Está en la página 1de 10

Item Descripción Und.

Metrado
01 OBRAS PROVISIONALES

01.01 CARTEL DE OBRA und 1.00


01.02 ALMACEN Y CASETA DE GUARDIANIA m2 90.00
02 OBRAS PRELIMINARES
02.01 ELEMENTOS DE SEGURIDAD
02.01.01 SEGURIDAD DURANTE LA CONSTRUCCION und 1.00
02.01.02 CERCO PERIMETRICO CON ARPILLA m 90.00
02.02 TRAZO, NIVELACION Y REPLANTEO
02.02.01 TRAZO Y REPLANTEO INICIAL m 959.32
02.02.02 TRAZO Y REPLANTEO DURANTE LA CONSTRUCCION m2 31,100.55
02.03 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPO
02.03.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA und 1.00
03 MOVIMIENTO DE TIERRAS
03.01 CORTES
03.01.01 CORTE DE TERRENO CON MAQUINARIA m3 6,995.98
03.02 EXCAVACIONES
03.02.01 EXCAVACION EN FORMA MANUAL m3 207.34
03.03 ACARREO Y ELIMINACION DE MATERIAL EXCEDENTE
03.03.01 ACARREO DE MATERIAL EXCEDENTE m3 259.17
03.03.02 CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE m3 9,004.15
03.04 PERFILADO Y COMPACTADO EN ZONA DE CORTE
03.04.01 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 10,366.85
04 PAVIMENTO
04.01 SUB RASANTE
04.01.01 MATERIAL SELECCIONADO m3 4,043.07
04.01.02 PERFILADO Y COMPACTADO DE SUB RASANTE m2 3,110.06
04.02 SUB BASE
04.02.01 MATERIAL SELECCIONADO m3 1,347.69
04.02.02 MATERIAL HORMIGON m3 1,244.02
04.02.03 MATERIAL MEZCLADO m3 2,591.71
04.02.04 PERFILADO Y COMPACTADO DE LA SUB BASE m2 10,366.85
04.03 PAVIMENTO RIGIDO
04.03.01 CONCRETO PREMEZCLADO F'C=245 KG/CM2 m3 1,829.32
04.03.02 PAVIMENTO RIGIDO: ENCOFRADO Y DESENCOFRADO m2 567.67
04.03.03 PAVIMENTO RIGIDO: CURADO DE LOSA m2 9,146.59
04.03.04 PAVIMENTO RIGIDO: JUNTA TRANSVERSAL DE CONTRACCION m 2,320.57
04.03.05 PAVIMENTO RIGIDO: SELLADO EN JUNTA TRANSVERSAL DE CONTRACCION m 2,320.57
04.03.06 PAVIMENTO RIGIDO: JUNTA LONGITUDINAL DE CONSTRUCCION m 1,043.50
04.03.07 PAVIMENTO RIGIDO: SELLADO EN JUNTA LONGITUDINAL DE m 1,043.50
CONSTRUCCION
04.03.08 PAVIMENTO RIGIDO: SELLADO DE JUNTAS DE DILATACION m 2,838.35
05 PRUEBAS DE CONTROL DE CALIDAD
05.01 PRUEBAS Y ENSAYOS DE CONTROL DE CALIDAD und 1.00
06 MITIGACION DE IMPACTO AMBIENTAL
06.01 ETAPA PRELIMINAR
06.01.01 REUNION DE CONCERTACION (RESIDENTE - HABITANTES) und 1.00
06.02 ETAPA DE CONSTRUCCION
06.02.01 RIEGO DE LAS VIAS AUXILIARES m2 4,500.00
06.02.02 RIEGO DE MATERIAL EN CANTERA m3 539.08
06.02.03 HABILITACION PROVISIONAL DE LETRINAS INCLUIDO CONEXION und 2.00
06.02.04 HABILITACION PROVISIONAL DE BASUREROS und 2.00
06.02.05 MITIGACION AMBIENTAL und 1.00
06.03 ETAPA DE ABANDONO
06.03.01 RECONFORMACION DE CANTERA ha 0.25
06.03.02 SEMBRADO DE ARBUSTOS und 50.00
06.03.03 RECONFORMACION DE BOTADERO ha 0.25
07 VARIOS, LIMPIEZA Y OTROS

07.01 NIVELACION DE BUZONES und 12.00


07.02 EVALUACION Y REPARACION CONEXIONES DOMICILIARIAS AGUA und 22.00
07.03 EVALUACION Y REPARACION CONEXIONES DOMICILIARIAS DESAGUE und 22.00
07.04 CAMA DE APOYO CONEXIONES DOMICILIARIAS AGUA m 264.00
07.05 CAMA DE APOYO CONEXIONES DOMICILIARIAS DESAGUE m 308.00
07.06 PROTECCION DEL CONCRETO m2 440.00
07.07 LIMPIEZA FINAL DE OBRA m2 9,146.59
01 OBRAS PRELIMINARES
01.01 TRAZO, NIVELACION Y REPLANTEO
01.01.01 TRAZO Y REPLANTEO DURANTE LA CONSTRUCCION m2 3,576.45
01.02 DEMOLICIONES
01.02.01 DEMOLICION DE VEREDAS Y CUNETAS m2 1,765.45
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACIONES
02.01.01 EXCAVACION EN FORMA MANUAL m3 333.72
02.02 ACARREO Y ELIMINACION DE MATERIAL EXCEDENTE
02.02.01 ACARREO DE MATERIAL EXCEDENTE m3 417.15
02.02.02 CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE m3 664.31
02.03 NIVELADO Y COMPACTADO
02.03.01 MATERIAL SELECCIONADO m3 488.57
02.03.02 RELLENO MANUAL CON MATERIAL DE PRESTAMO m3 488.57
02.03.03 NIVELADO Y COMPACTADO C/EQUIPO LIVIANO m2 3,547.73
03 CONCRETO SIMPLE
03.01 SARDINELES
03.01.01 SARDINELES: CONCRETO F'C=175 KG/CM2 m3 98.09
03.01.02 SARDINELES: ENCOFRADO Y DESENCOFRADO m2 527.14
03.01.03 SARDINELES: JUNTA ASFALTICA m 211.15
03.02 VEREDAS
03.02.01 VEREDAS: CONCRETO F'C=175 KG/CM2 E=10CM ACABADO FROTACHADO m2 1,668.61
03.02.02 VEREDAS: CONCRETO F'C=175 KG/CM2 E=10CM ACABADO COLOREADO m2 1,668.61
03.02.03 VEREDAS: ENCOFRADO Y DESENCOFRADO m2 223.35
03.02.04 VEREDAS: JUNTA ASFALTICA m 1,116.75
03.03 RAMPAS
03.03.01 RAMPA: CONCRETO F'C=175 KG/CM2 E=10CM BRUÑADO m2 146.52
03.03.02 RAMPAS: REJILLA METALICA und 36.00
04 PRUEBAS DE CONTROL DE CALIDAD
04.01 PRUEBAS Y ENSAYOS DE CONTROL DE CALIDAD und 1.00
05 MITIGACION DE IMPACTO AMBIENTAL
05.01 ETAPA DE CONSTRUCCION
05.01.01 RIEGO DE MATERIAL EN CANTERA m3 48.86
05.02 ETAPA DE ABANDONO
05.02.01 RECONFORMACION DE BOTADERO ha 0.25
06 VARIOS, LIMPIEZA Y OTROS
06.01 CURADO: SARDINELES, VEREDAS Y RAMPAS m2 3,576.45
06.02 NIVELACION DE CAJAS DE REGISTRO AGUA INSTALACIONES DOMICILIARIAS und 50.00
06.03 NIVELACION DE CAJAS DE REGISTRO DESAGUE INSTALACIONES und 50.00
DOMICILIARIAS
06.04 LIMPIEZA FINAL DE OBRA m2 3,576.45
01 OBRAS PROVISIONALES
01.01 TRAZO, NIVELACION Y REPLANTEO
01.01.01 TRAZO Y REPLANTEO DURANTE LA CONSTRUCCION m2 903.12
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACIONES
02.01.01 EXCAVACION EN FORMA MANUAL m3 14.31
02.02 ACARREO Y ELIMINACION DE MATERIAL EXCEDENTE
Precio S/. Parcial S/.
8,904.25

1,004.05 1,004.05
87.78 7,900.20
20,154.29
2,874.92
1,373.72 1,373.72
16.68 1,501.20
14,879.37
1.57 1,506.13
0.43 13,373.24
2,400.00
2,400.00 2,400.00
127,976.22
41,276.28
5.90 41,276.28
7,611.45
36.71 7,611.45
56,799.76
18.35 4,755.77
5.78 52,043.99
22,288.73
2.15 22,288.73
1,232,328.87
173,727.63
41.10 166,170.18
2.43 7,557.45
115,720.94
41.14 55,443.97
14.37 17,876.57
6.64 17,208.95
2.43 25,191.45
942,880.30
432.40 790,997.97
72.39 41,093.63
1.59 14,543.08
2.47 5,731.81
21.82 50,634.84
2.47 2,577.45
21.82 22,769.17

5.12 14,532.35
4,730.00
4,730.00 4,730.00
20,761.51
578.50
578.50 578.50
19,363.84
0.64 2,880.00
18.52 9,983.76
927.04 1,854.08
573.00 1,146.00
3,500.00 3,500.00
819.17
999.10 249.78
6.59 329.50
959.55 239.89
31,770.99

289.79 3,477.48
145.37 3,198.14
607.34 13,361.48
11.47 3,028.08
10.27 3,163.16
7.40 3,256.00
0.25 2,286.65
13,596.35
1,573.64
0.44 1,573.64
12,022.71
6.81 12,022.71
60,453.76
12,250.86
36.71 12,250.86
11,494.41
18.35 7,654.70
5.78 3,839.71
36,708.49
41.10 20,080.23
15.30 7,475.12
2.58 9,153.14
228,981.67
64,959.95
317.22 31,116.11
62.22 32,798.65
4.95 1,045.19
152,482.56
38.90 64,908.93
42.29 70,565.52
53.90 12,038.57
4.45 4,969.54
11,539.16
54.46 7,979.48
98.88 3,559.68
1,770.00
1,770.00 1,770.00
1,144.78
904.89
18.52 904.89
239.89
959.55 239.89
17,359.41
1.07 3,826.80
98.42 4,921.00
154.35 7,717.50

0.25 894.11
397.37
397.37
0.44 397.37
957.00
525.32
36.71 525.32
431.68
Item Descripción Und.
Metrado Precio S/. Parcial S/.

02.02.01 ACARREO DE MATERIAL EXCEDENTE m3


02.02.02 CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE m3
03 CONCRETO SIMPLE
03.01 CUNETA TIPO I
03.01.01 CUNETA TIPO I: CONCRETO F'C=175 KG/CM2 m3
03.01.02 CUNETA TIPO I: ENCOFRADO Y DESENCOFRADO m2
03.01.03 CUNETA TIPO I: JUNTA ASFALTICA m
03.02 CUNETA TIPO II
03.02.01 CUNETA TIPO II: CONCRETO F'C=210 KG/CM2 m3
03.02.02 CUNETA TIPO II: ENCOFRADO Y DESENCOFRADO m2
03.02.03 CUNETA TIPO II: JUNTA ASFALTICA m
04 PRUEBAS DE CONTROL DE CALIDAD
04.01 PRUEBAS Y ENSAYOS DE CONTROL DE CALIDAD und
05 VARIOS, LIMPIEZA Y OTROS
05.01 CURADO: CUNETAS TIPO I Y II m2
05.02 LIMPIEZA FINAL DE OBRA m2
01 OBRAS PRELIMINARES
01.01 TRAZO, NIVELACION Y REPLANTEO
01.01.01 TRAZO Y REPLANTEO DURANTE LA CONSTRUCCION m2
02 SEÑALIZACION HORIZONTAL
02.01 PINTURA EN SARDINELES m2
02.02 PINTURA EN PAVIMENTO m2
03 SEÑALIZACION VERTICAL
03.01 SEÑALES INFORMATIVAS und
04 VARIOS, LIMPIEZA Y OTROS
04.01 LIMPIEZA FINAL DE OBRA m2
01 OBRAS PRELIMINARES
01.01 TRAZO, NIVELACION Y REPLANTEO
01.01.01 TRAZO Y REPLANTEO DURANTE LA CONSTRUCCION m2
02 MOVIMIENTO DE TIERRAS
02.01 EXCAVACIONES
02.01.01 EXCAVACION EN FORMA MANUAL m3
02.02 ACARREO Y ELIMINACION DE MATERIAL EXCEDENTE
02.02.01 ACARREO DE MATERIAL EXCEDENTE m3
02.02.02 CARGUIO Y ELIMINACION DE MATERIAL EXCEDENTE m3
03 AREAS VERDES, JARDINERAS Y ASIENTOS
03.01 JARDINERIA
03.01.01 JARDINERAS: CONCRETO F'C=175 KG/CM2 m3
03.01.02 JARDINERAS: ENCOFRADO Y DESENCOFRADO m2
03.01.03 JARDINERAS: RELLENO MANUAL CON MATERIAL PROPIO m3
03.01.04 JARDINERAS: PREPARACION DE TERRENO PARA AREA VERDE m3
03.01.05 JARDINERAS: SEMBRADO DE GRASS m2
03.01.06 JARDINERAS: SEMBRADO DE ARBUSTOS Y ARBOLES und
03.02 ASIENTOS DE CONCRETO
03.02.01 ASIENTO TIPO I: CONCRETO F'C=175 KG/CM2 m3
03.02.02 ASIENTO TIPO I: ENCOFRADO Y DESENCOFRADO m2
03.02.03 ASIENTO TIPO I: ACERO GRADO 60 kg
03.02.04 ASIENTO TIPO II: CONCRETO F'C=175 KG/CM2 m3
03.02.05 ASIENTO TIPO II: ENCOFRADO Y DESENCOFRADO m2
03.02.06 ASIENTO TIPO II: ACERO GRADO 60 kg
04 PRUEBAS DE CONTROL DE CALIDAD
04.01 PRUEBAS Y ENSAYOS DE CONTROL DE CALIDAD und
05 VARIOS, LIMPIEZA Y OTROS
05.01 CURADO: JARDINERAS Y ASIENTOS m2
05.02 LIMPIEZA FINAL DE OBRA m2
01 EDUCACION VIAL
17.89 18.35 328.28
17.89 5.78 103.40
51,006.10
41,522.40
119.62 309.10 36,974.54
53.70 62.64 3,363.77
268.50 4.41 1,184.09
9,483.70
21.13 329.58 6,964.03
28.53 62.64 1,787.12
134.66 5.44 732.55
80.00
1.00 80.00 80.00
1,192.12
903.12 1.07 966.34
903.12 0.25 225.78
1,174.88
1,174.88
656.36 1.79 1,174.88
26,563.28
733.66 19.11 14,020.24
656.36 19.11 12,543.04
6,899.25
15.00 459.95 6,899.25
164.09
656.36 0.25 164.09
139.21
139.21
77.77 1.79 139.21
1,684.57
924.72
25.19 36.71 924.72
759.85
31.49 18.35 577.84
31.49 5.78 182.01
45,783.26
39,771.20
39.83 311.86 12,421.38
531.08 45.67 24,254.42
21.73 15.30 332.47
14.48 132.29 1,915.56
36.21 10.48 379.48
71.00 6.59 467.89
6,012.06
2.79 311.86 870.09
35.36 54.31 1,920.40
58.92 5.36 315.81
3.04 311.86 948.05
17.10 54.31 928.70
191.98 5.36 1,029.01
20.00
1.00 20.00 20.00
643.83
583.54 1.07 624.39
77.77 0.25 19.44
1,000.00
Item Descripción Und. Metrado
01.01 EDUCACION VIAL und 1.00

COSTO DIRECTO
GASTOS GENERALES (14.80%)
SUPERVISION (2.60%)
LIQUIDACION (1.25%)
EXPEDIENTE TECNICO (2.40%)

TOTAL PRESUPUESTO
Precio S/. Parcial S/.
1,000.00 1,000.00

1,907,637.06
282,330.28
49,598.56
23,845.46
45,783.29
==================

2,309,194.65

También podría gustarte