Planilla de Metrados
Planilla de Metrados
DESCRIP. Ancho (m) Long. (m) Alto (m) # VECES PARC. (m3)
Cimientos Corridos
Ejes A, C : Tramos 1-2, 6-7 0.50 2.28 1.25 4 5.69
Ejes A, C : Tramos 2-6 0.50 2.73 1.25 10 17.03
Ejes 1, 7 : Tramos A-C 0.60 1.88 1.25 4 5.63
Ejes 3, 5 : Tramos A-C 0.65 1.88 1.25 4 6.11
Zapatas
Z (1-A), Z (7-A) 1.15 1.15 1.33 2 3.50
Z (1-B), Z (7-B) 1.15 1.15 1.33 2 3.50
Z (1-C), Z (7-C) 1.15 1.15 1.33 2 3.50
Z (2-A), Z (4-A), Z (6-A) 1.15 1.15 1.33 3 5.26
Z (2-C), Z (4-C), Z (6-C) 1.15 1.15 1.33 3 5.26
Z (3-A), Z (5-A) 1.15 1.15 1.33 2 3.50
Z (3-B), Z (5-B), Z (6-B) 1.15 1.15 1.33 3 5.26
Z (3-C), Z (5-C) 1.15 1.15 1.33 2 3.50
TOTAL (m3) 67.75
N Modulos 1.00
TOTAL (m3) 67.75
DESCRIP. Ancho (m) Long. (m) Alto (m) # VECES PARC. (m3)
Cimientos Corridos
Ejes A, C : Tramos 1-2, 6-7 0.30 2.28 0.65 4 1.77
Ejes A, C : Tramos 2-6 0.30 2.73 0.65 10 5.31
Ejes 1, 7 : Tramos A-C 0.35 1.88 0.65 4 1.71
Ejes 3, 5 : Tramos A-C 0.35 1.88 0.65 4 1.71
Zapatas
Z (1-A), Z (7-A) 0.90 1.15 0.65 2 1.35
Z (1-B), Z (7-B) 0.90 1.15 0.65 2 1.35
Z (1-C), Z (7-C) 0.90 1.15 0.65 2 1.35
Z (2-A), Z (4-A), Z (6-A) 0.90 1.15 0.65 3 2.02
Z (2-C), Z (4-C), Z (6-C) 0.90 1.15 0.65 3 2.02
Z (3-A), Z (5-A) 0.90 1.15 0.65 2 1.35
Z (3-B), Z (5-B), Z(6-B) 0.90 1.15 0.65 3 2.02
Z (3-C), Z (5-C) 0.90 1.15 0.65 2 1.35
Total (m3) 23.29
N Modulos 2.00
TOTAL (m3) 46.58
TOTAL 26.47
03.05.00 CONCRETO EN FALSO PISO MEZCLA 1:8 CEMENTO - HORMIGON E=4" 133.50 m2
Descripcin Ancho (m) Long. (m) # VECES PARC. (m2)
DIRECCION Y SALA REUN 6.00 7.25 1.00 43.50
AULAS 6.00 7.50 2.00 90.00
TOTAL (m2) 133.50
N Modulos 1.00
TOTAL (m2) 133.50
03.06.00 CANALETA DE CONCRETO F'c=175 Kg/cm2 - EVACUACION AGUAS DE LLUVIA INC. ENCOF. 45.30 ml
Descripcin Long. (m) # VECES PARC. (ml)
Canaleta Ext. Modulo 27.50 1.00 27.50
8.90 2.00 17.80
DESCRIP. (Pulg) Long. (m) # Elem. # Piezas/Elem. Peso Kg/ml PARC. (Kg)
ACERO TRANSVERSAL 1/2"
Z (1-A), Z (7-A) 1/2 1.100 2 7 1.00 15.40
Z (1-B), Z (7-B) 1/2 0.900 2 6 1.00 10.80
Z (1-C), Z (7-C) 1/2 1.100 2 7 1.00 15.40
Z (2-A), Z (4-A), Z (6-A) 1/2 1.200 3 8 1.00 28.80
Z (2-C), Z (4-C), Z (6-C) 1/2 1.200 3 8 1.00 28.80
Z (3-A), Z (5-A) 1/2 1.100 2 8 1.00 17.60
Z (3-B), Z (5-B) Z (6-B) 1/2 1.000 3 7 1.00 21.00
Z (3-C), Z (5-C) 1/2 1.100 2 8 1.00 17.60
ACERO LONGITUDINAL 1/2"
Z (1-A), Z (7-A) 1/2 1.100 2 7 1.00 15.40
Z (1-B), Z (7-B) 1/2 0.900 2 6 1.00 10.80
Z (1-C), Z (7-C) 1/2 1.100 2 7 1.00 15.40
Z (2-A), Z (4-A), Z (6-A) 1/2 1.200 3 8 1.00 28.80
Z (2-C), Z (4-C), Z (6-C) 1/2 1.200 3 8 1.00 28.80
Z (3-A), Z (5-A) 1/2 1.200 2 7 1.00 16.80
Z (3-B), Z (5-B), Z (6-B) 1/2 1.000 3 7 1.00 21.00
Z (3-C), Z (5-C) 1/2 1.200 2 7 1.00 16.80
TOTAL (Kg) 309.20
N Modulos 1.00
TOTAL (Kg) 309.20
04.01.03 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACION 52.51 m2
DESCRIP. # Caras Long. (m) Alto (m) # VECES PARC. (m2)
Ejes A, C : Tramos 1-2, 6-7 2.00 3.22 0.40 4 10.30
Ejes A, C : Tramos 2-6 2.00 3.22 0.40 8 20.61
Ejes 1, 7 : Tramos A-C 2.00 2.58 0.40 4 8.26
Ejes 3, 6 : Tramos A-C 2.00 2.78 0.40 6 13.34
Total (m2) 52.51
N Modulos 1.00
TOTAL (m2) 52.51
DESCRIP. (Pulg) Long. (m) # Elem. # Piezas Peso Kg/ml PARC. (Kg)
ACERO LONGITUDINAL
Ejes A, C 5/8 24.00 2 4 1.58 303.36
Traslapes 5/8 0.60 2 4 1.58 7.58
Ejes 1, 3, 5, 7 5/8 6.80 4 4 1.58 171.90
ESTRIBOS 0.25 0.00
Ejes A, C 1/4 1.30 12 22 0.25 85.80
Ejes 1, 3, 5, 7 1/4 1.30 8 18 0.25 46.80
TOTAL (Kg) 615.45
N Modulos 1.00
TOTAL (Kg) 615.45
05.02.00 COLUMNAS
05.02.01 CONCRETO EN COLUMNAS F'c = 210 Kg/cm2 19.58 m3
1) MODULO AULAS
DESCRIP. b (m) t (m) ALTO (m) # Veces PARC. (m3)
C1 0.24 0.25 7.68 5 2.30
C2 0.24 0.64 6.93 4 4.26
C3 0.24 0.66 6.93 4 4.39
C4 0.24 0.80 6.93 6 7.98
Ca 0.15 0.15 1.35 12 0.36
Ca 0.15 0.15 1.05 12 0.28
TOTAL (m3) 19.58
N Modulos 1.00
TOTAL (m3) 19.58
06.01.02 MURO DE SOGA LADRILLO KK DE ARCILLA CON C:A 1:5 x 1.5cm. 91.53
DESCRIP. Long. (m) Alto (m) # VECES PARC. (m2)
Eje A, Tramos 1-2, 3-4, 5-6 2.00 1.05 6 12.60
Eje A, Tramos 2-3, 4-5, 5-6 3.22 1.05 6 20.29
Eje C: Tramos 1-2, 2-3, ...(Tip.) 3.22 1.35 12 52.16
02 Parapetos para librero/aula 0.40 1.35 12 6.48
TOTAL (m2) 91.53
N Modulos 1.00
TOTAL (m2) 91.53
06.03.00 CIELORRASOS
06.03.01 CIELORRASOS CON SUPERBOARD e=6mm. 613.64
DESCRIP. PARC. (m2) TOTAL (m2)
MODULO AULAS DIR Y SALA DE REUN 248.88 248.88
VEREDA POSTERIOR 14.57 14.57
VEREDAs LATERALES 9.66 9.66
VEREDA FRONTIS 33.71 33.71
TOTAL (m2) 306.82
N Modulos 2.00
TOTAL (m2) 613.64
06.04.00 PISOS Y PAVIMENTOS
06.04.01 VEREDA DE CONCRETO F'c = 140 Kg/cm2 e = 4" 76.35
DESCRIPC. Ancho (m) Long. (m) # VECES PARC. (m2)
VEREDAS AULAS DIR Y SALA DE REUN 1.50 26.80 1.00 40.20
0.60 32.80 1.00 19.68
2.70 3.05 2.00 16.47
TOTAL (m2) 76.35
N Modulos 1.00
TOTAL (ml) 76.35
07.06.00 CUBIERTAS
07.06.01 LARGUERO DE MADERA EUCALIPTO 6"x3" PARA ARMAZON DE TECHO 269.50
Descripcin Ancho (m) Long. (m) # VECES PARC. (m2)
LARGUERO 6"X3" 24.50 11.00 269.50
Total (m2) 269.50
N Modulos 1.00
TOTAL (m2) 269.50
07.06.02 TABLA CANTONERA MADERA EUCALIPTO 6"x1" PARA LARGUEROS EN TECHO 19.32
Descripcin Ancho (m) Long. (m) # VECES PARC. (m2)
TABLA 6"x1" 4.83 4.00 19.32
Total (m2) 19.32
N Modulos 1.00
TOTAL (m2) 19.32
07.06.06 TUBERIA BAJADA PVC-SAL C-5 3" EVAC. P/LLUVIAL TOTAL (ML) 22.70 22.70
N Modulos 1.00
TOTAL (ml) 22.70
07.08.00 CERRAJERIA
07.08.01 BISAGRA ALUMINIZADA CAPUCHINA 4" x 4" 16.00
# Puertas Cantid / puerta TOTAL (und)
4.00 4.00 16.00
N Modulos 1.00
TOTAL (UND) 16.00
07.10.00 PINTURA
07.10.01 PINTURA LATEX 2 MANOS EN CIELORRASO Y VIGAS 386.29
DESCRIPC. Area (m2) Ancho (m) Alto (m) # VECES PARC. (m2)
CIELORRASO 306.82 1.00 306.82
VIGAS 79.47 1.00 79.47
Total (m2) 386.29
N Modulos 1.00
TOTAL (m2) 386.29
08.09.00 ALIM. CABLE THW #14 AWG TUBERIA SAP ELECT. 3/4" 80.00
TOTAL (m) 80.00
N Modulos 1.00
TOTAL (ml) 80.00
08.10.00 ALIM. CABLE THW #12 AWG TUBERIA SAP ELECT. 3/4" 60.00
TOTAL (m) 60.00
N Modulos 1.00
TOTAL (ml) 60.00
m2
m2
m2
m2
ml
ml
m2
m2
m2
UND
ml
ml
ml
ml
m2
m2
m2
m2
ml
ml
UND
GLB
UND
UND
UND
UND
UND
P2
UND
m2
m2
m2
m2
m2
Pto
Und
Und
m2
ml
Und
ml
Und
ml
ml
Und
Und
Und
Und
3. PLANILLA DE METRADOS - MOBILIARIO
OBRA: CONSTRUCCION DE C.E PORCON LA ESPERANZA - PROVINCIA DE CAJMARCA- CAJAMARCA
FECHA: Octubre del 2009
01 MOBILIARIO
01.01 CARPETAS BIPERSONALES PARA NIO u 120.00
01.03 PUPITRES DE MADERA PARA DOCENTE u 5.00
01.04 SILLAS DE MADERA PARA DOCENTE u 5.00
BILIARIO
MARCA- CAJAMARCA
05.02.00 REVOQUES, ENLUCIDOS Y MOLDURAS
05.02.01 Tarrajeo (Interior y Exterior) Mezcla 1:5 C:A
Cantidad
Descripcin Long (m) # Veces Alto (m) Parcial (m2)
(m2)
Muros de cabeza 47.54 1.50 71.31
Muros de soga 28.84 2.00 57.68
Total (m2) 128.99
05.02.02 Tarrajeo del tipo rayado o Primario Mortero 1:5 C:A
Descripcin Cantidad Largo (m) # Veces Alto (m) Parcial (m2)
Muros de cabeza 8.00 0.85 1.20 8.16
Muros de cabeza 3.00 1.10 1.20 3.96
Muros de soga 15.00 1.35 1.20 24.30
Muros de soga SS.HH. Profs. 1.00 2.80 1.20 3.36
Total (m2) 39.78
05.02.03 Tarrajeo de Columnas Mezcla 1:5 C:A
Cantidad
Descripcin Largo (m) # Veces Alto (m) Parcial (m2)
(m2)
Del encofrado de columnas 19.82 1.00 19.82
Total (m2) 19.82
05.02.04 Tarrajeo de Vigas - Mezcla 1:5 C:A
Cantidad
Descripcin Largo (m) # Veces Alto (m) Parcial (m2)
(m2)
Del encofrado de vigas 21.38 1.00 21.38
05.03.00 CIELORRASOS
05.03.01 Cielorrasos con Mezcla Cemento-Arena 1:5 C:A
Cantidad
Descripcin Largo (m) # Veces Alto (m) Parcial (m2)
(m2)
Interiores y Exteriores 33.15 1.00 33.15
05.06.00 CUBIERTAS
05.06.01 Cobertura con teja de arcilla maquinada liviana
Descripcin Cantidad Largo (m) Ancho (m) Alto (m) Parcial (m2)
SS.HH. 1.00 9.50 4.50 42.75
Total (m2) 42.75
05.06.02 Cumbrera con teja de arcilla maquinada liviana
Descripcin Cantidad Largo (m) Ancho (m) Alto (m) Parcial (ml)
SS.HH. 1.00 4.50 4.50
Total (ml) 4.50
05.06.03 Tuberia de bajada PVC-SAP C-5 3" p/lluvias
Descripcin Cantidad Largo (m) Ancho (m) Alto (m) Parcial (ml)
Tubera BAP PVC SAP C-5 3" 2.00 3.60 7.20
Total (ml) 7.20
05.06.04 Canaleta de Zinc - evacuacin aguas de lluvia
Descripcin Cantidad Largo (m) Ancho (m) Alto (m) Parcial (ml)
Canaleta metlica en aleros 2.00 4.50 9.00
Total (ml) 9.00
TANQUE SEPTICO Ancho (m) Long. (m) h (m) # Veces PARC. (m3)
Fondo 1.10 2.50 0.15 1 0.41
Muros 0.80 0.15 1.75 2 0.42
Muros 2.50 0.15 1.75 2 1.31
Tapa 1.10 2.20 0.10 1 0.24
Tapa 0.15 0.15 1.10 4 0.10
POZO DE ABSORCION # Elem. Area (m2) h (m) # Veces
Losa 1.00 3.69 0.10 1 0.37
Tapa 1.00 0.97 0.10 1 0.10
Anillo Concreto 1.00 2.78 0.10 1 0.28
Total (m3) 3.23
04.04.04 MURO DE CABEZA LADRILLO ARCILLA FORMA CIRCULAR CON ESPACIOS 1" MORTERO C:A 1:5 X1.5 cm.
POZO DE ABSORCION Long. (m) h (m) # VECES
Area Interior 3.98 2.95 1 11.74
TOTAL (M2) 11.74
05.00.00 ARQUITECTURA
05.01.00 ALBAILERIA
05.01.01 Muro de Cabeza - Ladrillo KK de arcilla
Descripcin Cantidad Long (m) Ancho (m) Alto (m) Parcial (m2)
Ejes G 2.00 3.75 3.25 24.38
Ejes J 2.00 3.75 2.25 16.88
Descuento Puertas -2.00 0.85 2.60 -4.42
Descuento Ventanas -4.00 0.90 0.60 -2.16
Eje 9 1.00 3.30 3.90 12.87
Total (m2) 47.54
05.01.02 Muro de Soga - Ladrillo KK de arcilla
Descripcin Cantidad Largo (m) # Veces Alto (m) Parcial (m2)
Ejes 8, 10 2.00 3.30 2.55 16.83
Descuento Puertas -1.00 0.85 2.60 -2.21
Descuento Ventanas -2.00 0.90 0.60 -1.08
Muros H = 1.80 6.00 1.50 1.70 15.30
Total (m2) 28.84
2. PLANILLA DE METRADOS - MODULO SERVICIOS HIGIENICOS
OBRA: CONSTRUCCION C.E PORCON LA ESPERANZA - PROVINCIA CAJAMARCA - CAJAMARCA
FECHA: Octubre del 2009