CRONOGRAMA DE ADQUISICION DE MATERIALES

: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

SALON DE USOS MULTIPLES - AULAS


MANO DE OBRA
1 OFICIAL HH 4112.01 11.52 47,370.36 47,370.36
2 OPERADOR DE EQUIPO LIVIANO HH 238.38 13.24 3,156.15 394.52 394.52 394.52 394.52 394.52 394.52 394.52 394.52
3 OPERADOR DE EQUIPO PESADO HH 23.01 13.24 304.65 38.08 38.08 38.08 38.08 38.08 38.08 38.08 38.08
4 OPERARIO HH 9694.25 13.24 128,351.87 16,043.98 16,043.98 16,043.98 16,043.98 16,043.98 16,043.98 16,043.98 16,043.98
5 PEON HH 10300.56 10.38 106,919.81 13,364.98 13,364.98 13,364.98 13,364.98 13,364.98 13,364.98 13,364.98 13,364.98
6 TOPOGRAFO HH 17.08 13.24 226.14 28.27 28.27 28.27 28.27 28.27 28.27 28.27 28.27
MATERIALES
7 ACERO CORRUGADO F`y=4,200 Kg/cm2, GRADO 60 KG 37255.36 4.70 175,100.19 175,100.19
8 AGUA M3 244.47 1.00 244.47 30.56 30.56 30.56 30.56 30.56 30.56 30.56 30.56
9 ALAMBRE NEGRO RECOCIDO # 16 KG 2237.51 4.50 10,068.80 10,068.80
10 ALAMBRE NEGRO RECOCIDO # 8 KG 453.72 4.50 2,041.74 2,041.74
11 ARENA GRUESA M3 212.72 80.00 17,017.60 17,017.60
14 CEMENTO PORTLAND TIPO I (42.5KG) BOL 4769.06 23.80 113,503.63 56,751.81 28,375.91 28,375.91
16 CLAVOS PARA CEMENTO C/C 3" UND 8.24 2.50 20.60 20.60
17 CLAVOS PARA MADERA C/C 3" KG 595.73 4.50 2,680.79 1,340.39 1,340.39
18 ESTACA DE MADERA P2 1.28 1.00 1.28 1.28
20 HORMIGON (PUESTO EN OBRA) M3 65.06 80.00 5,204.80 1,301.20 1,301.20 1,301.20 1,301.20
21 LADRILLO P/TECHO DE 15x30x30 CM 8 HCOS. UND 6105.52 3.80 23,200.98 23,200.98
23 MADERA NACIONAL P/ENCOFRADO-CARP P2 11892.50 3.20 38,056.00 9,514.00 9,514.00 9,514.00 9,514.00
24 MATERIAL AFIRMADO M3 127.82 30.00 3,834.60 3,834.60
25 PIEDRA CHANCADA DE 1/2" M3 169.79 105.00 17,827.95 17,827.95
26 PIEDRA CHANCADA DE 3/4" M3 29.69 100.00 2,969.00 2,969.00
28 TRIPLAY DE 4'x8'x 12 mm PLN 1.25 20.00 25.00 25.00
29 YESO BOL 6.40 4.00 25.60 25.60
30 ANDAMIO DE MADERA P2 1867.08 3.20 5,974.66 746.83 746.83 746.83 746.83 746.83 746.83 746.83 746.83
31 ARENA FINA M3 103.41 100.00 10,340.85 5,170.43 5,170.43
32 ASFALTO RC-250 GLN 4.09 20.00 81.80 81.80
33 BARNIZ PARA MADERA GLN 1.64 42.00 68.88 68.88
34 BISAGRA ALUMINIZ.CAPUCHINA 4"x4" UND 44.00 4.50 198.00 198.00
35 CANTONERAS DE ALUMINIO 2" M 38.90 8.00 311.20 311.20
36 CERRADURA DE TRES GOLPES UND 10.00 45.00 450.00 450.00
37 CLAVOS PARA CEMENTO C/C 2 1/2" UND 76.44 4.50 343.98 343.98
38 CRISTAL TEMPLADO REFLEJANTE VERDE 8 MM + ESTRUCTU Y m2 245.70 420.00 103,194.00 103,194.00
39 CUMBRERA ARTICULADA SUPERIOR PARA TEJA ANDINA PZA 63.29 15.00 949.35 949.35
40 CUMBRERA INFERIOR TEJA ANDINA PZA 63.29 15.00 949.35 949.35
41 FRAGUA DE COLOR KG 123.68 3.50 432.88 432.88
42 IMPERMEABILIZANTE GLN 29.56 25.00 739.00 739.00
43 IMPRIMANTE GLN 422.47 25.00 10,561.75 10,561.75
44 JUNTA FLEXIBLE DE NEOPRENE pln 4.29 45.00 193.05 193.05
45 LADRILLO KING KONG 18 HUECOS 9x12x24 CM UND 22781.88 1.25 28,477.35 28,477.35
46 LIJA PARA CONCRETO HJA 391.87 2.00 783.74 783.74
47 LIJA PARA MADERA hja 0.82 2.00 1.64 1.64
48 MADERA TORNILLO DE 2" X 1" X 10' und 191.10 12.00 2,293.20 2,293.20
49 OCRE ROJO KG 113.92 8.00 911.36 911.36
50 PASTA MURAL gln 60.94 30.00 1,828.20 1,828.20
51 PEGAMENTO PARA PORCELANATO (25KG) BOL 289.13 25.00 7,228.25 7,228.25
52 PINTURA ANTICORROSIVA GLN 9.83 43.00 422.69 422.69
53 PINTURA ESMALTE GLN 28.11 45.00 1,264.95 1,264.95
54 PINTURA LATEX SUPERMATE GLN 115.01 30.00 3,450.30 3,450.30
55 PORCELANATO DE ALTO TRANSITO DE 60x60 m2 595.14 60.00 35,708.40 35,708.40
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

56 PUERTA DE MADERA TORNILLO, INC. COLOC. PINTURA m2 32.83 260.00 8,535.80 8,535.80
57 PUERTA METAL. INC.FABRIC., COLOC, PINTURA m2 9.98 350.00 3,493.00 3,493.00
58 REGLA DE ALUMINIO 1.5"x4"X10 pza 31.48 25.00 787.00 787.00
59 SELLADOR GLN 79.33 20.00 1,586.60 1,586.60
60 SOLDADURA CELLOCORD P 3/16" KG 6.14 12.00 73.68 73.68
61 TAPAPOROS DE MADERA ACABADA C/BARNIZ O LACA GLN 1.97 45.00 88.65 88.65
62 TARUGO DE PLASTICO 1/4"x2" UND 615.48 0.30 184.64 184.64
63 TEJA ANDINA ETERNIT 1.18 M X 0.745M X 5MM PZA 443.15 27.00 11,965.05 11,965.05
64 THINER GLN 1.31 15.00 19.65 19.65
65 TIRAFON DE 1/4" x 5" CON CAPUCHA UND 677.13 1.00 677.13 677.13
66 TUBO FIERRO GALVANIZADO DE 2" M 307.18 20.00 6,143.60 6,143.60
67 TUBO FIERRO GALVANIZADO DE 3" M 270.31 25.00 6,757.75 6,757.75
68 VENTANAS DE ALUM. VIDRIO 6MM SIST. VITROVEN INCL. INSTAL. m2 52.44 110.00 5,768.40 5,768.40
69 CABLE ELECTRICO 2.5 mm2 - LSOH M 989.42 1.40 1,385.19 1,385.19
70 CABLE ELECTRICO 4.0 mm2 - LSOH M 1339.79 1.80 2,411.62 2,411.62
71 CABLE ELECTRICO TW - 2 x 6 mm2 - LSOH M 112.74 15.00 1,691.10 1,691.10
72 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 92.00 1.00 92.00 92.00
73 CAJA RECTANGULAR DE 58mm x 93mm UND 86.00 1.00 86.00 86.00
74 CINTA AISLANTE RLL 28.54 5.00 142.70 142.70
75 CURVA PVC SAP LUZ 3/4" PZA 92.00 0.50 46.00 46.00
76 CURVAS PVC SAP 3/4" und 274.90 0.50 137.45 137.45
77 CURVAS PVC SEL 3/4" UND 31.53 0.50 15.77 15.77
78 FLUORES. RECTO ISPE 2X20 W C/EQ + PANT UND 20.00 55.00 1,100.00 1,100.00
79 FLUORES. RECTO ISPE 2X36 W C/EQ + PANT UND 52.00 60.00 3,120.00 3,120.00
80 FLUORES. RECTO ISPE 3X36 W C/EQ + PANT UND 12.00 65.00 780.00 780.00
81 FOCO AHORRADOR DE 100 W UND 7.00 8.00 56.00 56.00
82 INTERRUPTOR CONMUTACION PZA 4.00 8.00 32.00 32.00
83 INTERRUPTOR DOBLE UND 7.00 7.00 49.00 49.00
84 INTERRUPTOR SIMPLE PZA 11.00 4.50 49.50 49.50
85 INTERRUPTOR TERMOMAGNETICO DE 2x20Ax240V UND 4.00 32.00 128.00 128.00
86 INTERRUPTOR TERMOMAGNETICO DE 2x30A UND 3.00 35.00 105.00 105.00
87 INTERRUPTOR TERMOMAGNETICO MONOFASICO 2X10A pza 3.00 25.00 75.00 75.00
88 INTERRUPTOR TERMOMAGNETICO MONOFASICO 2X15A pza 9.00 30.00 270.00 270.00
89 INTERRUPTOR TRIPLE UND 1.00 7.00 7.00 7.00
90 PEGAMENTO PARA PVC GLN 4.28 45.00 192.60 192.60
91 POZO DE PUESTA A TIERRA INC. EQUIPOS MATERIAL E INSTALA GLB 1.00 850.00 850.00 850.00
92 SPOTH LIGHT INCLUYE/ACCESORIOS UND 7.00 10.00 70.00 70.00
93 TABLERO DE DISTRIBUCION DE 08 CIRC.PLANCHA GALV. UND 4.00 150.00 600.00 600.00
94 TOMACORRIENTE BIPOLAR DOBLE CON LINEA A TIERRA UND 63.00 12.00 756.00 756.00
95 TUBO PVC SAP (E/C) 3/4" X 3.00 M. m 824.71 0.90 742.24 742.24
96 TUBO PVC SAP 25 mm X 3 MTS. UND 21.47 1.10 23.62 23.62
97 TUBO PVC SEL (E/C) 3/4" X 3.00 M. m 66.15 0.90 59.54 59.54
98 CODO PVC SAL 3" X 90 UND 24.00 2.50 60.00 60.00
99 TUBO PVC SAL 3" M 109.73 3.50 384.06 384.06

MAQUINQRIA, EQUIPOS Y HERRAMIENTAS


97 CAMION VOLQUETE 15 M3. hm 0.83 160.00 132.80 16.60 16.60 16.60 16.60 16.60 16.60 16.60 16.60
98 CARGADOR SOBRE LLANTAS 125 HP 2.5 YD3. HM 1.68 220.00 369.60 369.60
99 CIZALLA PARA CORTE DE FIERRO HM 728.93 2.50 1,822.33 227.79 227.79 227.79 227.79 227.79 227.79 227.79 227.79
100 COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP HM 275.36 20.00 5,507.20 688.40 688.40 688.40 688.40 688.40 688.40 688.40 688.40
101 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 259.18 25.00 6,479.50 6,479.50
102 MIRAS Y JALONES HM 34.10 1.00 34.10 4.26 4.26 4.26 4.26 4.26 4.26 4.26 4.26
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

103 TEODOLITO HM 17.08 20.00 341.60 42.70 42.70 42.70 42.70 42.70 42.70 42.70 42.70
104 VIBRADOR DE CONCRETO 3/4" - 2" HM 166.84 15.00 2,502.60 312.83 312.83 312.83 312.83 312.83 312.83 312.83 312.83
105 MOTOSOLDADORA DE 250 AMP. HM 16.37 30.00 491.10 61.39 61.39 61.39 61.39 61.39 61.39 61.39 61.39
106 HERRAMIENTAS MANUALES %MO 8,531.09 1,066.39 1,066.39 1,066.39 1,066.39 1,066.39 1,066.39 1,066.39 1,066.39

CENTRO DE COMPUTO, LABORATORIO Y AULAS

MANO DE OBRA
107 TOPOGRAFO HH 15.02 13.24 198.86 24.86 24.86 24.86 24.86 24.86 24.86 24.86 24.86
108 OPERADOR DE EQUIPO LIVIANO HH 105.63 13.24 1,398.54 174.82 174.82 174.82 174.82 174.82 174.82 174.82 174.82
109 OPERADOR DE EQUIPO PESADO HH 20.69 13.24 273.94 34.24 34.24 34.24 34.24 34.24 34.24 34.24 34.24
110 OPERARIO HH 4913.53 13.24 65,055.14 8,131.89 8,131.89 8,131.89 8,131.89 8,131.89 8,131.89 8,131.89 8,131.89
111 OFICIAL HH 2260.30 11.52 26,038.66 3,254.83 3,254.83 3,254.83 3,254.83 3,254.83 3,254.83 3,254.83 3,254.83
112 PEON HH 5130.89 10.38 53,258.64 6,657.33 6,657.33 6,657.33 6,657.33 6,657.33 6,657.33 6,657.33 6,657.33

MATERIALES
113 ACERO CORRUGADO F`y=4,200 Kg/cm2, GRADO 60 KG 14804.85 4.70 69582.795 69,582.80
114 AGUA M3 126.89 1.00 126.89 126.89
115 ALAMBRE NEGRO RECOCIDO # 16 KG 871.60 4.50 3922.2 3,922.20
116 ALAMBRE NEGRO RECOCIDO # 8 KG 223.29 4.50 1004.8095 1,004.81
117 ARENA FINA M3 55.29 100.00 5529.45 5,529.45
118 ARENA GRUESA M3 115.83 80.00 9266.4 9,266.40
119 CEMENTO PORTLAND TIPO I (42.5KG) BOL 2501.26 23.80 59529.988 29,764.99 29,764.99
120 CLAVOS PARA CEMENTO C/C 3" UND 18.98 2.50 47.45 47.45
121 CLAVOS PARA MADERA C/C 3" KG 240.29 4.50 1081.305 1,081.31
122 ESTACA DE MADERA P2 1.12 1.00 1.12 1.12
123 HORMIGON (PUESTO EN OBRA) M3 31.33 80.00 2506.4 2,506.40
124 LADRILLO P/TECHO DE 15x30x30 CM 8 HCOS. UND 3173.87 3.80 12060.706 12,060.71
125 MADERA NACIONAL P/ENCOFRADO-CARP P2 5311.08 3.20 16995.456 16,995.46
126 MATERIAL AFIRMADO M3 22.12 30.00 663.6 663.60
127 PIEDRA CHANCADA DE 1/2" M3 76.91 105.00 8075.55 8,075.55
128 PIEDRA CHANCADA DE 3/4" M3 27.98 100.00 2798 2,798.00
129 TRIPLAY DE 4'x8'x 12 mm PLN 1.05 20.00 21 21.00
130 YESO BOL 5.62 4.00 22.48 22.48
131 ANDAMIO DE MADERA P2 801.11 3.20 2563.552 2,563.55
132 ASFALTO RC-250 GLN 4.43 20.00 88.6 88.60
133 BARNIZ PARA MADERA GLN 1.24 42.00 52.08 52.08
134 BISAGRA ALUMINIZ.CAPUCHINA 4"x4" UND 20.00 4.50 90 90.00
135 CANTONERAS DE ALUMINIO 2" M 42.00 8.00 336 336.00
136 CERAMICO ANTIDESLIZANTE DE 40X40CM M2 80.29 28.00 2248.12 2,248.12
137 CERAMICO DE 20 X 30 CM M2 72.42 22.00 1593.24 1,593.24
138 CERRADURA DE TRES GOLPES UND 5.00 45.00 225 225.00
139 CLAVOS PARA CEMENTO C/C 2 1/2" UND 44.74 4.50 201.33 201.33
140 CRISTAL TEMPLADO REFLEJANTE VERDE 8 MM + ESTRUCTU Y m2 109.01 420.00 45784.2 45,784.20
141 CUMBRERA ARTICULADA SUPERIOR PARA TEJA ANDINA PZA 41.01 15.00 615.15 615.15
142 CUMBRERA INFERIOR TEJA ANDINA PZA 41.01 15.00 615.15 615.15
143 FRAGUA DE COLOR KG 108.78 3.50 380.73 380.73
144 IMPERMEABILIZANTE GLN 31.18 25.00 779.5 779.50
145 IMPRIMANTE GLN 196.56 25.00 4914 4,914.00
146 JUNTA FLEXIBLE DE NEOPRENE pln 4.85 45.00 218.25 218.25
147 LADRILLO KING KONG 18 HUECOS 9x12x24 CM UND 16699.14 1.25 20873.925 20,873.93
148 LIJA PARA CONCRETO HJA 178.09 2.00 356.18 356.18
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

149 LIJA PARA MADERA hja 0.62 2.00 1.24 1.24


150 MADERA TORNILLO DE 2" X 1" X 10' und 111.85 12.00 1342.2 1,342.20
151 OCRE ROJO KG 47.59 8.00 380.72 380.72
152 PASTA MURAL gln 27.68 30.00 830.4 830.40
153 PEGAMENTO PARA CERMICOS kg 727.20 1.50 1090.8 1,090.80
154 PEGAMENTO PARA PORCELANATO (25KG) BOL 104.36 25.00 2609 2,609.00
155 PINTURA ANTICORROSIVA GLN 3.59 43.00 154.37 154.37
156 PINTURA ESMALTE GLN 18.56 45.00 835.2 835.20
157 PINTURA LATEX SUPERMATE GLN 48.73 30.00 1461.9 1,461.90
158 PORCELANATO DE ALTO TRANSITO DE 60x60 m2 218.41 60.00 13104.6 13,104.60
159 PUERTA DE MADERA TORNILLO, INC. COLOC. PINTURA m2 12.39 260.00 3221.4 3,221.40
160 REGLA DE ALUMINIO 1.5"x4"X10 pza 16.15 25.00 403.75 403.75
161 SELLADOR GLN 31.03 20.00 620.6 620.60
162 SOLDADURA CELLOCORD P 3/16" KG 2.24 12.00 26.88 26.88
163 TAPAPOROS DE MADERA ACABADA C/BARNIZ O LACA GLN 1.49 45.00 67.05 67.05
164 TARUGO DE PLASTICO 1/4"x2" UND 485.74 0.30 145.722 145.72
165 TEJA ANDINA ETERNIT 1.18 M X 0.745M X 5MM PZA 349.73 27.00 9442.71 9,442.71
166 THINER GLN 0.61 15.00 9.15 9.15
167 TIRAFON DE 1/4" x 5" CON CAPUCHA UND 525.69 1.00 525.69 525.69
168 TUBO FIERRO GALVANIZADO DE 2" M 98.71 25.00 2467.75 2,467.75
169 TUBO FIERRO GALVANIZADO DE 3" M 112.18 20.00 2243.6 2,243.60
170 VENTANAS DE ALUM. VIDRIO 6MM SIST. VITROVEN INCL. INSTAL. m2 44.90 110.00 4939 4,939.00
171 CABLE ELECTRICO 2.5 mm2 - LSOH M 455.24 1.40 637.336 637.34
172 CABLE ELECTRICO 4.0 mm2 - LSOH M 860.69 1.80 1549.242 1,549.24
173 CABLE ELECTRICO TW - 2 x 6 mm2 - LSOH M 64.45 15.00 966.75 966.75
174 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 43.00 1.00 43 43.00
175 CAJA RECTANGULAR DE 58mm x 93mm UND 106.00 1.00 106 106.00
176 CINTA AISLANTE RLL 21.04 12.00 252.48 252.48
177 CURVA PVC SAP LUZ 3/4" PZA 43.00 0.50 21.5 21.50
178 CURVAS PVC SAP 3/4" und 155.32 0.50 77.66 77.66
179 CURVAS PVC SEL 3/4" UND 11.00 0.50 5.5 5.50
180 CURVAS PVC SEL 3/4" UND 6.48 0.50 3.24 3.24
181 FLUORES. RECTO ISPE 2X20 W C/EQ + PANT UND 11.00 55.00 605 605.00
182 FLUORES. RECTO ISPE 2X36 W C/EQ + PANT UND 24.00 60.00 1440 1,440.00
183 FLUORES. RECTO ISPE 3X36 W C/EQ + PANT UND 8.00 65.00 520 520.00
184 INTERRUPTOR CONMUTACION PZA 2.00 8.00 16 16.00
185 INTERRUPTOR DOBLE UND 3.00 7.00 21 21.00
186 INTERRUPTOR SIMPLE PZA 4.00 4.50 18 18.00
187 INTERRUPTOR TERMOMAGNETICO DE 2x20Ax240V UND 5.00 32.00 160 160.00
188 INTERRUPTOR TERMOMAGNETICO DE 2x30A UND 1.00 35.00 35 35.00
189 INTERRUPTOR TERMOMAGNETICO DE 2x50A UND 1.00 50.00 50 50.00
190 INTERRUPTOR TERMOMAGNETICO MONOFASICO 2X10A pza 2.00 25.00 50 50.00
191 INTERRUPTOR TERMOMAGNETICO MONOFASICO 2X15A pza 5.00 30.00 150 150.00
192 INTERRUPTOR TRIPLE UND 4.00 7.00 28 28.00
193 PEGAMENTO PARA PVC GLN 2.37 45.00 106.65 106.65
194 POZO DE PUESTA A TIERRA INC. EQUIPOS MATERIAL E INSTALA GLB 1.00 850.00 850 850.00
195 TABLERO DE DISTRIBUCION DE 08 CIRC.PLANCHA GALV. UND 2.00 35.00 70 70.00
196 TOMACORRIENTE BIPOLAR DOBLE CON LINEA A TIERRA UND 93.00 5.50 511.5 511.50
197 TUBO PVC SAP (E/C) 3/4" X 3.00 M. m 465.97 0.90 419.373 419.37
198 TUBO PVC SAP 25 mm X 3 MTS. UND 11.10 1.10 12.21 12.21
199 TUBO PVC SEL (E/C) 1" X 3.00 M. Ml 93.00 3.00 279 279.00
200 TUBO PVC SEL (E/C) 3/4" X 3.00 M. m 65.10 0.90 58.59 58.59
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

201 CINTA TEFLON RLL 1.10 1.70 1.87 1.87


202 CODO PVC SAL 2" X 90 UND 8.00 3.50 28 28.00
203 CODO PVC SAL 3" X 90 UND 12.00 2.50 30 30.00
204 CODO PVC SAP 1/2" X 90 UND 26.00 1.00 26 26.00
205 CODOS PVC SAL 2" X 45 PZA 8.40 2.50 21 21.00
206 CODOS PVC SAL 2" X 90 PZA 9.00 2.00 18 18.00
207 GRIFERIA PARA LAVATORIOS TIPO CUELLO DE GANSO DE 1RA UND 9.00 95.00 855 855.00
208 LAVATORIOS DE ACERO INOXIDABLE DE 1 POZA INC/ACCESORIOPZA 9.00 220.00 1980 1,980.00
209 NIPLE DE Fo Go DE 1/2" x 1" UND 4.00 1.90 7.6 7.60
210 REGISTRO DE BRONCE DE 2" UND 4.00 5.00 20 20.00
211 SUMIDERO DE BRONCE DE 2" UND 8.00 6.00 48 48.00
212 TAPA C/MARCO FF DE DESAGUE 12" X 24" PZA 1.00 20.00 20 20.00
213 TEE PVC SAP DE 1/2" UND 6.00 1.00 6 6.00
214 TEE SANITARIA SIMP C/REDUC PVC SAL 4"A2" UND 8.00 3.50 28 28.00
215 TEE SANITARIA SIMPLE PVC SAL DE 2" UND 4.00 2.20 8.8 8.80
216 TUBERIA PVC SAL PARA DESAGUE DE 2" M 66.55 5.40 359.37 359.37
217 TUBERIA PVC SAP PRESION PARA AGUA C-10 R. 1/2" M 53.55 1.90 101.745 101.75
218 TUBO DE ABASTO 1/2" x 1/2" PLOMO UND 9.00 12.00 108 108.00
219 TUBO PVC SAL 3" M 33.01 3.50 115.535 115.54
220 UNION DE F GALVANIZADO DE 1/2" UND 2.00 1.80 3.6 3.60
221 VALVULA COMPUERTA BRONCE 1/2" UND 2.00 18.00 36 36.00
222 YEE PVC SAL DE 2" X 2" PZA 10.50 2.50 26.25 26.25

MAQUINARIA, EQUIPOS Y HERRAMIENTAS


223 TEODOLITO HM 15.02 20.00 300.40 37.55 37.55 37.55 37.55 37.55 37.55 37.55 37.55
224 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 135.39 25.00 3,384.75 423.09 423.09 423.09 423.09 423.09 423.09 423.09 423.09
225 MIRAS Y JALONES HM 29.98 1.00 29.98 29.98
226 COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP HM 120.12 20.00 2,402.40 300.30 300.30 300.30 300.30 300.30 300.30 300.30 300.30
227 CAMION VOLQUETE 15 M3. hm 0.42 160.00 67.20 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
228 CARGADOR SOBRE LLANTAS 125 HP 2.5 YD3. HM 0.86 220.00 189.20 23.65 23.65 23.65 23.65 23.65 23.65 23.65 23.65
229 CIZALLA PARA CORTE DE FIERRO HM 319.47 2.50 798.68 99.83 99.83 99.83 99.83 99.83 99.83 99.83 99.83
230 VIBRADOR DE CONCRETO 3/4" - 2" HM 88.84 15.00 1,332.60 166.58 166.58 166.58 166.58 166.58 166.58 166.58 166.58
231 MOTOSOLDADORA DE 250 AMP. HM 5.98 30.00 179.40 22.43 22.43 22.43 22.43 22.43 22.43 22.43 22.43
232 HERRAMIENTAS MANUALES %MO 1.00 4525.84 4,525.84 565.73 565.73 565.73 565.73 565.73 565.73 565.73 565.73

SERVICIOS HIGIENICOS
MANO DE OBRA
233 TOPOGRAFO HH 5.06 13.24 66.99 33.50 16.75 16.75
234 OPERADOR DE EQUIPO LIVIANO HH 17.73 13.24 234.75 234.75
235 OPERARIO HH 1,834.46 13.24 24,288.25 12,144.13 6,072.06 6,072.06
236 OFICIAL HH 475.23 11.52 5,474.65 2,737.32 1,368.66 1,368.66
237 PEON HH 1,422.79 10.38 14,768.56 7,384.28 3,692.14 3,692.14

MATERIALES
238 ACERO CORRUGADO F`y=4,200 Kg/cm2, GRADO 60 KG 2479.22 4.70 11,652.33 11,652.33
239 AGUA M3 40.65 1.00 40.65 40.65
240 ALAMBRE NEGRO RECOCIDO # 16 KG 147.90 4.50 665.55 665.55
241 ALAMBRE NEGRO RECOCIDO # 8 KG 53.69 4.50 241.61 241.61
242 ARENA FINA M3 14.25 100.00 1,424.86 1,424.86
243 ARENA GRUESA M3 23.80 80.00 1,903.84 1,903.84
244 CEMENTO PORTLAND TIPO I (42.5KG) BOL 573.53 23.80 13,650.01 13,650.01
245 CLAVOS PARA CEMENTO C/C 3" UND 5.86 2.50 14.65 14.65
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

246 CLAVOS PARA MADERA C/C 3" KG 60.07 4.50 270.32 270.32
247 ESTACA DE MADERA P2 0.38 1.00 0.38 0.38
248 HORMIGON (PUESTO EN OBRA) M3 23.65 80.00 1,892.00 1,892.00
249 LADRILLO P/TECHO DE 15x30x30 CM 8 HCOS. UND 666.33 3.80 2,532.05 2,532.05
250 MADERA NACIONAL P/ENCOFRADO-CARP P2 1060.71 3.20 3,394.27 3,394.27
251 MATERIAL AFIRMADO M3 5.08 30.00 152.40 152.40
252 PIEDRA CHANCADA DE 1/2" M3 13.89 105.00 1,458.45 1,458.45
253 PIEDRA CHANCADA DE 3/4" M3 6.44 100.00 644.00 644.00
254 PIEDRA GRANDE DE 8" M3 6.44 65.00 418.60 418.60
255 PIEDRA MEDIANA DE 4" M3 1.83 60.00 109.80 109.80
256 YESO BOL 1.90 4.00 7.60 7.60
257 ANDAMIO DE MADERA P2 157.73 3.20 504.74 504.74
258 ASFALTO RC-250 GLN 1.34 20.00 26.80 26.80
259 BARANDA METALICA PARA DISCAPACITADOS EN SS.HH. Ml 1.37 68.00 93.16 93.16
260 BARNIZ PARA MADERA GLN 0.99 42.00 41.58 41.58
261 BISAGRA ALUMINIZ.CAPUCHINA 4"x4" UND 20.00 4.50 90.00 90.00
262 CERAMICO ANTIDESLIZANTE DE 40X40CM M2 53.00 28.00 1,484.00 1,484.00
263 CERAMICO DE 20 X 30 CM M2 105.84 22.00 2,328.48 2,328.48
264 CERRADURA DE TRES GOLPES UND 5.00 45.00 225.00 225.00
265 CLAVOS PARA CEMENTO C/C 2 1/2" UND 14.55 4.50 65.48 65.48
266 CUMBRERA ARTICULADA SUPERIOR PARA TEJA ANDINA PZA 13.34 15.00 200.10 200.10
267 CUMBRERA INFERIOR TEJA ANDINA PZA 13.34 15.00 200.10 200.10
268 FRAGUA DE COLOR KG 52.97 3.50 185.40 185.40
269 IMPERMEABILIZANTE GLN 12.16 25.00 304.00 304.00
270 IMPRIMANTE GLN 44.98 25.00 1,124.50 1,124.50
271 JUNTA FLEXIBLE DE NEOPRENE pln 2.18 45.00 98.10 98.10
272 LADRILLO KING KONG 18 HUECOS 9x12x24 CM UND 5576.52 1.25 6,970.65 6,970.65
273 LIJA PARA CONCRETO HJA 38.90 2.00 77.80 77.80
274 LIJA PARA MADERA hja 0.49 2.00 0.98 0.98
275 MADERA TORNILLO DE 2" X 1" X 10' und 36.37 12.00 436.44 436.44
276 MELAMINA DE COLOR DE 18MM M2 52.63 45.00 2,368.35 2,368.35
277 OCRE ROJO KG 4.74 8.00 37.92 37.92
278 PASTA MURAL gln 5.92 30.00 177.60 177.60
279 PEGAMENTO PARA CERMICOS kg 756.40 1.50 1,134.60 1,134.60
280 PERFIL "U" ALUMINIO DE 1/2" M 150.36 5.50 826.98 826.98
281 PINTURA ESMALTE GLN 2.86 45.00 128.70 128.70
282 PINTURA LATEX SUPERMATE GLN 13.37 30.00 401.10 401.10
283 PUERTA DE MADERA TORNILLO, INC. COLOC. PINTURA m2 9.87 260.00 2,566.20 2,566.20
284 REGLA DE ALUMINIO 1.5"x4"X10 pza 4.13 25.00 103.25 103.25
285 SELLADOR GLN 7.20 20.00 144.00 144.00
286 TAPAPOROS DE MADERA ACABADA C/BARNIZ O LACA GLN 1.18 45.00 53.10 53.10
287 TARUGO DE PLASTICO 1/4"x2" UND 181.86 0.30 54.56 54.56
288 TEJA ANDINA ETERNIT 1.18 M X 0.745M X 5MM PZA 130.94 27.00 3,535.38 3,535.38
289 THINER GLN 0.20 15.00 3.00 3.00
290 TIRAFON DE 1/4" x 5" CON CAPUCHA UND 194.85 1.00 194.85 194.85
291 TORNILLOS PARA MADERA 5/8" x 1 UND 200.48 0.15 30.07 30.07
292 TUBO DE ALUMINIO CUADRADO DE 1/2" X 2" Ml 55.74 9.00 501.66 501.66
293 VENTANAS DE ALUM. VIDRIO 6MM SIST. VITROVEN INCL. INSTAL. m2 10.97 110.00 1,206.70 1,206.70
294 CABLE ELECTRICO 2.5 mm2 - LSOH M 123.67 1.40 173.14 173.14
295 CABLE ELECTRICO 4.0 mm2 - LSOH M 176.34 1.80 317.41 317.41
296 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 10.00 1.00 10.00 10.00
297 CAJA RECTANGULAR DE 58mm x 93mm UND 10.00 1.00 10.00 10.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

298 CINTA AISLANTE RLL 2.00 5.00 10.00 10.00


299 CURVA PVC SAP LUZ 3/4" PZA 10.00 0.50 5.00 5.00
300 CURVAS PVC SAP 3/4" und 34.99 0.70 24.49 24.49
301 CURVAS PVC SEL 3/4" UND 10.00 0.50 5.00 5.00
302 FLUORES. RECTO ISPE 2X20 W C/EQ + PANT UND 2.00 55.00 110.00 110.00
303 FLUORES. RECTO ISPE 2X36 W C/EQ + PANT UND 2.00 60.00 120.00 120.00
304 FLUORESCENTE CIRCULAR 40 W INCL. EQUIP. + PANT. UND 6.00 25.00 150.00 150.00
305 INTERRUPTOR DOBLE UND 4.00 7.00 28.00 28.00
306 INTERRUPTOR SIMPLE PZA 6.00 4.50 27.00 27.00
307 INTERRUPTOR TERMOMAGNETICO DE 2x20Ax240V UND 2.00 32.00 64.00 64.00
308 INTERRUPTOR TERMOMAGNETICO DE 2x30A UND 1.00 35.00 35.00 35.00
309 INTERRUPTOR TERMOMAGNETICO MONOFASICO 2X15A pza 2.00 30.00 60.00 60.00
310 PEGAMENTO PARA PVC GLN 1.95 45.00 87.75 87.75
311 POZO DE PUESTA A TIERRA INC. EQUIPOS MATERIAL E INSTALA GLB 1.00 850.00 850.00 850.00
312 TABLERO DE DISTRIBUCION DE 08 CIRC.PLANCHA GALV. UND 2.00 150.00 300.00 300.00
313 TUBO PVC SAP (E/C) 3/4" X 3.00 M. m 104.97 0.90 94.47 94.47
314 CINTA TEFLON RLL 1.60 1.70 2.72 2.72
315 CODO PVC SAL 2" X 90 UND 14.00 3.50 49.00 49.00
316 CODO PVC SAL 3" X 90 UND 12.00 2.50 30.00 30.00
317 CODO PVC SAL 4" X 90 PZA 11.00 3.50 38.50 38.50
318 CODO PVC SAP 1/2" X 90 UND 31.00 1.00 31.00 31.00
319 CODOS PVC SAL 2" X 45 PZA 4.20 2.50 10.50 10.50
320 CODOS PVC SAL 2" X 90 PZA 14.00 2.00 28.00 28.00
321 CODOS PVC SAL 4" X 45 PZA 4.20 4.50 18.90 18.90
322 CODOS PVC SAL 4" X 45 CON REDUCCION 4" A 2" PZA 1.05 4.50 4.73 4.73
323 DUCHA CROMADA INC.GRIF 1 LLAVE UND 4.00 120.00 480.00 480.00
324 INODORO TQUE. BAJO NORMAL COLOR INC/ ACCESORIOS UND 8.00 280.00 2,240.00 2,240.00
325 JABONERA DE LOSA COLOR PZA 4.00 15.00 60.00 60.00
326 LAVATORIO DE COLOR C/PEDESTAL INC/ ACCESORIOS PZA 3.00 95.00 285.00 285.00
327 LAVATORIO OVALIN INC/ ACCESORIOS PZA 6.00 95.00 570.00 570.00
328 LLAVE DE BRONCE PARA LAVADERO DE 1/2" UND 9.00 45.00 405.00 405.00
329 NIPLE DE Fo Go DE 1/2" x 1" UND 14.00 1.90 26.60 26.60
330 REDUCCION PVC SAL 4" A 2" PZA 6.30 4.00 25.20 25.20
331 REGISTRO DE BRONCE DE 4" UND 7.00 7.00 49.00 49.00
332 SILICONA (TUBO DE 10 ONZAS) UND 0.30 8.30 2.49 2.49
333 SOMBRERO DE VENTILACION PVC SAL 2" UND 7.00 3.50 24.50 24.50
334 SUMIDERO DE BRONCE DE 2" UND 7.00 6.00 42.00 42.00
335 TAPA C/MARCO FF DE DESAGUE 12" X 24" PZA 3.00 20.00 60.00 60.00
336 TEE PVC SAP DE 1/2" UND 6.00 1.00 6.00 6.00
337 TUBERIA PVC SAL PARA DESAGUE DE 2" M 113.26 5.40 611.60 611.60
338 TUBERIA PVC SAL PARA DESAGUE DE 4" M 37.31 8.40 313.40 313.40
339 TUBERIA PVC SAP PRESION PARA AGUA C-10 R. 1/2" M 106.68 1.90 202.69 202.69
340 TUBO DE ABASTO 1/2" x 1/2" PLOMO UND 17.00 12.00 204.00 204.00
341 TUBO PVC SAL 3" M 16.38 3.50 57.33 57.33
342 UNION DE F GALVANIZADO DE 1/2" UND 7.00 1.80 12.60 12.60
343 URINARIO PICO COLOR INC/ACCESORIOS UND 1.00 45.00 45.00 45.00
344 VALVULA COMPUERTA BRONCE 1/2" UND 7.00 18.00 126.00 126.00
345 YEE PVC SAL 4" UND 6.30 6.00 37.80 37.80
MAQUINARIA, EQUIPOS Y HERRAMIENTAS
346 CAMION VOLQUETE 15 M3. hm 0.17 160.00 27.20 27.20
347 CARGADOR SOBRE LLANTAS 125 HP 2.5 YD3. HM 0.35 220.00 77.00 77.00
348 CIZALLA PARA CORTE DE FIERRO HM 49.62 2.50 124.05 124.05
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

349 COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP HM 24.24 20.00 484.80 242.40 121.20 121.20
350 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 34.38 25.00 859.50 429.75 214.88 214.88
351 MIRAS Y JALONES HM 10.10 1.00 10.10 5.05 2.53 2.53
352 TEODOLITO HM 5.06 20.00 101.20 50.60 25.30 25.30
353 VIBRADOR DE CONCRETO 3/4" - 2" HM 16.74 15.00 251.10 125.55 62.78 62.78
354 HERRAMIENTAS MANUALES %MO 1.00 873.33 1,364.08 682.04 341.02 341.02
TANQUE ELEVADO
MANO DE OBRA
355 TOPOGRAFO HH 0.59 13.24 7.81 3.91 1.95 1.95
356 OPERADOR DE EQUIPO LIVIANO HH 6.89 13.24 91.22 45.61 22.81 22.81
357 OPERARIO HH 362.89 11.52 4,180.49 2,090.25 1,045.12 1,045.12
358 OFICIAL HH 98.95 10.38 1,027.10 513.55 256.78 256.78
359 PEON HH 351.15 10.38 3,644.94 1,822.47 911.23 911.23
MATERIALES
360 ACERO CORRUGADO F`y=4,200 Kg/cm2, GRADO 60 KG 811.35 4.70 3,813.35 3,813.35
361 ADAPTADOR PVC SAP 2" UND 2.00 4.00 8.00 8.00
362 AGUA M3 5.15 1.00 5.15 5.15
363 ALAMBRE NEGRO RECOCIDO # 16 KG 55.26 4.50 248.67 248.67
364 ALAMBRE NEGRO RECOCIDO # 8 KG 19.96 4.50 89.82 89.82
365 ANDAMIO DE MADERA P2 44.58 3.20 142.66 142.66
366 ARENA FINA M3 2.89 100.00 288.62 288.62
367 ARENA GRUESA M3 17.01 80.00 1,360.80 1,360.80
368 BISAGRA ALUMINIZ.CAPUCHINA 4"x4" UND 4.00 4.50 18.00 18.00
369 CABLE ELECTRICO 2.5 mm2 - LSOH M 19.95 1.40 27.93 27.93
370 CABLE ELECTRICO 4.0 mm2 - LSOH M 37.55 1.80 67.59 67.59
371 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 1.00 1.00 1.00 1.00
372 CAJA RECTANGULAR DE 58mm x 93mm UND 1.00 1.00 1.00 1.00
373 CEMENTO PORTLAND TIPO I (42.5KG) BOL 210.30 23.80 5,005.14 5,005.14
374 CERRADURA DE TRES GOLPES UND 1.00 45.00 45.00 45.00
375 CINTA AISLANTE RLL 0.20 5.00 1.00 1.00
376 CINTA TEFLON RLL 0.60 3.00 1.80 1.80
377 CLAVOS Fo No C/C 3" KG 3.78 4.00 15.12 15.12
378 CLAVOS PARA MADERA C/C 3" KG 21.49 4.50 96.71 96.71
379 CODO DE Fo. GALV. ISO-I DE 1" x 90 UND 6.00 3.50 21.00 21.00
380 CODO F GALVANIZADO 2" X 90 PZA 1.00 6.00 6.00 6.00
381 CODOS PVC SAL 2" X 90 PZA 2.10 2.50 5.25 5.25
382 CURVA PVC SAP LUZ 3/4" PZA 1.00 0.50 0.50 0.50
383 CURVAS PVC SAP 3/4" und 4.48 0.50 2.24 2.24
384 CURVAS PVC SEL 3/4" UND 1.00 0.50 0.50 0.50
385 ELECTROBOMBA 2 HP P/AGUA UND 1.00 500.00 500.00 500.00
386 ESCALERA DE GATO SEGUN DISEO Ml 6.94 120.00 832.80 832.80
387 ESTACA DE MADERA P2 0.04 1.00 0.04 0.04
388 FLUORES. RECTO ISPE 2X40 W C/EQ + PANT UND 1.00 60.00 60.00 60.00
389 HORMIGON (PUESTO EN OBRA) M3 0.39 80.00 31.20 31.20
390 IMPERMEABILIZANTE GLN 2.82 25.00 70.50 70.50
391 IMPRIMANTE GLN 7.99 25.00 199.75 199.75
392 INTERRUPTOR SIMPLE PZA 1.00 4.50 4.50 4.50
393 LADRILLO KING KONG 18 HUECOS 9x12x24 CM UND 487.20 1.25 609.00 609.00
394 LIJA PARA CONCRETO HJA 7.06 2.00 14.12 14.12
395 MADERA NACIONAL P/ENCOFRADO-CARP P2 457.98 3.20 1,465.54 1,465.54
396 PASTA MURAL gln 1.17 30.00 35.10 35.10
397 PEGAMENTO PARA PVC GLN 0.11 45.00 4.95 4.95
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

398 PIEDRA CHANCADA DE 1/2" M3 10.95 105.00 1,149.75 1,149.75


399 PIEDRA CHANCADA DE 3/4" M3 3.82 100.00 382.00 382.00
400 PINTURA ANTICORROSIVA GLN 1.14 43.00 49.02 49.02
401 PINTURA ESMALTE GLN 1.52 45.00 68.40 68.40
402 PINTURA LATEX SUPERMATE GLN 2.15 30.00 64.50 64.50
403 PUERTA METAL. INC.FABRIC., COLOC, PINTURA m2 1.90 100.00 190.00 190.00
404 REGLA DE ALUMINIO 1.5"x4"X10 pza 1.27 25.00 31.75 31.75
405 REJILLA DE F G DE 8" X 12" UND 2.00 25.00 50.00 50.00
406 SELLADOR GLN 1.63 20.00 32.60 32.60
407 SOMBRERO DE VENTILACION PVC SAL 2" UND 1.05 3.00 3.15 3.15
408 TABLERO ARRANQ-PARAD DIST-CONTROL AUTOMAT. UND 1.00 60.00 60.00 60.00
409 TABLERO DE DISTRIBUCION DE 04 CIRC.PLANCHA GALV. UND 1.00 50.00 50.00 50.00
410 TEE PVC SAL 2" UND 2.10 3.00 6.30 6.30
411 THINER GLN 0.07 15.00 1.05 1.05
412 TUB. FO.GO. PESADO 1" M 10.53 30.20 318.01 318.01
413 TUBO Fo.GALV. DE 1/2" M 9.44 28.50 269.04 269.04
414 TUBO NEGRO 2" Ml 13.22 20.00 264.40 264.40
415 TUBO PVC SAL 2" X 3 M PZA 2.45 12.00 29.40 29.40
416 TUBO PVC SAP (E/C) 3/4" X 3.00 M. m 13.44 0.90 12.10 12.10
417 TUBO PVC SAP 1" X 3M Ml 7.04 2.50 17.60 17.60
418 UNION ROSCADA DE F G 1/2" UND 0.80 4.00 3.20 3.20
419 UNION ROSCADA DE FO. GALV. DE 1" UND 1.30 16.00 20.80 20.80
420 UNION UNIVERSAL PVC SAL DE 2" UND 3.00 5.00 15.00 15.00
421 VALVULA CHECK DE BRONCE DE 1" UND 2.00 35.00 70.00 70.00
422 VALVULA COMPUERTA DE BRONCE DE 2" UND 1.00 20.00 20.00 20.00
423 VALVULA COMPUERTA DE BRONCE ROS. DE 1" UND 3.00 38.00 114.00 114.00
424 VALVULA DE PIE C/CANASTILLA DE 1" UND 3.00 25.00 75.00 75.00
YESO BOL 0.22 4.00 0.88 0.88

MAQUINARIA, EQUIPOS Y HERRAMIENTAS


425 VIBRADOR DE CONCRETO 3/4" - 2" HM 10.07 15.00 151.05 75.53 37.76 37.76
426 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 10.29 25.00 257.25 128.63 64.31 64.31
427 MIRAS Y JALONES HM 1.18 1.00 1.18 0.59 0.30 0.30
428 CAMION VOLQUETE 15 M3. hm 0.08 160.00 12.80 6.40 3.20 3.20
429 CARGADOR SOBRE LLANTAS 125 HP 2.5 YD3. HM 0.16 220.00 35.20 17.60 8.80 8.80
430 COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP HM 0.65 20.00 291.02 145.51 72.76 72.76
431 TEODOLITO HM 0.59 20.00 11.80 5.90 2.95 2.95
432 CIZALLA PARA CORTE DE FIERRO HM 12.52 2.50 31.30 15.65 7.83 7.83
433 HERRAMIENTAS MANUALES %MO 1.00 300.45 300.45 150.23 75.11 75.11

MURO DE CONTENCION
MANO DE OBRA
434 TOPOGRAFO HH 6.38 13.24 84.47 42.24 42.24
435 OPERADOR DE EQUIPO LIVIANO HH 90.20 13.24 1194.25 597.12 597.12
436 OPERARIO HH 1397.86 13.24 18507.67 9,253.83 9,253.83
437 OFICIAL HH 629.14 11.52 7247.69 3,623.85 3,623.85
438 PEON HH 4049.50 10.38 42033.81 21,016.91 21,016.91
MATERIALES
439 ACERO CORRUGADO F`y=4,200 Kg/cm2, GRADO 60 KG 11828.42 4.70 55,593.57 55,593.57
440 AGUA M3 73.74 1.00 73.74 73.74
441 ALAMBRE NEGRO RECOCIDO # 16 KG 737.66 4.50 3,319.47 3,319.47
442 ALAMBRE NEGRO RECOCIDO # 8 KG 65.38 4.50 294.21 294.21
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

443 ANDAMIO DE MADERA P2 41.12 3.20 131.58 131.58


444 ARENA FINA M3 2.43 100.00 243.00 243.00
445 ARENA GRUESA M3 83.63 80.00 6,690.40 6,690.40
446 ASFALTO RC-250 GLN 5.96 20.00 119.12 119.12
447 CEMENTO PORTLAND TIPO I (42.5KG) BOL 1634.43 23.80 38,899.43 38,899.43
448 CLAVOS PARA MADERA C/C 3" KG 97.69 4.50 439.61 439.61
449 ESTACA DE MADERA P2 0.48 1.00 0.48 0.48
450 HORMIGON (PUESTO EN OBRA) M3 25.14 80.00 2,011.20 2,011.20
451 LIJA PARA CONCRETO HJA 37.66 2.00 75.32 75.32
452 MADERA NACIONAL P/ENCOFRADO-CARP P2 1692.24 3.20 5,415.17 5,415.17
453 MATERIAL AFIRMADO M3 349.89 30.00 10,496.70 10,496.70
454 PIEDRA CHANCADA DE 1/2" M3 62.75 105.00 6,588.75 6,588.75
455 PIEDRA CHANCADA DE 3/4" M3 37.92 100.00 3,792.00 3,792.00
456 PIEDRA MEDIANA DE 4" M3 3.76 60.00 225.60 225.60
457 PINTURA ESMALTE GLN 6.02 45.00 270.90 270.90
458 REGLA DE ALUMINIO 1.5"x4"X10 pza 2.06 25.00 51.50 51.50
459 SOLDADURA CELLOCORD P 3/16" KG 4.97 12.00 59.64 59.64
460 TUBO FIERRO GALVANIZADO DE 1 1/2" M 248.50 21.00 5,218.50 5,218.50
461 TUBO FIERRO GALVANIZADO DE 2" M 218.68 25.00 5,467.00 5,467.00
462 VIBRADOR DE CONCRETO 3/4" - 2" HM 109.76 15.00 1,646.40 1,646.40
463 YESO BOL 2.40 4.00 9.60 9.60

EQUIPOS Y HERRAMIENTAS 0.00


464 TEODOLITO HM 6.38 20.00 127.60 63.80 63.80
465 CIZALLA PARA CORTE DE FIERRO HM 232.73 2.50 581.83 290.91 290.91
466 CAMION VOLQUETE 15 M3. hm 2.31 160.00 369.60 184.80 184.80
467 CARGADOR SOBRE LLANTAS 125 HP 2.5 YD3. HM 4.66 220.00 1,025.20 512.60 512.60
468 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 119.30 25.00 2,982.50 1,491.25 1,491.25
469 MIRAS Y JALONES HM 12.74 1.00 12.74 6.37 6.37
470 MOTOSOLDADORA DE 250 AMP. HM 13.24 30.00 397.20 198.60 198.60
471 COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP HM 368.59 20.00 7,371.80 7,371.80
472 HERRAMIENTAS MANUALES %MO 1.00 1981.66 2,040.63 1,020.32 1,020.32

OBRAS EXTERIORES
MANO DE OBRA
473 TOPOGRAFO HH 145.98 13.24 1,932.78 1,932.78
474 OPERARIO HH 604.78 13.24 8,007.29 2,001.82 2,001.82 2,001.82 2,001.82
475 OFICIAL HH 555.72 11.52 6,401.89 1,600.47 1,600.47 1,600.47 1,600.47
476 PEON HH 2490.09 10.38 25,847.13 6,461.78 6,461.78 6,461.78 6,461.78
MATERIALES
477 ALAMBRE NEGRO RECOCIDO # 8 KG 102.55 4.50 461.48 461.48
478 CLAVOS PARA MADERA C/C 3" KG 105.96 4.50 476.82 476.82
479 REJILLA FIERRO CORRUGADO DE 3/8" Ml 108.64 40.00 4,345.60 4,345.60
480 ARENA FINA M3 0.71 100.00 71.00 71.00
481 PIEDRA CHANCADA DE 1/2" M3 56.00 105.00 5,880.00 5,880.00
482 ARENA GRUESA M3 45.40 80.00 3,632.00 3,632.00
483 MATERIAL AFIRMADO M3 147.37 30.00 4,421.10 4,421.10
484 CABLE ELECTRICO TW - 3 -1x 16 MM2 NYY M 28.08 15.00 421.20 421.20
485 CABLE ELECTRICO TW - 3 -1x10+1x10 MM2 NYY M 77.50 20.00 1,550.00 1,550.00
486 CABLE ELECTRICO TW - 2 -1x 1x6 T MM2 NYY M 68.32 23.00 1,571.36 1,571.36
487 TABLERO DE DISTRIBUCION DE 12 POLOS PLANCAHA GALVANIZ UND 1.00 250.00 250.00 250.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

488 ASFALTO RC-250 GLN 25.36 20.00 507.20 507.20


489 CEMENTO PORTLAND TIPO I (42.5KG) BOL 632.41 23.80 15,051.36 15,051.36
490 YESO BOL 54.68 4.00 218.72 218.72
491 CINTA AISLANTE RLL 16.56 5.00 82.80 82.80
492 POZO DE PUESTA A TIERRA INC. EQUIPOS MATERIAL E INSTALA GLB 1.00 850.00 850.00 850.00
493 CINTA DE SEGURIDAD rll 5.00 80.00 400.00 400.00
494 CARTEL DE SEALIZACION und 10.00 20.00 200.00 200.00
495 PLACA RECORDATORIA und 1.00 450.00 450.00 450.00
496 PEGAMENTO PARA PVC GLN 0.43 45.00 19.35 19.35
497 HORMIGON (PUESTO EN OBRA) M3 0.11 80.00 8.80 8.80
498 AGUA M3 23.20 1.00 23.20 23.20
499 GUARDIANIA Y ALMACEN GLB 8.00 200.00 1,600.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00 200.00
500 INSTALACION DE PARARAYO INCL. ACCESORIOS E INSTALACIONGLB 1.00 1200.00 1,200.00 1,200.00
501 CARTEL DE OBRA S/DISEO INC.INST. Y TRANSP(3.60x2.40) UND 1.00 500.00 500.00 500.00
502 MADERA NACIONAL P/ENCOFRADO-CARP P2 632.35 3.20 2,023.52 2,023.52
503 ESTACA DE MADERA P2 10.94 1.00 10.94 10.94
504 TAPA C/MARCO FF DE DESAGUE 12" X 24" PZA 11.00 20.00 220.00 220.00
505 MASTIL DE TUB FG INCL. ACCESORIOS E INSTALACION und 3.00 550.00 1,650.00 1,650.00
506 ANILLO DE JEBE A-7.5 DE 6" UND 18.39 15.00 275.85 275.85
507 TUBERIA PVC SAP A-10 DE 3/4" M 24.26 17.00 412.42 412.42
508 TUBERIA PVC SAL PARA DESAGUE DE 6" M 107.29 40.00 4,291.60 4,291.60
509 TUBO PVC SAP D=0.50 MM m 10.71 5.00 53.55 53.55
510 TUBO PVC SAP D=0.35 MM m 74.60 4.00 298.40 298.40
511 TUBO PVC SAP D=0.25 MM m 66.20 3.70 244.94 244.94
512 SEGURIDAD E HIGIENE DE OBRA GLB 1.00 1000.00 1,000.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00 125.00
513 LIMPIEZA DURANTE LA EJECUCION GLB 1.00 800.00 800.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
514 INTERRUPTOR TERMOMAGNETICO DE 3x40 A und 1.00 65.00 65.00 65.00
515 INTERRUPTOR TERMOMAGNETICO DE 3x30 A und 1.00 60.00 60.00 60.00
516 INTERRUPTOR TERMOMAGNETICO DE 3x50 A und 1.00 70.00 70.00 70.00
MAQUINARIA, EQUIPOS Y HERRAMIENTAS
517 MIRAS Y JALONES HM 294.50 1.00 294.50 58.90 58.90 58.90 58.90 58.90
518 CAMION VOLQUETE 15 M3. hm 0.49 160.00 78.40 15.68 15.68 15.68 15.68 15.68
519 COMPACTADOR VIBR. TIPO PLANCHA 5.8 HP HM 182.03 20.00 3,640.60 728.12 728.12 728.12 728.12 728.12
520 CARGADOR SOBRE LLANTAS 125 HP 2.5 YD3. HM 15.15 220.00 3,333.00 833.25 833.25 833.25 833.25
521 VIBRADOR DE CONCRETO 3/4" - 2" HM 28.49 15.00 427.35 106.84 106.84 106.84 106.84
522 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 28.49 25.00 712.25 178.06 178.06 178.06 178.06
523 TEODOLITO HM 145.98 20.00 2,919.60 729.90 729.90 729.90 729.90
524 HERRAMIENTAS MANUALES %MO 1,296.85 324.21 324.21 324.21 324.21

CERCO PERIMETRICO
MANO DE OBRA
525 TOPOGRAFO HH 2.88 13.24 38.13 19.07 19.07
526 OPERADOR DE EQUIPO PESADO HH 20.39 13.24 269.96 134.98 134.98
527 OPERARIO HH 442.20 13.24 5,854.73 2,927.36 2,927.36
528 OFICIAL HH 314.23 11.52 3,619.93 1,809.96 1,809.96
529 PEON HH 673.53 10.38 6,991.24 3,495.62 3,495.62

MATERIALES
530 ACERO CORRUGADO F`y=4,200 Kg/cm2, GRADO 60 KG 965.87 4.70 4,539.59 4,539.59
531 AGUA M3 10.90 1.00 10.90 10.90
532 ALAMBRE NEGRO RECOCIDO # 16 KG 54.29 4.50 244.31 244.31
533 ALAMBRE NEGRO RECOCIDO # 8 KG 110.10 4.50 495.45 495.45
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

534 ANDAMIO DE MADERA P2 37.34 3.20 119.49 119.49


535 ARENA FINA M3 1.93 100.00 193.00 193.00
536 ARENA GRUESA M3 10.73 80.00 858.40 858.40
537 CEMENTO PORTLAND TIPO I (42.5KG) BOL 231.37 23.80 5,506.61 5,506.61
538 CLAVOS PARA MADERA C/C 3" KG 59.15 4.50 266.18 266.18
539 ESTACA DE MADERA P2 0.22 1.00 0.22 0.22
540 HORMIGON (PUESTO EN OBRA) M3 11.79 80.00 943.20 943.20
541 IMPRIMANTE GLN 15.71 25.00 392.75 392.75
542 LIJA PARA CONCRETO HJA 30.21 2.00 60.42 60.42
543 MADERA NACIONAL P/ENCOFRADO-CARP P2 2015.56 3.20 6,449.79 6,449.79
544 PASTA MURAL gln 3.62 30.00 108.60 108.60
545 PIEDRA CHANCADA DE 1/2" M3 11.55 105.00 1,212.75 1,212.75
546 PIEDRA GRANDE DE 8" M3 5.37 45.00 241.65 241.65
547 PINTURA ANTICORROSIVA GLN 3.80 43.00 163.40 163.40
548 PINTURA ESMALTE GLN 8.63 45.00 388.35 388.35
549 PLATINA 2" X 1/8" M 31.92 15.00 478.80 478.80
550 REGLA DE ALUMINIO 1.5"x4"X10 pza 1.21 25.00 30.25 30.25
551 SOLDADURA CELLOCORD P 3/16" KG 7.78 12.00 93.36 93.36
552 TECNOPORT E=1/2" pln 0.76 10.00 7.60 7.60
553 THINER GLN 0.24 15.00 3.60 3.60
554 TUBO NEGRO 2" X 2" X 6 ML M 608.00 35.00 21,280.00 21,280.00
555 YESO BOL 1.08 4.00 4.32 4.32

EQUIPOS
556 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 20.93 25.00 523.25 261.63 261.63
557 MIRAS Y JALONES HM 3.52 1.00 3.52 1.76 1.76
558 CAMION VOLQUETE 15 M3. hm 0.71 160.00 113.60 56.80 56.80
559 CARGADOR SOBRE LLANTAS 125 HP 2.5 YD3. HM 1.45 220.00 319.00 159.50 159.50
560 TEODOLITO HM 2.88 20.00 57.60 28.80 28.80
561 CIZALLA PARA CORTE DE FIERRO HM 26.02 2.50 65.05 32.53 32.53
562 VIBRADOR DE CONCRETO 3/4" - 2" HM 15.89 15.00 238.35 119.18 119.18
563 HERRAMIENTAS MANUALES %MO 1.00 490.25 490.25 245.13 245.13

EQUIPAMIENTO
MATERIALES Y EQUIPOS
564 ALGEBRA - EDUARDO ESPINOZA und 10.00 50.00 500.00 250.00 250.00
565 ANILLO OAROS GRANDES UND 5.00 6.00 30.00 15.00 15.00
566 ARO PARA SOPORTE UNIVERSAL UND 5.00 10.00 50.00 25.00 25.00
567 ATRILES UND 10.00 120.00 1,200.00 600.00 600.00
568 AUDIFONOS und 35.00 55.00 1,925.00 962.50 962.50
569 BALAS PARA LANZAMIENTO und 1.00 5.00 5.00 2.50 2.50
570 BALON DE BASE PLANA 250 ML UND 2.00 25.00 50.00 25.00 25.00
571 BALON DE BASE PLANA 500 ML UND 2.00 30.00 60.00 30.00 30.00
572 BANCA UNIPERSONAL (TORNILLO) SEGUN NDISEO UND 35.00 35.00 1,225.00 612.50 612.50
573 BIBLIA BILINGUE und 10.00 35.00 350.00 175.00 175.00
574 BIOLOGIA SUPERIOR - MOREY MIGUEL und 10.00 60.00 600.00 300.00 300.00
575 BOMBO SINFONICO UND 2.00 250.00 500.00 250.00 250.00
576 BURETA DE 100 ML UND 3.00 30.00 90.00 45.00 45.00
577 CALCULO MATEMATICO - LARSON HORTETLER und 5.00 105.00 525.00 262.50 262.50
578 CALCULO MATEMATICO -LEITHOLD und 5.00 100.00 500.00 250.00 250.00
579 CALCULO- WILLAM GRANVILLE und 5.00 95.00 475.00 237.50 237.50
580 CANMCIONEROS CATOLICOS und 10.00 3.00 30.00 15.00 15.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

581 CAPSULA DE PORCELANA DE 100 ML UND 5.00 5.00 25.00 12.50 12.50
582 CAPSULA DE PORCELANA DE 180 ML UND 5.00 10.00 50.00 25.00 25.00
583 CATESISMO ILUSTRADO und 15.00 10.00 150.00 75.00 75.00
584 CEPILLO PARA MADERA UND 3.00 2500.00 7,500.00 3,750.00 3,750.00
585 CHOLITO EN LOS ANDES MAGICOS und 10.00 6.00 60.00 30.00 30.00
586 CLARINETES UND 4.00 300.00 1,200.00 600.00 600.00
587 COCINILLA ELECTRICA UND 5.00 50.00 250.00 125.00 125.00
588 COLCHONETAS und 5.00 30.00 150.00 75.00 75.00
589 COLCHONETAS PARA EL SALTO DE 1.00 X 2.50 M und 5.00 250.00 1,250.00 625.00 625.00
590 COLECCION INGENIO und 24.00 45.00 1,080.00 540.00 540.00
591 COLECCION LUMBRERAS und 24.00 45.00 1,080.00 540.00 540.00
592 COLECCIONES AURELIO BALDOR und 15.00 300.00 4,500.00 2,250.00 2,250.00
593 COMPAS METALICO JGO 20.00 75.00 1,500.00 750.00 750.00
594 CONDENSADOR UND 5.00 120.00 600.00 300.00 300.00
595 CORTINAS PARA VENTANAS INCL. RIELES, ACCES E INSTALAC. GLB 1.00 4200.00 4,200.00 2,100.00 2,100.00
596 CPU INTEL CORE i3 3.3GB, MEM. 4GB,D.D. 500GB,PLACA H61M UND 31.00 1400.00 43,400.00 21,700.00 21,700.00
597 CRISOL CHICO UND 5.00 5.00 25.00 12.50 12.50
598 CURSO ESPERIMENTAL EN QUIOMICA FISICA- VARIOS AUTORES und 10.00 50.00 500.00 250.00 250.00
599 DATA SHOW UND 1.00 4200.00 4,200.00 2,100.00 2,100.00
600 DICCIONARIO DE MUSICA und 10.00 95.00 950.00 475.00 475.00
601 DICCIONARIO DE SINONIMOS Y ANTONIMOS und 10.00 100.00 1,000.00 500.00 500.00
602 DICCIONARIO FILOSOFICO ROSSENTAL und 5.00 135.00 675.00 337.50 337.50
603 DICCIONARIO GEOGRAFICO E HISTORICO und 5.00 60.00 300.00 150.00 150.00
604 DICCIONARIO PEDAGOGICO und 10.00 200.00 2,000.00 1,000.00 1,000.00
605 DISCO PARA LANZAMIENTO und 5.00 50.00 250.00 125.00 125.00
606 DOMINE SU LENGUAJE und 10.00 200.00 2,000.00 1,000.00 1,000.00
607 DOMINGO GUZMAN HUAMAN und 10.00 10.00 100.00 50.00 50.00
608 ECONOMIA POLITICA NIKITIN und 5.00 35.00 175.00 87.50 87.50
609 EDICIONES COREFO und 10.00 120.00 1,200.00 600.00 600.00
610 EL MUNDO ES ANCHO Y AJENO - CIRO ALEGRIA und 10.00 32.00 320.00 160.00 160.00
611 EL PODER DEL EXITO und 10.00 8.00 80.00 40.00 40.00
612 EMBUDO DE VIDRIO DE 60 x 120 UND 10.00 5.00 50.00 25.00 25.00
613 EN QUE MOMENTO SE JODIO EL PERU und 10.00 8.00 80.00 40.00 40.00
614 ENSAYOS - LUIS LOAYZA und 10.00 60.00 600.00 300.00 300.00
615 EQUIPO DE SONIDO (MICROFONO, MEZCLADORA Y PARLANTES)UND 1.00 8000.00 8,000.00 4,000.00 4,000.00
616 ESCALIMETRO PAR SALTO ALTO UND 2.00 60.00 120.00 60.00 60.00
617 ESCRITORIO DE MELAMINE 6 GAVETAS 1.60 X 0.60 M UND 2.00 600.00 1,200.00 600.00 600.00
618 ESCRITORIO EN "L" C/MELANIME-TABLE.VIDRIO 1.6X1.6/CAJON UND 1.00 900.00 900.00 450.00 450.00
619 ESCUADRA 30, 45, 60 jgo 20.00 40.00 800.00 400.00 400.00
620 ESCUADRAS METALICAS JGO 10.00 35.00 350.00 175.00 175.00
621 ESTABILIZADOR STABY LINE BLH-RL3, 4 SALIDAS UND 34.00 30.00 1,020.00 510.00 510.00
622 ESTANTE METALICO DE 0.80 X 2.50 X 2.50 pza 13.00 450.00 5,850.00 2,925.00 2,925.00
623 EUFONIAS (BAJO) UND 6.00 380.00 2,280.00 1,140.00 1,140.00
624 EXTINTORES DE 30 KG UND 2.00 180.00 360.00 180.00 180.00
625 FIOLA DE 100 ML UND 5.00 10.00 50.00 25.00 25.00
626 FISICA CIENCIA Y TEC. ELECTR. MAGNETISMO-TUPLER GENE und 10.00 30.00 300.00 150.00 150.00
627 FISICA GENERAL 2 - SERWAY und 10.00 80.00 800.00 400.00 400.00
628 FISICA TERMICA - CHARLES KITEL und 10.00 70.00 700.00 350.00 350.00
629 FLAUTAS TRAVERSAS UND 2.00 650.00 1,300.00 650.00 650.00
630 FOTOCOPIADORA DE PISO UND 2.00 3500.00 7,000.00 3,500.00 3,500.00
631 GARLOPA AUTOMATICA UND 3.00 3500.00 10,500.00 5,250.00 5,250.00
632 GEOMETRIA - EDUARDO ESPINOZA und 10.00 60.00 600.00 300.00 300.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

633 GEOMETRICS - LEHMAN CHARLES und 5.00 120.00 600.00 300.00 300.00
634 GRASIMILLA PARA TUBO DE PRUEBA UND 10.00 4.00 40.00 20.00 20.00
635 GUIA PARA LA FORMULACION DE PROYECTOS DE INVERSION und 10.00 35.00 350.00 175.00 175.00
636 GUITARRAS ACUSTICAS PROFESIONALES UND 3.00 300.00 900.00 450.00 450.00
637 HAY UNA CHICA EN MI SOPA - SILVIA NUES DEL ARCO und 10.00 32.00 320.00 160.00 160.00
638 HORAS DE LUCHA- MANUEL GONZALES PRADA und 10.00 8.00 80.00 40.00 40.00
639 IMPRESORA LASER MULTIFUNCIONAL CON TONER UND 2.00 650.00 1,300.00 650.00 650.00
640 INGENIERO DE PROYECTOS - FERNANDO SANTOS und 10.00 40.00 400.00 200.00 200.00
641 INTRODUCCION A LA ELECTROTECNIA - SOBNRE VILLA ALSINA und 10.00 35.00 350.00 175.00 175.00
642 JABALINAS PARA LANZAMIENTO und 5.00 22.00 110.00 55.00 55.00
643 JUEGO DE BATERIAS CON TAMBORES/TIMBALES jgo 1.00 700.00 700.00 350.00 350.00
644 KIT DE MAQUINARIA DE MAQUETA DE ESQUELETO HUMANO EN UND 2.00 850.00 1,700.00 850.00 850.00
645 KIT TECLADO + MOUSE GENIUS SATANDARD OPTICO UND 30.00 40.00 1,200.00 600.00 600.00
646 LA VACA - CAMILO DE LA CRUZ und 10.00 6.00 60.00 30.00 30.00
647 LAMINA PARA ALUMNOS und 10.00 25.00 250.00 125.00 125.00
648 LAMINA PARA EDUCACION SEXUAL und 10.00 10.00 100.00 50.00 50.00
649 LAPTOP INTEL CORE i3/ DE 15.6" RAM 2GB, 500GB UND 8.00 1650.00 13,200.00 6,600.00 6,600.00
650 LIBRO DE ARTES PLASTICAS - JUAN VILLA CORTA und 10.00 10.00 100.00 50.00 50.00
651 LIBRO DE DANZA - JOSE OBREGON MORAN und 10.00 10.00 100.00 50.00 50.00
652 LIBRO DE I NGLES EDITORIAL NAVARRETE und 10.00 65.00 650.00 325.00 325.00
653 LIBRO DE LEMNGUAJE Y COMUNICACION und 10.00 145.00 1,450.00 725.00 725.00
654 LIBRO DE MUSICA - ESTEBANM ECOBEDO ACUA und 10.00 10.00 100.00 50.00 50.00
655 LIBRO DE MUSICA - FRANSICO PULGAR VIDAL und 10.00 20.00 200.00 100.00 100.00
656 LITERATURA PERUANA - CASERES CHAUPIN und 10.00 60.00 600.00 300.00 300.00
657 LITERATURA PERUANA - TORO MONTALVO und 10.00 330.00 3,300.00 1,650.00 1,650.00
658 LITERATURA UNIVERSAL - CASERES CHAUPIN und 10.00 50.00 500.00 250.00 250.00
659 LOCKERS DE ALUMINIO DE H=1.74 M und 6.00 1200.00 7,200.00 3,600.00 3,600.00
660 LOS 7 ENSAYOS - JOSE CARLOS MARIATEGUI und 10.00 6.00 60.00 30.00 30.00
661 LOS DIOSES DE CHAVIN und 10.00 6.00 60.00 30.00 30.00
662 LUNAS DE RELOJ DE 100 MM UND 10.00 12.00 120.00 60.00 60.00
663 LUPA DE 8 AUMENTOS UND 10.00 10.00 100.00 50.00 50.00
664 MALLA DE ASBESTO UND 12.00 5.00 60.00 30.00 30.00
665 MANUAL ACADEMICO DE ECONOMIA und 10.00 45.00 450.00 225.00 225.00
666 MANUAL ACADEMICO DE FILOSOFIA und 10.00 60.00 600.00 300.00 300.00
667 MANUAL ACADEMICO DE HISTORIA DE LA HUMANIDAD und 10.00 52.00 520.00 260.00 260.00
668 MANUAL ACADEMICO DE HISTORIA DE LA PSICOLOGIA und 10.00 48.00 480.00 240.00 240.00
669 MANUAL ACADEMICO DE HISTORIA DEL PERU EDIT. und 10.00 52.00 520.00 260.00 260.00
670 MANUALES DE CRIANZA DE ANIMALES MENORES und 10.00 200.00 2,000.00 1,000.00 1,000.00
671 MARTILLO CARPINTERIA DE 1 1/2 LBS. UND 10.00 35.00 350.00 175.00 175.00
672 MATEMATICA P/ALUMN. 1ro a 5to - ALFONSO ROJAS und 40.00 40.00 1,600.00 800.00 800.00
673 MATEMATICA P/ALUMN. 1ro a 5to - EDUARDO ESPINOZA und 30.00 65.00 1,950.00 975.00 975.00
674 MATEMATICA P/ALUMN. 1ro a 5to - MANUEL COVEAS und 30.00 50.00 1,500.00 750.00 750.00
675 MATEMATICA P/ALUMN. 1ro a 5to - MAXIMO DE LA CRUIZ SOLOR und 40.00 40.00 1,600.00 800.00 800.00
676 MATEMATICA P/ALUMN. 1ro a 5to - RUBIOS und 40.00 40.00 1,600.00 800.00 800.00
677 MATERIALES DE RED SWITCH, CABLE RJ 45 UND 2.00 650.00 1,300.00 650.00 650.00
678 MATRAS ERLEMNEYER DE 300 ML UND 10.00 20.00 200.00 100.00 100.00
679 MECANICA DE SISTEMAS Y FENOMENOS ONDULATORIOS und 10.00 45.00 450.00 225.00 225.00
680 MECHERO DE BUNSEN ALCOHOL UND 10.00 5.00 50.00 25.00 25.00
681 MECHERO DE BUNSEN CHICO UND 5.00 10.00 50.00 25.00 25.00
682 MECHERO DE BUNSEN GRANDE UND 5.00 15.00 75.00 37.50 37.50
683 MESA DE MADERA TORNILLO 2.5 X 1.80 M SEGUN DISEO und 4.00 1400.00 5,600.00 2,800.00 2,800.00
684 MESA UNIPERSONAL DE ESTRUCT. METALICA, C/MELAMINE DE 1und 240.00 120.00 28,800.00 14,400.00 14,400.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

685 METODOS NUMERICOS - CHAPRA CANALE und 10.00 45.00 450.00 225.00 225.00
686 MICROSCOPIOS UND 10.00 500.00 5,000.00 2,500.00 2,500.00
687 MOBILIARIO EMP. DIV. EN CLOSET INC./MATR-INSTAL. LABORAT GLB 1.00 3000.00 3,000.00 1,500.00 1,500.00
688 MODULO DE MADERA PARA BIBLIOTECA 1.0X0.6+SILLA/TORN UND 30.00 150.00 4,500.00 2,250.00 2,250.00
689 MONITOR SAMSUNG 18.5" -LED WIDE UND 31.00 450.00 13,950.00 6,975.00 6,975.00
690 MORTERO EN PILON DE 170 ML UND 5.00 25.00 125.00 62.50 62.50
691 MUEBLE DE MADERA PARA ATENCION UND 1.00 120.00 120.00 60.00 60.00
692 MUEBLES CONFORT DE CUERO jgo 1.00 1200.00 1,200.00 600.00 600.00
693 MUEBLES PARA COMPUTADORA+SILLA DE MADERA TORNILLO UND 33.00 350.00 11,550.00 5,775.00 5,775.00
694 NAPOLEONES UND 10.00 60.00 600.00 300.00 300.00
695 NET OFICIAL DE NAYLON UND 1.00 134.62 134.62 67.31 67.31
696 NUNCA CONFIES EN MI - RENATO CISNEROS und 10.00 45.00 450.00 225.00 225.00
697 OBRAS LITERARIAS DIVERSOS GLB 1.00 3000.00 3,000.00 1,500.00 1,500.00
698 OXFORD STUDY und 10.00 100.00 1,000.00 500.00 500.00
699 PARLANTES GENIUS P.M.P.O.- S110 100 W UND 31.00 20.00 620.00 310.00 310.00
700 PASAMANOS KG 5.00 220.00 1,100.00 550.00 550.00
701 PETRIX DE 802 CM UND 12.00 5.00 60.00 30.00 30.00
702 PINZA DE MADERA PARA TUBOS DE PRUEBA UND 15.00 5.00 75.00 37.50 37.50
703 PINZA PARA SOPORTE UNIVERSAL UND 5.00 30.00 150.00 75.00 75.00
704 PIPETA DE 10 ML UND 10.00 6.00 60.00 30.00 30.00
705 PIPETA DE 5 ML UND 10.00 5.00 50.00 25.00 25.00
706 PIZARRA ACRILICA 3.00 X 1.50 M INCL. INSTALACI. UND 15.00 250.00 3,750.00 1,875.00 1,875.00
707 PLATILLO PROFESIONAL UND 4.00 100.00 400.00 200.00 200.00
708 PROBETA GRADUADA DE 100 ML UND 10.00 20.00 200.00 100.00 100.00
709 PROBETA GRADUADA DE 250 ML UND 12.00 25.00 300.00 150.00 150.00
710 PROYECTOR MULTIMEDIA UND 3.00 2200.00 6,600.00 3,300.00 3,300.00
711 PUERTA DE MELAMINA BAJO MESA DE TRABAJO C/DIV. GLB 1.00 1500.00 1,500.00 750.00 750.00
712 RAZONAMIENTO MATEMATICO - COLECCION INGENIO und 5.00 60.00 300.00 150.00 150.00
713 RAZONAMIENTO MATEMATICO - HERNAN HERNADEZ und 10.00 50.00 500.00 250.00 250.00
714 RAZONAMIENTO MATEMATICO - RUBIOS und 5.00 60.00 300.00 150.00 150.00
715 REDES ELECTRICAS - CAUDENCIO SOPETTI und 10.00 80.00 800.00 400.00 400.00
716 REGLAS METALICAS und 20.00 35.00 700.00 350.00 350.00
717 SAXOS UND 4.00 440.00 1,760.00 880.00 880.00
718 SERRUCHO UND 10.00 45.00 450.00 225.00 225.00
719 SIERRA CIRCULAR und 2.00 3000.00 6,000.00 3,000.00 3,000.00
720 SILLA GIRATORIA und 2.00 200.00 400.00 200.00 200.00
721 SILLA GIRATORIA CON PISTON und 1.00 300.00 300.00 150.00 150.00
722 SILLAS DE MADERA TORNILLOS CON ESPUMA UND 114.00 65.00 7,410.00 3,705.00 3,705.00
723 SOPORTE UNIVERSAL DE BASE CUADRADO DE HIERRO UND 10.00 10.00 100.00 50.00 50.00
724 STAND DE ARCHIVOS DE MELAMINE und 5.00 800.00 4,000.00 2,000.00 2,000.00
725 TABLERO DE BASQUET DE FIBRA DE VIDRIO UND 2.00 500.00 1,000.00 500.00 500.00
726 TAROLAS PROFESIONALES UND 5.00 50.00 250.00 125.00 125.00
727 TE RECORDARAS DE MI - ARMANDO ECHEANDIA und 10.00 29.00 290.00 145.00 145.00
728 TECLADO PROFESIONAL CASSIO UND 1.00 450.00 450.00 225.00 225.00
729 TERMOMETRO DE 0 A 150 GRADOS UND 10.00 40.00 400.00 200.00 200.00
730 TRADICIONES PERUANAS DE RICARDO PLMA und 10.00 8.00 80.00 40.00 40.00
731 TRANSPORTADORES METALICOS und 20.00 10.00 200.00 100.00 100.00
732 TRAS EL SALTO MORTAL - ANUOR AGUILAR und 10.00 30.00 300.00 150.00 150.00
733 TRIGONOMETRIA - EDUARDO ESPINOZA und 10.00 40.00 400.00 200.00 200.00
734 TRIPODE DE TRES PIES UND 10.00 100.00 1,000.00 500.00 500.00
735 TROMBON DE VARA UND 6.00 480.00 2,880.00 1,440.00 1,440.00
736 TROMPETAS UND 7.00 200.00 1,400.00 700.00 700.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : JUNIO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND CANT P.U PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

737 TUBAS ACRILICOS UND 4.00 500.00 2,000.00 1,000.00 1,000.00


738 TUBO DE ENSAYO 10 X 100 ML UND 10.00 4.00 40.00 20.00 20.00
739 TUBO DE ENSAYO 16 X 100 ML UND 10.00 8.00 80.00 40.00 40.00
740 VALLAS PARA CARRERA DE POSTAS und 5.00 10.00 50.00 25.00 25.00
741 VARIABLE COMPLEJA Y APLICACIONES - CHURCHIL und 10.00 25.00 250.00 125.00 125.00
742 VASO PRESIPIATADO DE 250 ML UND 5.00 15.00 75.00 37.50 37.50
743 VASO PRESIPIATADO DE 300 ML UND 5.00 25.00 125.00 62.50 62.50
744 VIDEOTECAS und 1.00 2000.00 2,000.00 1,000.00 1,000.00
745 XILOFONO UND 10.00 90.00 900.00 450.00 450.00
4,739.48 2,369.74 2,369.74
MITIGACION AMBIENTAL
MANO DE OBRA
746 OPERARIO HH 3.20 13.24 42.37 21.18 21.18
747 PEON HH 16.00 10.38 166.08 83.04 83.04
MATERIALES Y EQUIPOS
748 ARBUSTOS ORNAMENTALES UND 100.00 18.00 1,800.00 900.00 900.00
749 BASUREROS METALICOS S/DISEO, INLUY INMSTAL. PAR 7.00 800.00 5,600.00 5,600.00
750 CAPACITACION AMBIENTAL A ALUMNOS Y DOCENTES GLB 1.00 2500.00 2,500.00 1,250.00 1,250.00
751 CAPACITACION AMBIENTAL A PERSONAL DE OBRA GLB 1.00 2500.00 2,500.00 1,250.00 1,250.00
752 CAPACITACION AMBIENTAL A POBLACION EN GENERAL GLB 1.00 2500.00 2,500.00 1,250.00 1,250.00
753 CONFORMACION DE LETRINA PARA USO PERS. OBRERO GLB 2.00 800.00 1,600.00 1,600.00
754 FERTILIZANTE KG 30.00 35.00 1,050.00 1,050.00
755 FLORES DIVERSOS UND 300.00 5.50 1,650.00 1,650.00
756 GRASS KG 20.00 16.00 320.00 320.00
757 TIERRA DE CHACRA O VEGETAL M3 40.00 40.00 1,600.00 1,600.00
HERRAMIENTAS MANUALES
758 HERRAMIENTAS MANUALES %MO 6.25 6.25

CAPACITACION EN OPERACIN Y MANTENIMIENTO


759 CAPACITACION EN OPER Y MANTE. A PADRES DE FAMILIA GLB 1.00 5893.08 5,893.08 2,946.54 2,946.54
760 CAPACITACION EN OPER. Y MANTE. A DOCENTES Y ALUMNOS GLB 1.00 5893.08 5,893.08 2,946.54 2,946.54

FLETE TERRESTRE
761 FLETE TERRESTRE PABELLON A GLB 37,097.58 1.00 37,097.58 4,637.20 4,637.20 4,637.20 4,637.20 4,637.20 4,637.20 4,637.20 4,637.20
762 FLETE TERRESTRE PABELLON B GLB 19,887.68 1.00 19,887.68 2,485.96 2,485.96 2,485.96 2,485.96 2,485.96 2,485.96 2,485.96 2,485.96
763 FLETE TERRESTRE DE SERVICIOS HIGIENICOS GLB 4,925.24 1.00 4,925.24 615.66 615.66 615.66 615.66 615.66 615.66 615.66 615.66
764 FLETE TERRESTRE DE MURO DE CONTENCION GLB 1,259.19 1.00 1,259.19 157.40 157.40 157.40 157.40 157.40 157.40 157.40 157.40
765 FLETE TERRESTRE OBRAS EXTERIORES GLB 9,884.97 1.00 9,884.97 1,235.62 1,235.62 1,235.62 1,235.62 1,235.62 1,235.62 1,235.62 1,235.62
766 FLETE TERRESTRE DE TANQUE ELEVADO GLB 3,158.10 1.00 3,158.10 394.76 394.76 394.76 394.76 394.76 394.76 394.76 394.76
767 FLETE TERRESTRE DE CERCO PERIMETRICO GLB 1,461.53 1.00 1,461.53 182.69 182.69 182.69 182.69 182.69 182.69 182.69 182.69
768 FLETE TERRESTRE DE MITIGACION AMBIENTAL GLB 1,319.61 1.00 1,319.61 164.95 164.95 164.95 164.95 164.95 164.95 164.95 164.95
769 FLETE TERRESTRE DE EQUIPAMIENTO GLB 60.56 1.00 60.56 7.57 7.57 7.57 7.57 7.57 7.57 7.57 7.57

TOTAL DE COSTO DIRECTO 2,486,281.80 622,150.62 334,012.38 268,016.32 253,943.91 225,831.13 186,272.11 351,651.09 244,404.26
RESUMEN

SUM
ESTRUCTURA ARQ ELEC

OEL 143.91 72.15


OEP 21.8
TOPO 17.08
OPE 3707.44 5669.53 363.16
OF 3878.77 363.17 36.66
PEON 7245.91 3589.64 92.73

CEMENTO 3812.35 1037.3


ACERO 41235.36
A. GRUESA 189.11 58.78 247.89
A FINA 63.26

104.84 19
128.87 286.88
233.71 305.88

HERRA M SUM 5010.38


3853.49
8863.87
SANIT

216.06
21.8
17.08
99.6 9839.73
4278.6
10928.28

4849.65

203.39
72.15
275.54