Está en la página 1de 17

CRONOGRAMA DE ADQUISICION DE MATERIALES

: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES

FORMULA 01 PABELLON A

MANO DE OBRA
1 TOPOGRAFO HH 14.14 22.90 323.81 46.26 46.26 46.26 46.26 46.26 46.26 46.26
2 OPERARIO HH 14.14 8,477.05 119,865.49 17,123.64 17,123.64 17,123.64 17,123.64 17,123.64 17,123.64 17,123.64
3 OFICIAL HH 12.40 3,968.14 49,204.94 7,029.28 7,029.28 7,029.28 7,029.28 7,029.28 7,029.28 7,029.28
4 PEON HH 11.21 11,472.61 128,607.96 18,372.57 18,372.57 18,372.57 18,372.57 18,372.57 18,372.57 18,372.57

MATERIALES

5 ALAMBRE NEGRO RECOCIDO # 16 KG 6.50 2,252.92 14,643.98 14,643.98


6 ALAMBRE NEGRO RECOCIDO # 8 KG 6.50 309.48 2,011.62 2,011.62
7 CLAVOS PARA MADERA C/C 1 1/2 " KG 6.00 20.25 121.50 121.50
8 CLAVOS PARA MADERA C/C 3" KG 6.00 362.22 2,173.32 2,173.32
9 CLAVOS PARA MADERA C/C 4" KG 6.00 92.81 556.86 556.86
10 PERNOS 3/8" X 4 " PZA 2.20 368.00 809.60 809.60
11 ACERO DE REFUERZO FY=4200 GRADO 60 KG 4.70 30,508.38 143,389.39 143,389.39
12 ARENA FINA M3 100.00 44.99 4,499.00 1,124.75 1,124.75 1,124.75 1,124.75
13 TIERRA DE CHACRA O VEGETAL M3 10.00 1.40 14.00 3.50 3.50 3.50 3.50
14 PIEDRA CHANCADA DE 1/2" M3 105.00 99.05 10,400.25 2,600.06 2,600.06 2,600.06 2,600.06
15 PIEDRA CHANCADA DE 3/4" M3 95.00 111.18 10,562.10 2,640.53 2,640.53 2,640.53 2,640.53
16 PIEDRA MEDIANA DE 4" M3 60.00 4.54 272.40 68.10 68.10 68.10 68.10
17 GRAVA CANTO RODADO M3 75.00 9.43 707.25 176.81 176.81 176.81 176.81
18 ARENA GRUESA M3 80.00 225.64 18,051.20 4,512.80 4,512.80 4,512.80 4,512.80
19 ALAMBRE TW # 12 AWG M 1.20 684.87 821.84 821.84
20 CABLE TW # 14 AWG 2.5 MM2 M 1.20 9.00 10.80 10.80
21 CABLE TW # 6 AWG - 16 MM2. M 1.20 292.67 351.20 117.07 117.07 117.07
22 CABLE ELECTRICO N14 THW AWG M 1.20 1,065.10 1,278.12 426.04 426.04 426.04
23 CRUCETAS PZA 0.20 2,173.50 434.70 144.90 144.90 144.90
24 TABLERO MONOFASICO DE 12 POLOS UND 90.00 3.00 270.00 90.00 90.00 90.00
25 TABLERO GENERADOR AUTOMATICO DE 4 CIRCUI UND 60.00 1.00 60.00 20.00 20.00 20.00
26 INTERRUPTOR TERMOMAGNETIC DE 3x100Ax240V UND 42.00 3.00 126.00 42.00 42.00 42.00
27 INTERRUPTOR TERMOMAGNETIC DE 2x100Ax380V UND 48.00 3.00 144.00 48.00 48.00 48.00
28 INTERRUPTOR TERMOMAGNETIC DE 2x100Ax500V UND 60.00 3.00 180.00 60.00 60.00 60.00
29 INTERRUPTOR BAKELITA X 2 SWITCH UND 8.00 9.00 72.00 24.00 24.00 24.00
30 CAJA RECTANG GALV 4"X2 1/8" UND 2.00 72.00 144.00 48.00 48.00 48.00
31 CAJA RECTANG GALV PESADA 4"x2 1/8"x2 1/8 UND 2.00 9.00 18.00 6.00 6.00 6.00
32 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 2.20 97.00 213.40 71.13 71.13 71.13
33 FLUORES. RECTO ISPE 1X40 W C/EQ + PANT UND 45.00 97.00 4,365.00 1,455.00 1,455.00 1,455.00
34 INTERRUPTOR SIMPLE PZA 4.50 6.00 27.00 9.00 9.00 9.00
35 TOMACORRIENTE DOBLE PZA 4.50 66.00 297.00 99.00 99.00 99.00
36 ASFALTO RC-250 GLN 12.00 3.62 43.44 14.48 14.48 14.48
37 LADRILLO CORRIENTE 8 x 12 x 24 CM UND 0.75 36,951.05 27,713.29 27,713.29
38 LADRILLO P/TECHO DE 12x30x30 CM 4 HCOS. UND 3.50 1,588.41 5,559.44 5,559.44
39 LADRILLO P/TECHO DE 15x30x30 CM 8 HCOS. UND 3.80 4,765.23 18,107.87 18,107.87
40 CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.80 3,922.12 93,346.46 23,336.61 23,336.61 23,336.61 23,336.61
41 BISAGRA CAPUCHINA PLOMA 3 1/2" X 3 1/2" PAR 4.50 32.00 144.00 144.00
42 YESO EN BOLSAS DE 25 KG. BOL 4.00 3.43 13.72 13.72
43 CINTA AISLANTE RLL 3.50 47.85 167.48 167.48
44 TAPAJUNTA PARA CIELORRASO M 3.00 305.16 915.48 915.48
45 OCRE KG 13.00 0.23 2.99 2.99
46 VARILLA DE COBRE DE 1/2" x 2.40m UND 180.00 1.00 180.00 180.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
47 IMPERMEAB.MORTERO/CONCRETO CHEMA 1 POLVO KG 18.00 29.28 527.04 527.04
48 PEGAMENTO PARA PVC AGUA FORDUIT GLN 38.00 0.82 31.16 31.16
49 PEGAMENTO PARA LOSETAS Y CERAMICAS UND 25.00 108.68 2,717.00 2,717.00
50 FRAGUA GRIS CLARO KG 8.00 10.87 86.96 86.96
51 NIVEL DIA 10.00 0.92 9.20 9.20
52 HORMIGON M3 80.00 58.42 4,673.60 2,336.80 2,336.80
53 ALQUILER DE CASA PARA CAMPAMENTO Y/O ALMACEN GLB 600.00 1.00 600.00 100.00 100.00 100.00 100.00 100.00 100.00
54 LIJA PARA MADERA UND 2.00 36.33 72.66 72.66
55 AGUA M3 0.50 79.09 39.55 39.55
56 TIJERAL SEGUN DISEO GLB 850.00 6.00 5,100.00 5,100.00
57 PRUEBAS DE CALIDAD DE CONCRETO ROTURA UND 25.00 20.00 500.00 83.33 83.33 83.33 83.33 83.33 83.33
58 CARTEL DE OBRA 2.40X3.60 INC.INSTALACION Y TRANSP GLB 450.00 1.00 450.00 450.00
59 MADERA NACIONAL P/ENCOFRADO-CARP P2 3.20 7,828.19 25,050.21 8,350.07 8,350.07 8,350.07
60 MADERA TORNILLO DE 2" X 2" X 10" PZA 3.50 386.04 1,351.14 450.38 450.38 450.38
61 RODON DE MADERA 3/4" x 3/4" M 2.20 417.15 917.73 305.91 305.91 305.91
62 CONTRAZOCALO DE CEDRO BOLEAD. 3/4"X2" M 4.00 417.15 1,668.60 556.20 556.20 556.20
63 MADERA PINO (REGLAS) P2 4.00 96.64 386.56 128.85 128.85 128.85
64 PUERTA DE MADERA DE CEDRO UND 480.00 10.30 4,944.00 4,944.00
65 VENTANA DE MADERA DE CEDRO M2 80.00 177.28 14,182.40 14,182.40
66 ESTACA DE MADERA P2 1.00 4.58 4.58 4.58
67 MADERA TORNILLO CEPILLADA P2 3.20 175.24 560.77 186.92 186.92 186.92
68 TRIPLAY DE 4 MM M2 25.00 132.36 3,309.00 1,103.00 1,103.00 1,103.00
69 ALUMINIO 3 X 2" M 18.00 134.40 2,419.20 2,419.20
70 THINER GLN 12.00 12.23 146.76 48.92 48.92 48.92
71 IMPRIMANTE GLN 12.00 305.79 3,669.48 1,223.16 1,223.16 1,223.16
72 PINTURA ESMALTE SINTETICO GLN 26.00 41.98 1,091.48 363.83 363.83 363.83
73 PINTURA LATEX SUPERMATE GLN 24.00 170.64 4,095.36 1,365.12 1,365.12 1,365.12
74 PINTURA ANTICORROSIVA GLN 38.00 1.32 50.16 16.72 16.72 16.72
75 TAPAPOROS DE MADERA ACABADA C/BARNIZ O LACA GLN 45.00 1.43 64.35 21.45 21.45 21.45
76 BARNIZ MARINO GLN 42.00 1.29 54.18 18.06 18.06 18.06
77 TEJA ANDINA ETERNIT 1.18m x0.745m x5mm PZA 36.00 211.52 7,614.72 7,614.72
78 TEKNOPOR DE 1" x 4' x 8' PLN 4.20 92.52 388.58 388.58
79 MARCO Y TAPA FO. GO. P/MEDIDOR 1/2"-3/4" UND 45.00 1.00 45.00 45.00
80 TIRAFON 4" UND 1.50 1,057.60 1,586.40 1,586.40
81 CUMBRERAS TEJA DE ETERNIT M 28.00 27.30 764.40 764.40
82 TUBO DE FIERRO FUNDIDO 3"x6' UND 122.00 17.96 2,191.12 2,191.12
83 TUBERIA PVC SAP A-10 DE 1/2" M 2.50 288.41 721.03 721.03
84 TUB. PVC SAP P/INST. ELECT. DE 1" M 0.40 5.00 2.00 2.00
85 CURVA PESADO PVC SAP P/INST. ELECT. 1" UND 1.00 1.00 1.00 1.00
86 CURVA PVC SAP LUZ 3/4" PZA 2.00 291.00 582.00 582.00
87 TUBO PVC SEL (E/C) 3/4" X 3.00 M. PZA 2.50 509.85 1,274.63 1,274.63
88 VIDRIO TRANSPARENTE INCOLORO CRUDO MEDIODOBLE P2 2.20 74.83 164.63 164.63
89 PLATINA DE FIERRO 4" x 4" x 1/2" UND 35.00 92.00 3,220.00 3,220.00
90 DISEO DE MEZCLA DE CONCRETO UND 15.00 3.00 45.00 45.00
91 CORREAS DE MADERA 2"X3"X10' M 17.00 400.51 6,808.67 6,808.67
92 CERAMICA COLOR CLARO 0.30X0.30 DESLIZANTE M2 28.00 456.44 12,780.32 12,780.32
93 CHAPA FORTE 3 GOLPES UND 45.00 8.00 360.00 360.00

EQUIPOS
94 MIRAS Y JALONES HM 1.00 4.58 4.58 4.58
95 ANDAMIO METAL TABLAS-ALQUILER EST 4.00 0.07 0.28 0.28
96 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 95.48 1,909.60 238.70 238.70 238.70 238.70 238.70 238.70 238.70 238.70
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
97 SEGURIDAD E HIGIENE EN OBRA GLB 450.00 1.00 450.00 75.00 75.00 75.00 75.00 75.00 75.00
98 VIBRADOR DE CONCRETO 4 HP 1.35" HM 15.00 75.62 1,134.30 189.05 189.05 189.05 189.05 189.05 189.05
99 VIBRADOR DE CONCRETO 4 HP 2.40" HM 15.00 3.60 54.00 9.00 9.00 9.00 9.00 9.00 9.00
100 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 147.25 3,681.25 613.54 613.54 613.54 613.54 613.54 613.54
101 TEODOLITO HM 20.00 22.90 458.00 76.33 76.33 76.33 76.33 76.33 76.33
102 HERRAMIENTAS MANUALES %MO 11,209.40 1,868.23 1,868.23 1,868.23 1,868.23 1,868.23 1,868.23

FORMULA 02 PABELLON B

MANO DE OBRA
103 TOPOGRAFO HH 14.14 32.91 465.35 77.56 77.56 77.56 77.56 77.56 77.56
104 OPERARIO HH 14.14 6,262.31 88,549.06 14,758.18 14,758.18 14,758.18 14,758.18 14,758.18 14,758.18
105 OFICIAL HH 12.40 2,475.35 30,694.34 5,115.72 5,115.72 5,115.72 5,115.72 5,115.72 5,115.72
106 PEON HH 11.21 9,044.98 101,394.23 16,899.04 16,899.04 16,899.04 16,899.04 16,899.04 16,899.04

MATERIALES

107 ALAMBRE NEGRO RECOCIDO # 16 KG 6.50 1,226.56 7,972.64 7,972.64


108 ALAMBRE NEGRO RECOCIDO # 8 KG 6.50 298.46 1,939.99 1,939.99
109 CLAVOS PARA MADERA C/C 1" KG 6.00 1.40 8.40 8.40
110 CLAVOS PARA MADERA C/C 2 1/2" KG 5.00 0.57 2.85 2.85
111 CLAVOS PARA MADERA C/C 3" KG 6.00 250.72 1,504.32 1,504.32
112 CLAVOS PARA MADERA C/C 4" KG 6.00 52.51 315.06 315.06
113 FIERRO LISO DE 1/2" x 6m. AREQUIPA VAR 35.00 6.30 220.50 220.50
114 PERNOS 3/8" X 4 " PZA 2.20 480.00 1,056.00 1,056.00
115 ACERO DE REFUERZO FY=4200 GRADO 60 KG 4.70 15,109.30 71,013.71 71,013.71
116 ARENA FINA M3 100.00 37.17 3,717.00 1,239.00 1,239.00 1,239.00
117 TIERRA DE CHACRA O VEGETAL M3 10.00 1.40 14.00 4.67 4.67 4.67
118 PIEDRA CHANCADA DE 1/2" M3 105.00 36.41 3,823.05 1,274.35 1,274.35 1,274.35
119 PIEDRA CHANCADA DE 3/4" M3 95.00 63.68 6,049.60 2,016.53 2,016.53 2,016.53
120 PIEDRA GRANDE DE 8" M3 65.00 4.32 280.80 93.60 93.60 93.60
121 PIEDRA MEDIANA DE 4" M3 60.00 3.73 223.80 74.60 74.60 74.60
122 GRAVA CANTO RODADO M3 75.00 8.04 603.00 201.00 201.00 201.00
123 ARENA GRUESA M3 80.00 114.94 9,195.20 3,065.07 3,065.07 3,065.07
124 PIEDRA CHANCADA DE 3/4" M3 80.00 9.35 748.00 249.33 249.33 249.33
125 ALAMBRE TW # 12 AWG M 1.20 158.40 190.08 190.08
126 CABLE TW # 14 AWG 2.5 MM2 M 1.20 718.10 861.72 861.72
127 CABLE TW # 6 AWG - 16 MM2. M 1.20 505.26 606.31 606.31
128 CABLE ELECTRICO SOLIDO TW N 12 M 8.00 151.20 1,209.60 1,209.60
129 CABLE ELECTRICO N14 THW AWG M 1.20 471.86 566.23 566.23
130 INODORO TQUE. BAJO NORMAL BLANCO C/A. UND 140.00 8.00 1,120.00 1,120.00
131 LAVATORIO 20"x17" DE 1 LLAVE B C/A. UND 42.00 5.00 210.00 210.00
132 REGISTRO DE BRONCE DE 2" UND 12.00 11.00 132.00 132.00
133 SUMIDERO CROMADO DE 2" UND 4.00 12.00 48.00 48.00
134 GRIFO DE BRONCE 1/2" UND 20.00 2.00 40.00 40.00
135 GRIFO TIPO DE CUELLO DE CISNE DE BRONCE 1/2" UND 40.00 10.00 400.00 400.00
136 CRUCETAS PZA 0.20 2,013.80 402.76 402.76
137 TABLERO MONOFASICO DE 12 POLOS UND 90.00 2.00 180.00 180.00
138 TABLERO GENERADOR AUTOMATICO DE 4 CIRCUI UND 60.00 1.00 60.00 60.00
139 TOMACORRIENTE SIMPLE PLANO BAKELITA UND 8.00 34.00 272.00 272.00
140 TOMACORRIENTE DOBLE PLANO BAKELITA UND 12.00 38.00 456.00 456.00
141 INTERRUPTOR SIMPLE BIPOLAR BAKELITA UND 14.00 1.80 25.20 25.20
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
142 INTERRUPTOR TERMOMAGNETIC DE 3x100Ax240V UND 42.00 2.00 84.00 84.00
143 INTERRUPTOR TERMOMAGNETIC DE 2x100Ax380V UND 48.00 2.00 96.00 96.00
144 INTERRUPTOR TERMOMAGNETIC DE 2x100Ax500V UND 60.00 2.00 120.00 120.00
145 CAJA DE PASE GALVANIZADA DE 4" X 4"X 2" PZA 3.00 4.00 12.00 12.00
146 SPOT LIGTH CROMADO UND 30.00 2.00 60.00 60.00
147 CAJA OCTOGONAL GALV. LIVIANA 4"x4"x2 1/2 UND 2.00 36.86 73.72 73.72
148 CAJA RECTANG GALV 4"X2 1/8" UND 2.00 4.00 8.00 8.00
149 CAJA RECTANG GALV PESADA 4"x2 1/8"x2 1/8 UND 2.00 76.00 152.00 152.00
150 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 2.20 43.00 94.60 94.60
151 FLUORES. RECTO ISPE 2X40 W C/EQ + PANT UND 60.00 5.00 300.00 300.00
152 FLUORES. RECTO ISPE 1X40 W C/EQ + PANT UND 45.00 40.00 1,800.00 1,800.00
153 INTERRUPTOR DOBLE PZA 15.00 4.00 60.00 60.00
154 TOMACORRIENTE DOBLE PZA 4.50 38.00 171.00 171.00
155 INTERRUPTOR SIMPLE BAKELITA PZA 4.50 38.00 171.00 171.00
156 INTERRUPTORES DE COMMUTACION UND 14.00 4.00 56.00 56.00
157 ASFALTO RC-250 GLN 12.00 3.62 43.44 43.44
158 LADRILLO ARCILLA CORRIENTE REX 6x12x25 CM UND 0.80 48.00 38.40 38.40
159 LADRILLO CORRIENTE 8 x 12 x 24 CM UND 0.75 20,542.90 15,407.18 3,851.79 3,851.79 3,851.79 3,851.79
160 LADRILLO P/TECHO DE 15x30x30 CM 8 HCOS. UND 3.80 2,060.82 7,831.12 1,957.78 1,957.78 1,957.78 1,957.78
161 CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.80 2,267.46 53,965.55 13,491.39 13,491.39 13,491.39 13,491.39
162 CERAMICO DE 1RA DE 20 x 30 CM. M2 22.00 25.52 561.44 187.15 187.15 187.15
163 CERAMICO DE 1RA DE 10 x 30 CM. M2 23.00 134.61 3,096.03 1,032.01 1,032.01 1,032.01
164 MAYOLICA BLANCA 20 X 20 M2 23.00 18.93 435.39 145.13 145.13 145.13
165 MAYOLICA ANTIDESLIZ. COLOR 1ra 15x15cm M2 25.00 2.40 60.00 20.00 20.00 20.00
166 CERRADURA LGO DOS GOLPES C/MANIJA UND 45.00 9.00 405.00 405.00
167 BISAGRA CAPUCHINA PLOMA 3 1/2" X 3 1/2" PAR 4.50 24.00 108.00 108.00
168 BISAGRA CAPUCHINA PLOMA 3.5" x 3.5" pza 8.00 15.00 120.00 120.00
169 MANIJA DE BRONCE P/VENTANA FIERRO UND 18.00 9.00 162.00 162.00
170 CERRADEURA DE PERILLA EPOLEG BAO UND 25.00 8.00 200.00 200.00
171 YESO EN BOLSAS DE 25 KG. BOL 4.00 4.94 19.76 19.76
172 CINTA AISLANTE RLL 3.50 61.11 213.89 213.89
173 TAPAJUNTA PARA CIELORRASO M 3.00 157.04 471.12 471.12
174 OCRE KG 13.00 2.48 32.24 32.24
175 PIZARRA 5 X 1.2 MTS. UND 180.00 1.00 180.00 180.00
176 VARILLA DE COBRE DE 1/2" x 2.40m UND 180.00 1.00 180.00 180.00
177 PORCELANA KG 1.00 4.74 4.74 4.74
178 PORCELANA BLANCA KG 8.00 3.52 28.16 28.16
179 LAVADERO A.INOX.19"x37"C/ESC. P. SAT.C/A UND 170.00 10.00 1,700.00 1,700.00
180 PEGAMENTO PARA PVC AGUA FORDUIT GLN 95.00 21.75 2,066.25 2,066.25
181 PEGAMENTO PARA LOSETAS Y CERAMICAS UND 25.00 84.34 2,108.50 2,108.50
182 FRAGUA GRIS CLARO KG 8.00 17.01 136.08 136.08
183 MASILLA PARA VIDRIO KG 2.20 51.23 112.71 112.71
184 NIVEL DIA 10.00 1.32 13.20 2.20 2.20 2.20 2.20 2.20 2.20
185 HORMIGON M3 80.00 61.57 4,925.60 985.12 985.12 985.12 985.12 985.12
186 COLA SINTETICA FULLER GLN 22.00 2.58 56.76 56.76
187 LIJA PARA MADERA UND 2.00 54.23 108.46 108.46
188 AGUA M3 0.50 43.10 21.55 3.59 3.59 3.59 3.59 3.59 3.59
189 TIJERAL SEGUN DISEO GLB 850.00 5.00 4,250.00 2,125.00 2,125.00
190 PRUEBAS DE CALIDAD DE CONCRETO ROTURA UND 25.00 20.00 500.00 83.33 83.33 83.33 83.33 83.33 83.33
191 MADERA NACIONAL P/ENCOFRADO-CARP P2 3.20 6,821.19 21,827.81 7,275.94 7,275.94 7,275.94
192 MADERA TORNILLO P2 4.00 9.36 37.44 12.48 12.48 12.48
193 MADERA TORNILLO DE 2" X 2" X 10" PZA 3.50 198.66 695.31 231.77 231.77 231.77
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
194 VENTANA DE MADERA DE CEDRO M2 80.00 29.72 2,377.60 792.53 792.53 792.53
195 MADERA CEDRO CEPILLADO P2 114.00 380.55 43,382.70 14,460.90 14,460.90 14,460.90
196 REGLA DE MADERA P2 1.00 0.36 0.36 0.12 0.12 0.12
197 ESTACA DE MADERA P2 1.00 6.58 6.58 2.19 2.19 2.19
198 MADERA TORNILLO CEPILLADA P2 3.20 26.25 84.00 28.00 28.00 28.00
199 TRIPLAY LUPUNA DE 4'x8'x 4 mm PLN 25.00 5.62 140.50 46.83 46.83 46.83
200 TRIPLAY DE 4 MM M2 25.00 68.11 1,702.75 567.58 567.58 567.58
201 CAJA DE DESAGUE DE 12"X24" UND 24.00 1.00 24.00 24.00
202 TAPA C/MARCO FF DE DESAGUE 12" X 24" PZA 18.00 1.00 18.00 18.00
203 DIVISI. METALICAS P/BAOS PAL.LEGISLATI. M2 75.00 35.78 2,683.50 2,683.50
204 ALUMINIO 3 X 2" M 18.00 91.19 1,641.42 1,641.42
205 THINER GLN 12.00 1.96 23.52 23.52
206 IMPRIMANTE GLN 12.00 207.18 2,486.16 2,486.16
207 PINTURA ESMALTE SINTETICO GLN 26.00 2.61 67.86 67.86
208 PINTURA LATEX SUPERMATE GLN 24.00 116.23 2,789.52 2,789.52
209 TAPAPOROS DE MADERA ACABADA C/BARNIZ O LACA GLN 45.00 3.32 149.40 149.40
210 BARNIZ MARINO GLN 42.00 2.98 125.16 125.16
211 PUERTA METALICA C/PLANCHA M2 92.00 7.68 706.56 706.56
212 TEJA ANDINA ETERNIT 1.18m x0.745m x5mm PZA 25.00 194.75 4,868.75 2,434.38 2,434.38
213 TEKNOPOR DE 1" x 4' x 8' PLN 4.20 92.52 388.58 388.58
214 NIPLE DE Fo Go DE 1/2" x 1 1/2" UND 3.00 2.00 6.00 6.00
215 MARCO Y TAPA FO. GO. P/MEDIDOR 1/2"-3/4" UND 45.00 1.00 45.00 45.00
216 TIRAFON 4" UND 1.30 973.76 1,265.89 1,265.89
217 CUMBRERAS TEJA DE ETERNIT M 20.00 23.73 474.60 237.30 237.30
218 SUMIDERO DE BRONCE DE 2" UND 4.00 2.00 8.00 8.00
219 TUBO DE FIERRO FUNDIDO 3"x6' UND 122.00 2.10 256.20 256.20
220 YEE DE PVC C/REDUCCION 4" A 2" PZA 8.00 18.00 144.00 144.00
221 TUB. PVC SAP PRESION P/AGUA C-10 R. 1/2" M 2.40 122.55 294.12 294.12
222 TUB. PVC SAP P/INST. ELECT. DE 1" M 0.40 5.00 2.00 2.00
223 CURVA PESADO PVC SAP P/INST. ELECT. 1" UND 1.00 1.00 1.00 1.00
224 TEE PVC SAP ROSCADO 1/2" PZA 2.50 12.75 31.88 31.88
225 TEE PVC SAP 1/2" PZA 5.00 15.00 75.00 75.00
226 REDUCCION PVC 4" A 2" PZA 8.00 8.00 64.00 64.00
227 TUB. PVC SEL P/INST. ELECT. DE 3/4" M 3.10 380.36 1,179.12 1,179.12
228 ADAPTADOR PVC SAL 4" UND 4.00 32.00 128.00 128.00
229 ADAPTADOR PVC SAL 2" UND 3.00 12.00 36.00 36.00
230 YEE PVC SAL 4" UND 6.50 5.00 32.50 32.50
231 YEE PVC SAL 2" UND 2.50 24.00 60.00 60.00
232 CODO PVC SAP 1/2" UND 1.50 54.50 81.75 81.75
233 CODO PVC SAL 2" X 90 PZA 3.00 34.00 102.00 102.00
234 CODO PVC SAL 4" X 90 PZA 9.50 24.00 228.00 228.00
235 CODO PVC SAL 2" X 45 PZA 9.00 18.00 162.00 162.00
236 TUBERIA PVC SAL 2" M 1.70 91.25 155.13 155.13
237 CODOS PVC SAL 4" X 45 PZA 7.50 8.00 60.00 60.00
238 TEE PVC C/REDUCCION 4" A 2" UND 6.50 1.00 6.50 6.50
239 TEE PVC DESAGUE 4" UND 6.50 7.00 45.50 45.50
240 REDUCCION DE PVC 3/4" A 1/2" PZA 2.00 1.00 2.00 2.00
241 SOMBRERO DE VENTILACION PVC SAL 2" PZA 4.00 2.10 8.40 8.40
242 TUBO PVC SAP (LUZ) (E/C) 1" X 3 M. PZA 16.00 83.90 1,342.40 1,342.40
243 TUBO PVC SEL (E/C) 3/4" X 3.00 M. PZA 2.50 121.50 303.75 303.75
244 CURVAS PVC SEL 3/4" PZA 1.00 141.00 141.00 141.00
245 VALVULA COMPUERTA DE BRONCE ROS. DE 1/2" UND 25.00 1.00 25.00 25.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
246 REGISTRO ROSCADO DE BRONCE DE 4" PZA 20.00 8.00 160.00 160.00
247 VIDRIO TRANSPARENTE INCOLORO CRUDO MEDIODOBLE P2 2.20 1,075.85 2,366.87 2,366.87
248 PLATINA DE FIERRO 4" x 4" x 1/2" UND 35.00 120.00 4,200.00 4,200.00
249 DISEO DE MEZCLA DE CONCRETO UND 15.00 3.00 45.00 45.00
250 CORREAS DE MADERA 2"X3"X10' M 4.50 245.30 1,103.85 1,103.85
251 CERAMICA COLOR CLARO 0.30X0.30 DESLIZANTE M2 27.00 294.80 7,959.60 7,959.60

EQUIPOS

252 MIRAS Y JALONES HM 1.00 6.58 6.58 3.29 3.29


253 ANDAMIO METAL TABLAS-ALQUILER EST 4.00 0.01 0.04 0.04
254 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 17.93 358.60 59.77 59.77 59.77 59.77 59.77 59.77
255 VIBRADOR DE CONCRETO 4 HP 1.35" HM 15.00 36.03 540.45 90.08 90.08 90.08 90.08 90.08 90.08
256 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 65.65 1,641.25 273.54 273.54 273.54 273.54 273.54 273.54
257 TEODOLITO HM 20.00 32.91 658.20 109.70 109.70 109.70 109.70 109.70 109.70
258 HERRAMIENTAS MANUALES %MO 7,632.16 1,272.03 1,272.03 1,272.03 1,272.03 1,272.03 1,272.03

FORMULA 03 SALA DE USOS MULTIPLES

MANO DE OBRA

259 OPERADOR DE EQUIPO LIVIANO HH 14.14 6.88 97.28 48.64 48.64


260 TOPOGRAFO HH 14.14 2.34 33.09 16.54 16.54
261 OPERARIO HH 14.14 1,871.78 26,466.97 13,233.48 13,233.48
262 OFICIAL HH 12.40 1,114.72 13,822.53 6,911.26 6,911.26
263 PEON HH 11.21 2,898.22 32,489.05 16,244.52 16,244.52

MATERIALES

264 ALAMBRE NEGRO RECOCIDO # 16 KG 6.50 889.49 5,781.69 5,781.69


265 ALAMBRE NEGRO RECOCIDO # 8 KG 6.50 102.05 663.33 663.33
266 CLAVOS PARA MADERA C/C 3" KG 6.00 89.59 537.54 537.54
267 CLAVOS PARA MADERA C/C 4" KG 6.00 21.56 129.36 129.36
268 CLAVOS ACERO GALVANIZADO DE 4" KG 5.00 334.00 1,670.00 1,670.00
269 ACERO DE REFUERZO FY=4200 GRADO 60 KG 4.70 4,697.35 22,077.55 22,077.55
270 ARENA FINA M3 100.00 13.03 1,303.00 1,303.00
271 PIEDRA CHANCADA DE 1/2" M3 105.00 47.36 4,972.80 4,972.80
272 PIEDRA CHANCADA DE 3/4" M3 95.00 2.23 211.85 211.85
273 PIEDRA MEDIANA DE 4" M3 60.00 1.11 66.60 66.60
274 ARENA GRUESA M3 80.00 35.49 2,839.20 2,839.20
275 BARRA DE COBRE DE 4 CIRCUITOS KG 35.00 1.00 35.00 35.00
276 ALAMBRE TW # 12 AWG M 1.20 136.50 163.80 163.80
277 CABLE TW # 6 AWG - 16 MM2. M 1.20 52.50 63.00 63.00
278 CABLE ELECTRICO N14 THW AWG M 1.20 82.50 99.00 99.00
279 FLUORESCENTE CIRCULAR 40 W UND 35.00 6.00 210.00 210.00
280 CRUCETAS PZA 0.20 154.80 30.96 30.96
281 REFLECTOR ALTA PRESION DE 250W C/EQUIPO DE ALOGENURO M PZA 50.00 2.00 100.00 100.00
282 TABLERO MONOFASICO DE 12 POLOS UND 90.00 1.00 90.00 90.00
283 TABLERO ARRANQ-PARAD 3M. INC.CABLES/CR4 UND 65.00 1.00 65.00 65.00
284 TOMACORRIENTE DOBLE PLANO BAKELITA UND 12.00 12.00 144.00 144.00
285 INTERRUPTOR UNIPOLAR DOBLE BAKELITA UND 22.00 8.00 176.00 176.00
286 INTERRUPTOR SIMPLE BIPOLAR BAKELITA UND 14.00 1.80 25.20 25.20
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
287 INTERRUPTOR TERMOMAGNETIC DE 3x100Ax240V UND 42.00 1.00 42.00 42.00
288 INTERRUPTOR TERMOMAGNETIC DE 2x100Ax380V UND 48.00 1.00 48.00 48.00
289 INTERRUPTOR TERMOMAGNETIC DE 2x100Ax500V UND 60.00 1.00 60.00 60.00
290 INTERRUPTOR BAKELITA X 2 SWITCH UND 8.00 4.00 32.00 32.00
291 CAJA DE PASE GALVANIZADA DE 4" X 4"X 2" PZA 3.00 1.00 3.00 3.00
292 CAJA OCTOGONAL GALV. LIVIANA 4"x4"x2 1/2 UND 2.00 2.86 5.72 5.72
293 CAJA RECTANG GALV 4"X2 1/8" UND 2.00 18.00 36.00 36.00
294 CAJA RECTANG GALV PESADA 4"x2 1/8"x2 1/8 UND 2.00 20.00 40.00 40.00
295 CAJA OCTOGONAL GALV . DE 4" x 2" x5/8" PESADA UND 2.00 19.00 38.00 38.00
296 FLUORES. RECTO ISPE 2X40 W C/EQ + PANT UND 60.00 13.00 780.00 780.00
297 TOMACORRIENTE DOBLE PZA 4.50 26.00 117.00 117.00
298 INTERRUPTOR SIMPLE BAKELITA PZA 4.50 4.00 18.00 18.00
299 SALIDA PARA ELECTROBOMBA PTO 5.00 1.00 5.00 5.00
300 ASFALTO RC-250 GLN 12.00 2.93 35.16 35.16
301 LADRILLO CORRIENTE 6 x 12 x 24 CM UND 0.75 4,179.89 3,134.92 3,134.92
302 LADRILLO P/TECHO DE 12x30x30 CM 4 HCOS. UND 3.50 1,004.85 3,516.98 3,516.98
303 CUMBRERA INFERIOR TEJA ANDINA BARRO PZA 22.00 38.40 844.80 844.80
304 GANCHO GALV. PARA TEJA ANDINA PZA 2.50 105.20 263.00 263.00
305 CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.80 778.51 18,528.54 18,528.54
306 CERAMICO DE 1RA DE 10 x 30 CM. M2 23.00 40.64 934.72 934.72
307 CERRADURA EXTERIOR DE DOS GOLPES UND 45.00 1.00 45.00 45.00
308 BISAGRA ALUMINIZ.CAPUCHINA 4"x4" UND 4.00 2.00 8.00 8.00
309 YESO EN BOLSAS DE 25 KG. BOL 4.00 0.56 2.24 2.24
310 CINTA AISLANTE RLL 3.50 6.70 23.45 23.45
311 IMPERMEAB.MORTERO/CONCRETO CHEMA 1 POLVO KG 18.00 22.56 406.08 406.08
312 PEGAMENTO PARA PVC AGUA FORDUIT GLN 85.00 17.57 1,493.45 1,493.45
313 PEGAMENTO PARA LOSETAS Y CERAMICAS UND 25.00 0.97 24.25 24.25
314 FRAGUA GRIS CLARO KG 8.00 0.97 7.76 7.76
315 BUTACAS DE F. DE VID. UND 180.00 82.00 14,760.00 14,760.00
316 HORMIGON M3 80.00 15.73 1,258.40 1,258.40
317 LIJA PARA MADERA UND 2.00 2.52 5.04 5.04
318 AGUA M3 0.50 33.69 16.85 16.85
319 PRUEBAS DE CALIDAD DE CONCRETO ROTURA UND 25.00 42.00 1,050.00 1,050.00
320 MADERA ANDAMIAJE P2 3.20 41.33 132.26 132.26
321 MADERA NACIONAL P/ENCOFRADO-CARP P2 3.20 2,099.60 6,718.72 6,718.72
322 PUERTA DE MADERA TORNILLO CON MARCO M2 80.00 8.40 672.00 672.00
323 REGLA DE MADERA P2 1.00 5.84 5.84 5.84
324 ESTACA DE MADERA P2 1.00 3.98 3.98 3.98
325 MADERA TORNILLO CEPILLADA P2 3.20 124.11 397.15 397.15
326 IMPRIMANTE GLN 12.00 38.92 467.04 467.04
327 PINTURA LATEX GLN 24.00 1.01 24.24 24.24
328 PINTURA ESMALTE SINTETICO GLN 26.00 7.18 186.68 186.68
329 PINTURA LATEX SUPERMATE GLN 24.00 30.33 727.92 727.92
330 TEJA ANDINA ETERNIT 1.18m x0.745m x5mm PZA 28.00 103.05 2,885.40 2,885.40
331 TIRAFON 4" UND 1.50 620.44 930.66 930.66
332 LUZ DE EMERGENCIA c/ AUTONOMIA 2 a 4 hrs. Incluido Accesorio UND 65.00 1.00 65.00 65.00
333 TUBERIA PVC SAL DE 2" UND 12.00 15.75 189.00 189.00
334 CODO DE 90 PVC SAL DE 2" UND 2.50 8.00 20.00 20.00
335 TUB. PVC SEL P/INST. ELECT. DE 3/4" M 3.10 329.29 1,020.80 1,020.80
336 YEE PVC SAL 2" UND 2.50 8.00 20.00 20.00
337 CODO PVC SAL 2" X 90 PZA 3.00 4.00 12.00 12.00
338 TUBO PVC SAL 2" X 3M PZA 3.00 7.35 22.05 22.05
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
339 TUBERIA PVC SAL 2" M 1.70 4.00 6.80 6.80
340 SOMBRERO DE VENTILACION PVC SAL 2" PZA 4.00 4.20 16.80 16.80
341 CURVA PVC SAP LUZ 3/4" PZA 2.00 57.00 114.00 114.00
342 CURVAS PVC SEL 3/4" PZA 1.00 4.00 4.00 4.00
343 VIDRIO TRANSPAR.INCOLOR DOBLE P2 2.50 15.64 39.10 39.10
344 DISEO DE MEZCLA DE CONCRETO UND 15.00 3.00 45.00 45.00
345 CERAMICA COLOR CLARO 0.30X0.30 DESLIZANTE M2 28.00 91.03 2,548.84 2,548.84

EQUIPOS

346 MIRAS Y JALONES HM 1.00 2.34 2.34 1.17 1.17


347 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 16.73 334.60 167.30 167.30
348 TRACTOR DE ORUGAS DE 140-160 HP HM 180.00 11.17 2,010.60 1,005.30 1,005.30
349 VIBRADOR DE CONCRETO 4 HP 2.40" HM 15.00 22.14 332.10 166.05 166.05
350 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 39.57 989.25 494.63 494.63
351 TEODOLITO HM 20.00 3.66 73.20 36.60 36.60
352 HERRAMIENTAS MANUALES %MO 1,893.90 946.95 946.95

FORMULA 04 MURO DE CONTENCION

MANO DE OBRA

353 TOPOGRAFO HH 14.14 4.36 61.65 61.65


354 OPERARIO HH 14.14 1,517.26 21,454.06 21,454.06
355 OFICIAL HH 12.40 670.10 8,309.24 8,309.24
356 PEON HH 11.21 3,928.48 44,038.26 44,038.26
0.00
MATERIALES 0.00
0.00
357 ALAMBRE NEGRO RECOCIDO # 16 KG 6.50 916.54 5,957.51 5,957.51
358 ALAMBRE NEGRO RECOCIDO # 8 KG 6.50 129.24 840.06 840.06
359 CLAVOS PARA MADERA C/C 3" KG 6.00 87.87 527.22 527.22
360 ACERO DE REFUERZO FY=4200 GRADO 60 KG 4.70 4,903.47 23,046.31 23,046.31
361 ARENA FINA M3 100.00 3.62 362.00 362.00
362 PIEDRA CHANCADA DE 1/2" M3 105.00 63.92 6,711.60 6,711.60
363 PIEDRA CHANCADA DE 3/4" M3 95.00 34.08 3,237.60 3,237.60
364 PIEDRA MEDIANA DE 4" M3 60.00 5.38 322.80 322.80
365 GRAVA CANTO RODADO M3 75.00 6.81 510.75 510.75
366 AFIRMADO M3 30.00 315.40 9,462.00 9,462.00
367 ARENA GRUESA M3 80.00 74.80 5,984.00 5,984.00
368 ASFALTO RC-250 GLN 12.00 12.79 153.48 153.48
369 CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.80 1,445.19 34,395.52 34,395.52
370 YESO EN BOLSAS DE 25 KG. BOL 4.00 1.53 6.12 6.12
371 SERVICIO DE SOLDADURA EN FIERRO GALVANIZADO pto 35.00 58.00 2,030.00 2,030.00
372 HORMIGON M3 80.00 22.31 1,784.80 1,784.80
373 AGUA M3 0.50 29.51 14.76 14.76
374 MADERA NACIONAL P/ENCOFRADO-CARP P2 3.20 2,055.08 6,576.26 6,576.26
375 ESTACA DE MADERA P2 1.00 8.72 8.72 8.72
376 TUBO Fo.GALV. DE 2" M 130.00 89.40 11,622.00 11,622.00
TUBO Fo.GALV. DE 2 1/2" M 150.00 10.00 0.00
EQUIPOS 0.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
378 MIRAS Y JALONES HM 1.00 4.36 4.36 4.36
379 VOLQUETE DE 10 M3 HM 100.00 23.58 2,358.00 2,358.00
380 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 316.21 6,324.20 6,324.20
381 VIBRADOR DE CONCRETO 4 HP 1.35" HM 15.00 9.09 136.35 136.35
382 VIBRADOR DE CONCRETO 4 HP 2.40" HM 15.00 52.53 787.95 787.95
383 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 70.15 1,753.75 1,753.75
384 TEODOLITO HM 20.00 4.36 1,495.90 1,495.90

FORMULA 05 SERVICIOS HIGIENICOS

MANO DE OBRA

385 OPERARIO hh 1,780.5270 14.14 25,176.65 12,588.33 12,588.33


386 OFICIAL hh 216.5130 12.40 2,684.76 1,342.38 1,342.38
387 PEON hh 1,183.6906 11.21 13,269.17 6,634.59 6,634.59

HERRAMIENTAS

388 ALAMBRE NEGRO RECOCIDO # 16 kg 68.8277 6.50 447.38 447.38


389 ALAMBRE NEGRO RECOCIDO # 8 kg 30.7174 6.50 199.66 199.66
390 CLAVOS PARA MADERA CON CABEZA DE 2" kg 3.8733 6.00 23.24 23.24
391 CLAVOS PARA MADERA CON CABEZA DE 3" kg 27.7218 6.00 166.33 166.33
392 GANCHO GALVANIZADO PARA TEJA ANDINA pza 9.2000 5.95 54.74 54.74
393 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 1,227.4064 4.70 5,768.81 5,768.81
394 ARENA FINA m3 9.4549 100.00 945.49 472.75 472.75
395 PIEDRA CHANCADA DE 1/2" m3 20.2149 105.00 2,122.56 1,061.28 1,061.28
396 PIEDRA GRANDE DE 8" m3 5.8150 65.00 377.98 188.99 188.99
397 PIEDRA MEDIANA DE 4" m3 0.5880 60.00 35.28 17.64 17.64
398 ARENA GRUESA m3 15.0738 80.00 1,205.90 602.95 602.95
399 CABLE TW # 14 AWG 2.5 mm2 ml 179.3950 1.40 251.15 251.15
400 CABLE TW # 12 AWG - 4 mm2 ml 58.8250 1.80 105.89 105.89
401 CABLE TW (2X10+1X10)MM2 NH-80 ml 171.1500 3.00 513.45 513.45
402 INODORO TANQUE BAJO NORMAL BLANCO INCLUYE ACCESORIOS und 10.0000 210.00 2,100.00 2,100.00
403 LAVATORIO 20"X11" DE 1 LLAVE C INCLUYE ACCESORIOS und 2.0000 85.00 170.00 170.00
404 REGISTRO DE BRONCE DE 4" und 3.1500 12.00 37.80 37.80
405 SOPORTE METALICO DE PLATINA 1 1/2" X 1/4", U + TUERCAS Y PERNOS 3/8" und 2.1000 6.00 12.60 12.60
406 FLUORESCENTE CIRCULAR 32 W (INCLUYE EQUIPO COMPLETO) und 2.0000 45.00 90.00 90.00
407 TOMACORRIENTE DOBLE PLANO BAKELITA und 2.0000 12.00 24.00 24.00
408 INTERRUPTOR BAKELITA X 1 SWITCH und 4.0000 7.50 30.00 30.00
409 INTERRUPTOR BAKELITA X 2 SWITCH und 1.0000 8.00 8.00 8.00
410 CAJA OCTOGONAL GALVANIZADA LIVIANA 4" X 4" X 2 1/2 und 8.0000 2.00 16.00 16.00
411 CAJA RECTANGULAR GALVANIZADA LIVIANA DE 4" X 2 1/8" und 1.0000 3.00 3.00 3.00
412 CAJA RECTANGULAR GALVANIZADA 4" X 2 1/4" X 2 1/2" und 5.0000 3.00 15.00 15.00
413 FLUORESCENTE RECTO ISPE 2X40 W C/EQ + PANTALLA und 4.0000 102.00 408.00 408.00
414 FLUORESCENTE RECTO ISPE 3X40 W C/EQ + PANTALLA und 2.0000 102.00 204.00 204.00
415 LADRILLO DE ARCILLA PARA TECHO h=15 cm und 514.4370 3.80 1,954.86 1,954.86
416 LADRILLO CORRIENTE 24 X 14 X 9 cm und 3,621.5400 0.84 3,042.09 3,042.09
417 CEMENTO PORTLAND TIPO I (42.5 kg) bls 348.2273 23.80 8,287.81 8,287.81
418 CAJA DE CONCRETO DE 12" X 24" und 17.1400 29.75 509.92 509.92
419 MAYOLICA DE COLOR DE PRIMERA DE 20 X 20 cm m2 85.9215 25.00 2,148.04 2,148.04
420 CERRADURA EXTERIOR DE DOS GOLPES und 4.0000 45.00 180.00 180.00
421 BISAGRA CAPUCHINA PLOMA 2 1/2" X 2 1/2" und 24.0000 5.00 120.00 120.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
422 BISAGRA CAPUCHINA 3 1/2" X 3 1/2" und 16.0000 5.00 80.00 80.00
423 TIRADOR DE BRONCE REDONDO DE 2 1/2 " und 8.0000 5.00 40.00 40.00
424 CINTA AISLANTE rll 3.1300 3.00 9.39 9.39
425 YESO EN BOLSAS DE 25 kg bls 0.9680 6.50 6.29 6.29
426 OCRE ROJO IMPORTADO kg 0.0968 9.00 0.87 0.87
427 FRAGUA PARA CERAMICO kg 36.1680 7.00 253.18 253.18
428 THINNER CORRIENTE gal 37.8380 15.00 567.57 567.57
429 PEGAMENTO PARA PVC AGUA FORDUIT gal 0.0815 25.00 2.04 2.04
430 PEGAMENTO PLASTICO PARA PVC CCP gal 0.0076 42.00 0.32 0.32
431 PEGAMENTO EN POLVO BLANCO PARA CERAMICOS kg 223.1610 1.00 223.16 223.16
432 PEGAMENTO PARA PVC gal 2.6518 45.00 119.33 119.33
433 CINTA TEFLON pza 0.3000 1.20 0.36 0.36
434 CINTA TEFLON und 5.1000 1.20 6.12 6.12
435 HORMIGON m3 14.8143 80.00 1,185.14 1,185.14
436 LIJA DE FIERRO # 80 pza 123.8407 2.40 297.22 297.22
437 LIJA PARA MADERA N' 100 und 0.8285 1.90 1.57 1.57
438 AGUA m3 0.0139 5.00 0.07 0.07
439 CERAMICO ALTO TRANSITO 30 x 30 CM m2 29.1585 23.80 693.97 693.97
440 MADERA TORNILLO p2 843.2743 4.20 3,541.75 3,541.75
441 CORDEL ml 12.1000 0.20 2.42 2.42
442 REGLA DE MADERA p2 20.0017 4.70 94.01 94.01
443 PUERTA DE MADERA TORNILLO SEGUN DISEO m2 12.3795 110.00 1,361.75 1,361.75
444 VENTANA DE MADERA CEDRO SEGUN DISEO INCL. INSTALACION Y ACCESORIOS m2 5.0190 80.00 401.52 401.52
445 MADERA ANDAMIAJE p2 140.6941 3.50 492.43 492.43
446 ANDAMIO DE MADERA p2 90.7788 4.20 381.27 381.27
447 ESTACA DE MADERA p2 12.1000 2.50 30.25 30.25
448 MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 40.8960 4.20 171.76 171.76
449 TAPA CON MARCO FIERRO FUNDIDO DE DESAGUE 12" X 24" pza 17.1400 33.30 570.76 570.76
450 DISOLVENTE THINER gal 0.0800 18.00 1.44 1.44
451 PINTURA ESMALTE SINTETICO gal 28.9440 45.00 1,302.48 1,302.48
452 PINTURA LATEX LAVABLE gal 14.2944 25.00 357.36 357.36
453 LACA MATE O BRILLANTE gal 0.4400 20.00 8.80 8.80
454 IMPRIMANTE gal 8.1541 22.00 179.39 179.39
455 BARNIZ gal 1.3803 30.00 41.41 41.41
456 SELLADOR DE MADERA gal 0.6628 32.00 21.21 21.21
457 CUMBRERA ARTICULADA SUPERIOR PARA TEJA ANDINA 72 CM pza 6.5780 17.00 111.83 111.83
458 TEJA ANDINA 1.14m X0.72m E=5mm pza 87.4640 28.00 2,448.99 2,448.99
459 CRUCETA DE PLASTICO pza 83.3100 0.20 16.66 16.66
460 UNION UNIVERSAL DE FIERRO GALVANIZADO DE 3/4" und 16.0000 7.50 120.00 120.00
461 NIPLE DE FIERRO GALVANIZADO DE 3/4" X 2" und 16.0000 3.50 56.00 56.00
462 TIRAFON 4" CON ARANDELA Y TAPA DE PLASTICO und 92.0640 1.50 138.10 138.10
463 SUMIDERO DE BRONCE DE 2" und 8.0000 4.00 32.00 32.00
464 SUMIDERO DE BRONCE DE 3" und 2.0000 5.00 10.00 10.00
465 TUBERIA PVC SAP PRESION PARA AGUA C-10 R. 1/2" ml 49.9100 3.50 174.69 174.69
466 TUBERIA PVC SAP PRESION C-10 EC 3/4" x 5 M. ml 50.0000 4.70 235.00 235.00
467 REDUCCION PVC SAP PARA AGUA CON ROSCA 3/4" A 1/2" und 1.0000 2.50 2.50 2.50
468 TEE PVC SAP PARA AGUA CON ROSCA DE 1/2" und 4.0000 2.00 8.00 8.00
469 TEE PVC SAP PARA AGUA CON ROSCA DE 3/4" und 12.0000 2.00 24.00 24.00
470 TUBERIA PVC SAL PARA DESAGUE DE 2" ml 76.5945 4.00 306.38 306.38
471 TUBERIA PVC SAL PARA DESAGUE DE 3" ml 14.4140 4.85 69.91 69.91
472 TUBERIA PVC SAL PARA DESAGUE DE 4" ml 144.6150 7.60 1,099.07 1,099.07
473 UNION UNIVERSAL CPVC PARA AGUA CALIENTE 1/2" und 4.0000 4.50 18.00 18.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
474 ADAPTADOR HEMBRA CPVC PRRESION PARA AGUA CALIENTE 3/4" A 1/2" und 4.0000 2.00 8.00 8.00
475 ADAPTADOR MACHO CPVC PRESION PARA AGUA CALIENTE DE 1/2" A 1/2" und 4.0000 2.00 8.00 8.00
476 ADAPTADOR PVC SAP 3/4" und 16.0000 2.80 44.80 44.80
477 YEE PVC SAL 4" und 15.0000 3.00 45.00 45.00
478 YEE PVC SAL CON REDUCCION 4" - 2" und 2.0000 3.00 6.00 6.00
479 TUBERIA PVC SAL 2" ml 3.1500 5.00 15.75 15.75
480 TUBERIA PVC SAL 3" ml 5.0000 6.00 30.00 30.00
481 CODO PVC SAL 3" X 90 pza 14.0000 2.00 28.00 28.00
482 CODO PVC SAL 4" X 90 pza 10.0000 5.00 50.00 50.00
483 CODO PVC SAL 2" X 45 pza 2.0000 3.00 6.00 6.00
484 CODO PVC SAP 3/4" und 40.0000 3.00 120.00 120.00
485 CODO PVC SAL 2"X90 pza 4.0000 2.00 8.00 8.00
486 CODO PVC SAP 1/2" und 6.0000 2.00 12.00 12.00
487 TEE PVC SAP 3/4" CON REDUCCION A 1/2" pza 6.0000 2.00 12.00 12.00
488 TRAMPA P PVC SAL 2" pza 8.0000 4.80 38.40 38.40
489 TUBO PVC SAP E/C PARA INSTALACIONES ELECTRICAS 3/4" und 21.6000 3.80 82.08 82.08
490 TUBERIA PVC SAP PARA INSTALACIONES ELECTRICAS DE 3" ml 171.1500 4.00 684.60 684.60
491 TUBERIA PVC SEL PARA INSTALACIONES ELECTRICAS DE 3/4" ml 100.4500 3.30 331.49 331.49
492 CURVA PVC SEL 3/4" pza 229.9000 0.95 218.41 218.41
493 UNION SIMPLE PVC SAP PARA INSTALACIONES ELECTRICAS 3/4" pza 100.4500 2.40 241.08 241.08
494 VALVULA COMPUERTA DE BRONCE DE 1/2" und 2.0000 21.45 42.90 42.90
495 VALVULA COMPUERTA DE BRONCE DE 3/4" und 8.0000 25.00 200.00 200.00
496 VIDRIO SEMIDOBLE p2 53.9490 5.00 269.75 269.75

EQUIPOS

497 HERRAMIENTAS MANUALES %MO 1,901.69 1,901.69 950.85 950.85


498 MEZCLADORA DE CONCRETO DE 9 -11p3 hm 25.5052 25.00 637.63 318.82 318.82
499 CAMION VOLQUETE DE 8 m3 hm 2.1220 95.00 201.59 100.80 100.80
500 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP hm 1.5857 25.00 39.64 19.82 19.82
501 VIBRADOR DE CONCRETO 4 HP 2.40" hm 9.0697 15.00 136.05 68.02 68.02
502 TEODOLITO hm 3.4848 10.00 34.85 17.42 17.42

FORMULA 06 TANQUE ELEVADO

MANO DE OBRA
503 OPERADOR DE EQUIPO LIVIANO HH 14.14 8.85 125.14 62.57 62.57
504 TOPOGRAFO HH 14.14 0.69 9.76 4.88 4.88
505 OPERARIO HH 14.14 780.87 11,041.50 5,520.75 5,520.75
506 OFICIAL HH 12.40 282.47 3,502.63 1,751.31 1,751.31
507 PEON HH 11.21 426.59 4,782.07 2,391.04 2,391.04

MATERIALES

508 ALAMBRE NEGRO RECOCIDO # 16 KG 6.50 138.36 899.34 899.34


509 ALAMBRE NEGRO RECOCIDO # 8 KG 6.50 27.27 177.26 177.26
510 CLAVOS PARA MADERA C/C 3" KG 6.00 16.21 97.26 97.26
511 CLAVOS PARA MADERA C/C 3/4" KG 7.00 0.46 3.22 3.22
512 CLAVOS PARA MADERA C/C 4" KG 6.00 5.78 34.68 34.68
513 CLAVOS Fo No C/C 3/4" KG 6.00 5.88 35.28 35.28
514 VENTANA METALICA INCLUYENDO ACCESORIOS M2 120.00 1.22 146.40 146.40
515 ACERO DE REFUERZO FY=4200 GRADO 60 KG 4.70 2,252.64 10,587.41 10,587.41
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
516 ARENA FINA M3 100.00 2.78 278.00 278.00
517 PIEDRA CHANCADA DE 1/2" M3 105.00 8.18 858.90 858.90
518 PIEDRA CHANCADA DE 3/4" M3 95.00 7.47 709.65 709.65
519 ARENA GRUESA M3 80.00 8.01 640.80 640.80
520 CABLE TW # 14 AWG 2.5 MM2 M 1.20 90.90 109.08 109.08
521 CABLE ELECTRICO 2 X 4.0 MM2 M 1.40 63.00 88.20 88.20
522 CABLE ELECTRICO 3-1X 6 MM2 TW M 1.70 31.50 53.55 53.55
523 REJILLA DE F G 8" X 12" EN CAJA RECEPTORA pza 62.00 1.00 62.00 62.00
524 TABL. ARRANQ-PARAD DIST-CONTROL AUTOMAT. UND 85.00 1.00 85.00 85.00
525 CAJA RECTANG GALV PESADA 4"x2 1/8"x2 1/8 UND 2.00 1.00 2.00 2.00
526 CAJA OCTOGONAL GALV. 4" X 2 1/8 " UND 2.20 1.00 2.20 2.20
527 FLUORES. RECTO ISPE 2X40 W C/EQ + PANT UND 60.00 1.00 60.00 60.00
528 INTERRUPTOR SIMPLE BAKELITA PZA 4.50 1.00 4.50 4.50
529 LADRILLO CORRIENTE 6 x 12 x 24 CM UND 0.75 653.40 490.05 490.05
530 CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.80 201.36 4,792.37 4,792.37
531 BISAGRA CAPUCHINA PLOMA 3 1/2" X 3 1/2" PAR 4.50 4.00 18.00 18.00
532 MANIJA DE BRONCE P/VENTANA FIERRO UND 18.00 1.00 18.00 18.00
533 YESO EN BOLSAS DE 25 KG. BOL 4.00 0.01 0.04 0.04
534 CINTA AISLANTE RLL 3.50 0.10 0.35 0.35
535 CINTA TEFLON UND 1.20 32.50 39.00 39.00
536 OCRE ROJO KG 8.00 0.70 5.60 5.60
537 CORDEL M 1.00 1.27 1.27 1.27
538 IMPERMEAB.MORTERO/CONCRETO CHEMA 1 POLVO KG 18.00 13.60 244.80 244.80
539 HORMIGON M3 80.00 1.45 116.00 116.00
540 LIJA PARA MADERA UND 2.00 0.80 1.60 1.60
541 AGUA M3 0.50 2.75 1.38 1.38
542 MADERA ANDAMIAJE P2 3.20 9.45 30.24 30.24
543 MADERA NACIONAL P/ENCOFRADO-CARP P2 3.20 570.98 1,827.14 1,827.14
544 MADERA TORNILLO P2 4.00 0.26 1.04 1.04
545 PUERTA DE MADERA DE CEDRO UND 250.00 0.76 190.00 190.00
546 ESTACA DE MADERA P2 1.00 0.23 0.23 0.23
547 ROMPE AGUAS DE F G 1" pza 20.00 1.00 20.00 20.00
548 ROMPE AGUAS DE F G 3/4" pza 16.00 1.00 16.00 16.00
549 ROMPE AGUAS DE F G 2" pza 42.00 1.00 42.00 42.00
550 THINER GLN 12.00 0.02 0.24 0.24
551 IMPRIMANTE GLN 12.00 14.01 168.12 168.12
552 PINTURA LATEX GLN 24.00 0.32 7.68 7.68
553 PINTURA ESMALTE SINTETICO GLN 26.00 3.50 91.00 91.00
554 PINTURA LATEX SUPERMATE GLN 24.00 4.79 114.96 114.96
555 PINTURA ANTICORROSIVA GLN 38.00 0.19 7.22 7.22
556 PINTURA ANTICORROSIVA EPOX-USO NAVAL GLN 60.00 0.22 13.20 13.20
557 TAPAPOROS DE MADERA ACABADA C/BARNIZ O LACA GLN 45.00 0.08 3.60 3.60
558 BARNIZ MARINO GLN 42.00 0.08 3.36 3.36
559 BRIDA ROMPE AGUAS UND 36.00 2.00 72.00 72.00
560 TEKNOPOR DE 1" x 4' x 8' PLN 4.20 6.72 28.22 28.22
561 ABRAZADERA DE 1" DE DIAMETRO UND 12.00 6.00 72.00 72.00
562 TUB. FO.GO. PESADO C-40 1" M 14.00 27.08 379.12 379.12
563 UNION ROSCADA DE FO. GALV. DE 1" UND 16.00 4.22 67.52 67.52
564 TUBO DE IMPULCION Fo. G 3/4" x 6.4m m 28.50 10.61 302.39 302.39
565 CODO DE FG U.R. DE 1"x90 PZA 18.00 4.00 72.00 72.00
566 CODO DE FG U.R. DE 3/4"x90 PZA 16.00 1.00 16.00 16.00
567 CODO F GALV. ISO-I DE 2" X 90 PZA 20.00 2.00 40.00 40.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
568 TEE DE F GALV. ISO-I DE 2" PZA 23.00 2.00 46.00 46.00
569 TEE DE F GALV. DE 1" UND 30.00 1.00 30.00 30.00
570 REDUCTOR DE AIRE DE 1" PZA 44.50 1.00 44.50 44.50
571 UNION ROSCADA DE F G 3/4" UND 6.00 1.65 9.90 9.90
572 TAPON F G CERRADO DE 3/4" PZA 9.00 3.00 27.00 27.00
573 ESCALERA DE GATO SEGUN DISEO m 25.00 8.40 210.00 210.00
574 CANASTILLA DE BRONCE DE 1" UND 14.00 1.00 14.00 14.00
575 CANASTILLA DE SUCCION DE 1" UND 21.00 2.00 42.00 42.00
576 ABRAZADERA DE FP/TUBO DE 2" PZA 20.00 4.00 80.00 80.00
577 ABRAZADERA DE FF DE 3" PZA 32.00 3.00 96.00 96.00
578 TEE FF C/REDUCCION Y ROSCA 3/4" X 3/4" PZA 14.00 3.00 42.00 42.00
579 TUBERIA PVC SAP A-10 DE 1/2" M 2.50 68.25 170.63 170.63
580 ADAPTADOR PVC DE 1/2" PZA 1.50 6.50 9.75 9.75
581 TUBERIA PVC SEL 1" M 1.00 30.90 30.90 30.90
582 SOMBRERO DE VENTILACION F G 2" PZA 12.00 1.00 12.00 12.00
583 TUBO PVC SEL (E/C) 3/4" X 3.00 M. PZA 2.50 19.04 47.60 47.60
584 CURVAS PVC SEL 3/4" PZA 1.00 3.00 3.00 3.00
585 VALVULA COMPUERTA DE BRONCE DE 1" CON UNION ROSCA UND 25.00 1.00 25.00 25.00
586 VALVULA DE BRONCE DE 1/2" UND 6.50 3.90 25.35 25.35
587 VALVULA CHECK DE BRONCE DE 3/4" UND 19.00 2.00 38.00 38.00
588 VALVULA CHECK DE BRONCE DE 1" UND 24.00 1.00 24.00 24.00
589 VALVULA FLOTADORA C/PILOTO DE 11/2" UND 25.00 2.00 50.00 50.00
590 VALVULA COMPUERTA ACERO INOXIDABLE 2" UND 62.00 1.00 62.00 62.00
591 VALVULA COMPUERTA BRONCE 3/4" UNION ROSCADO UND 28.00 3.00 84.00 84.00
592 ENSAYO DE RESISTENCIA DE CONCRETO UND 25.00 4.00 100.00 100.00
593 DISEO DE MEZCLA DE CONCRETO UND 15.00 3.00 45.00 45.00
594 ENSAYO DE DENSIDAD DE CAMPO UND 20.00 2.00 40.00 40.00
595 CHAPA FORTE 3 GOLPES UND 45.00 1.00 45.00 45.00

EQUIPOS

596 ELECTROBOMBA 0.6 HP,HDT=11m , Q=2.2 LTS/Se (Inc. Inst) UND 250.00 2.00 500.00 250.00 250.00
597 ANDAMIO METAL TABLAS-ALQUILER EST 4.00 0.89 3.56 1.78 1.78
598 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 0.38 7.60 3.80 3.80
599 VIBRADOR DE CONCRETO 4 HP 1.35" HM 15.00 10.67 160.05 80.03 80.03
600 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 0.44 11.00 5.50 5.50
601 MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 HM 20.00 10.91 218.20 109.10 109.10
602 TEODOLITO HM 20.00 0.46 9.20 4.60 4.60
603 NIVEL HE 5.00 0.46 2.30 1.15 1.15
604 HERRAMIENTAS MANUALES %MO 434.50 217.25 217.25

FORMULA 07 EQUIPAMIENTO
605 MECHERO DE BUNSEN CHICO UND 10.00 5.00 50.00 50.00
606 MECHERO DE BUNSEN CRANDE UND 15.00 5.00 75.00 75.00
607 MECHEROS DE ALCOHOL UND 5.00 10.00 50.00 50.00
608 TAROLA PROFECIONALES UND 500.00 5.00 2,500.00 2,500.00
609 SOPORTE UNIVERSAL DE BASE CUADRADO DE HIERRO UND 10.00 10.00 100.00 100.00
610 MUEBLES CON FORT DE CUERO jgo 2,300.00 1.00 2,300.00 2,300.00
611 MATRAS ERLEMNEYER DE 300 ML und 20.00 10.00 200.00 200.00
612 VARIABLE COMPLEJA Y APLICACIONES AUTOR CHURCHIL UND 25.00 5.00 125.00 125.00
613 BIBLIA BILINGUE UND 35.00 10.00 350.00 350.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
614 BIOLOGIA SUPERIOR AUTOR MOREY MIGUEL UND 60.00 10.00 600.00 600.00
615 MANUAL ACADEMICO DE HISTORIA DEL PERU EDIT. UND 52.00 30.00 1,560.00 1,560.00
616 MANUAL ACADEMICO DE HISTORIA DE LA HUMANIDAD UND 52.00 30.00 1,560.00 1,560.00
617 MANUAL ACADEMICO DE HISTORIA DE LA PSICOLOGIA UND 48.00 5.00 240.00 240.00
618 MANUAL ACADEMICO DE ECONOMIA UND 45.00 30.00 1,350.00 1,350.00
619 MANUAL ACADEMICO DE LA FILOSOFIA UND 60.00 5.00 300.00 300.00
620 MANUALES DE CRIANZA DE ANIMALES MENORES UND 200.00 15.00 3,000.00 3,000.00
621 GUIA PARA LA FORMULACION DE PROYECTOS DE INVERSION UND 35.00 10.00 350.00 350.00
622 BALAS PARA LANZAMIENTO UND 35.00 5.00 175.00 175.00
623 CONDENSADOR UND 120.00 5.00 600.00 600.00
624 PROYECTOR MULTIMEDIA UND 1,200.00 2.00 2,400.00 2,400.00
625 DATA SHOW UND 4,500.00 1.00 4,500.00 4,500.00
626 PIPETA DE 5ML UND 5.00 10.00 50.00 50.00
627 PIPETA DE 10ML UND 6.00 10.00 60.00 60.00
628 PINZA PARA SOPORTE UNIVERSAL UND 30.00 5.00 150.00 150.00
629 PINZA DE MADERA PARA TUBOS DE PRUEBA UND 5.00 15.00 75.00 75.00
630 DICCIONARIO DE MUSICA und 95.00 15.00 1,425.00 1,425.00
631 DICCIONARIO FILOSOFICO ROSSENTAL und 135.00 5.00 675.00 675.00
632 DICCIONARIO DE PEDAGOGICO und 200.00 30.00 6,000.00 6,000.00
633 DICCIONARIO DE SINONIMOS Y ANTONIMOS und 100.00 30.00 3,000.00 3,000.00
634 VIDEOTECAS und 3,500.00 1.00 3,500.00 3,500.00
635 NET OFICIAL DE NAILON und 200.00 1.00 200.00 200.00
636 TABLERO DE BASQUET DE VIDRIO UND 500.00 2.00 1,000.00 1,000.00
637 PIZARRA FIJA 3.00 X 1.50 UND 300.00 17.00 5,100.00 5,100.00
638 OXFORD STUDY und 100.00 35.00 3,500.00 3,500.00
639 DISCO EPARA LANSAMIENTO UND 50.00 5.00 250.00 250.00
640 CANCIONEROS CATOLICOS UND 3.00 80.00 240.00 240.00
641 MESA UNIPOLARES (TORNILLO) S/ DISEO UND 100.00 418.00 41,800.00 41,800.00
642 FOTOCOPIADORA HP UND 7,000.00 1.00 7,000.00 7,000.00
643 ECONOMIA POLITICA NIKITIN UND 35.00 5.00 175.00 175.00
644 DICCIONARIO GEOGRAFICO E HISTORICO UND 60.00 5.00 300.00 300.00
645 MICROSCOPIOS UND 500.00 10.00 5,000.00 5,000.00
646 INTRODUCCION A LA ELECTROTECNIA AUTOR SOBRE VILLA ALSINA UND 35.00 5.00 175.00 175.00
647 METODOS MUNERICOS AUTOR CHAPRA CANALE UND 40.00 5.00 200.00 200.00
648 MECANICA DE CISTEMAS Y FENOMENOS ONDULATORIOS UND 45.00 5.00 225.00 225.00
649 BALON DE BASE PLANA 250 ML und 25.00 2.00 50.00 50.00
650 BALON DE BASE PLANA 500 ML und 30.00 2.00 60.00 60.00
651 BURETA DE 100 ML UND 30.00 3.00 90.00 90.00
652 LAMINA PARA LOS ALUMNOS und 25.00 10.00 250.00 250.00
653 LAMINA PARA EDUCACION SEXUAL und 10.00 10.00 100.00 100.00
654 VASO PRESIPITADO DE 250ML und 15.00 5.00 75.00 75.00
655 VASO PRESIPITADO DE 300ML und 25.00 5.00 125.00 125.00
656 COMPAS METALICO UND 75.00 24.00 1,800.00 1,800.00
657 REGLAS METALICAS DE 100CM UND 35.00 24.00 840.00 840.00
658 EDICIONES COREFO UND 120.00 25.00 3,000.00 3,000.00
659 VITRL LENGUAJE Y COMUNICACION UND 145.00 25.00 3,625.00 3,625.00
660 DOMINE SU LENGUAJE UND 200.00 25.00 5,000.00 5,000.00
661 LITERATURA UNIVERSAL: CASERES CHAUPIN UND 50.00 25.00 1,250.00 1,250.00
662 LITERATURA PERUANA: TORRO MONTALVO UND 328.00 25.00 8,200.00 8,200.00
663 LITERATURA PERUANA: CASERES CHAUPIN UND 45.00 25.00 1,125.00 1,125.00
664 TRADICIONES PERUANAS DE RICARDO PALMA UND 8.00 35.00 280.00 280.00
665 ENSALLOS POR LUIS LOAYZA UND 60.00 24.00 1,440.00 1,440.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
666 HAY YUNA CHICA EN MI SOPA POR SILVIA UNES DEL ARCO UND 32.00 24.00 768.00 768.00
667 TRAS EL SALTO MORTAL: ANUOR AGUILAR UND 29.00 24.00 696.00 696.00
668 TE RECORDARAS DE MI POR ARMANDO ECHEANDIA UND 29.00 24.00 696.00 696.00
669 NUNCA CONFIES EN MI RENATO CISNEROS UND 45.00 24.00 1,080.00 1,080.00
670 EL MUNDO ES ANCHO Y AGENO: CIRO ALEGRIA UND 32.00 24.00 768.00 768.00
671 IMPRESORA MATRICIAL DE DOS CAVEZALES UND 450.00 1.00 450.00 450.00
672 FISICA GENERAL 2 AUTOR SERWAY und 80.00 10.00 800.00 800.00
673 FISICA TERMICA AUTPR CHALES KITEL und 70.00 10.00 700.00 700.00
674 FISICA CIENCIA Y TEC. ELECTR. MAGNETISMO (TUPLER GENE) und 30.00 10.00 300.00 300.00
675 ATRIO DE MADERA S/DISEO UND 160.00 1.00 160.00 160.00
676 ESCUADRA und 35.00 10.00 350.00 350.00
677 EMBUDO DE VIDRIO DE 60 X 120 UND 5.00 10.00 50.00 50.00
678 ARO PARA SOPORTE UNIVERSAL und 10.00 5.00 50.00 50.00
679 TERMOMETRO DE 0 A 150 CRADOS UND 40.00 10.00 400.00 400.00
680 CURSO EXPERMENTAL EN QUIMICA FISICA AUTOR VV AA UND 50.00 10.00 500.00 500.00
681 LIBRO DE IGLES EDITORIAL NAVARRETE UND 65.00 35.00 2,275.00 2,275.00
682 ESCUADRAS 30, 45 y 60 GRADOS und 40.00 24.00 960.00 960.00
683 TRANSPORTADORES UND 5.00 24.00 120.00 120.00
684 LA VACA POR CAMILO CRUZ UND 6.00 35.00 210.00 210.00
685 CHOLITO EN LOS ANDES MAGICOS UND 6.00 30.00 180.00 180.00
686 LOS DIOSES DE CHAVIN UND 6.00 35.00 210.00 210.00
687 LOA 7 ENSALLOS DE JOSE CARLOS MARIETEGUI UND 6.00 35.00 210.00 210.00
688 EN QUE MOMENTO SE JUDIO EL PERU UND 8.00 35.00 280.00 280.00
689 EL PODER DEL EXITO UND 8.00 35.00 280.00 280.00
690 HORAS DE LUCHA: MANUEL GONZALES PRADA UND 8.00 35.00 280.00 280.00
691 LAPTOP UND 3,800.00 2.00 7,600.00 7,600.00
692 FRANCISCO PULGAR VIDAL (MUSICA) und 20.00 35.00 700.00 700.00
693 JUAN VILLA CORTA (ARTES PLASTICAS) und 10.00 15.00 150.00 150.00
694 ESTEBAN ESCOBEDO ACUA (MUSICA) und 15.00 15.00 225.00 225.00
695 JOSE OBREGON MORAN (DANZA) und 10.00 15.00 150.00 150.00
696 DOMINGO GUZMAN HUAMAN und 10.00 15.00 150.00 150.00
697 CONINILLA ELECTRICA UND 50.00 5.00 250.00 250.00
698 COLCHANETAS PARA EL SALTO DE 1.00 X 2.50 M UND 250.00 6.00 1,500.00 1,500.00
699 COLCHONETAS PZA 30.00 12.00 360.00 360.00
700 COLECCIONES AURELIO BALDOR UND 350.00 30.00 10,500.00 10,500.00
701 CRISOL CHICO UND 5.00 5.00 25.00 25.00
702 VALLA PARA CARRERA DE POSTAS UND 10.00 24.00 240.00 240.00
703 SILLA UNIPOLARES (TORNILLO) S/ DISEO PZA 60.00 418.00 25,080.00 25,080.00
704 SILLA GIRATORIA und 100.00 2.00 200.00 200.00
705 MATERIALES DE RED SWITCH, CABLE RJ 45 und 650.00 2.00 1,300.00 1,300.00
706 JABALINAS PARA LANZAMIENTO und 22.00 5.00 110.00 110.00
707 MATEMATICA ALUMNOS DEL 1ro AL 5to AO POR MANUEL COVEAS und 50.00 50.00 2,500.00 2,500.00
708 MATEMATICA ALUMNOS DEL 1ro AL 5to AO POR EDUARDO ESPINOZA und 65.00 50.00 3,250.00 3,250.00
709 ALGEBRA POR EDUARDO ESPINOZA und 50.00 20.00 1,000.00 1,000.00
710 GEOMETRICS POR EDUARDO ESPINOZA und 60.00 20.00 1,200.00 1,200.00
711 TRIGONOMETRIA POR EDUARDO ESPINOZA und 40.00 20.00 800.00 800.00
712 RAZONAMIENTO MATEMATICO POR HERNAN HERNANDEZ und 50.00 20.00 1,000.00 1,000.00
713 CALCULO POR LARSON HORTETLER und 105.00 20.00 2,100.00 2,100.00
714 CALCULO POR LEITHOLD und 100.00 20.00 2,000.00 2,000.00
715 CALCULO POR WILLIAM GRANVILLE und 95.00 20.00 1,900.00 1,900.00
716 GEOMETRICS POR LEHMAN CHARLES und 120.00 20.00 2,400.00 2,400.00
717 MESA MADERA und 160.00 2.00 320.00 320.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
718 LOCKERS DE ALUMINIO DE H=1.74 M und 1,200.00 7.00 8,400.00 8,400.00
719 ESTANTE DE MATALICOS PZA 500.00 4.00 2,000.00 2,000.00
720 TUBO DE ENSAYO 10 X 100ML und 4.00 10.00 40.00 40.00
721 TUBO DE ENSAYO 16 X 160ML und 8.00 10.00 80.00 80.00
722 SILLAS DE MADERA und 65.00 114.00 7,410.00 7,410.00
723 MUEBLES PARA COMPUTADORA S/ DISEO und 250.00 30.00 7,500.00 7,500.00
724 MALLA DE ASBESTO und 5.00 12.00 60.00 60.00
725 INGENIERO DE PROYECTOS AUTOR FERNANDO SANTOS und 40.00 10.00 400.00 400.00
726 STAND DE ARCHIVOS UND 800.00 5.00 4,000.00 4,000.00
727 MONTERO EN PILON DE 170 ML und 25.00 5.00 125.00 125.00
728 MODULO DE LABORATORIO S/DISEO UND 25,000.00 1.00 25,000.00 25,000.00
729 CAPSULA DE PORCELANA DE 100 ML UND 5.00 5.00 25.00 25.00
730 CAPSULA DE PORCELANA DE 180 ML UND 10.00 5.00 50.00 50.00
731 PROBETA CRADUADA DE 100 ML UND 20.00 10.00 200.00 200.00
732 PROBETA CRADUADA DE 250 ML UND 25.00 12.00 300.00 300.00
733 KIT DE MAQUINARIA DE ESQUELETO HUMANO EN PLASTICO und 850.00 2.00 1,700.00 1,700.00
734 CAPACITACION EN OPERACION Y MANTENIMIENTO GLB 23,000.00 1.00 23,000.00 23,000.00
735 MARTILLO und 30.00 10.00 300.00 300.00
736 TROMPETAS und 800.00 8.00 6,400.00 6,400.00
737 EUFONIAS(BAJO) und 1,200.00 8.00 9,600.00 9,600.00
738 SAXOS und 1,800.00 3.00 5,400.00 5,400.00
739 CLARINETES und 650.00 3.00 1,950.00 1,950.00
740 TROMBOMES und 1,400.00 2.00 2,800.00 2,800.00
741 BOMBO SINFONICO und 3,000.00 2.00 6,000.00 6,000.00
742 TUBAS ACRILICOS und 3,500.00 2.00 7,000.00 7,000.00
743 FLAUTAS TRAVERSAS und 1,600.00 5.00 8,000.00 8,000.00
744 ATRILES und 250.00 8.00 2,000.00 2,000.00
745 SEPILLOS PARA MADERA und 300.00 1.00 300.00 300.00
746 TRIPODE DE TRES PIES und 100.00 10.00 1,000.00 1,000.00
747 PUPITRE UND 700.00 3.00 2,100.00 2,100.00
748 FIOLA DE 100ML und 10.00 5.00 50.00 50.00
749 PASAMANOS und 220.00 7.00 1,540.00 1,540.00
750 CATESISMO ILUSTRADO und 10.00 10.00 100.00 100.00
751 EXTINTORES DE 30KG und 180.00 2.00 360.00 360.00
752 PETRIX DE 80 CM und 5.00 12.00 60.00 60.00
753 GRASIMILLA PARA TUBO DE PRUEBA und 4.00 10.00 40.00 40.00
754 ESCALIMETRO PARA SALTO ALTO und 60.00 2.00 120.00 120.00
755 LUPA DE 8 AUMENTOS und 10.00 10.00 100.00 100.00
756 LUNAS DE RELOJ DE 100MM und 12.00 10.00 120.00 120.00
757 ANILLO O AROS CRANDES UND 6.00 5.00 30.00 30.00
758 REDES ELECTRICAS AUTOR CAUDENCIO SOPETTI UND 38.00 5.00 190.00 190.00
759 AUDIFONOS UND 55.00 35.00 1,925.00 1,925.00
760 IMPRESORA LASER HP CON TONER UND 600.00 4.00 2,400.00 2,400.00
761 EQUIPO COMPLETO DE COMPUTO INTEL CORE DUO UND 3,200.00 30.00 96,000.00 96,000.00
762 EQUIPAMIENTO DE SONIDO (MICROFONO, MEZLADORA y PARLANTES) UND 8,000.00 1.00 8,000.00 8,000.00
0.00
EQUIPOS 0.00

763 GARLOPA und 2,000.00 1.00 2,000.00 2,000.00


764 SIERRA CIRCULAR und 2,500.00 1.00 2,500.00 2,500.00
CRONOGRAMA DE ADQUISICION DE MATERIALES
: MEJORAMIENTO DE LOS SERVICIOS DE EDUCACION SECUNDARIA DE LA INSTITUCION EDUCATIVA "JOSE CARLOS MARIATEGUI DE CCOLLPAPAMPA", DEL
PROYECTO
DISTRITO DE LIRCAY, PROVINCIA DE ANGARAES-HVCA
FECHA : MARZO -2012 DEPART : : Huancavelica
CONSULTOR : ARQ. FRANK FREDDY ZAMUDIO MORALES PROV : : Angaraes
MODALIDAD : ADMINISTRACIN DIRECTA DISTRITO : Lircay
LOCALIDAD : Ccollpapampa

ITEM DECRIPCION UND C.U. CANT. PARCIAL 1er MES 2do MES 3er MES 4to MES 5to MES 6to MES 7mo MES 8vo MES
0.00
FORMULA 08 MITIGACION

MANO DE OBRA
766 OPERARIO HH 14.14 47.70 674.48 674.48
767 OFICIAL HH 12.40 26.60 329.84 329.84
768 PEON HH 11.21 94.40 1,058.22 1,058.22
0.00
MATERIALES 0.00

769 ALAMBRE NEGRO RECOCIDO # 16 KG 6.50 5.23 34.00 34.00


770 ALAMBRE NEGRO RECOCIDO # 8 KG 6.50 6.65 43.23 43.23
771 CLAVOS PARA MADERA C/C 3" KG 6.00 7.26 43.56 43.56
772 ACERO DE REFUERZO FY=4200 GRADO 60 KG 4.70 78.68 369.80 369.80
773 ARENA FINA M3 100.00 0.28 28.00 28.00
774 TIERRA DE CHACRA O VEGETAL M3 10.00 2.03 20.30 20.30
775 GRASS M3 35.00 1.01 35.35 35.35
776 CEMENTO PORTLAND TIPO I (42.5KG) BOL 23.80 92.18 2,193.88 2,193.88
777 YESO EN BOLSAS DE 25 KG. BOL 4.00 0.02 0.08 0.08
778 HORMIGON M3 80.00 7.97 637.60 637.60
779 AGUA M3 1.00 0.64 0.64 0.64
780 MADERA NACIONAL P/ENCOFRADO-CARP P2 3.20 6.53 20.90 20.90
781 ESTACA DE MADERA P2 1.00 0.19 0.19 0.19
782 MADERA TORNILLO INC.CORTE P/ENCOFRADO P2 3.20 79.80 255.36 255.36
783 ARBOLIZACION Y OTROS GLB 25.00 40.00 1,000.00 1,000.00
784 TACHO DE BASURA METALICA und 60.00 6.00 360.00 360.00
785 GRANITO ROJO OSCURO KG 35.00 6.41 224.35 224.35
786 GRANITO NEGRO OSCURO KG 35.00 16.31 570.85 570.85

EQUIPOS

787 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 20.00 0.02 0.40 0.40


788 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 25.00 0.32 8.00 8.00
789 HERRAMIENTAS MANUALES %MO 1 82.7 82.70 82.70

FORMULA 09 FLETE TERRESTRE

FLETE TERRESTRE PABELLON A GLB 37,907.60 1.00 37,907.60 4,738.45 4,738.45 4,738.45 4,738.45 4,738.45 4,738.45 4,738.45 4,738.45
FLETE TERRESTRE PABELLON B GLB 23,332.84 1.00 23,332.84 2,916.61 2,916.61 2,916.61 2,916.61 2,916.61 2,916.61 2,916.61 2,916.61
FLETE TERRESTRE DE SALA DE USOS MULTIPLES GLB 6,667.63 1.00 6,667.63 833.45 833.45 833.45 833.45 833.45 833.45 833.45 833.45
FLETE TERRESTRE DE MURO DE CONTENCION GLB 1,592.44 1.00 1,592.44 199.06 199.06 199.06 199.06 199.06 199.06 199.06 199.06
FLETE TERRESTRE DE TANQUE ELEVADO GLB 1,592.44 1.00 1,592.44 199.06 199.06 199.06 199.06 199.06 199.06 199.06 199.06
FLETE TERRESTRE DE SS-HH GLB 2,262.75 1.00 2,262.75 282.84 282.84 282.84 282.84 282.84 282.84 282.84 282.84
FLETE TERRESTRE DE MITIGACION AMBIENTAL GLB 492.10 1.00 492.10 61.51 61.51 61.51 61.51 61.51 61.51 61.51 61.51
FLETE TERRESTRE DE EQUIPAMIENTO GLB 5,632.31 1.00 5,632.31 704.04 704.04 704.04 704.04 704.04 704.04 704.04 704.04

TOTAL DE COSTO DIRECTO 2,431,153.95 253,027.53 439,963.01 323,105.24 295,768.20 223,600.86 145,951.75 216,822.28 531,116.52

También podría gustarte