Dosificacion de Concretos y Morteros

También podría gustarte

Está en la página 1de 8

TABLAS DE CONCRETOS NORMAL Y RESISTENCIA

-COSTO Y TIEMPO EN LAS OBRAS- ING. CARLOS SUAREZ SALAZAR 3ERA EDICION DE 2002

AGREGADO CEMENTO AREANA GRAVA


CLASIFICACION
MAXIMO TON M3 M3

F'c REVENIMIENTO
100 KG/CM2 8 A 10 CM. 3/4" 0.26 0.5 0.68
1 1/2" 0.254 0.47 0.7
12 A 15 CM. 3/4" 0.286 0.5 0.68
1 1/2" 0.28 0.47 0.7

150 KG/CM2 8 A 10 CM. 3/4" 0.323 0.48 0.67


1 1/2" 0.308 0.45 0.7
12 A 15 CM. 3/4" 0.354 0.48 0.67
1 1/2" 0.338 0.45 0.7

200 KG/CM2 8 A 10 CM. 3/4" 0.355 0.47 0.65


1 1/2" 0.337 0.44 0.68
12 A 15 CM. 3/4" 0.391 0.47 0.65
1 1/2" 0.373 0.44 0.68

250 KG/CM2 8 A 10 CM. 3/4" 0.423 0.465 0.64


1 1/2" 0.4 0.435 0.67
12 A 15 CM. 3/4" 0.467 0.465 0.64
1 1/2" 0.445 0.435 0.67
TENCIA

EDICION DE 2002

AGUA M3

0.195
0.19
0.215
0.21

0.21
0.2
0.23
0.22

0.195
0.185
0.215
0.205

0.19
0.18
0.21
0.2
DOSIFICAION Y PROPORCIONAMIENTO PARA FABRICAION DE CONCRETO
MANUAL TECNICO DE CONSTRUCCION APASCO

TAM= 19 MM
CEMENTO
CONCRETO ARENA BOTE GRAVA BOTE AGUA BOTE
BULTO

100 KG/CM2 1 7.5 8 3

150 KG/CM2 1 5.5 6.5 2.5

200 KG/CM2 1 4 6 2

250 KG/CM2 1 3.5 5 1.75

300 KG/CM2 1 2.5 4.5 1.25

1 BOTE= 19 LITROS
1 BULTO= 50KG

TAM= 40 MM

CEMENTO
CONCRETO ARENA BOTE GRAVA BOTE AGUA BOTE
BULTO

100 KG/CM2 1 7.5 9.5 3

150 KG/CM2 1 5.5 8.5 2.5

200 KG/CM2 1 4 7.5 2

250 KG/CM2 1 3.5 6.5 1.75

300 KG/CM2 1 2.5 5.5 1.25

1 BOTE= 19 LITROS
1 BULTO= 50KG
DE CONCRETO DOSIFICAION Y PROPORCIONAMIENTO PARA FABRICAION DE
MANUAL TECNICO DE CONSTRUCCION APASCO

PROPORCIONAMIENTO PARA 1 M3 DE CONCRETO TAM= 19 MM


TAM= 19 MM
CEMENTO ARENA GRAVA AGUA
CONCRETO CONCRETO
BULTO BOTE BOTE BOTE

100 KG/CM2 1 7.5 8 3 100 KG/CM2

150 KG/CM2 1 5.5 6.5 2.5 150 KG/CM2

200 KG/CM2 1 4 6 2 200 KG/CM2

250 KG/CM2 1 3.5 5 1.75 250 KG/CM2

300 KG/CM2 1 2.5 4.5 1.25 300 KG/CM2

1 BOTE= 19 LITROS
1 BULTO= 50KG 1 BOTE= 19 LITROS
1 BULTO= 50KG

TAM= 40 MM

CEMENTO ARENA AGUA


CONCRETO GRAVA M3 CONCRETO
BULTO M3 M3

100 KG/CM2 2.84495 0.40541 0.43243 0.16216 100 KG/CM2

150 KG/CM2 3.62976 0.37931 0.44828 0.17241 150 KG/CM2

200 KG/CM2 4.38596 0.33333 0.5 0.16667 200 KG/CM2

250 KG/CM2 5.13479 0.34146 0.4878 0.17073 250 KG/CM2

300 KG/CM2 6.37959 0.30303 0.54545 0.15152 300 KG/CM2

1 BOTE= 19 LITROS
1 BULTO= 50KG
ARA FABRICAION DE CONCRETO DOSIFICAION Y PROPORCIONAMIENTO PA
RUCCION APASCO MANUAL TECNICO DE CONSTR

E CONCRETO TAM= 19 MM PROPORCIONAMIENTO PARA 1 M3 DE

CEMENTO ARENA GRAVA AGUA DE CEMENTO ARENA GRAVA AGUA


CONCRETO
BULTO M3 M3 M3 M3 BULTO BOTE BOTE BOTE

1 0.1425 0.152 0.057 0.352 100 KG/CM2 1 7.5 9.5 3

1 0.1045 0.1235 0.0475 0.276 150 KG/CM2 1 5.5 8.5 2.5

1 0.076 0.114 0.038 0.228 200 KG/CM2 1 4 7.5 2

1 0.0665 0.095 0.0333 0.195 250 KG/CM2 1 3.5 6.5 1.75

1 0.0475 0.0855 0.0238 0.157 300 KG/CM2 1 2.5 5.5 1.25

1 BOTE= 19 LIT
1 BULTO= 50K

CEMENTO ARENA GRAVA AGUA CEMENTO ARENA GRAVA AGUA


CONCRETO
TON M3 M3 M3 BULTO M3 M3 M3

0.14225 0.40541 0.43243 0.1622 100 KG/CM2 2.63158 0.375 0.475 0.15

0.18149 0.37931 0.44828 0.1724 150 KG/CM2 3.18979 0.33333 0.5152 0.15152

0.2193 0.33333 0.5 0.1667 200 KG/CM2 3.89864 0.2963 0.5556 0.14815

0.25674 0.34146 0.4878 0.1707 250 KG/CM2 4.47928 0.29787 0.5532 0.14894

0.31898 0.30303 0.54545 0.1515 300 KG/CM2 5.6899 0.27027 0.5946 0.13514
RCIONAMIENTO PARA FABRICAION DE CONCRETO
UAL TECNICO DE CONSTRUCCION APASCO

NAMIENTO PARA 1 M3 DE CONCRETO TAM= 40MM

CEMENTO ARENA GRAVA AGUA


CONCRETO DE M3
BULTO M3 M3 M3

100 KG/CM2 1 0.1425 0.1805 0.057 0.38

150 KG/CM2 1 0.1045 0.1615 0.0475 0.314

200 KG/CM2 1 0.076 0.1425 0.038 0.257

250 KG/CM2 1 0.0665 0.1235 0.03325 0.223

300 KG/CM2 1 0.0475 0.1045 0.02375 0.176

1 BOTE= 19 LITROS
1 BULTO= 50KG

CEMENTO ARENA GRAVA AGUA


CONCRETO
TON M3 M3 M3

100 KG/CM2 0.13158 0.375 0.475 0.15

150 KG/CM2 0.15949 0.3333 0.5152 0.15152

200 KG/CM2 0.19493 0.2963 0.5556 0.14815

250 KG/CM2 0.22396 0.2979 0.5532 0.14894

300 KG/CM2 0.2845 0.2703 0.5946 0.13514


DOSIFICACION PARA MORTEROS PARA FABRICAR 1 M3 DE MEZCLA

MORTERO: MORTERO MAESTRO-ARENA


DOSIFICACION MORTERO (TON) ARENA (M3)
1A4 0.3 1.15
1A5 0.26 1.2
1A6 0.225 1.24

MORTERO: CEMENTO-ARENA
DOSIFICACION CEMENTO (TON) ARENA (M3)
1A2 0.6 1
1A3 0.51 1.05
1A4 0.43 1.1
1A5 0.36 1.15
1A6 0.3 1.17
AR 1 M3 DE MEZCLA

RO-ARENA
AGUA (M3)
0.29
0.285
0.28

RENA
AGUA (M3)
0.275
0.272
0.266
0.261
0.257