Cronograma de Obra Nva. Esperanza Ok
Cronograma de Obra Nva. Esperanza Ok
de 31 may '16 07 jun '16 14 jun '16 21 jun '16 28 jun '16 05 jul '16 12 jul '16 19 jul '16 26 jul '16 02 ago '16 09 ago '16 16 ago '16 23 ago '16 30 ago '16 06 sep '16 13 sep '16 20 sep '16 27 sep '16 04 oct '16 11 oct '16 18 oct '16
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X
1 PROYECTO: "MEJORAMIENTO DEL SERVICIO EDUCATIVO POR AMPLIACIN DE COBERTURA DEL NIVEL INICIAL
DISTRITO DE OLMOS, DE LA REGIN LAMBAYEQUE"
EN LA I.E.I N 348 - CASERIO NUEVA ESPERANZA
2 ESTRUCTURAS
4 CONSTRUCCIONES PROVISIONALES
5 OFICINA DE OBRAS
6 ALMACEN DE OBRA
7 CASETA DE GUARDIANIA
11 INSTALACIONES PROVISIONALES
14 TRABAJOS PRELIMINARES
17 FLETE TERRESTRE
18 REMOCIONES
19 DESMONTAJE DE PUERTAS
20 DESMONTAJE DE VENTANAS
22 DEMOLICIONES
29 SEGURIDAD Y SALUD
34 MOVIMIENTO DE TIERRAS
51 ZAPATAS
54 VIGA DE CIMENTACION
58 SOBRECIMIENTO REFORZADO
66 COLUMNAS
67 COLUMNETAS-CONCRETO FC=175KG/CM2
68 COLUMNAS-CONCRETO FC=210KG/CM2
69 COLUMNAS-ENCOFRADO Y DESENCOFRADO
70 COLUMNAS-ACERO FY=4200KG/CM2
71 VIGAS
74 VIGAS-ENCOFRADO Y DESENCOFRADO
75 VIGAS-ACERO FY=4200KG/CM2
76 LOSAS ALIGERADAS
81 CISTERNA
83 CISTERNA-ENCOFRADO Y DESENCOFRADO
85 GRADAS
89 TANQUE SEPTICO
93 POZO PERCOLADOR
97 MESA DE CONCRETO
101 VARIOS
104 JUNTAS
109 ARQUITECTURA
Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha lmite Progreso manual
Proyecto: DIAGRAMA GANNT -
Divisin Resumen Tarea inactiva Resumen inactivo solo duracin Resumen manual solo fin Hito externo Progreso
Pgina 1
Id Modo Nombre de tarea
de 31 may '16 07 jun '16 14 jun '16 21 jun '16 28 jun '16 05 jul '16 12 jul '16 19 jul '16 26 jul '16 02 ago '16 09 ago '16 16 ago '16 23 ago '16 30 ago '16 06 sep '16 13 sep '16 20 sep '16 27 sep '16 04 oct '16 11 oct '16 18 oct '16
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X
125 CIELO RASOS
128 CONTRAPISOS
129 CONTRAPISO DE 35 mm
130 PISOS
139 ZOCALOS
141 CONTRAZOCALOS
144 CUBIERTAS
161 CERRAJERIA
166 CERRADURA PTA. BAO SEG, INT. PER. MANIJ. CERRAD. BAO
170 PINTURA
204 ACCESORIOS
215 VALVULAS
Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha lmite Progreso manual
Proyecto: DIAGRAMA GANNT -
Divisin Resumen Tarea inactiva Resumen inactivo solo duracin Resumen manual solo fin Hito externo Progreso
Pgina 2
Id Modo Nombre de tarea
de 31 may '16 07 jun '16 14 jun '16 21 jun '16 28 jun '16 05 jul '16 12 jul '16 19 jul '16 26 jul '16 02 ago '16 09 ago '16 16 ago '16 23 ago '16 30 ago '16 06 sep '16 13 sep '16 20 sep '16 27 sep '16 04 oct '16 11 oct '16 18 oct '16
tarea S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M
253 GRIFERIA SIMPLE PARA DUCHA
259 VARIOS
277 SALIDAS
326 VARIOS
344 EQUIPAMIENTO
Tarea Hito Resumen del proyecto Hito inactivo Tarea manual Informe de resumen manual solo el comienzo Tareas externas Fecha lmite Progreso manual
Proyecto: DIAGRAMA GANNT -
Divisin Resumen Tarea inactiva Resumen inactivo solo duracin Resumen manual solo fin Hito externo Progreso
Pgina 3