.0 OBRAS DE CONCRETO ARMADO
5.01 ZAPATAS
5.01.01 ZAPATAS:CONCRETO F'c=210 Kg/cm2 M3 21.68 21.68
Zapatas M3 CANT. LONG ANCHO ALTURA PARCIAL
Z-1 2 1.25 1.25 0.60 1.88
Z-2 2 2.20 1.60 0.60 4.22
Z-3 1 1.70 1.30 0.60 1.33
HOJA DE METRADOS ESTRUCTURAS : I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO
Z-4 8 1.00 1.00 0.60 4.80
Z-5 2 1.20 1.20 0.60 1.73
Z-6 2 1.10 1.10 0.60 1.45
Z-7 2 2.20 1.40 0.60 3.70
Z-8 1 1.70 1.10 0.60 1.12
Z-9 1 2.70 0.90 0.60 1.46
5.01.02 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 477.15 TOTAL 477.15
5.02 VIGAS DE CIMENTACION
5.02.01 VIGAS DE CIMENTACION:CONCRETO f'c=210 Kg/cm2 M3 CANT. LONG ANCHO ALTURA PARCIAL 1.68 1.68
VC1 30X80 2 3.50 0.30 0.80 1.68
5.02.02 VIGAS DE CIMENTACION:ENCOFRADO Y DESENCOFRADO NORMAL M3 CANT. LONG ANCHO ALTURA PARCIAL 11.20 11.20
VC1 30X80 2 7.00 0.80 11.20
5.02.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 308.83 TOTAL 308.83
5.03 SOBRECIMIENTO REFORZADO
5.03.01 SOBRECIMIENTO REFORZADO:CONCRETO f'c=175 Kg/cm2 M3 CANT. LONG ANCHO ALTURA PARCIAL 13.46 13.46
C 1-1 1 18.20 0.15 0.90 2.46
C 3-3 1 6.30 0.25 0.90 1.42
C 4-4 1 8.20 0.25 0.90 1.85
C 5-5 1 7.00 0.25 0.90 1.58
C 6-6 1 4.40 0.15 0.90 0.59
En zapata
Z-1 2 1.80 0.15 1.20 0.65
Z-2 2 1.30 0.15 1.20 0.47
Z-3 1 1.65 0.15 1.20 0.30
Z-4 8 1.40 0.15 1.20 2.02
Z-5 2 0.90 0.15 1.20 0.32
Z-6 2 1.50 0.15 1.20 0.54
Z-7 2 1.30 0.15 1.20 0.47
Z-8 1 2.10 0.15 1.20 0.38
Z-9 1 2.40 0.15 1.20 0.43
5.03.02 SOBRECIMIENTO REFORZADO:ENCOFRADO Y DESENCOFRADO NORMAL M2 CANT. LONG ANCHO ALTURA PARCIAL 153.66 153.66
C 1-1 1 18.20 1.80 32.76
C 3-3 1 6.30 1.80 11.34
C 4-4 1 8.20 1.80 14.76
C 5-5 1 7.00 1.80 12.60
C 6-6 1 4.40 1.80 7.92
En zapata
Z-1 2 1.80 2.40 8.64
Z-2 2 1.30 2.40 6.24
Z-3 1 1.65 2.40 3.96
Z-4 8 1.40 2.40 26.88
Z-5 2 0.90 2.40 4.32
Z-6 2 1.50 2.40 7.20
Z-7 2 1.30 2.40 6.24
Z-8 1 2.10 2.40 5.04
Z-9 1 2.40 2.40 5.76
5.03.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 450.76 TOTAL 450.76
5.04 COLUMNAS Y COLUMNETAS
5.04.01 COLUMNAS Y COLUMNETAS:CONCRETO F'c=210 Kg/cm2 M3 CANT. AREA ANCHO ALTURA PARCIAL 21.69 21.69
PRIMER NIVEL
C-1 6 0.12 3.65 2.63
C-2 4 0.09 3.65 1.31
C-3 4 0.36 3.65 5.26
C-4 6 0.09 3.65 1.97
PL-1 1 0.48 3.65 1.75
COLUMNETAS
Eje A 8 0.02 1.28 0.23
Eje B 8 0.02 1.08 0.19
Eje 5 2 0.02 2.40 0.11
Eje 6 2 0.02 2.40 0.11
SEGUNDO NIVEL
C-1 6 0.12 2.60 1.87
C-2 4 0.09 3.60 1.30
C-3 4 0.36 2.60 3.74
C-4 4 0.09 2.05 0.74
COLUMNETAS
Eje A 8 0.02 1.43 0.26
Eje B 8 0.02 1.23 0.22
5.04.02 COLUMNAS Y COLUMNETAS:ENCOFRADO Y DESENCOFRADO NORMAL M2 CANT. LONG ANCHO ALTURA PARCIAL 239.72 239.72
PRIMER NIVEL
C-1 6 1.40 3.65 30.66
C-2 4 1.20 3.65 17.52
C-3 4 3.00 3.65 43.80
C-4 6 1.20 3.65 26.28
PL-1 1 5.20 3.65 18.98
COLUMNETAS
Eje A 8 0.30 1.28 3.06
Eje B 8 0.30 1.08 2.58
Eje 5 4 0.45 2.60 4.68
Eje 6 4 0.45 2.60 4.68
SEGUNDO NIVEL
C-1 6 1.40 2.60 21.84
C-2 4 1.20 3.60 17.28
C-3 4 3.00 2.60 31.20
C-4 4 1.20 2.05 9.84
COLUMNETAS
Eje A 8 0.30 1.63 3.90
Eje B 8 0.30 1.43 3.42
5.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 7,335.98 TOTAL 7,335.98
5.05.00 VIGAS Y VIGUETAS
5.05.01 VIGAS Y VIGUETAS:CONCRETO F'c=210 Kg/cm2 M3 CANT. LONG ANCHO ALTURA PARCIAL 18.48 18.48
HOJA DE METRADOS ESTRUCTURAS : I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO
PRIMER NIVEL
VP 100/200 (30x45) 2 3.40 0.30 0.45 0.92
2 3.45 0.30 0.45 0.93
VP 101/201 (30x50) 2 6.80 0.30 0.50 2.04
VP (30x35) 3 1.50 0.30 0.35 0.47
VS - 1 (30x35) 2 5.90 0.30 0.35 1.24
VS - 2 (30x35) 1 5.90 0.30 0.35 0.62
CORTE 1-1 (25*20) 4 3.80 0.25 0.20 0.76
CORTE 2-2 (30*20) 2 3.45 0.30 0.20 0.41
2 2.15 0.30 0.20 0.26
2 3.10 0.30 0.20 0.37
CORTE 3-3 (30*20) 2 1.50 0.30 0.20 0.18
2 1.00 0.30 0.20 0.12
CORTE 4-4 (15*20) 2 3.10 0.15 0.20 0.19
CORTE 4'-4' (30*40) 2 1.45 0.30 0.40 0.35
VIGUETAS
Eje A (0.15x0.20) 2 3.40 0.15 0.20 0.20
2 2.28 0.15 0.20 0.14
Eje B (0.15x0.20) 4 3.40 0.15 0.20 0.41
2 3.05 0.15 0.20 0.18
SEGUNDO NIVEL
VP 100/200 (30x45) 2 3.40 0.30 0.45 0.92
2 3.45 0.30 0.45 0.93
VP 101/201 (30x50) 2 7.80 0.30 0.50 2.34
VP (30x35) 6 1.50 0.30 0.35 0.95
VS - 1 (30x35) 2 5.90 0.30 0.35 1.24
VS - 2 (30x35) 1 5.90 0.30 0.35 0.62
CORTE 1-1 (25*20) 8 3.80 0.25 0.20 1.52
CORTE 2-2 (30*20) 2 1.45 0.30 0.20 0.17
CORTE 2'-2' (30*20) 1 3.10 0.30 0.20 0.19
VIGUETAS
Eje A (0.15x0.20) 2 3.40 0.15 0.20 0.20
2 2.28 0.15 0.20 0.14
Eje B (0.15x0.20) 4 3.40 0.15 0.20 0.41
5.05.02 VIGAS Y VIGUETAS:ENCOFRADO Y DESENCOFRADO NORMAL M2 CANT. LONG ANCHO ALTURA PARCIAL 149.13 149.13
PRIMER NIVEL
VP 100/200 (30x45) 2 3.40 1.00 6.80
2 3.45 1.00 6.90
VP 101/201 (30x50) 2 6.80 0.90 12.24
VP (30x35) 3 1.50 0.80 3.60
VS - 1 (30x35) 2 5.90 0.80 9.44
VS - 2 (30x35) 1 5.90 0.60 3.54
CORTE 1-1 (25*20) 4 3.80 0.45 6.84
CORTE 2-2 (30*20) 2 3.45 0.55 3.80
2 2.15 0.35 1.51
2 3.10 0.20 1.24
CORTE 3-3 (30*20) 2 1.50 0.50 1.50
2 1.00 0.50 1.00
CORTE 4-4 (15*20) 2 3.10 0.35 2.17
CORTE 4'-4' (30*40) 2 1.45 0.70 2.03
VIGUETAS
Eje A (0.15x0.20) 2 3.40 0.40 2.72
2 2.28 0.40 1.82
Eje B (0.15x0.20) 4 3.40 0.40 5.44
2 3.05 0.40 2.44
SEGUNDO NIVEL
VP 100/200 (30x45) 2 3.40 1.00 6.80
2 3.45 1.00 6.90
VP 101/201 (30x50) 2 7.80 0.90 14.04
VP (30x35) 6 1.50 0.80 7.20
VS - 1 (30x35) 2 5.90 0.80 9.44
VS - 2 (30x35) 1 5.90 0.60 3.54
CORTE 1-1 (25*20) 8 3.80 0.45 13.68
CORTE 2-2 (30*20) 2 1.45 0.55 1.60
CORTE 2'-2' (30*20) 1 3.10 0.30 0.93
VIGUETAS
Eje A (0.15x0.20) 2 3.40 0.40 2.72
2 2.28 0.40 1.82
Eje B (0.15x0.20) 4 3.40 0.40 5.44
5.05.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 2,747.77 TOTAL 2,747.77
5.06.00 LOSA ALIGERADA
5.06.01 LOSA ALIGERADA:CONCRETO F'c=210 Kg/cm2 M3 CANT. AREA ESPESOR PARCIAL 22.65 22.65
AREA PRIMER NIVEL 4 Area 27.17 0.05 5.43
1 Area 9.30 0.05 0.47
AREA SEGUNDO NIVEL 4 Area 30.78 0.05 6.16
VIGUETA PRIMER NIVEL 18 13.80 0.10 0.15 3.73
14 13.00 0.10 0.15 2.73
VIGUETA SEGUNDO NIVEL 20 13.80 0.10 0.15 4.14
5.06.02 LOSA ALIGERADA:ENCOFRADO Y DESENCOFRADO NORMAL M2 CANT. Area ALTURA PARCIAL 241.10 241.10
SUMADE AREAS 1 Area 241.10 - 241.10
5.06.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 1,461.75 TOTAL 1,461.75
5.06.04 LADRILLO PARA TECHO DE ARCILLA 30x30x15cm UND CANT. UND DESP. ALTURA PARCIAL 2,354.67 2,354.67
VIGUETA PRIMER NIVEL 18 46 828.00
14 43 606.67
VIGUETA SEGUNDO NIVEL 20 46 920.00
5.07.00 LOSAS MACIZAS
5.07.01 LOSAS MACIZAS:CONCRETO F'c=210 Kg/cm2 M3 CANT. LONG ANCHO ALTURA PARCIAL 0.42 0.42
AREA DE TECHO 1 3.10 1.35 0.10 0.42
5.07.02 LOSAS MACIZAS:ENCOFRADO Y DESENCOFRADO NORMAL M2 CANT. LONG ANCHO ALTURA PARCIAL 4.19 4.19
AREA DE TECHO 1 3.10 1.35 4.19
5.07.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 34.36 TOTAL 34.36
HOJA DE METRADOS ESTRUCTURAS : I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO
5.08.00 ESCALERAS Y GRADERIAS
5.08.01 ESCALERA Y GRADERIAS:CONCRETO F'c=210 Kg/cm2 M3 CANT. LONG ANCHO ALTURA PARCIAL 2.80 2.80
ESCALERAS DE INGRESO 1 2.70 1.50 0.15 0.61
GARDERIAS ACCESO A LOSA 1 1.25 3.20 0.20 0.80
GRADERIAS PASO 1 2.60 1.50 0.15 0.59
GRADERIAS CONTRAPASO 18 1.50 0.30 0.10 0.81
5.08.02 ESCALERA Y GRADERIAS:ENCOFRADO Y DESENCOFRADO NORMAL M2 CANT. LONG ANCHO ALTURA PARCIAL 16.43 16.43
ESCALERAS DE INGRESO 1 2.70 1.50 4.05
GARDERIAS ACCESO A LOSA 1 1.25 3.20 4.00
GRADERIAS PASO 1 2.60 1.50 3.90
GRADERIAS CONTRAPASO 18 1.50 0.17 4.48
5.08.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 235.25 TOTAL 235.25
5.09 CANAL CON REJILLA
5.09.01 CANAL CON REJILLA:CONCRETO F'c=210 Kg/cm2 M3 CANT. LONG AREA ALTURA PARCIAL 23.91 23.91
LADOS LATERALES 1 41.23 0.58 23.91
5.09.02 CANAL CON REJILLA:ENCOFRADO Y DESENCOFRADO NORMAL M2 CANT. LONG ANCHO ALTURA PARCIAL 32.98 32.98
LADOS LATERALES 1 41.23 0.80 32.98
5.09.03 REJILLA CON PLATINA M CANT. LONG AREA ALTURA PARCIAL 41.23 41.23
LADOS LATERALES 1 41.23 41.23
5.09.04 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 214.11 TOTAL 214.11
HOJA DE RESUMEN DE ACERO DE ESTRUCTURAS :I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO

UNIDAD
LONG.
PARTID DESCRIPCION (DESCRIPCIO longitud CANT VECES
TOTAL
N) 1/4 3/8 1/2 5/8 3/4
TOTAL
5.0 OBRAS DE CONCRETO ARMADO
5.01 ZAPATAS
5.01.01 ACERO DE REFUERZO Fy=4200 Kg/cm2
Z-1 KG 1.25 8.33 2.00 20.83 20.71
KG 1.25 8.33 2.00 20.83 20.71
Z-2 KG 2.20 14.67 2.00 64.53 64.15
KG 1.60 10.67 2.00 34.13 33.93
Z-3 KG 1.70 11.33 1.00 19.27 19.15
KG 1.30 8.67 1.00 11.27 11.20
Z-4 KG 1.00 5.00 8.00 40.00 39.76
KG 1.00 5.00 8.00 40.00 39.76
Z-5 KG 1.20 8.00 2.00 19.20 19.08 477.15
KG 1.20 8.00 2.00 19.20 19.08
Z-6 KG 1.10 7.33 2.00 16.13 16.04
KG 1.10 7.33 2.00 16.13 16.04
Z-7 KG 2.20 14.67 2.00 64.53 64.15
KG 1.40 9.33 2.00 26.13 25.98
Z-8 KG 1.70 11.33 1.00 19.27 19.15
KG 1.10 7.33 1.00 8.07 8.02
Z-9 KG 2.70 13.50 1.00 36.45 36.23
KG 0.90 4.50 1.00 4.05 4.03
5.02 VIGAS DE CIMENTACION
5.02.01 ACERO DE REFUERZO Fy=4200 Kg/cm2
VC1 30X80
KG 6.30 10.00 2.00 126.00 195.55 308.83
KG 6.30 2.00 2.00 25.20 25.05
KG 2.02 39.00 2.00 157.56 88.23

5.03 SOBRECIMIENTO REFORZADO


5.03.03 ACERO DE REFUERZO Fy=4200 Kg/cm2
C 1-1 KG 18.20 5.00 1.00 91.00 22.75
KG 1.20 72.80 1.00 87.36 21.84
C 3-3 KG 6.30 5.00 2.00 63.00 35.28
KG 1.20 25.20 2.00 60.48 33.87
C 4-4 KG 8.20 5.00 2.00 82.00 45.92
KG 1.20 32.80 2.00 78.72 44.08
C 5-5 KG 7.00 5.00 2.00 70.00 17.50
KG 1.20 28.00 2.00 67.20 16.80
C 6-6 KG 4.40 5.00 1.00 22.00 5.50
KG 1.20 17.60 1.00 21.12 5.28
Z-1 KG 1.80 6.00 2.00 21.60 12.10
KG 1.50 7.20 2.00 21.60 12.10
Z-2 KG 1.30 6.00 2.00 15.60 8.74
KG 1.50 5.20 2.00 15.60 8.74 450.76
Z-3 KG 1.65 6.00 1.00 9.90 5.54
KG 1.50 6.60 1.00 9.90 5.54
Z-4 KG 1.40 6.00 8.00 67.20 37.63
KG 1.50 5.60 8.00 67.20 37.63
Z-5 KG 0.90 6.00 1.00 5.40 3.02
KG 1.50 3.60 1.00 5.40 3.02
Z-6 KG 1.50 6.00 2.00 18.00 10.08
KG 1.50 6.00 2.00 18.00 10.08
Z-7 KG 1.30 6.00 2.00 15.60 8.74
KG 1.50 5.20 2.00 15.60 8.74
Z-8 KG 2.10 6.00 1.00 12.60 7.06
KG 1.50 8.40 1.00 12.60 7.06
Z-9 KG 2.40 6.00 1.00 14.40 8.06
KG 1.50 9.60 1.00 14.40 8.06
5.04 COLUMNAS Y COLUMNETAS
5.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2
C-1 KG 4.75 4.00 6.00 114.00 176.93
KG 4.75 4.00 6.00 114.00 113.32
KG 2.28 32.00 6.00 437.76 245.15
C-2 KG 4.75 4.00 4.00 76.00 117.95
KG 4.75 2.00 4.00 38.00 37.77
KG 1.82 32.00 4.00 232.96 130.46
C-3 KG 4.75 18.00 4.00 342.00 530.78
KG 5.86 32.00 4.00 750.08 420.04
C-4 KG 4.75 6.00 6.00 171.00 265.39
KG 1.82 32.00 6.00 349.44 195.69
PL-1 KG 4.75 26.00 2.00 247.00 138.32
KG 4.75 4.00 2.00 38.00 37.77
KG 1.90 23.00 2.00 87.40 48.94
KG 0.88 32.00 2.00 56.32 31.54
COLUMNETAS
Eje A KG 2.88 4.00 8.00 92.00 51.52
KG 0.58 24.00 8.00 111.36 27.84
Eje B KG 2.68 4.00 8.00 85.60 47.94
KG 0.58 22.00 8.00 102.08 25.52
Eje 5 KG 3.45 6.00 2.00 41.40 23.18
KG 0.58 28.75 2.00 33.35 8.34
7335.98
Eje 6 KG 3.45 6.00 2.00 41.40 23.18
KG 0.58 28.75 2.00 33.35 8.34
7335.98

BASTONES EN COLUMNETAS KG 0.70 108.00 1.00 75.60 18.90

SEGUNDO NIVEL
C-1 KG 3.45 25.00 6.00 517.50 803.16
KG 3.45 27.60 6.00 571.32 567.89
KG 2.28 24.00 6.00 328.32 183.86
C-2 KG 4.45 26.00 4.00 462.80 718.27
KG 4.45 35.60 4.00 633.68 629.88
KG 1.82 28.00 4.00 203.84 114.15
C-3 KG 3.45 27.00 4.00 372.60 578.28
KG 5.86 24.00 4.00 562.56 315.03
C-4 KG 2.90 28.00 4.00 324.80 504.09
KG 1.82 20.00 4.00 145.60 81.54
COLUMNETAS
Eje A KG 1.83 4.00 8.00 58.40 32.70
KG 0.58 18.00 8.00 83.52 20.88
Eje B KG 1.63 4.00 8.00 52.00 29.12
KG 0.58 17.00 8.00 78.88 19.72
BASTONES EN COLUMNETAS KG 0.70 72.00 1.00 50.40 12.60

5.05.00 VIGAS y VIGUETAS


5.05.03 ACERO DE REFUERZO Fy=4200 Kg/cm2
VP 100/200 (30x45) KG 4.30 4.00 8.00 137.60 213.56
KG 4.30 2.00 8.00 68.80 68.39
KG 1.32 27.00 8.00 285.12 159.67
VP 101/201 (30x50) KG 8.00 5.00 2.00 80.00 124.16
KG 8.00 2.00 2.00 32.00 31.81
KG 1.42 52.00 2.00 147.68 82.70
VP (30x35) KG 1.90 4.00 3.00 22.80 35.39
KG 1.12 14.00 3.00 47.04 26.34
VS - 1 (30x35) KG 6.30 6.00 2.00 75.60 75.15
KG 1.12 32.40 2.00 72.58 40.64
VS - 2 (30x35) KG 6.30 4.00 1.00 25.20 39.11
KG 1.12 32.40 1.00 36.29 20.32
CORTE 1-1 (25*20) KG 4.20 5.00 4.00 84.00 83.50
KG 0.72 24.00 4.00 69.12 38.71
CORTE 2-2 (30*20) KG 3.85 6.00 2.00 46.20 45.92
KG 0.82 22.60 2.00 37.06 20.76
KG 2.55 6.00 2.00 30.60 30.42
KG 0.82 17.40 2.00 28.54 15.98
KG 3.50 6.00 2.00 42.00 41.75
KG 0.82 21.20 2.00 34.77 19.47
CORTE 3-3 (30*20) KG 1.90 5.00 2.00 19.00 18.89
KG 0.82 15.00 2.00 24.60 13.78
KG 1.40 5.00 2.00 14.00 13.92
KG 0.82 11.00 2.00 18.04 10.10
CORTE 4-4 (15*20) KG 3.50 4.00 2.00 28.00 27.83
KG 0.52 21.20 2.00 22.05 12.35
CORTE 4'-4' (30*40) KG 1.85 4.00 2.00 14.80 14.71
KG 1.22 15.00 2.00 36.60 20.50
Eje A (0.15x0.20) KG 3.70 2.00 2.00 14.80 8.29
2747.77
KG 2.58 2.00 2.00 10.30 5.77
KG 0.22 39.00 2.00 17.16 4.29
Eje B (0.15x0.20) KG 3.70 2.00 4.00 29.60 16.58
KG 0.22 23.00 4.00 20.24 5.06
KG 3.35 2.00 2.00 13.40 7.50
KG 0.22 20.00 2.00 8.80 2.20
SEGUNDO NIVEL
VP 100/200 (30x45) KG 4.30 4.00 8.00 137.60 213.56
KG 4.30 2.00 8.00 68.80 68.39
KG 1.32 27.00 8.00 285.12 159.67
VP 101/201 (30x50) KG 9.00 5.00 2.00 54.60 84.74
KG 9.00 2.00 2.00 54.60 54.27
KG 1.42 61.00 2.00 173.24 97.01
VP (30x35) KG 3.85 4.00 4.00 61.60 95.60
KG 1.12 22.60 4.00 101.25 56.70
VS - 1 (30x35) KG 6.30 6.00 2.00 75.60 75.15
KG 1.12 32.40 2.00 72.58 40.64
VS - 2 (30x35) KG 6.30 4.00 1.00 25.20 39.11
KG 1.12 32.40 1.00 36.29 20.32
CORTE 1-1 (25*20) KG 4.20 5.00 8.00 168.00 166.99
KG 0.72 24.00 8.00 138.24 77.41
CORTE 2-2 (30*20) KG 1.85 6.00 2.00 22.20 22.07
KG 0.82 14.75 2.00 24.19 13.55
CORTE 2'-2' (30*20) KG 3.50 5.00 1.00 17.50 17.40
KG 0.82 21.20 1.00 17.38 9.74
Eje A (0.15x0.20) KG 3.70 2.00 2.00 14.80 8.29
KG 2.58 2.00 2.00 10.30 5.77
KG 0.22 39.00 2.00 17.16 4.29
Eje B (0.15x0.20) KG 3.70 2.00 4.00 29.60 16.58
KG 0.22 23.00 4.00 20.24 5.06
5.06.00 LOSA ALIGERADA
5.06.03 ACERO DE REFUERZO Fy=4200 Kg/cm2
VIGUETA PRIMER NIVEL KG 13.80 18 1.00 248.40 246.91
KG 13.00 14 1.00 182.00 180.91
1461.75
VIGUETA SEGUNDO NIVEL KG 13.80 20 1.00 276.00 274.34
BASTONES PRIMER NIVEL KG 16.90 18 2.00 608.40 340.70
BASTONES SEGUNDO NIVEL KG 18.70 20 2.00 748.00 418.88

5.07.00 LOSAS MACIZAS


5.07.03 ACERO DE REFUERZO Fy=4200 Kg/cm2
PLATAFORMA KG 1.70 16 1.00 26.35 14.76
34.36
KG 1.50 16 1.00 23.25 13.02
PLATAFORMA KG 3.90 7 1.00 26.33 6.58
KG 3.60 7 1.00 24.30 6.08
5.08.00 ESCALERAS Y GRADERIAS
5.08.03 ACERO DE REFUERZO Fy=4200 Kg/cm2
PRIMER TRAMO
ACERO LONGITUDINAL KG 5.80 7 1.00 40.60 40.36
KG 5.50 7 1.00 38.50 38.27
ACERO TRANSVERSAL KG 1.90 30 1.00 57.00 31.92
235.25
SEGUNDO TRAMO
ACERO LONGITUDINAL KG 4.55 7 1.00 31.85 31.66
KG 4.35 7 1.00 30.45 30.27
KG 1.90 7 2.00 26.60 14.90
ACERO TRANSVERSAL KG 1.90 45 1.00 85.50 47.88
HOJA DE METRADOS ARQUITECTURA: I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO
1.0 MUROS Y TABIQUES DE ALBAÑILERIA UND CANT. LONG ANCHO ALTURA PARCIAL
1.01 MURO DE LADRILLO K.K. TIPO IV APAREJO DE SOGA M2 81.32
PRIMER NIVEL
Eje A 2 3.15 1.28 8.03
2 1.98 1.08 4.25
Eje B 4 3.15 1.08 13.55
SS.HH. 2 2.75 2.60 14.30
1 3.85 2.60 10.01
SEGUNDO NIVEL
Eje A 2 3.15 1.48 9.29
2 1.98 1.48 5.83
Eje B 4 3.15 1.28 16.07
1.02 MURO DE LADRILLO K.K. DE CABEZA M2 137.93
PRIMER NIVEL
Eje 1 1 5.30 2.60 13.78
Eje 3 1 5.30 2.60 13.78
Eje 5 1 5.30 2.60 13.78
EN DIRECCION 1 5.3 2.60 13.78
SS.HH. Y ESCALERA 2 3.45 2.60 17.94
1 2.15 2.60 5.59
SEGUNDO NIVEL
Eje 1 1 5.30 2.60 13.78
Eje 3 1 5.30 2.60 13.78
Eje 5 1 5.30 2.60 13.78
SS.HH. Y ESCALERA 2 3.45 2.60 17.94
2.0 REVOQUES ENLUCIDOS Y MOLDURAS
2.01 TARRAJEO EN MUROS INTERIORES M2 CANT. AREA ANCHO ALTURA PARCIAL 219.25
ITEM Nº 01.01 1 81.32 81.32
ITEM Nº 01.02 1 137.93 137.93
2.02 TARRAJEO EN MUROS EXTERIORES M2 CANT. LONG ANCHO ALTURA PARCIAL 196.50
ITEM Nº 01.01 1 81.32 81.32
ITEM Nº 01.02 1 115.18 115.18
2.03 TARRAJEO DE COLUMNAS M2 CANT. LONG ANCHO ALTURA PARCIAL 39.95
PRIMER NIVEL
C-1 6 0.12 7.30 5.26
C-2 4 0.09 2.50 0.90
C-3 4 0.36 7.30 10.51
C-4 6 0.09 7.30 3.94
PL-1 1 0.48 7.30 3.50
COLUMNETAS 0 0.00 0.00 0.00
Eje A 8 0.02 2.55 0.46
Eje B 8 0.02 2.15 0.39
Eje 5 2 0.02 4.80 0.22
Eje 6 2 0.02 4.80 0.22
SEGUNDO NIVEL 0 0.00
C-1 6 0.12 5.20 3.74
C-2 4 0.09 2.50 0.90
C-3 4 0.36 5.20 7.49
C-4 4 0.09 4.10 1.48
COLUMNETAS 0 0.00 0.00 0.00
Eje A 8 0.02 2.85 0.51
Eje B 8 0.02 2.45 0.44
2.04 TARRAJEO DE VIGAS M2 CANT. LONG ANCHO ALTURA PARCIAL 134.22
PRIMER NIVEL
VP 100/200 (30x45) 2 3.40 0.75 5.10
2 3.45 0.75 5.18
VP 101/201 (30x50) 2 6.80 0.80 10.88
VP (30x35) 3 1.50 0.65 2.93
VS - 1 (30x35) 2 5.90 0.65 7.67
VS - 2 (30x35) 1 5.90 0.65 3.84
CORTE 1-1 (25*20) 4 3.80 0.45 6.84
CORTE 2-2 (30*20) 2 3.45 0.50 3.45
2 2.15 0.50 2.15
2 3.10 0.50 3.10
CORTE 3-3 (30*20) 2 1.50 0.50 1.50
2 1.00 0.50 1.00
CORTE 4-4 (15*20) 2 3.10 0.35 2.17
CORTE 4'-4' (30*40) 2 1.45 0.70 2.03
VIGUETAS 0 0.00 0.00 0.00
Eje A (0.15x0.20) 2 3.40 0.35 2.38
2 2.28 0.35 1.59
Eje B (0.15x0.20) 4 3.40 0.35 4.76
2 3.05 0.35 2.14
SEGUNDO NIVEL
VP 100/200 (30x45) 2 3.40 0.75 5.10
2 3.45 0.75 5.18
VP 101/201 (30x50) 2 7.80 0.80 12.48
VP (30x35) 6 1.50 0.65 5.85
VS - 1 (30x35) 2 5.90 0.65 7.67
VS - 2 (30x35) 1 5.90 0.65 3.84
CORTE 1-1 (25*20) 8 3.80 0.45 13.68
CORTE 2-2 (30*20) 2 1.45 0.50 1.45
CORTE 2'-2' (30*20) 1 3.10 0.50 1.55
VIGUETAS 0 0.00 0.00 0.00
Eje A (0.15x0.20) 2 3.40 0.35 2.38
2 2.28 0.35 1.59
Eje B (0.15x0.20) 4 3.40 0.35 4.76
2.05 VESTIDURA DE DERRAMES M CANT. LONG ANCHO ALTURA PARCIAL 148.12
PUERTA P-1 (AULAS) 4 1.20 2.60 25.60
PUERTA P-2 (ALMACEN) 1 1.00 2.60 6.20
PUERTA P-3 (SS.HH) 2 0.80 2.60 12.00
VENTANA V-1 8 3.50 1.20 67.20
VENTANA VA-1 4 3.50 0.80 22.40
VENTANA VA-2 4 2.30 0.80 14.72
3.0 CIELOS RASOS M2
3.01 CIELO RASO CON MEZCLA C: 1:5 M2 CANT. AREA PARCIAL 245.29
ITEM Nº 05.06.02 (ESTRUCTURAS)
LOSA ALIGERADA 1 245.29
4.0 CUBIERTAS Y ESTRUCTURA DE MADERA
4.01 COBERTURA DE TEJA ANDINA 1.14m x 0.72m X 5 mm M2 CANT. LONG ANCHO ALTURA PARCIAL 234.32
TECHO POSTERIOR AULAS 1 17.80 5.50 97.90
TECHO DELANTERO AULAS 1 17.80 5.20 92.56
TECHO LARGO DE ESCALERA 1 8.08 4.30 34.74
TECHO PEQUEÑO DE ESCALERA 1 2.12 4.30 9.12
4.02 TIJETAL DE ESTRUCTURA DE MADERA Nº 01 UND CANT. LONG ANCHO ALTURA PARCIAL 2.00
2 2.00
4.03 CORREAS DE MADERA TORNILLO 3"X5" ML CANT. LONG ANCHO ALTURA PARCIAL 195.80
AULAS 11 17.80 195.80
4.04 CUMBRERAS ARTICULADAS DE TEJA ANDINA ML CANT. LONG ANCHO ALTURA PARCIAL 20.43
AULAS Y SSHH 1 20.43 20.43
5.0 REVESTIMIENTO ESCALERAS
5.01 REVESTIMIENTO DE ESCALERAS M2 CANT. LONG ANCHO ALTURA PARCIAL 16.43
ITEM Nº 05.09.02 (ESTRUCTURAS) Area 16.43 16.43
6.0 PISOS Y PAVIMENTOS
6.01 CONTRAPISOS 40 mm M2 CANT. AREA PARCIAL 139.31
ITEM Nº 4.02 (ESTRUCTURAS) 1 139.31 139.31
6.02 PISO CERAMICO DE ALTO TRANSITO DE 30 x 30 cm M2 CANT. AREA PARCIAL 7.26
SSHH 1 7.26 7.26
6.03 PISO CONCRETO COLOREADO, ACABADO FROTACHADO M2 CANT. AREA PARCIAL 132.05
TODOS LOS CONTRAPISOS 1 132.05 132.05
7.0 CONTRAZOCALOS
7.01 CONTRAZOCALO SANITARIO DE LOSETA H=0.10M . M CANT. LONG ANCHO ALTURA PARCIAL 4.00
SS HH DE HOMBRE Y MUJERES 1 4.00 4.00
7.02 CONTRAZOCALO DE CEMENTO PULIDO H=0.30M e=1.5 cm. M CANT. LONG ANCHO ALTURA PARCIAL 165.70
ZONAS DE CONTRAPISOS 1 165.70 165.70
8.0 ZOCALOS Y ENCHAPES
8.01 REVESTIMIENTO DE ESCALERAS M2 CANT. LONG ANCHO ALTURA PARCIAL 32.60
2 8.15 2.00 32.60
9.0 CARPINTERIA DE MADERA
9.01 PUERTA DE MADERA CON MARCOS Y BASTIDORES M2 CANT. LONG ANCHO ALTURA PARCIAL 18.56
PUERTA P-1 (AULAS) 5 1.2 2.1 12.60
PUERTA P-2 (ALMACEN) 1 1 2.6 2.60
PUERTA P-3 (SS.HH) 2 0.8 2.1 3.36
9.02 PUERTA CONTRAPLACADA CON MARCOS Y BASTIDORES DE TORNI M2 CANT. LONG ANCHO ALTURA PARCIAL 9.60
SSHH 8 0.6 2 9.60
9.03 VENTANA DE MADERA C/CEDRO SEGUN DISEÑO, INCLUIDO PROTE M2 CANT. LONG ANCHO ALTURA PARCIAL 54.56
VENTANA 8.00 3.50 1.20 33.60
VENTANA 4.00 3.50 0.80 11.20
VENTANA 5.00 2.30 0.80 7.36
VENTANA 4.00 1.20 0.50 2.40
10.0 CARPINTERIA METALICA Y HERRERIA
10.01 BARANDA PASAMANO TUBO DE F° DIAM. 2" INCLUYE PINTADO M CANT. LONG ANCHO ALTURA PARCIAL 15.90
ESCALERA DERECHO 1.00 10.90 10.90
ESCALERA IZQUIERDO 1.00 5.00 5.00
10.02 CANTONERA DE PLANCHA ESTRIADA EN GRADAS DE ESCALERAS M CANT. LONG ANCHO ALTURA PARCIAL 27.00
ESCALONES 18.00 1.50 27.00
11.0 CERRAJERIA CANT. UND ANCHO ALTURA PARCIAL
11.01 BISAGRA ALUMIN. 4" , PESADA EN PUERTAS Pz. 20 4.00 80.00 80.00
11.02 JALADORES CROMADOS UND 20 1.00 20.00 20.00
11.03 CERRADURA DE SEGURIDAD DE SOBREPONER TRES GOLPES UND 12 1.00 12.00 12.00
11.04 CERRADURA DE SEGURIDAD DE EMBUTIR DE PERILLA UND 8 1.00 8.00 8.00
12.0 VIDRIOS, CRISTALES Y SIMILARES
12.01 VIDRIO 6 MM, PROVISION Y COLOCACION EN VENTANAS P2 CANT. FACTOR ANCHO ALTURA PARCIAL 270.47
VENTANA 8.00 10.71 3.50 1.20 33.60
VENTANA 4.00 10.71 3.50 0.80 11.20
VENTANA 5.00 10.71 2.30 0.80 7.36
VENTANA 4.00 10.71 1.20 0.50 2.40
PUERTAS P3 8.00 10.71 1.20 2.10 215.91
13.0 PINTURA
13.01 PINTURA LATEX 2 MANOS EN CIELO RASO Y VIGAS M2 CANT. AREA ANCHO ALTURA PARCIAL 379.50
ITEM Nº 3.01 1 245.29 245.29
ITEM Nº 2.04 1 134.22 134.22
13.02 PINTURA AL LATEX EN MUROS INTERIORES Y EXTERIORES M2 CANT. AREA ANCHO ALTURA PARCIAL 415.75
ITEM Nº 02.01 1 219.25 219.25
ITEM Nº 02.02 1 196.50 196.50
13.03 PINTURA AL LATEX EN COLUMNAS M2 CANT. AREA FACTOR ALTURA PARCIAL 39.95
ITEM Nº 02.03 1 39.95 39.95
13.04 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALOS M2 CANT. AREA FACTOR ALTURA PARCIAL 165.70
ITEM Nº 7.02 1 165.70 165.70
13.05 PINTURA PARA DEMARCACION DE LOSA DEPORTIVA M CANT. LONGITUD FACTOR ALTURA PARCIAL 458.40
FUTBOL 1 250.00 250.00
BASQUETBOL 1 90.40 90.40
VOLEY 1 118.00 118.00
14.0 VARIOS
14.01 ARCO DE FULBITO CON TABLERO DE BASQUET BALL (METAL-MADER
UND CANT. AREA ANCHO ALTURA PARCIAL 2.00
ARCOS 2 2.00
14.02 RED DE VOLEY PARA LOSA DEPORTIVA UND CANT. AREA ANCHO ALTURA PARCIAL 1.00
RED DE VOLEY PARA LOSA DEPORTIVA 1 1.00
14.03 JUNTA DE CONSTRUCCION CON TEKNOPORT M2 CANT. LONGITUD ANCHO ALTURA PARCIAL 3.30
C8 11 0.15 2.00 3.30
C9 10 0.15 3.00 4.50
14.04 JUNTA DE ASFALTICAS ML CANTIDADLONGITUD ANCHO ALTURA PARCIAL 440.00
LOSA 8 30 240.00
10 20 200.00
CANT. AREA 0.00
14.05 PIZARRA ACRILICA UND CANT. AREA ANCHO ALTURA PARCIAL 3.00
AULAS 3 3.00
HOJA DE METRADOS INSTALACIONES SANITARIAS : I.E. Nº 80565 SEÑOR
DE LOS MILAGROS PICHINCHUCO

ITEM DESCRIPCION UND CANT

1.00 DESAGUE
1.01 SUMINISTRO E INSTALACION DE TUBERÍA SAL DIAM. 2" ML 40.00
1.02 SUMINISTRO E INSTALACION DE TUBERÍA SAL DIAM. 4" ML 12.00
1.03 SUMINISTRO E INSTALACION DE TUBERÍA SAL DIAM. 6" ML 26.20
1.04 SALIDA PARA VENTILACION DE 2" PVC INC. SOMBRERO EN TECHO PTO 2.00
1.05 REDUCCION PVC SAL DE 4" x 2" UND 3.00
1.06 REGISTRO ROSCADO DE 4" UND 2.00
1.07 CAJA DE REGISTRO DE 12" x 24" C/TAPA DE CONCRETO UND 3.00
2.00 SISTEMA DE AGUA FRIA
2.01 SALIDA DE AGUA FRIA, PVC PTO 5.00
2.02 TUBERIA PVC CLASE 10 - Ø 1/2" M 8.00
2.03 TEE 1/2 " PVC P/ AGUA UND 3.00
2.04 CODO DE 90º 1/2" PVC P/ AGUA UND 2.00
2.05 VALVULA COMPUERTA DE BRONCE Ø 1/2" UND 1.00
2.06 SUM. E INSTAL. DE TANQUE ELEVADO DE POLIETILENO CAP. 1,100 Lts. GLB 1.00
2.07 SISTEMA DE REBOCE Y LIMPIEZA UND 1.00
3.00 APARATOS Y ACCESORIOS SANITARIOS
3.01 INODORO VITRIFICADO TANQUE BAJO COLOR BLANCO UND 2.00
3.02 OVALIN LOSA SONET UND 2.00
3.03 URINARIOS UND 1.00
3.04 LLAVE CUELLO DE GANZO SIMPLE PARA LAVADERO UND 2.00
4.00 SISTEMA DE EVACUACION DE AGUAS PLUVIALES
4.01 CANALETA DE EVACUACION DE AGUAS PLUVIALES ML 72.00
4.02 TUBERIA DE DRENAJE PVC SAL 4"/PLUVIAL ML 32.00
5.00 TANQUE SÉPTICO
5.01 TRABAJOS PRELIMINARES
5.01.01 LIMPIEZA DE TERRENO MANUAL M2 0.98
5.01.02 TRAZO Y REPLANTEO M2 0.98
5.02 MOVIMIENTO DE TIERRAS
5.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 1.64
5.02.02 CORTE EN MATERIAL SUELTO (PERFILADO GENERAL) M2 0.98
5.02.03 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m M3 1.97
5.03 OBRAS DE CONCRETO SIMPLE
5.03.01 SOLADO DE CONCRETO C:H 1:10 E=10CM M2 0.98
5.04 OBRAS DE CONCRETO ARMADO
5.04.01 TANQUE SEPTICO:CONCRETO f'c=175kg/cm2 M3 0.97
5.04.02 ENCOFRADO Y DESENCOFRADO EN TANQUE SEPTICO M2 6.66
5.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 16.97
5.05 TARRAJEOS
5.05.01 TARRAJEO INT. CON IMPERMEA 1:2 M2 5.33
5.05.02 TARRAJEO EN MUROS EXTERIORES M2 1.02
5.06 ACCESORIOS TANQUE SÉPTICO
5.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS TANQUE SEPTICO GLB 1.00
5.06.02 PRUEBA DE ABSORCIÓN GLB 1.00
5.06.03 TEST DE PERCOLACIÓN GLB 1.00
5.06.04 PRUEBA HIDRÁULICA MAS ESCORRENTÍA PARA DESAGÜE GLB 1.00
6.00 CÁMARA DE SECADO
6.01 TRABAJOS PRELIMINARES
6.01.01 LIMPIEZA DE TERRENO MANUAL M2 1.00
6.01.02 TRAZO Y REPLANTEO M2 1.00
6.02 MOVIMIENTO DE TIERRAS
6.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 1.60
6.02.02 RELLENO CON MATERIAL PROPIO M3 0.13
6.02.03 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m M3 1.77
6.03 OBRAS DE CONCRETO SIMPLE
6.03.01 SOLADO DE CONCRETO C:H 1:10 E=10CM M2 1.00
6.03.02 CONCRETO C:H 1:10 +30% P.G. M3 0.72
6.04 OBRAS DE CONCRETO ARMADO
6.04.01 CAMARA SECA:CONCRETO f'c=175 Kg/cm2 M3 0.58
6.04.02 ENCOFRADO Y DESENCOFRADO EN CAMARA DE SECADO M2 3.84
6.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 4.48
6.05 REVOQUES, ENLUCIDOS Y MOLDURAS
6.05.01 TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZCLA 1:1 M2 7.04
6.05.02 TARRAJEO EN MUROS EXTERIOR IORES 1:4 M2 1.80
6.06 FILTRO DE GRAVA
6.06.01 FILTRO DE GRAVA UND 1.00
6.07 ACCESORIOS TANQUE SÉPTICO
6.07.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS TANQUE SEPTICO GLB 1.00
7.00 POZO DE PERCOLACIÓN
7.01 TRABAJOS PRELIMINARES
7.01.01 LIMPIEZA DE TERRENO MANUAL M2 1.77
7.01.02 TRAZO Y REPLANTEO M2 1.77
7.02 MOVIMIENTO DE TIERRAS
7.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 2.45
7.02.02 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m M3 2.94
7.03 MUROS Y TABIQUES
7.03.01 MURO DE CABEZA LADRILLO CORRIENTE M2 6.91
7.04 OBRAS DE CONCRETO SIMPLE
7.04.01 SOLADO DE CONCRETO C:H 1:10 E=10CM M2 1.77
7.05 OBRAS DE CONCRETO ARMADO
7.05.01 POZO DE PERCOLACION:CONCRETO f'c=175 Kg/cm2 M3 0.36
7.05.02 ENCOFRADO Y DESENCOFRADO EN POZO DE PERCOLACION M2 2.11
7.05.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 19.96
7.06 FILTROS
7.06.01 FILTRO DE GRAVA M3 1.01
7.07 ACCESORIOS DE POZO DE PERCOLACIÓN
7.07.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS POZO DE PERCOLAC GLB 1.00
8.00 CAJA DE REGISTRO
8.01 TRABAJOS PRELIMINARES
8.01.01 LIMPIEZA DE TERRENO MANUAL M2 0.37
8.01.02 TRAZO Y REPLANTEO M2 0.37
8.02 MOVIMIENTO DE TIERRAS
8.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 0.35
8.02.02 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m M3 0.42
8.03 OBRAS DE CONCRETO SIMPLE
8.03.01 SOLADO DE CONCRETO C:H 1:10 E=10CM M2 0.37
8.04 OBRAS DE CONCRETO ARMADO
8.04.01 CAJA DE REGISTRO:CONCRETO f'c=175 Kg/cm2 M3 0.46
8.04.02 ENCOFRADO Y DESENCOFRADO EN CAJA DE REGISTRO M2 3.66
8.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 14.92
8.05 REVOQUES, ENLUCIDOS Y MOLDURAS
8.05.01 TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZCLA 1:1 M2 1.82
8.06 ACCESORIOS CAJA REGISTRO
8.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS EN CAJA DE REGISTR GLB 2.00
9.00 CAJA DE VÁLVULA
9.01 TRABAJOS PRELIMINARES
9.01.01 LIMPIEZA DE TERRENO MANUAL M2 0.16
9.01.02 TRAZO Y REPLANTEO M2 0.16
9.02 MOVIMIENTO DE TIERRAS
9.02.01 EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO M3 0.06
9.02.02 ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m M3 0.08
9.03 OBRAS DE CONCRETO SIMPLE
9.03.01 SOLADO DE CONCRETO C:H 1:10 E=10cm M2 0.16
9.04 OBRAS DE CONCRETO ARMADO
9.04.01 CAJA DE VALVULA:CONCRETO f'c=175 Kg/cm2 M3 0.14
9.04.02 ENCOFRADO Y DESENCOFRADO EN CAJA DE VALVULA M2 1.02
9.04.03 ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 3.58
9.05 REVOQUES, ENLUCIDOS Y MOLDURAS
9.05.01 TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZCLA 1:1 M2 0.40
9.06 ACCESORIOS CAJA DE VÁLVULA
9.06.01 SUMINISTRO E INSTALACIÓN DE ACCESORIOS EN CAJA DE VALVULA GLB 1.00
HOJA DE METRADO - SISTEMA DE DESAGUE - I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO

TANQUE SÉPTICO


UND bloque Nº LARGO ANCHO ALTURA AREA PARCIAL TOTAL
DESCRIPCION
s
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL M2 1 1 1.30 0.75 0.98 0.98
TRAZO Y REPLANTEO M2 1 1 1.30 0.75 0.98 0.98
MOVIMIENTO DE TIERRAS
EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO 1.64
M3 1 1 1.30 0.75 1.68 1.64

CORTE EN MATERIAL SUELTO (PERFILADO GENERAL) M2 1 1 1.30 0.75 0.98 0.98

ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m M3 1 1 1.97 1.97

OBRAS DE CONCRETO SIMPLE

SOLADO DE CONCRETO C:H 1:10 E=10CM 0.98


BASE DE LOSA M2 1 1 1.30 0.75 0.98

OBRAS DE CONCRETO ARMADO


TANQUE SEPTICO:CONCRETO f'c=175kg/cm2 0.97
PISO Y LOSA SUPERIOR M3 1 2 1.30 0.75 0.10 0.20
PAREDES M3 1 2 1.30 0.15 1.48 0.58
M3 1 2 0.45 0.15 1.48 0.20

ENCOFRADO Y DESENCOFRADO EN TANQUE SEPTICO M2 6.66


PAREDES M2 1 2 1.80 1.48 5.33
TAPA M2 1 2 1.80 0.10 0.36
BASE M2 1 1 1.30 0.75 0.98

ACERO DE REFUERZO Fy=4200 Kg/cm2 KG 1 1 D= PESO 16.97


BASE 1 6 0.75 3/8" 0.56 2.52
1 3 1.3 3/8" 0.56 2.18
VIGA 1 8 0.75 3/8" 0.56 3.36
1 8 1.3 3/8" 0.56 5.82
1 8 0.7 1/4" 0.4 2.24
1 3 0.7 1/4" 0.4 0.84

REVOQUES, ENLUCIDOS Y MOLDURAS


TARRAJEO INT. CON IMPERMEA 1:2 M2 5.33
1 2 1.8 1.48 5.33

TARRAJEO EN MUROS EXTERIORES M2 1.02


1 2 1.30 0.15 0.39
1 2 2.10 0.15 0.63

ACCESORIOS TANQUE SÉPTICO


SUMINISTRO E INSTALACIÓN DE ACCESORIOS TANQUE SEPTICO GLB 1 1 1 1.00
PRUEBA DE ABSORCIÓN GLB 1 1 1 1.00
TEST DE PERCOLACIÓN GLB 1 1 1 1.00
PRUEBA HIDRÁULICA MAS ESCORRENTÍA PARA DESAGÜE GLB 1 1 1 1.00
HOJA DE METRADO - SISTEMA DE DESAGUE - I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO

POZO DE PERCOLACIÓN


UND bloque Nº LARGO ANCHO ALTURA AREA PARCIAL TOTAL
DESCRIPCION
s

TRABAJOS PRELIMINARES

LIMPIEZA DE TERRENO MANUAL M2 1 1 1.50 1.77 1.77 1.76625

TRAZO Y REPLANTEO M2 1 1 1.50 1.77 1.77 1.76625

MOVIMIENTO DE TIERRAS
EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO 2.45

ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m MANUAL M3 1 1 2.94 2.94

ALBAÑILERÍA M3 1 1 2.45 1.77 2.45


MUROS Y TABIQUES
MURO DE CABEZA LADRILLO CORRIENTE 6.91
M2 1 1 3.45 2.00 6.91
OBRAS DE CONCRETO SIMPLE

SOLADO DE CONCRETO C:H 1:10 E=10CM 1.77


BASE DE LOSA M2 1 1 1.77 1.77

OBRAS DE CONCRETO ARMADO


POZO DE PERCOLACION:CONCRETO f'c=175 Kg/cm2 0.36
PISO M3 1 1 0.15 1.77 0.26
LOSA-TECHO M3 1 1 1.00 1.00 0.10 0.10
ANILLOS M3 1 1 2.00 0.24 0.15 0.07

ENCOFRADO Y DESENCOFRADO EN POZO DE PERCOLACION M2 2.11


techo M2 1 1 1.77 1.77
techo M2 1 1 3.45 0.10 0.35

ACERO DE REFUERZO Fy=4200 Kg/cm2 KG D= PESO 19.96


LOSA 1 16 1.05 3/8" 0.56 9.41
ANILLOS 1 4 4.71 3/8" 0.56 10.55
TAPA 1 6 0.6 1/4" 0.4 1.44
FILTROS
FILTRO DE GRAVA M3 1.007
M3 1 2 0.21 1.77 0.742
M3 1 1 0.15 1.77 0.265

ACCESORIOS POZO DE PERCOLACION


SUMINISTRO E INSTALACIÓN DE ACCESORIOS POZO DE PERCOLACION GLB 1 1 1 1.00
TUBERIA 4" M 1 1
CODO 4"X 90ª UND 1 1
HOJA DE METRADO - SISTEMA DE DESAGUE - I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO
CÁMARA DE SECADO


DESCRIPCION UND bloque Nº LARGO ANCHO ALTURA AREA PARCIAL TOTAL
s

TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL M2 1 1 1.00 1.00 1.00 1
TRAZO Y REPLANTEO M2 1 1 1.00 1.00 1.00 1
MOVIMIENTO DE TIERRAS
EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO 1.60
M3 1 1 1.00 1.00 1.60 1.60
RELLENO CON MATERIAL PROPIO 0.13
M3 1 2 0.40 0.40 0.40 0.13

ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMAX<=100m M3 1 1 1.77 1.77

OBRAS DE CONCRETO SIMPLE

SOLADO DE CONCRETO C:H 1:10 E=10CM 1.00


BASE DE LOSA M2 1 1 1.00 1.00 1.00

CONCRETO C:H 1:10 +30% P.G. 0.72


CIMIENTO M3 1 2 1.00 0.30 0.40 0.24

OBRAS DE CONCRETO ARMADO


CAMARA SECA:CONCRETO f'c=175 Kg/cm2 0.58
PAREDES M3 1 1 4.00 0.10 1.20 0.48
TAPA M3 1 1 1.00 1.00 0.10 0.10

ENCOFRADO Y DESENCOFRADO EN CAMARA DE SECADO M2 3.84


PAREDES M2 1 2 1.60 1.20 3.84

ACERO DE REFUERZO Fy=4200 Kg/cm2 KG D= PESO 4.48


TAPA 1 8 1 3/8" 0.56 4.48

REVOQUES, ENLUCIDOS Y MOLDURAS


TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZCLA 1:1 M2 7.04
1 2 3.2 1.1 7.04

TARRAJEO EN MUROS EXTERIOR IORES 1:4 M2 1.8


1 1 1.00 1.00 1
1 2 4.00 0.10 0.8
FILTRO DE GRAVA M3 1 1 1
GRAVA DE 1" A 1 1/2" M3 1 1 0.80 0.80 0.15 0.096
GRAVA DE 2" A 3" M3 1 1 0.80 0.80 0.15 0.096
ARENA GRUESA M3 1 1 0.80 0.80 0.15 0.096

ACCESORIOS CAMARA SECADO


SUMINISTRO E INSTALACIÓN DE ACCESORIOS CAMARA SECA GLB 1 1 1 1.00
TUBERIA 4" M 1 1
CODO 90ª UND 1 1
HOJA DE METRADO - SISTEMA DE DESAGUE - I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO

CAJA DE REGISTRO


UND bloque Nº LARGO ANCHO ALTURA AREA PARCIAL TOTAL
DESCRIPCION
s

TRABAJOS PRELIMINARES

LIMPIEZA DE TERRENO MANUAL M2 2 1 0.61 0.30 0.37 0.37

TRAZO Y REPLANTEO M2 2 1 0.61 0.30 0.37 0.37

MOVIMIENTO DE TIERRAS
EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO 0.35
M3 2 1 0.61 0.30 0.95 0.35

ACARREO Y ELIMINACION DE MATERIAL ECEDENTE DMA M3 2 1 0.42 0.42

OBRAS DE CONCRETO SIMPLE

SOLADO DE CONCRETO C:H 1:10 E=10CM 0.37


BASE DE LOSA M2 2 1 0.61 0.30 0.37

OBRAS DE CONCRETO ARMADO


CAJA DE REGISTRO:CONCRETO f'c=175 Kg/cm2 0.46
PISO M3 2 1 0.61 0.30 0.15 0.06
ANCLAJE M3 2 2 0.61 0.10 0.15 0.04
MUROS M3 2 2 0.91 0.10 0.70 0.26
TECHO M3 2 2 0.61 0.30 0.15 0.11

ENCOFRADO Y DESENCOFRADO EN CAJA DE REGISTRO M2 3.66


ANCLAJE M2 2 2 0.61 0.15 0.37
MUROS M2 2 2 0.91 0.70 2.56
TECHO M2 2 1 0.61 0.30 0.37
M2 2 1 1.83 0.10 0.37

ACERO DE REFUERZO Fy=4200 Kg/cm2 KG D= PESO 14.92


2 11 0.7 3/8" 0.56 8.62
2 5 0.61 3/8" 0.56 3.41
TAPA 2 5 0.6 1/4" 0.4 2.40
2 2 0.3 1/4" 0.4 0.48

REVOQUES, ENLUCIDOS Y MOLDURAS


TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZCLA 1:1 M2 2 1 1.30 0.70 1.82 1.82

ACCESORIOS CAJA REGISTRO


SUMINISTRO E INSTALACIÓN DE ACCESORIOS EN CAJA DE GLB 2 1 2 2.00
TUBERIA 4" M 2 1
CODO 4"X 90ª UND 2 1
PERFIL 2"X2"X3/16" M 2 0.4
HOJA DE METRADO - SISTEMA DE DESAGUE - I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO

CAJA DE VÁLVULA


DESCRIPCION UND bloque Nº LARGO ANCHO ALTURA AREA PARCIAL TOTAL
s

TRABAJOS PRELIMINARES

LIMPIEZA DE TERRENO MANUAL M2 1 1 0.40 0.40 0.16 0.16

TRAZO Y REPLANTEO M2 1 1 0.40 0.40 0.16 0.16

MOVIMIENTO DE TIERRAS
EXCAVACION DE ZANJAS MANUAL, MATERIAL ROCA SUELTO 0.06
M3 1 1 0.40 0.40 0.40 0.06

ACARREO Y ELIMINACION DE MATERIAL ECEDEN M3 1 1 0.08 0.08

OBRAS DE CONCRETO SIMPLE

SOLADO DE CONCRETO C:H 1:10 E=10cm 0.16


BASE DE LOSA M2 1 1 0.40 0.40 0.16

OBRAS DE CONCRETO ARMADO


CAJA DE VALVULA:CONCRETO f'c=175 Kg/cm2 0.14
PISO M3 1 1 0.40 0.40 0.15 0.02
ANCLAJE M3 1 2 0.20 0.10 0.15 0.01
MUROS M3 1 2 0.80 0.10 0.40 0.06
TECHO M3 1 2 0.40 0.40 0.15 0.05

ENCOFRADO Y DESENCOFRADO EN CAJA DE VALV M2 1.02


ANCLAJE M2 1 2 0.20 0.15 0.06
MUROS M2 1 2 0.80 0.40 0.64
TECHO M2 1 1 0.40 0.40 0.16
M2 1 1 1.60 0.10 0.16

ACERO DE REFUERZO Fy=4200 Kg/cm2 KG D= PESO 3.58


1 8 0.4 3/8" 0.56 1.79
1 8 0.40 3/8" 0.56 1.79
REVOQUES, ENLUCIDOS Y MOLDURAS
TARRAJEO MUROS INT/IMPERMEABILIZANTES MEZC M2 1 1 1.00 0.40 0.40 0.4

ACCESORIOS CAJA DE VÁLVULA


SUMINISTRO E INSTALACIÓN DE ACCESORIOS EN C GLB 1 1 1 1.00
TUBERIA 4" M 1 1
CODO 4"X 90ª UND 1 1
VÁLVULA UND 1 1
HOJA DE METRADOS INSTALACIONES ELECTRICAS: I.E. Nº 80565 SEÑOR DE LOS MILAGROS PICHINCHUCO

ITEM DESCRIPCION UND CANT

1.0 ALIMENTADOR PRINCIPAL

1.01 TUBERIA PVC-SAP DE 40mm INCLUYE ACCESORIOS M 20.00

1.02 CABLE 3*10mm2 WP+1*10MM2(N)WP(CPI) M 20.00

1.03 CAJA DE FG CUADRADA DE DISTRIBUCION Y PASO DE 350X350X100mm UND 1.00

1.04 POZO DE PUESTA A TIERRA UND 1.00

2.0 COMPONENTES GENERALES DE LA INSTALACION

2.01 CAJA DE FG CUADRADA DE DISTRIBUCIONY PASO DE100mm UND 2.00

2.02 CAJA DE FG OCTOGONAL DE DISTRIBUCIONY PASO DE100mm UND 2.00

3.0 TABLEROS Y SUB TABLEROS ELECTRICOS

3.01 TABLEROS GENERAL(TG) PZA 1.00

3.02 SUBTABLERO DE DISTRIBUCION: PRIMER NIVEL PZA 1.00

3.03 SUBTABLERO DE DISTRIBUCION: SEGUNDO NIVEL PZA 1.00

4.0 ALIMENTADORES SECUNDARIOS

4.01 TUBERIA PVC SAP D=25mm M 208.00

4.02 CABLE TW 6mm2 M 208.00

4.03 CABLE DE COBRE DESNUDO DE 10mm2 M 208.00

5.0 CIRCUITOS DERIVADOS

5.01 CABLE TW 6mm2 M 15.00

5.02 CABLE TW 4mm2 M 15.00

5.03 CABLE TW 2.5mm2 M 624.00

5.04 TUBERIA PVC SAP D= 20mm M 162.00

5.05 TUBERIA PVC SAP D= 25mm M 462.00

5.06 SALIDA PARA CENTRO DE LUZ PTO 22.00

5.07 WALL SOCKET O BRAQUETE PTO 8.00

5.08 SALIDA PARA TOMACORRIENTE USO NORMAL H=1.1 PTO 8.00

5.09 SALIDA PARA ARTEFACTO FLUORESECENTE 2x40 W UND 4.00

5.1 INTERRUPTOR SIMPLE UND 2.00

5.11 INTERRUPTOR DOBLE UND 4.00

5.12 INTERRUPTOR TRIPLE UND 2.00


HOJA DE METRADOS MOBILIARIO Y EQUIPAMIENTO: I.E. Nº 80565 SEÑOR DE LOS
MILAGROS PICHINCHUCO
ITEM DESCRIPCION UND CANT

1.0 MOBILIARIO Y EQUIPAMIENTO

1.01 SILLA DE METAL CON AMDERA PRIMARIA GLB 90.00

1.02 MESA DE METAL CON AMDERA PRIMARIA GLB 90.00

1.03 SILLA DE METAL CON AMDERA PROFESORES GLB 7.00

1.04 MESA DE METAL CON AMDERA PROFESORES GLB 7.00