MES V
ENERO/FEBRERO 281336.02 FECHA DE INICIO 25-Jan-15
MARZO 713471.04 VALOR REFERENCIAL Oct-14
ABRIL 411873.05
MAYO 273719.89 ADELANTO DIRECTO 1 5%
1680400.00 ADELANTO DIRECTO 2 3%
V-Programado
MES V K
ENERO/FEBRERO 300000.00 1.01
MARZO 680000.00 1.02
ABRIL 480000.00 1.03
MAYO 220400.00 1.04
JUNIO 1.05
1680400.00
MESES
MATERIAL TOTAL
1 2 3 4
CEMENTO 20000 15000 5000 5000 45000
PIEDRA 10000 5000 0 0 15000
60000
FORMULA POLINOMICA
Imo IU = Imr
MATERIAL OCTUBRE ENERO FEBRERO MARZO ABRIL MAYO
CEMENTO 400 440 450 460 470 450
PIEDRA 500 550 560 570 580 500
VR
CEMENTO
Datos
Ci 0.18 MMO= 340281.00
SBV 1680400.00
FR 1.00000 Como es de VR Octubre 2014 se usa
Ima 450 40% de MC =
Imo 400
ADELANTO SOLICITADO
56000.00
PIEDRA
Datos 672160.00
Ci 0.100 MMO= 188204.80
SBV 1680400.00
FR 1.00000
Ima 560
Imo 500
VERIFICACION DE REAJUSTES
PROGRAMADO EJECUTADO
NUMERO MES K
MES ACUM MES ACUM
0 ENERO 0.01
1 FEBRERO 300000.00 300000.00 281336.02 281336.02 0.02
2 MARZO 680000.00 980000.00 713471.04 994807.06 0.03
3 ABRIL 480000.00 1460000.00 411873.05 1406680.11 0.04
4 MAYO 220400.00 1680400.00 273719.89 1680400.00 0.05
EJECUTADO
V-1 POR SEPARADO
LA OBRA COMENZO EL 25 DE ENERO, ENTONCES SE CUENTRA HASTA EL 31 DE ENERO Y SON
EL MES DE FEBRERO TERMINO UN 28 DEFEBRERO Y SON
V-2 713471.04
MARZO
5% 35673.552 3% 21404.1312
Kr 1.03 kr 1.03
Ka 1.005 ka 1.01
D= 887.402 D= 423.844 1311.25
V-3 685592.94
ABRIL
5% 34279.647 3% 20567.7882
Kr 1.04 kr 1.04
Ka 1.005 ka 1.01
D= 1193.819 D= 610.924 1804.74
PIEDRA
1 2 3 4
JUNIO
490
590
Ima/Imo
DELANTO SOLICITADO
> 56000.00
MAYO
Programado Ejecutado
Acumulado Acumulado
1680400.00 1680400.00
RPA 56620.00
REA 56629.10
DIFERENCIA 9.096
DIRECTO
FEBRERO 225068.816
3% 6752.06448
kr 1.02 136.84
ka 1.01
D= 66.8521236
O DIRECTO
ALES
0.180
273719.89
490
450
400
4926.95802
933.33
0.100
273719.89
590
560
500
1642.31934
250.00
ALES
0.180
273719.89
450
400
55428.277725
0.100
273719.89
560
500
30656.62768
134432
8%MC SIN IGV
VR= 2556556.00 INCLUIDO IGV
VR= 2166572.88136 SIN IGV Jul-15
FR= 0.99556
ARQUITECTURA 45% 974957.80
970628.984
DEDUCTIVO VINCULANTE
5% 48531.45 25-Mar-16
MCV 922097.53
EJECUTADO
MES V % K
ENERO 271776.12 28% 1.012 FECHA DE INICIO
FEBRERO 368839.01 38% 1.025 VALOR REFERENCIAL
MARZO 135888.06 14% 1.03
ABRIL 97062.90 10% 1.025 ADELANTO DIRECTO 1
MAYO 48531.45 10% 1.035 ADELANTO DIRECTO 2
JUNIO 1.038
922097.53 AD1
V-Programado AD2
MES V K ADELANTO DIRECTO
ENERO 339720.14 1.01 35%
FEBRERO 320307.56 1.02 33%
MARZO 97062.90 1.03 10%
ABRIL 165006.93 1.04 22%
922097.53
MESES
MATERIAL TOTAL
ENERO FEBRERO MARZO ABRIL
CEMENTO 80000 12000 10000 0 102000
LADRILLO 20000 18500 0 0 38500
CERAMICO 18000 10000 15000 0 43000
183500
FORMULA POLINOMICA
Imo IU = Imr
MATERIAL Jul-15 ENERO FEBRERO MARZO ABRIL
CEMENTO 400 430 450 460 480
LADRILLO 500 540 550 500 530
CERAMICO 600 640 650 660 600
VR
MMO= Ci * SBV * FR
CEMENTO
Datos
Ci 0.18 MMO= 9783.98
SBV 48531.45
FR 0.99556
Ima 450
Imo 400
PIEDRA
Datos
Ci 0.120 MMO= 6377.71
SBV 48531.45
FR 0.99556
Ima 550
Imo 500
VERIFICACION DE REAJUSTES
PROGRAMADO EJECUTADO
NUMERO MES
MES ACUM MES ACUM
1 ENERO 339720.14 339720.14 271776.12 271776.12
2 FEBRERO 320307.56 660027.71 368839.01 640615.13
3 MARZO 97062.90 757090.61 135888.06 776503.19
4 ABRIL 165006.93 922097.53 97062.90 873566.09
5 MAYO 0.00 922097.53 48531.45 922097.53
EJECUTADO
V-1 POR SEPARADO
LA OBRA COMENZO EL 25 DE ENERO, ENTONCES SE CUENTRA HASTA EL 31
EL MES DE FEBRERO TERMINO UN 28 DEFEBRERO Y SON
V173767.8028 * 0.025
V1'
295071.211 * 0.03
368839.014
COMPARAMOS LOS ACUMULADOS PARA VERIFICAR EL 80% DE AVANCE
V-1 271776.12
ENERO
2% 5435.52 8% 21742.09
Kr 1.03 kr 1.03
Ka 1.01 ka 1.03
D= 69.82 D= 0.00
V-2 368839.01
FEBRERO
2% 7376.78 8% 29507.12
Kr 1.03 kr 1.03
Ka 1.01 ka 1.03
D= 131.21 D= 143.94
V-3 135888.06
MARZO
2% 2717.76 8% 10871.04
Kr 1.03 kr 1.03
Ka 1.01 ka 1.03
D= 34.91 D= 0.00
V-4 97062.90
ABRIL
2% 1941.26 8% 7765.03
Kr 1.04 kr 1.04
Ka 1.01 ka 1.03
D= 44.12 D= 75.76
V-5 48531.45
MAYO
2% 970.63 8% 3882.52
Kr 1.04 kr 1.04
Ka 1.01 ka 1.03
D= 24.94 D= 49.24
PIEDRA
AMORTIZACIONES - MATERIALES
1 2 3 4
5-Jan-16 19412.58
6-Feb-16 77650.32
ADELANTO DIRECTO 97062.90
= Imr
MAYO JUNIO
490 500
560 590
690 700
ADELANTO OTORGADO
102000
38500
43000
* Ima/Imo
ADELANTO SOLICITADO
140500.00
MARZO MAYO
RPA 26304.05
REA 26498.17
DIFERENCIA 194.126
20528.80
21256.77
727.97
DELANTO DIRECTO
69.82
275.14
34.91
119.88
74.18
ADELANTO DIRECTO
R MATERIALES
MAYO
Ci 0.180
V 97062.90
Imr 500
Ima 450
Imo 400
D= 2183.91521
D= 2266.67
MAYO
Ci 0.120
V 97062.90
Imr 590
Ima 550
Imo 500
D= 931.80382
D= -3500.00
- MATERIALES
MAYO
Ci 0.180
V 97062.90
Ima 450
Imo 400
D= 19655.2369259
MAYO
Ci 0.120
V 97062.90
Ima 550
Imo 500
D= 12812.3025887
87356.6085594 3882.51593597
8%MC SIN IGV