CUADRO CONSOLIDADO DE FECHAS QUE ORIGINARON RETRASOS EN OBRA
CAUSALES QUE ORIGINARON RETRAZOS DE OBRA
PRIMERA CAUSAL: DEMORAS ADMINISTRATIVAS SUSTENTADAS

2016 2017 2018


JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

ENTREGA  FECHA DE CULMINACION DE  


REQUERIMIENTO DE FECHA DE INICIO DE OBRA 21/08/2017 03/10/2017 1ra AMPLIACION DE PLAZO
ADQUISICION DE AGREGADO 1ra AMPLIACION DE PLAZO (31/12/2017)          
1 (02/05/2017),           36 DIAS
INFORME Nª 149-2017 GR-
CUSCO/SGNGER-PRT

2015 2017 2018


JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

REQUERIMIENTO DE ENTREGA 
30/08/2017
ADQUISICION DE CEMENTO 21/08/2017
2 08 DIAS
INFORME Nª 149-2017 GR-
CUSCO/SGNGER-PRT

2016 2017 2018


JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

REQUERIMIENTO DE ENTREGA 
05
ADQUISICION DE ACCESORIOS 28/08/2017
3 21/08/2017 DI
INFORME Nª 149-2017 GR-
AS
CUSCO/SGNGER-PRT

2016 2017 2018


JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

REQUERIMIENTO DE ENTREGA 
21/08/2017 11/09/2017
ADQUISICION DE TUBERIA
4 14 DIAS
INFORME Nª 149-2017 GR-
CUSCO/SGNGER-PRT

2016 2017 2018


JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

ENTREGA 
REQUERIMIENTO DE 20/10/2017
ADQUISICION DE PUERTAS Y 08/09/2017
5 53 DIAS
COMPUERTAS INFORME Nª 158-
2017 GR- CUSCO/SGNGER-PRT

2016 2017 2017


JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

ENTREGA 
REQUERIMIENTO DE 27/11/2017
ADQUISICION DE PIEDRA 03/11/2017
6 18 DIAS
GRANDE INFORME Nª 191-2017
GR- CUSCO/SGNGER-PRT

2016 2017 2018


JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

REQUERIMIENTO DE ENTREGA 
22/11/2017 06 30/11/2017
ADQUISICION DE TUBERIA
7 DI
INFORME Nª 220-2017 GR-
AS
CUSCO/SGNGER-PRT

SEGUNDA CAUSAL: REDUCIDA ASIGNACION PRESUPUESTAL

2016 2017 2018


JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC ENE FEB MAR ABR MAY JUN JUL AGO SET OCT NOV DIC

FECHA DE INICIO DE OBRA FECHA DE CULMINACION DE  


1ra AMPLIACION DE PLAZO 1ra AMPLIACION DE PLAZO
RESULOCION DE APROBACION (31/12/2017)          
1 PRESUPUESTAL 6,962,051.14
(02/05/2017),          

ENTREGA 
EN TODO EL PERIODO DE 
EJECUCION DE LA OBRA  21/08/2017 30/11/2017
AFECTO LA REDUCIDA 
ASIGNACION  101 DIAS
TOTAL PARALIZACIONES CON TRASLAPE PRESUPUESTAL

244 DIAS
REDUCIDA ASIGNACION

244 DIAS
TOTAL CON TRASLAPE

TOTAL DIAS DE RETRAZO 244 DIAS