Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Cronograma Valorizado Fin
Cronograma Valorizado Fin
1 01 OBRAS PRELIMINARES
9 02 MOVIMIENTO DE TIERRAS
12 02.03 EXCAV. DESQ. Y PEINADO DE TALUD ROCA SUELTA R=350M3 TRACTOR ORUGA D7
14 02.05 EXCAV. DESQ. Y PEYNADO DE TALUD ROCA DURA R=350M3/DIA TRACTOR ORUGA D7
15 02.06 CONFORMACION DE TERRAPLENES
17 03 PAVIMENTOS
51 04.03 BADENES
61 04.04 CUNETAS
66 05 ESTABILIDAD DE TALUDES
124 06.05.06 PISO DE CEMENTO PULIDO Y BRUADO DE E=15 mm, MECLA 1:4
137 07.02.06 PISO DE CEMENTO PULIDO Y BRUADO DE E=15 mm, MECLA 1:4
184 10 ARQUEOLOGIA
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
Und. Metrado Precio (S/.) Parcial (S/.)
368,758.66
m2 240.00 81.20 19,488.00
GLB 1.00 36,261.59 36,261.59
m2 104,469.75 0.48 50,145.48
KM 54.27 1,380.31 74,909.42
KM 54.27 631.57 34,275.30
und 2.00 3,433.85 6,867.70
GLB 1.00 146,811.17 146,811.17
9,951,572.95
m3 513,291.38 5.07 2,602,387.30
m3 110,751.96 17.40 1,927,084.10
m3 110,571.96 5.69 629,154.45
m3 93,864.28 19.79 1,857,574.10
m3 93,864.28 5.12 480,585.11
m3 10,037.93 5.84 58,621.51
m3 224,570.42 10.67 2,396,166.38
1,653,606.90
m2 271,350.00 1.50 407,025.00
m3 54,270.00 4.13 224,135.10
m3 54,270.00 4.44 240,958.80
m3 54,270.00 1.84 99,856.80
m3 54,270.00 3.56 193,201.20
m2 271,350.00 1.80 488,430.00
910,201.75
318,539.44
m2 1,679.60 2.80 4,702.88
m2 1,679.60 1.67 2,804.93
m3 852.47 39.78 33,911.26
m3 463.38 24.86 11,519.63
m3 602.20 31.25 18,818.75
m3 21.39 254.47 5,443.11
m3 140.74 408.46 57,486.66
m2 1,133.60 41.18 46,681.65
kg 5,252.41 4.91 25,789.33
m2 595.40 20.64 12,289.06
m2 292.50 29.31 8,573.18
m 357.50 253.20 90,519.00
80,238.22
m2 390.29 2.80 1,092.81
m2 390.29 1.67 651.78
m3 249.33 39.78 9,918.35
m3 140.90 24.86 3,502.77
m3 158.30 31.25 4,946.88
m3 4.56 254.47 1,160.38
m3 40.22 408.46 16,428.26
m2 283.92 41.18 11,691.83
kg 1,111.20 4.91 5,455.99
m2 56.52 20.64 1,166.57
m2 56.52 29.31 1,656.60
m 60.00 376.10 22,566.00
244,151.29
m2 1,277.77 2.80 3,577.76
m2 1,277.77 1.67 2,133.88
m3 492.30 39.78 19,583.69
m3 615.37 24.86 15,298.10
m2 397.14 43.58 17,307.36
m3 348.06 254.47 88,570.83
m3 189.35 408.46 77,341.90
kg 3,893.67 4.91 19,117.92
m 233.24 5.23 1,219.85
267,272.80
m 38,802.10 2.82 109,421.92
m 8,372.26 7.12 59,610.49
m 7,095.64 9.54 67,692.41
m 447.00 68.34 30,547.98
598,991.42
243,179.02
m2 350.00 1.67 584.50
m3 590.80 39.78 23,502.02
m3 177.24 31.25 5,538.75
m3 496.27 24.86 12,337.27
m3 630.00 251.71 158,577.30
m2 840.00 43.58 36,607.20
m2 728.50 8.28 6,031.98
241,549.59
m2 694.80 1.67 1,160.32
m3 890.44 19.89 17,710.85
m3 1,113.05 183.03 203,721.54
m3 445.22 31.25 13,913.13
m 189.33 26.64 5,043.75
114,262.81
m2 115.20 1.67 192.38
m3 581.76 5.07 2,949.52
m3 23.04 19.89 458.27
m3 340.20 5.84 1,986.77
m2 115.20 49.61 5,715.07
m3 120.24 408.46 49,113.23
kg 6,345.84 4.91 31,158.07
m2 324.00 53.31 17,272.44
m2 324.00 9.94 3,220.56
m2 26.72 10.42 278.42
m 72.00 26.64 1,918.08
676,274.90
51,109.43
m2 1,704.00 2.80 4,771.20
m2 1,704.00 2.11 3,595.44
m2 1,704.00 2.85 4,856.40
m3 190.47 198.91 37,886.39
71,355.54
m3 1,296.99 17.40 22,567.63
m2 681.21 19.89 13,549.27
m2 246.18 35.55 8,751.70
m3 399.50 31.25 12,484.38
m3 1,312.33 10.67 14,002.56
223,686.28
m2 246.18 45.24 11,137.18
m2 832.59 53.31 44,385.37
m3 420.94 293.14 123,394.35
kg 2,387.16 4.91 11,720.96
m3 57.44 408.46 23,461.94
m2 832.59 9.94 8,275.94
m3 3.89 336.90 1,310.54
199,934.53
m 48.00 1,419.04 68,113.92
kg 14,069.79 4.91 69,082.67
m3 138.31 408.46 56,494.10
m 48.00 130.08 6,243.84
130,189.12
m 610.00 101.12 61,683.20
m 91.00 340.39 30,975.49
pza 10.00 1,357.24 13,572.40
m 610.00 22.92 13,981.20
m 70.20 26.64 1,870.13
m2 140.14 46.69 6,543.14
m2 40.04 39.05 1,563.56
42,137.32
4,656.00
m2 600.00 2.80 1,680.00
m2 600.00 2.11 1,266.00
m2 600.00 2.85 1,710.00
37,481.32
m 208.70 101.12 21,103.74
m 18.20 340.39 6,195.10
pza 2.00 1,357.24 2,714.48
m 208.70 22.92 4,783.40
m 13.00 26.64 346.32
m2 43.34 46.69 2,023.54
m2 8.06 39.05 314.74
280,435.83
27,625.66
m2 33.00 2.80 92.40
m2 33.00 1.67 55.11
m3 12.62 39.78 502.02
m3 4.46 31.25 139.38
m3 5.57 24.86 138.47
m2 14.85 45.24 671.81
m3 7.43 293.14 2,178.03
und 33.00 722.68 23,848.44
112,263.36
m2 238.00 2.80 666.40
m2 238.00 1.67 397.46
m3 91.04 39.78 3,621.57
m3 32.13 31.25 1,004.06
m3 40.16 24.86 998.38
m2 107.10 45.24 4,845.20
m3 53.55 293.14 15,697.65
und 238.00 357.28 85,032.64
38,020.15
m2 46.20 2.80 129.36
m2 46.20 1.67 77.15
m3 17.42 39.78 692.97
m3 1.58 31.25 49.38
m3 1.98 24.86 49.22
m2 15.84 45.24 716.60
m3 19.01 293.14 5,572.59
m2 52.80 43.58 2,301.02
kg 333.52 4.91 1,637.58
m2 47.52 20.64 980.81
m2 47.52 29.31 1,392.81
und 22.00 1,110.03 24,420.66
91,730.71
m2 495.00 2.80 1,386.00
m2 495.00 1.67 826.65
m3 32.74 39.78 1,302.40
m3 9.35 31.25 292.19
m3 11.69 24.86 290.61
m2 46.77 45.24 2,115.87
m3 23.39 293.14 6,856.54
m 495.00 158.91 78,660.45
10,795.95
und 55.00 196.29 10,795.95
336,576.27
GLB 1.00 336,576.27 336,576.27
40,255.00
GLB 1.00 40,255.00 40,255.00
CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA
PROYECTO : MEJORAMIENTO DE LA CARRETERA DEPARTAMENTAL HV-109, ABRA ACOPALCA WARI TRANCAPAMPA YANANYA SAN MARCO DE ROCCHAC MATIBAMBA EMP. HV- 101 (NUEVA ESPERANZA) EN LA PROVINCIA DE TAYACAJA HUANCAVELICA.
FECHA : SETIEMBE 2016
PRESUPUESTO AO 2016 AO 2017
ITEM PARTIDAS Und S/. 14-30 SET 01-31 OCT 01-30 NOV 01-31 DIC 01-31 ENE 01-28 FEB 01-31 MAR 01-30 ABR 01-31 MAY 01-30 JUN 01-31 JUL 01-31 AGO 01-13 SET
01 OBRAS PRELIMINARES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01 CAMPAMENTO PROVISIONAL DE OBRA m2 19,488.00 S/. 19,488.00 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.02 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPO PESADO GLB 36,261.59 S/. 18,130.80 (50%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 18,130.80 (50%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.03 DESBROCE Y DESFORESTACION m2 50,145.48 S/. 11,123.76 (22.18%) S/. 26,783.42 (53.41%) S/. 12,238.30 (24.41%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.04 TRAZO NIVELACION Y REPLANTEO CARRETERA SIERRA KM 74,909.42 S/. 12,492.07 (16.68%) S/. 27,794.84 (37.1%) S/. 26,898.23 (35.91%) S/. 7,724.28 (10.31%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.05 CONTROL TOPOGRAFICO KM 34,275.30 S/. 5,494.46 (16.03%) S/. 15,662.35 (45.7%) S/. 13,118.49 (38.27%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.06 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 x 2.40M und 6,867.70 S/. 6,867.70 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.07 FLETE TERRESTRE DE MATERIALES Y HERRAMIENTAS GLB 146,811.17 S/. 11,293.17 (7.69%) S/. 11,293.17 (7.69%) S/. 11,293.16 (7.69%) S/. 11,293.16 (7.69%) S/. 11,293.16 (7.69%) S/. 11,293.16 (7.69%) S/. 11,293.17 (7.69%) S/. 11,293.17 (7.69%) S/. 11,293.17 (7.69%) S/. 11,293.17 (7.69%) S/. 11,293.17 (7.69%) S/. 11,293.17 (7.69%) S/. 11,293.17 (7.69%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.01 CORTE DE MATERIAL SUELTO RENDIMIENTO=570 M3/DIA m3 2,602,387.30 0.00 S/. 190,170.60 (7.31%) S/. 210,698.23 (8.1%) S/. 254,259.52 (9.77%) S/. 254,259.52 (9.77%) S/. 93,854.90 (3.61%) S/. 86,522.55 (3.32%) S/. 293,680.91 (11.29%) S/. 318,923.37 (12.26%) S/. 298,639.91 (11.48%) S/. 303,832.19 (11.68%) S/. 297,545.60 (11.43%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.02 CORTE ROCA SUELTA (PERF. Y DISP.) RENDIMIENTO=250 M3/DIA m3 1,927,084.10 0.00 0.00 0.00 S/. 173,647.29 (9.01%) S/. 220,507.16 (11.44%) S/. 244,108.05 (12.67%) S/. 320,017.80 (16.61%) S/. 261,544.33 (13.57%) S/. 270,262.48 (14.02%) S/. 261,544.33 (13.57%) S/. 175,452.66 (9.1%) 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.03 EXCAV. DESQ. Y PEINADO DE TALUD ROCA SUELTA R=350M3 TRACTOR ORUGA D7 m3 629,154.45 0.00 0.00 0.00 0.00 0.00 S/. 63,230.10 (10.05%) S/. 123,472.95 (19.63%) S/. 119,489.96 (18.99%) S/. 123,472.95 (19.63%) S/. 119,489.96 (18.99%) S/. 79,998.53 (12.72%) 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.04 CORTE ROCA FIJA (PERF. Y DISP.) RENDIMIENTO=260 M3/DIA m3 1,857,574.10 0.00 0.00 0.00 S/. 215,149.88 (11.58%) S/. 318,947.30 (17.17%) S/. 152,282.57 (8.2%) S/. 454,746.15 (24.48%) S/. 308,658.67 (16.62%) S/. 318,947.29 (17.17%) S/. 88,842.25 (4.78%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.05 EXCAV. DESQ. Y PEYNADO DE TALUD ROCA DURA R=350M3/DIA TRACTOR ORUGA D7 m3 480,585.11 0.00 S/. 63,748.80 (13.26%) S/. 23,931.85 (4.98%) S/. 45,396.23 (9.45%) S/. 45,396.24 (9.45%) S/. 41,003.06 (8.53%) S/. 45,396.24 (9.45%) S/. 43,931.85 (9.14%) S/. 45,396.24 (9.45%) S/. 43,931.85 (9.14%) S/. 45,396.24 (9.45%) S/. 37,056.51 (7.71%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.06 CONFORMACION DE TERRAPLENES m3 58,621.51 0.00 0.00 0.00 0.00 0.00 0.00 S/. 6,616.89 (11.29%) S/. 9,987.76 (17.04%) S/. 10,320.69 (17.61%) S/. 9,987.76 (17.04%) S/. 10,320.69 (17.61%) S/. 10,320.69 (17.61%) S/. 1,067.03 (1.82%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
02.07 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 2,396,166.38 0.00 S/. 14,822.39 (0.62%) S/. 329,387.95 (13.75%) S/. 364,896.46 (15.23%) S/. 33,000.41 (1.38%) S/. 221,347.56 (9.24%) S/. 245,063.37 (10.23%) S/. 237,158.10 (9.9%) S/. 245,063.37 (10.23%) S/. 237,158.10 (9.9%) S/. 245,063.37 (10.23%) S/. 223,205.30 (9.32%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03 PAVIMENTOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.01 PERFILADO Y COMPACTACION SUB RASANTE: REND.=2860 M2/DIA m2 407,025.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 74,408.19 (18.28%) S/. 128,696.77 (31.62%) S/. 132,986.67 (32.67%) S/. 70,933.37 (17.43%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.02 EXTRACCION Y APILAMIENTO DEL MATERIAL PARA AFIRMADO m3 224,135.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 52,885.15 (23.6%) S/. 70,623.39 (31.51%) S/. 72,977.50 (32.56%) S/. 27,649.06 (12.34%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.03 ZARANDEO DEL MATERIAL PARA AFIRMADO m3 240,958.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 44,203.10 (18.34%) S/. 76,852.69 (31.89%) S/. 79,414.45 (32.96%) S/. 40,488.56 (16.8%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.04 CARGUIO DEL MATERIAL PARA AFIRMADO m3 99,856.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 20,393.29 (20.42%) S/. 47,911.48 (47.98%) S/. 31,552.03 (31.6%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.05 TRANSPORTE DEL MATERIAL PARA AFIRMADO m3 193,201.20 0.00 0.00 0.00 0.00 0.00 S/. 25,680.12 (13.29%) S/. 31,409.88 (16.26%) S/. 30,396.66 (15.73%) S/. 31,409.89 (16.26%) S/. 30,396.66 (15.73%) S/. 31,409.89 (16.26%) S/. 12,498.10 (6.47%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
03.06 EXTENDIDO Y COMPACTACION DEL MATERIAL PARA AFIRMADO E=0.15 M. m2 488,430.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 14,379.56 (2.94%) S/. 134,999.40 (27.64%) S/. 139,499.41 (28.56%) S/. 126,243.45 (25.85%) S/. 73,308.18 (15.01%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04 OBRAS DE ARTE Y DRENAJE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01 ALCANTARILLAS DE ALIVIO TMC DE 24" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.01 LIMPIEZA DE TERRENO MANUAL m2 4,702.88 S/. 1,542.80 (32.81%) S/. 3,160.08 (67.19%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.02 TRAZO Y REPLANTEO m2 2,804.93 S/. 2,804.93 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.03 EXCAVACION PARA ESTRUCTURAS (MANUAL) m3 33,911.26 S/. 972.14 (2.87%) S/. 3,082.93 (9.09%) S/. 2,983.48 (8.8%) S/. 3,082.93 (9.09%) S/. 3,082.93 (9.09%) S/. 2,784.58 (8.21%) S/. 3,082.93 (9.09%) S/. 2,983.48 (8.8%) S/. 3,082.93 (9.09%) S/. 2,983.48 (8.8%) S/. 3,082.93 (9.09%) S/. 2,706.52 (7.98%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.04 ELIMINACION DE MATERIAL EXCEDENTE Dmax=30 Mts. m3 11,519.63 S/. 261.24 (2.27%) S/. 1,041.57 (9.04%) S/. 1,007.99 (8.75%) S/. 1,041.59 (9.04%) S/. 1,041.59 (9.04%) S/. 940.79 (8.17%) S/. 1,041.59 (9.04%) S/. 1,007.99 (8.75%) S/. 1,041.59 (9.04%) S/. 1,007.99 (8.75%) S/. 1,041.59 (9.04%) S/. 1,041.59 (9.04%) S/. 2.52 (0.02%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.05 RELLENO CON MATERIAL PROPIO m3 18,818.75 0.00 S/. 1,154.68 (6.14%) S/. 1,747.64 (9.29%) S/. 1,805.87 (9.6%) S/. 1,805.87 (9.6%) S/. 1,631.11 (8.67%) S/. 1,805.87 (9.6%) S/. 1,747.62 (9.29%) S/. 1,805.87 (9.6%) S/. 1,747.62 (9.29%) S/. 1,805.87 (9.6%) S/. 1,760.73 (9.36%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.06 EMBOQUILLADO DE PIEDRA CON MORTERO 1:4 m3 5,443.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 3,013.98 (55.37%) S/. 2,429.13 (44.63%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.07 CONCRETO f'c=210 KG/CM2 m3 57,486.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 57,486.66 (100%) 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.08 ENCOFRADO Y DESENCOFRADO NORMAL - ALCANTARILLAS m2 46,681.65 0.00 0.00 0.00 0.00 0.00 0.00 S/. 16,762.65 (35.91%) S/. 18,527.61 (39.69%) S/. 11,391.39 (24.4%) 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.09 ACERO DE REFUERZO FY=4200 KG/CM2 kg 25,789.33 0.00 0.00 0.00 0.00 S/. 12,962.86 (50.26%) S/. 12,826.47 (49.74%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.10 TARRAJEO EXTERIORES C/MORTERO 1:5 x 1.5 CM. m2 12,289.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,542.95 (20.69%) S/. 9,746.11 (79.31%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.11 PINTURA EN ALCANTARILLAS m2 8,573.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 8,573.18 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.01.12 INSTALACION Y COLOCACION DE ALCANTARILLA TMC D=24" m 90,519.00 0.00 0.00 S/. 30,173.00 (33.33%) S/. 30,173.00 (33.33%) S/. 30,173.00 (33.33%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02 ALCANTARILLAS DE CRUCE TMC DE 36" 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.01 LIMPIEZA DE TERRENO MANUAL m2 1,092.81 S/. 281.89 (25.79%) S/. 810.92 (74.21%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.02 TRAZO Y REPLANTEO m2 651.78 0.00 S/. 651.78 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.03 EXCAVACION PARA ESTRUCTURAS (MANUAL) m3 9,918.35 0.00 S/. 2,398.29 (24.18%) S/. 2,983.56 (30.08%) S/. 3,083.01 (31.08%) S/. 1,453.49 (14.65%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.04 ELIMINACION DE MATERIAL EXCEDENTE Dmax=30 Mts. m3 3,502.77 0.00 S/. 776.81 (22.18%) S/. 1,008.18 (28.78%) S/. 1,041.79 (29.74%) S/. 675.99 (19.3%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.05 RELLENO CON MATERIAL PROPIO m3 4,946.88 0.00 S/. 187.01 (3.78%) S/. 1,780.61 (35.99%) S/. 1,839.97 (37.19%) S/. 1,139.29 (23.03%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.06 EMBOQUILLADO DE PIEDRA CON MORTERO 1:4 m3 1,160.38 0.00 0.00 0.00 0.00 S/. 1,160.38 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.07 CONCRETO f'c=210 KG/CM2 m3 16,428.26 0.00 0.00 0.00 0.00 S/. 16,428.26 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.08 ENCOFRADO Y DESENCOFRADO NORMAL - ALCANTARILLAS m2 11,691.83 0.00 0.00 S/. 4,020.49 (34.39%) S/. 4,769.11 (40.79%) S/. 2,902.23 (24.82%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.09 ACERO DE REFUERZO FY=4200 KG/CM2 kg 5,455.99 0.00 S/. 1,209.92 (22.18%) S/. 4,246.07 (77.82%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.10 TARRAJEO EXTERIORES C/MORTERO 1:5 x 1.5 CM. m2 1,166.57 0.00 0.00 0.00 0.00 S/. 1,166.57 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.11 PINTURA EN ALCANTARILLAS m2 1,656.60 0.00 0.00 0.00 0.00 S/. 1,656.60 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.02.12 INSTALACION Y COLOCACION DE ALCANTARILLA TMC D=36" m 22,566.00 0.00 0.00 S/. 9,031.29 (40.02%) S/. 9,560.81 (42.37%) S/. 3,973.90 (17.61%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03 BADENES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.01 LIMPIEZA DE TERRENO MANUAL m2 3,577.76 0.00 0.00 0.00 0.00 S/. 1,942.90 (54.3%) S/. 1,634.86 (45.7%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.02 TRAZO Y REPLANTEO m2 2,133.88 0.00 0.00 0.00 0.00 0.00 S/. 2,133.88 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.03 EXCAVACION PARA ESTRUCTURAS (MANUAL) m3 19,583.69 0.00 0.00 0.00 0.00 0.00 S/. 1,015.88 (5.19%) S/. 3,082.95 (15.74%) S/. 2,983.50 (15.23%) S/. 3,082.95 (15.74%) S/. 2,983.50 (15.23%) S/. 3,082.95 (15.74%) S/. 3,082.95 (15.74%) S/. 269.01 (1.37%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.04 ELIMINACION DE MATERIAL EXCEDENTE Dmax=30 Mts. m3 15,298.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,813.70 (18.39%) S/. 3,082.69 (20.15%) S/. 2,983.25 (19.5%) S/. 3,082.69 (20.15%) S/. 3,082.69 (20.15%) S/. 253.08 (1.65%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.05 ENCOFRADO Y DESENCOFRADO DE BADEN m2 17,307.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 3,576.26 (20.66%) S/. 4,202.33 (24.28%) S/. 4,342.40 (25.09%) S/. 4,342.40 (25.09%) S/. 843.97 (4.88%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.06 CONCRETO CICLOPEO f'c=175 KG/CM2 + 30% PM m3 88,570.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 9,926.89 (11.21%) S/. 24,518.76 (27.68%) S/. 25,336.06 (28.61%) S/. 25,336.06 (28.61%) S/. 3,453.06 (3.9%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.07 CONCRETO f'c=210 KG/CM2 m3 77,341.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 14,688.55 (18.99%) S/. 62,653.35 (81.01%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.08 ACERO DE REFUERZO FY=4200 KG/CM2 kg 19,117.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,139.24 (11.19%) S/. 16,978.68 (88.81%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.03.09 JUNTA DE DILATACION ASFALTICA DE 1" m 1,219.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,219.85 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04 CUNETAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.01 EXCAVACION EN MATERIAL SUELTO - CUNETA m 109,421.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 30,244.58 (27.64%) S/. 50,760.13 (46.39%) S/. 28,417.21 (25.97%) 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.02 EXCAVACION EN ROCA SUELTA - CUNETA m 59,610.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 42,594.54 (71.45%) S/. 17,015.95 (28.55%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.03 EXCAVACION EN ROCA FIJA - CUNETA m 67,692.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 67,692.41 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
04.04.04 CUNETAS TRIANGULARES REVESTIDAS m 30,547.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 22,864.81 (74.85%) S/. 7,683.17 (25.15%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05 ESTABILIDAD DE TALUDES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01 MUROS DE GAVIONES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.01 TRAZO Y REPLANTEO m2 584.50 0.00 S/. 584.50 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.02 EXCAVACION PARA ESTRUCTURAS (MANUAL) m3 23,502.02 0.00 S/. 2,059.11 (8.76%) S/. 2,983.50 (12.69%) S/. 3,082.95 (13.12%) S/. 3,082.95 (13.12%) S/. 2,784.60 (11.85%) S/. 3,082.95 (13.12%) S/. 2,983.50 (12.69%) S/. 3,082.95 (13.12%) S/. 359.51 (1.53%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.03 RELLENO CON MATERIAL PROPIO m3 5,538.75 0.00 0.00 0.00 0.00 S/. 642.51 (11.6%) S/. 1,094.35 (19.76%) S/. 1,211.60 (21.87%) S/. 1,172.52 (21.17%) S/. 1,211.60 (21.87%) S/. 206.17 (3.72%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.04 ELIMINACION DE MATERIAL EXCEDENTE Dmax=30 Mts. m3 12,337.27 0.00 0.00 0.00 0.00 S/. 455.17 (3.69%) S/. 2,697.30 (21.86%) S/. 2,986.30 (24.21%) S/. 2,889.97 (23.42%) S/. 2,986.30 (24.21%) S/. 322.23 (2.61%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.05 MURO EN GAVION CAJA MALLA TIPO A m3 158,577.30 0.00 0.00 0.00 0.00 0.00 0.00 S/. 36,225.59 (22.84%) S/. 45,162.12 (28.48%) S/. 46,667.52 (29.43%) S/. 30,522.07 (19.25%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.06 ENCOFRADO Y DESENCOFRADO NORMAL m2 36,607.20 0.00 0.00 0.00 0.00 0.00 0.00 S/. 8,279.68 (22.62%) S/. 10,456.18 (28.56%) S/. 10,804.71 (29.52%) S/. 7,066.63 (19.3%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.01.07 GEOTEXTIL MAC TEX MT200 m2 6,031.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 6,031.98 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02 MUROS DE SOSTENIMIENTO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.01 TRAZO Y REPLANTEO m2 1,160.32 0.00 S/. 1,160.32 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.02 EXCAVACION PARA BASE DE MURO DE SOSTENIMIENTO m3 17,710.85 0.00 S/. 1,886.05 (10.65%) S/. 2,983.46 (16.85%) S/. 3,082.91 (17.41%) S/. 3,082.92 (17.41%) S/. 2,784.57 (15.72%) S/. 3,082.92 (17.41%) S/. 808.02 (4.56%) 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.03 CCONCRETO CICLOPEO f'c=140 KG/CM2 + 70% P.M. m3 203,721.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 80,164.08 (39.35%) S/. 113,405.81 (55.67%) S/. 10,151.65 (4.98%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.04 RELLENO CON MATERIAL PROPIO m3 13,913.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 11,911.78 (85.62%) S/. 2,001.35 (14.38%) 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.02.05 DRENAJE EN MUROS CON TUBO PVC 3" m 5,043.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 5,043.75 (100%) 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03 MUROS REFORZADOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.01 TRAZO Y REPLANTEO m2 192.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 192.38 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.02 EXCAVACION PARA ESTRUCTURAS CON EQUIPO m3 2,949.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,949.52 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.03 EXCAVACION PARA BASE DE MURO DE SOSTENIMIENTO m3 458.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 458.27 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.04 RELLENO CON MATERIAL PROPIO CON MAQUINARIA m3 1,986.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,986.77 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.05 SOLADO PARA ESTRUCTURAS E=20cm m2 5,715.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 5,715.07 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.06 CONCRETO f'c=210 KG/CM2 m3 49,113.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 49,113.23 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.07 ACERO DE REFUERZO FY=4200 KG/CM2 kg 31,158.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,712.54 (8.71%) S/. 28,445.53 (91.29%) 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.08 ENCOFRADO CON PANELES m2 17,272.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 3,773.95 (21.85%) S/. 13,498.49 (78.15%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.09 DESENCOFRADO DE PANELES m2 3,220.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 3,220.56 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.10 JUNTA DE CONSTRUCCION CON TEKNOPORT m2 278.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 278.42 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
05.03.11 DRENAJE EN MUROS CON TUBO PVC 3" m 1,918.08 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,381.39 (72.02%) S/. 536.69 (27.98%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06 PONTONES (10 UNID) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PRESUPUESTO AO 2016 AO 2017
ITEM PARTIDAS Und
S/. 14-30 SET 01-31 OCT 01-30 NOV 01-31 DIC 01-31 ENE 01-28 FEB 01-31 MAR 01-30 ABR 01-31 MAY 01-30 JUN 01-31 JUL 01-31 AGO 01-13 SET
06.01 OBRAS PRELIMINARES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.01 LIMPIEZA DE TERRENO m2 4,771.20 S/. 546.00 (11.44%) S/. 3,472.00 (72.77%) S/. 753.20 (15.79%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 3,595.44 0.00 0.00 S/. 3,595.44 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.03 TRAZO Y REPLANTEO DURANTE EL PROCESO DE EJECUCION m2 4,856.40 0.00 0.00 S/. 4,856.40 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.01.04 DEMOLICION DE ESTRUCTURA EXISTENTE m3 37,886.39 0.00 0.00 S/. 18,694.53 (49.34%) S/. 19,191.86 (50.66%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.01 CORTE DE MATERIAL CONGLOMERADO m3 22,567.63 0.00 0.00 0.00 S/. 22,567.63 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.02 PERFILADO DE TALUDES m2 13,549.27 0.00 0.00 0.00 S/. 3,626.00 (26.76%) S/. 9,923.27 (73.24%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.03 ADECUACION DE FONDOS m2 8,751.70 0.00 0.00 0.00 0.00 S/. 3,229.22 (36.9%) S/. 5,522.48 (63.1%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.04 RELLENO CON MATERIAL PROPIO m3 12,484.38 0.00 0.00 0.00 0.00 0.00 S/. 7,719.34 (61.83%) S/. 4,765.04 (38.17%) 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.02.05 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 14,002.56 0.00 0.00 0.00 0.00 0.00 0.00 S/. 14,002.56 (100%) 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03 SUBESTRUCTURA DE PONTON 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.01 SOLADO PARA ESTRUCTURAS E=15cm m2 11,137.18 0.00 0.00 0.00 0.00 0.00 0.00 S/. 11,137.18 (100%) 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.02 ENCOFRADO CON PANELES m2 44,385.37 0.00 0.00 0.00 0.00 0.00 0.00 S/. 12,517.60 (28.2%) S/. 23,957.73 (53.98%) S/. 7,910.04 (17.82%) 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.03 CONCRETO CICLOPEO f'c=175 KG/CM2 + 30% PM m3 123,394.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 123,394.35 (100%) 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.04 ACERO DE REFUERZO FY=4200 KG/CM2 kg 11,720.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 10,851.84 (92.58%) S/. 869.12 (7.42%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.05 CONCRETO f'c=210 KG/CM2 m3 23,461.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 23,461.94 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.06 DESENCOFRADO DE PANELES m2 8,275.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 8,275.94 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.03.07 DADOS DE CONCRETO SIMPLE m3 1,310.54 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,310.54 (100%) 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.04 SUPERESTRUCTURA DE PONTON 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.04.01 FALSO PUENTE PARA SUPERESTRUCTURA m 68,113.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 68,113.92 (100%) 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.04.02 ACERO DE REFUERZO FY=4200 KG/CM2 kg 69,082.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 23,775.58 (34.42%) S/. 33,484.80 (48.47%) S/. 11,822.29 (17.11%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.04.03 CONCRETO f'c=210 KG/CM2 m3 56,494.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 56,494.10 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.04.04 DESENCOFRADO DE FALSO PUENTE m 6,243.84 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 6,243.84 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05 OTROS (APOYOS DE LOSA Y ESTRIBOS) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05.01 BARANDA METALICA DE FG D=3" m 61,683.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 17,608.76 (28.55%) S/. 31,319.37 (50.77%) S/. 12,755.07 (20.68%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05.02 JUNTA DE DILATACION DE ACERO PREFABRICADO m 30,975.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 25,315.62 (81.73%) S/. 5,659.87 (18.27%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05.03 ADQUISICION Y COLOCACION DE PLANCHAS DE NEOPRENO pza 13,572.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 13,572.40 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05.04 PINTURA EN BARANDA METALICA m 13,981.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 11,371.30 (81.33%) S/. 2,609.90 (18.67%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05.05 DRENAJE EN TABLERO CON TUBO PVC 3" m 1,870.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,870.13 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05.06 PISO DE CEMENTO PULIDO Y BRUADO DE E=15 mm, MECLA 1:4 m2 6,543.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 5,793.28 (88.54%) S/. 749.86 (11.46%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
06.05.07 PINTURA EN CONCRETO m2 1,563.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,563.56 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07 PUENTES (02 UNIDADES) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01 OBRAS PRELIMINARES 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.01 LIMPIEZA DE TERRENO m2 1,680.00 0.00 S/. 1,680.00 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.02 TRAZO Y REPLANTEO PRELIMINAR m2 1,266.00 0.00 S/. 1,266.00 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.01.03 TRAZO Y REPLANTEO DURANTE EL PROCESO DE EJECUCION m2 1,710.00 0.00 S/. 1,710.00 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02 OTROS (APOYOS DE LOSA Y ESTRIBOS) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.01 BARANDA METALICA DE FG D=3" m 21,103.74 0.00 S/. 8,420.89 (39.9%) S/. 12,682.85 (60.1%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.02 JUNTA DE DILATACION DE ACERO PREFABRICADO m 6,195.10 0.00 0.00 S/. 6,195.10 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.03 ADQUISICION Y COLOCACION DE PLANCHAS DE NEOPRENO pza 2,714.48 0.00 0.00 S/. 2,714.48 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.04 PINTURA EN BARANDA METALICA m 4,783.40 0.00 0.00 S/. 4,783.40 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.05 DRENAJE EN TABLERO CON TUBO PVC 3" m 346.32 0.00 0.00 S/. 346.32 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.06 PISO DE CEMENTO PULIDO Y BRUADO DE E=15 mm, MECLA 1:4 m2 2,023.54 0.00 0.00 S/. 2,023.54 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
07.02.07 PINTURA EN CONCRETO m2 314.74 0.00 0.00 S/. 314.74 (100%) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08 SEALIZACION Y SEGURIDAD VIAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01 SEALIZACION REGLAMENTARIA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.01 LIMPIEZA DE TERRENO MANUAL m2 92.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 92.40 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.02 TRAZO Y REPLANTEO m2 55.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 55.11 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.03 EXCAVACION PARA ESTRUCTURAS (MANUAL) m3 502.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 502.02 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.04 RELLENO CON MATERIAL PROPIO m3 139.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 139.38 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.05 ELIMINACION DE MATERIAL EXCEDENTE Dmax=30 Mts. m3 138.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 138.47 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.06 SOLADO PARA ESTRUCTURAS E=10cm m2 671.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 671.81 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.07 CONCRETO CICLOPEO f'c=175 KG/CM2 + 30% PM m3 2,178.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,178.03 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.01.08 SEAL REGLAMENTARIA und 23,848.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 23,848.44 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02 SEALIZACION PREVENTIVA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.01 LIMPIEZA DE TERRENO MANUAL m2 666.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 666.40 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.02 TRAZO Y REPLANTEO m2 397.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 397.46 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.03 EXCAVACION PARA ESTRUCTURAS (MANUAL) m3 3,621.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,795.73 (77.2%) S/. 825.84 (22.8%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.04 RELLENO CON MATERIAL PROPIO m3 1,004.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,004.06 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.05 ELIMINACION DE MATERIAL EXCEDENTE Dmax=30 Mts. m3 998.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 998.38 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.06 SOLADO PARA ESTRUCTURAS E=10cm m2 4,845.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 4,845.20 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.07 CONCRETO CICLOPEO f'c=175 KG/CM2 + 30% PM m3 15,697.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 15,697.65 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.02.08 SEAL PREVENTIVA und 85,032.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 85,032.64 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03 SEALIZACION INFORMATIVA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.01 LIMPIEZA DE TERRENO MANUAL m2 129.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 129.36 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.02 TRAZO Y REPLANTEO m2 77.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 77.15 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.03 EXCAVACION PARA ESTRUCTURAS (MANUAL) m3 692.97 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 692.97 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.04 RELLENO CON MATERIAL PROPIO m3 49.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 49.38 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.05 ELIMINACION DE MATERIAL EXCEDENTE Dmax=30 Mts. m3 49.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 49.22 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.06 SOLADO PARA ESTRUCTURAS E=10cm m2 716.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 716.60 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.07 CONCRETO CICLOPEO f'c=175 KG/CM2 + 30% PM m3 5,572.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,055.59 (36.89%) S/. 3,517.00 (63.11%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.08 ENCOFRADO Y DESENCOFRADO NORMAL m2 2,301.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,301.02 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.09 ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,637.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,637.58 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.10 TARRAJEO EXTERIORES C/MORTERO 1:5 x 1.5 CM. m2 980.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 980.81 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.11 PINTURA EN EXTERIORES m2 1,392.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,392.81 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.03.12 SEAL INFORMATIVA und 24,420.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 24,420.66 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04 GUARDAVIAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.01 LIMPIEZA DE TERRENO MANUAL m2 1,386.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 1,386.00 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.02 TRAZO Y REPLANTEO m2 826.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 826.65 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.03 EXCAVACION PARA ESTRUCTURAS (MANUAL) m3 1,302.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 446.89 (34.31%) S/. 855.51 (65.69%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.04 RELLENO CON MATERIAL PROPIO m3 292.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 292.19 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.05 ELIMINACION DE MATERIAL EXCEDENTE Dmax=30 Mts. m3 290.61 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 290.61 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.06 SOLADO PARA ESTRUCTURAS E=10cm m2 2,115.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 2,115.87 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.07 CONCRETO CICLOPEO f'c=175 KG/CM2 + 30% PM m3 6,856.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 6,856.54 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.04.08 GUARDAVIAS INC. PERNOS Y TERMINALES m 78,660.45 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 78,660.45 (100%) 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.05 POSTES KILOMETRICOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
08.05.01 HITOS KILOMETRICOS und 10,795.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 S/. 10,795.95 (100%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09 MITIGACION AMBIENTAL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
09.01 PLAN DE MANEJO AMBIENTAL GLB 336,576.27 0.00 S/. 28,048.03 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%) S/. 28,048.02 (8.33%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 ARQUEOLOGIA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10.01 MONITOREO ARQUEOLOGICO GLB 40,255.00 0.00 S/. 3,354.59 (8.33%) S/. 3,354.59 (8.33%) S/. 3,354.59 (8.33%) S/. 3,354.59 (8.33%) S/. 3,354.58 (8.33%) S/. 3,354.58 (8.33%) S/. 3,354.58 (8.33%) S/. 3,354.58 (8.33%) S/. 3,354.58 (8.33%) S/. 3,354.58 (8.33%) S/. 3,354.58 (8.33%) S/. 3,354.58 (8.33%)
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
COSTO DIRECTO 14,858,811.00 91,298.96 418,391.05 780,878.09 1,211,718.86 1,016,788.30 929,772.33 1,480,319.54 1,545,202.03 2,056,775.72 2,007,586.81 1,610,103.23 1,343,759.27 366,216.80
GASTOS GENERALES (6.24 %CD) 927,189.81 5,697.05 26,107.60 48,726.79 75,611.26 63,447.59 58,017.79 92,371.94 96,420.61 128,342.81 125,273.42 100,470.44 83,850.58 22,851.93
UTILIDAD (6 %CD) 891,528.66 5,477.94 25,103.46 46,852.69 72,703.13 61,007.30 55,786.34 88,819.17 92,712.12 123,406.54 120,455.21 96,606.19 80,625.56 21,973.01
SUB TOTAL 16,677,529.46 102,473.95 469,602.11 876,457.57 1,360,033.25 1,141,243.19 1,043,576.46 1,661,510.65 1,734,334.76 2,308,525.07 2,253,315.44 1,807,179.87 1,508,235.41 411,041.73
IGV (18% ST) 3,001,955.30 18,445.31 84,528.38 157,762.36 244,805.98 205,423.77 187,843.76 299,071.92 312,180.26 415,534.51 405,596.78 325,292.38 271,482.37 73,987.51
COSTO DE OBRA 19,679,484.77 120,919.26 554,130.50 1,034,219.93 1,604,839.23 1,346,666.97 1,231,420.22 1,960,582.57 2,046,515.02 2,724,059.58 2,658,912.22 2,132,472.24 1,779,717.78 485,029.25
AVANCE MENSUAL (%) 100.00% 0.61% 2.82% 5.26% 8.15% 6.84% 6.26% 9.96% 10.40% 13.84% 13.51% 10.84% 9.04% 2.46%
AVANCE ACUMULADO (%) 100.00% 0.61% 3.43% 8.69% 16.84% 23.68% 29.94% 39.90% 50.30% 64.14% 77.66% 88.49% 97.54% 100.00%