Está en la página 1de 151

VALOR REFERENCIAL

OBRA
ENTIDAD
UBICACIN
FECHA

=
=
=
=

ITEM

1.00.00
1.01.00
1.02.00
1.03.00
2.00.00
2.01.00
2.02.00
3.00.00
3.01.00
3.02.00
3.02.00
4.00.00
4.01.00
4.02.00
4.03.00
5.00.00
5.01.01
5.01.02
5.02.01
5.02.02
5.02.03
5.03.01
5.03.02

5.03.03
5.04.01
5.04.02
5.04.03
5.05.01
5.05.02
5.05.03
5.06.01
5.06.02
5.06.03
5.07.01
5.07.02
5.07.03
5.07.04
5.08.01
5.08.02
5.08.03
6.00.00
6.01.00
6.02.00
7.00.00
7.01.00

VALOR REFERENCIAL - ESTRUCTURAS


CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.
GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
PARTIDA

UNIDAD

OBRAS PROVISIONALES
Caseta para Oficinas y Almacen
Cartel de Obra (2.40m x 4.80m)
Agua para la Construccin

m2.
Und.
Global

TRABAJOS PRELIMINARES
Limpieza Manual del Terreno

m2.

Trazo, Nivel y Replanteo

m2.

MOVIMIENTO DE TIERRAS
Excavaciones Manuales Simples

m3.

Relleno Compactado con Material Propio

m3.

Eliminacion de Material Excedente, Distancia Prom. 10 Km.

m3.

OBRAS DE CONCRETO SIMPLE


Cimientos Corridos, Concreto 1:10 + 30% P.G.

m3.

Solado, Concreto 1:12, Espesor 10 cm.

m2.

Falso Piso, Concreto 1:10, Espesor 10 cm.

m2.

OBRAS DE CONCRETO ARMADO


Zapatas, Acero Grado 60 - f`y = 4,200 Kg/cm2.

m3.
kg.

Viga de Cimentacion, Concreto f`c = 210 Kg/cm2.

m3.

Viga de Cimentacion, Encofrado y Desencofrado.


Viga de Cimentacin, Acero Grado 60 - f`y = 4,200 Kg/cm2.

m2.
kg.

Sobrecimientos, Concreto f`c = 175 Kg/cm2.

m3.

Sobrecimientos, Encofrado y Desencofrado.

m2.

Zapatas, Concreto f`c = 210 Kg/cm2.

Sobrecimiento, Acero Grado 60 - f`y = 4,200 Kg/cm2.

kg.

Columnas de Estructurales, Concreto f`c = 210 Kg/cm2.

m3.

Columnas Estructurales, Encofrado y Desencofrado.


Columnas Estructurales, Acero Grado 60 - f`y = 4,200 Kg/cm2.

m2.
kg.

Columnas de Confinamiento, Concreto f`c = 175 Kg/cm2.

m3.

Columnas de Confinamiento, Encofrado y Desencofrado.


Columnas de Confin., Acero Grado 60 - f`y = 4,200 Kg/cm2.

m2.
kg.

Vigas, Concreto f`c = 210 Kg/cm2.

m3.

Vigas, Encofrado y Desencofrado.


Vigas, Acero Grado 60 - f`y = 4,200 Kg/cm2.

m2.
kg.

Losa Aligerada, Concreto f`c = 210 Kg/cm2.

m3.

Losa Aligerada, Encofrado y Desencofrado.


Losa Aligerada, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Ladrillo Hueco h = 0.15 m.

m2.
kg.
und.

Escalera, Concreto f`c = 210 Kg/cm2.

m3.

Escalera, Encofrado y Desencofrado

m2.
kg.

Escalera, Acero Grado 60 - f`y = 4,200 Kg/cm2.


ALBAILERIA
Muros de Cabeza, con Ladrillo Maquinado, Mortero 1:4 (c-a)

m2.

Muros de Soga, con Ladrillo Maquinado, Mortero 1:5 (c-a)

m2.

LIMPIEZA, VARIOS
Limpieza Final de Obra

Global

COSTO DIRECTO DE OBR


GASTO GENERAL ( 10%
UTILIDAD
( 10%
SUB-TOTAL DE OBRA
I. G. V. (18%)

PRESUPUESTO ESTRUC

GASTO GENERAL ( 10%


GASTO GENERAL FIJO ( 3%
GASTO GENERAL VARIABLE

MONTO MAXIMO S/. =


MONTO MINIMO S/. =

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

RUCTURAS

CANTIDAD

PRECIO

PRECIO

PRECIO

UNITARIO

PARCIAL

TOTAL

2,861.23
30.00
1.00
1.00

38.73
1,099.21
600.00

1,162.02
1,099.21
600.00
1,309.63

440.00

1.02

449.68

722.75

1.19

859.95
8,509.78

111.05

30.66

3,404.85

92.49

37.39

3,458.04

80.00

20.59

1,646.89
26,820.82

66.22

199.47

13,207.80

40.76

31.40

1,279.77

349.14

35.33

12,333.25
196,844.30

12.37
491.67

347.79
4.10

4,301.51
2,014.51

1.64

396.18

649.74

13.12
269.92

59.80
4.10

784.55
1,105.93

8.99

364.07

3,274.26

92.18

57.04

5,258.35

523.48

4.10

2,144.84

5.76

464.05

2,672.96

67.20
1,003.32

62.21
4.10

4,180.85
4,110.84

16.03

427.38

6,848.83

228.70
2,498.99

57.26
4.10

13,095.13
10,239.02

34.52

401.95

13,873.73

219.36
4,272.90

75.05
4.10

16,463.80
17,507.19

49.61

419.38

20,805.21

566.96
3,979.20
4,724.00

62.09
4.10
2.27

35,200.08
16,303.81
10,724.52

4.33

444.20

1,922.95

30.16
345.13

64.58
4.10

1,947.61
1,414.08
29,665.18

265.50

83.51

22,172.35

151.20

49.56

7,492.83
981.12

1.00

981.12

981.12

266,992.06
26,699.21
26,699.21
320,390.47
57,670.28

DIRECTO DE OBRA S/. =


GENERAL ( 10% )
S/. =
AD
( 10% )
S/.
=
TAL DE OBRA
S/. =
(18%)
S/. =

PUESTO ESTRUCTURAS

S/.

378,060.76

26,699.21
8,009.76
18,689.45
26,699.21

GENERAL ( 10% )
S/. =
GENERAL FIJO ( 3% )
S/. =
GENERAL VARIABLE ( 7% ) S/. =

O MAXIMO S/. =
O MINIMO S/. =

+ (10%)
- (10%)

415,866.83
340,254.68

RESUMEN DEL C
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
A SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

Adelanto Directo ( = o

<

Adelanto Materiales ( = o

10% Monto Cont.) Sin IGV =

<

Valorizacin N 01 al =
Valorizacin N 02 al =
Valorizacin N 03 al =

20% Monto Cont.) Sin IGV =


31 de mayo de 2015
30 de junio de 2015
29 de julio de 2015

CRONOGRAMA BASE - ESTRUCTURAS


ITEM

DESCRIPCIN

MONTO

1.00.00

OBRAS PROVISIONALES

2,861.23

2.00.00

TRABAJOS PRELIMINARES

1,309.63

3.00.00

MOVIMIENTO DE TIERRAS

8,509.78

4.00.00

OBRAS DE CONCRETO SIMPLE

26,820.82

5.00.00

OBRAS DE CONCRETO ARMADO

196,844.30

6.00.00

ALBAILERIA

29,665.18

7.00.00

LIMPIEZA, VARIOS

981.12

COSTO DIRECTO DE OBRA S/. =


GASTO GENERAL ( 10% )
S/. =
UTILIDAD
( 10% )
S/.
=
SUB-TOTAL DE OBRA
S/. =
I. G. V.

(18%)

S/.

PRESUPUESTO ESTRUCTURAS S/. =

AVANCE DEL MES

266,992.06
26,699.21
26,699.21
320,390.47
57,670.28

378,060.76

AVANCE ACUMULADO =

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

ESUMEN DEL CONTRATO DE OBRA

Valor Referencial =
Valor Referencial =
Monto Contractual =
Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =

(Sin IGV)
(Con IGV)
(Sin IGV)
(Con IGV)

S/. 29,475.92

Pagado el =

4 de mayo de 2015

S/. 58,951.85

Pagado el =

27 de mayo de 2015

GASTO GENERAL ( 10% )


S/. =
GASTO GENERAL FIJO ( 3% )
S/. =
GASTO GENERAL VARIABLE ( 7% ) S/. =

STRUCTURAS
MES 1

MES 2

MES 3

Verficacin

30 Dias

30 Dias

20 Dias

2,461.23

200.00

200.00

2,861.23

1,309.63

0.00

0.00

1,309.63

7,686.33

0.00

823.45

8,509.78

26,820.82

0.00

0.00

26,820.82

66,105.53

109,503.68

21,235.09

196,844.30

16,064.39

13,600.79

0.00

29,665.18

245.28

245.28

490.56

981.12

120,693.21
12,069.32
12,069.32
144,831.85

123,549.75
12,354.98
12,354.98
148,259.70

22,749.10
2,274.91
2,274.91
27,298.92

266,992.06
26,699.21
26,699.21
320,390.47

26,069.73

26,686.75

4,913.81

57,670.28

170,901.58

174,946.45

32,212.73

378,060.76

45.20%
45.20%

46.27%
91.48%

8.52%
100.00%

III IIIII IIIIIIII IIIII


IIIIIIIII IIIII

S/. 320,390.47
S/. 378,060.76
S/. 294,759.23
S/. 347,815.90
0.92000
80
Dias Cal.
11 de mayo de 2015
29 de julio de 2015

S/. 26,699.21
S/. 8,009.76
S/. 18,689.44

CRONOGRAMA REPROGRAMADO - ESTRUCTURAS


Dias Programados =
ITEM

1.00.00

DESCRIPCIN

MONTO

Dias de Trabajo del Mes=


2,861.23
OBRAS PROVISIONALES

2.00.00

TRABAJOS PRELIMINARES

1,309.63

3.00.00

MOVIMIENTO DE TIERRAS

8,509.78

4.00.00

OBRAS DE CONCRETO SIMPLE

26,820.82

5.00.00

OBRAS DE CONCRETO ARMADO

196,844.30

6.00.00

ALBAILERIA

29,665.18

7.00.00

LIMPIEZA, VARIOS

981.12

COSTO DIRECTO DE OBRA S/. =


GASTO GENERAL ( 10% )
S/. =
UTILIDAD
( 10% )
S/.
=
SUB-TOTAL DE OBRA
S/. =
SUB-TOTAL DE OFERTADO
S/. =
I. G. V. (18%)
S/. =

266,992.06
26,699.21
26,699.21
320,390.47
294,759.23
53,056.66

PRESUPUESTO ESTRUCTURAS S/. =

347,815.90

AVANCE DEL MES

AVANCE ACUMULADO =

MADO - ESTRUCTURAS
30

30

20

11-May-15
31-May-15

1-Jun-15
30-Jun-15

1-Jul-15
29-Jul-15

21

30

29

1,722.86

878.37

260.00

2,861.23

916.74

392.89

0.00

1,309.63

5,380.43

2,305.90

823.45

8,509.78

18,774.57

8,046.25

0.00

26,820.82

46,273.87

96,484.23

54,086.20

196,844.30

11,245.07

14,339.87

4,080.24

29,665.18

171.70

245.28

564.14

981.12

Verficacin

80

84,485.24
8,448.52
8,448.52
101,382.29
93,271.71
16,788.91

122,692.79
12,269.28
12,269.28
147,231.34
135,452.84
24,381.51

59,814.03
5,981.40
5,981.40
71,776.83
66,034.69
11,886.24

266,992.06
26,699.21
26,699.21
320,390.47
294,759.23
53,056.66

110,060.62

159,834.35

77,920.93

347,815.90

31.64%
31.64%

45.95%
77.60%

22.40%
100.00%

Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

Monto Maximo =

C.I x % Inc. x Pres. x ( Ima/Imo )

Donde :
C.I. =
% =
Pres. =
Imo =

Coeficiente de Incidencia del Elemento Representativo


Porcentaje de Incidencia del Elemento Representativo en el
Monto Contractual (sin IGV)

Ima =

Indice del elemento Representativo a la Fecha del Adelanto

SIMBOLO

Indice del Elemento Representativo a la Fecha Base

ELEMENTO

Indice
Unificado

Mo
I
0.12

Ac
C-Af

Mn-Mqn-D

Mano de Obra

47

Indice gral. de prec. al consum.

39

Acero de construc. corrugado

03

Cemento portland tipo I


Agregado Fino

21
04

Madera nacional p/encofrados


Maquinaria y equipo nacional

43
48
30

Dlar + inflacion de mercado USA

B-Al-Mqi

Bloque y Ladrillo
Acero de construccin liso

17
02
49

Maquinaria y equipo importado

Ag-He-Ho

05
37
38

Agregado Grueso
Herramienta Manual
Hormign

SIMBOLO

SUMATORIA =

ELEMENTO

Indice
Unificado

Ac

Acero de construc. corrugado

03

Cemento portland tipo I

21

Madera nacional p/encofrados

43

Mn

Descripcion

Monto de Adelanto de
Materiales

Adelanto Otorgado

S/. 58,610.00

Monto Contratado Sin IGV :


Monto Maximo de Adelanto de Materiales ( 20 % )

IGV
TOTAL
Otorgado

AMORTIZAC
Acero de construc. corrugado
Insumo =
03
Indice Unificado =
Adelanto Otorgado =

S/. 17,750.00

(Sin I.G.V)

VALORIZACIN
N

Fecha

1
2
3

31-May-15
30-Jun-15
29-Jul-15

MONTO

ADELANTO

VALORIZADO

OTORGADO

117,195.80
93,247.11
84,316.32

17,750.00
17,750.00
17,750.00

294,759.24

Insumo =

Cemento portland tipo I

Indice Unificado =

21

Adelanto Otorgado =

S/. 16,810.00

VALORIZACIN

MONTO

ADELANTO

VALORIZADO

OTORGADO

117,195.80
93,247.11
84,316.32

16,810.00
16,810.00
16,810.00

Fecha

1
2
3

31-May-15
30-Jun-15
29-Jul-15

Sin I.G.V.

294,759.24

Insumo =

Madera nacional p/encofrados

Indice Unificado =

43

Adelanto Otorgado =

S/. 24,050.00

VALORIZACIN

MONTO

ADELANTO

VALORIZADO

OTORGADO

117,195.80
93,247.11
84,316.32

24,050.00
24,050.00
24,050.00

1
2
3

Fecha

31-May-15
30-Jun-15
29-Jul-15

Sin I.G.V.

294,759.24

RESUMEN DE LAS AMORTIZACIONES DE MA


Monto de Adelanto para Materiales Otorgado :
Acero de construc. corrugado

S/. 17,750.00

Cemento portland tipo I

S/. 16,810.00

Madera nacional p/encofrados

S/. 24,050.00

VALORIZACIN

ACERO CORR.

CEMENTO

Fecha

( 03 )

( 21 )

1
2
3

31-May-15
30-Jun-15
29-Jul-15

7,057.37
5,615.21
5,077.41

6,683.63
5,317.84
4,808.53

17,750.00

16,810.00

DEDUCCION DE REAJUSTE QUE NO CORRES


POR EL ADELANTO DE MATERIALES
D = A * ((Imr-Ima)/Imo)
Donde:
D

: Deduccin en cada valorizacin bruta reajustada

: Adelanto utilizado en la valorizacin que se reajusta

Imo

: Indice a la fecha del presupuesto base, del elemento representativo dentro de

que se encuentra el material o materiales para los cuales se otorg el adelant


Ima

: Indice del mismo elemento representativo a la fecha efectiva del adelanto

Imr

: Indice del mismo elemento representativo a la fecha del reajuste

Acero de construc. corrugado


03
Indice Unificado =
S/. 17,750.00
Adelanto Otorgado =

Insumo =

VALORIZACIN

Adelanto Utiliz.

(Sin I.G.V)

INDICE

Fecha

1
2
3

31-May-15
30-Jun-15
29-Jul-15

en la Valoriz. (A)

Imo

7,057.37
5,615.21
5,077.41

474.67
474.67
474.67

17,750.00

Insumo =

Cemento portland tipo I

Indice Unificado =
Adelanto Otorgado =

21
S/. 16,810.00

VALORIZACIN

Adelanto Utiliz.

Fecha

1
2
3

31-May-15
30-Jun-15
29-Jul-15

(Sin I.G.V)

INDICE

en la Valoriz. (A)

Imo

6,683.63
5,317.84
4,808.53

460.44
460.44
460.44

16,810.00

Madera nacional p/encofrados


43
Indice Unificado =
S/. 24,050.00
Adelanto Otorgado =

Insumo =

VALORIZACIN
N

1
2
3

Fecha

31-May-15
30-Jun-15
29-Jul-15

(Sin I.G.V)

INDICE

Adelanto Utiliz.
en la Valoriz. (A)

Imo

9,562.24
7,608.22
6,879.54

646.07
646.07
646.07

24,050.00

RESUMEN DE LOA DEDUCTIVOS DE MATE

Monto de Adelanto para Materiales Otorgado :


VALORIZACIN

ACERO CORR.

CEMENTO

Fecha

( 03 )

( 21 )

1
2
3

31-May-15
30-Jun-15
29-Jul-15

0.00
-89.79
-92.42

0.00
85.00
65.58

-182.21

150.59

ADELANTO PARA MATERIALES


CALCULO DEL MONTO MAXIMO A SOLITAR
Valor Referencial =
Valor Referencial =
Monto Contractual =
Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =
Area Geografica =
Monto Mx. a Solicitar (A.M.) =
Monto Mx. a Solicitar (A.M.) =

x ( Ima/Imo )

Adelanto de Materiales Otrogado =

ento Representativo
nto Representativo en el Monomio

o a la Fecha Base

Enero del 2014

a la Fecha del Adelanto


Coefic. de

Imo

Ima

Incidencia

Agrup.

(Enero/14)

(Mayo/15)

0.279

100.00

498.10

523.15

0.171

100.00

393.46

411.50

0.113

100.00

474.67

505.20

0.131

87.79
12.21

460.44
523.06

454.07
520.55

0.163

94.24
5.14
0.61

646.07
339.09
381.51

675.16
354.51
429.32

0.085

71.56
19.62
8.81

578.76
479.33
249.28

583.17
510.43
279.73

0.058

42.78
24.35
32.87

432.50
298.19
428.11

447.27
296.12
416.74

1.000

7193.16865614
MONTO

MONTO A

Precio a la

MAXIMO

Represent.

SOLICITAR

Fecha Actual

35,481.47

30.50%

17,982.92

2.50

33,428.36

28.74%

16,942.35

20.50

47,405.98

40.76%

24,026.57

6.50

116,315.81

100.00%

58,951.85

I.G.V.
( 18 % )
10,549.80

TOTAL
S/. 69,159.80

S/. 294,759.23
S/. 58,951.85
S/. 10,611.33
S/. 69,563.18
69,159.80

AMORTIZACIONES DE ADELANTO ESPECIFICO PARA MATERIALES

INDICES

COEFICIENTES
Coeficiente

Incid. (%)

Imo

Ima

0.113
0.113
0.113

100.00
100.00
100.00

474.67
474.67
474.67

505.20
505.20
505.20

INDICES

COEFICIENTES
Coeficiente

Incid. (%)

Imo

Ima

0.131
0.131
0.131

87.79
87.79
87.79

460.44
460.44
460.44

454.07
454.07
454.07

INDICES

COEFICIENTES
Coeficiente

Incid. (%)

Imo

Ima

0.163
0.163
0.163

94.24
94.24
94.24

646.07
646.07
646.07

675.16
675.16
675.16

ZACIONES DE MATERIALES
S/. 58,610.00

MADERA

AMORTIZACION

( 43 )

(A)

9,562.24
7,608.22
6,879.54

23,303.24
18,541.28
16,765.48

24,050.00

58,610.00

Sin I.G.V.

E QUE NO CORRESPONDE
O DE MATERIALES

representativo dentro del

ales se otorg el adelanto

efectiva del adelanto

del reajuste

INDICES

DEDUCCION

Ima

Imr

(D)

5=1x((4-3)/2)

505.20
505.20
505.20

505.20
497.61
496.56

0.00
-89.79
-92.42
-182.21

INDICES

DEDUCCION

Ima

Imr

(D)

5=1x((4-3)/2)

454.07
454.07
454.07

454.07
461.43
460.35

0.00
85.00
65.58
150.59

INDICES

DEDUCCION

Ima

Imr

(D)

5=1x((4-3)/2)

675.16
675.16
675.16

675.16
679.52
677.84

0.00
51.34
28.54

CTIVOS DE MATERIALES

79.88

S/. 58,610.00
MADERA

DEDUCCION

( 43 )

(D)

0.00
51.34
28.54

0.00
46.56
1.70

79.88

48.26

Sin I.G.V.

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

RA MATERIALES

O MAXIMO A SOLITAR

Referencial =
Referencial =
Contractual =
Contractual =
de Relacin =
Contractual =
del Plazo Contractual =
no del Plazo Contractual =
eografica =
Mx. a Solicitar (A.M.) =
Mx. a Solicitar (A.M.) =

(Sin IGV)
(Con IGV)
(Sin IGV)
(Con IGV)

320,390.47
378,060.76
294,759.23
347,815.90
0.92000
80

Dias Calendario

11 de mayo de 2015
29 de julio de 2015

1
S/. 58,951.85
S/. 69,563.18

to de Materiales Otrogado =

Ima / Imo

S/.
S/.
S/.
S/.

(Sin IGV)
(Con IGV)

27 de mayo de 2015

MONTO

MONTO

MONTO

MAXIMO

SOLICITADO

OTORGADO

1.050

S/. 86,497.49

S/. 0.00

S/. 0.00

1.046

S/. 52,684.00

S/. 0.00

S/. 0.00

1.064

S/. 35,481.47

S/. 35,481.47

S/. 17,750.00

0.986
0.995

S/. 33,428.36
S/. 4,693.52

S/. 33,428.36
S/. 4,693.52

S/. 16,810.00
S/. 0.00

1.045
1.045
1.125

S/. 47,405.98
S/. 2,588.57
S/. 331.70

S/. 47,405.98
S/. 0.00
S/. 0.00

S/. 24,050.00
S/. 0.00
S/. 0.00

1.008
1.065
1.122

S/. 18,087.62
S/. 5,241.86
S/. 2,480.73

S/. 18,087.62
S/. 5,241.86
S/. 0.00

S/. 0.00
S/. 0.00
S/. 0.00

1.034
0.993
0.973

S/. 7,498.70
S/. 4,097.98
S/. 5,422.99

S/. 7,498.70
S/. 0.00
S/. 5,422.99

S/. 0.00
S/. 0.00
S/. 0.00

S/. 305,940.98

S/. 157,260.50

S/. 58,610.00

MONTO

% REAL

OTORGADO

OTORGADO

17,750.00

50.03%

16,810.00

50.29%

24,050.00

50.73%

58,610.00

RA MATERIALES

Monto Max. Solicitado

SI CUMPLE

<= 20 % Del Monto Contratado

CES

Adelanto - Fecha

MONTO

Amortiz. Utiliz.

Imr

del Valor Refer.

UTILIZADO

a la Fecha del Adel.

8 = 2 x (5/6)

9=1x3x 4

10 = 9 x (6/5)

505.20
497.61
496.56

16,677.34
16,677.34
16,677.34

6,630.88
5,275.88
4,770.58

7,057.37
5,615.21
5,077.41

16,677.34

17,750.00

Adelanto - Fecha

MONTO

Amortiz. Utiliz.

Imr

del Valor Refer.

UTILIZADO

a la Fecha del Adel.

8 = 2 x (5/6)

9=1x3x 4

10 = 9 x (6/5)

454.07
461.43
460.35

17,045.82
17,045.82
17,045.82

6,777.39
5,392.45
4,875.98

6,683.63
5,317.84
4,808.53

17,045.82

16,810.00

Adelanto - Fecha

MONTO

Amortiz. Utiliz.

Imr

del Valor Refer.

UTILIZADO

a la Fecha del Adel.

8 = 2 x (5/6)

9=1x3x 4

10 = 9 x (6/5)

675.16
679.52
677.84

23,013.78
23,013.78
23,013.78

9,150.24
7,280.41
6,583.13

9,562.24
7,608.22
6,879.54

CES

CES

23,013.78

24,050.00

I.G.V.

TOTAL

( 18% )

OTORGADO

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

S/. 3,195.00

S/. 20,945.00

S/. 3,025.80
S/. 0.00

S/. 19,835.80
S/. 0.00

S/. 4,329.00
S/. 0.00
S/. 0.00

S/. 28,379.00
S/. 0.00
S/. 0.00

S/. 0.00
S/. 0.00
S/. 0.00

S/. 0.00
S/. 0.00
S/. 0.00

S/. 0.00
S/. 0.00
S/. 0.00

S/. 0.00
S/. 0.00
S/. 0.00

S/. 10,549.80

S/. 69,159.80

Amortiz. Acumul.

Saldo Amortiz.

a la Fecha del Adel.

a la Fecha del Adel.

11

12

7,057.37
12,672.59
17,750.00

24,807.37
5,077.41
0.00

Amortiz. Acumul.

Saldo Amortiz.

a la Fecha del Adel.

a la Fecha del Adel.

11

12

6,683.63
12,001.47
16,810.00

10,126.37
4,808.53
0.00

Amortiz. Acumul.

Saldo Amortiz.

a la Fecha del Adel.

a la Fecha del Adel.

11

12

9,562.24
17,170.46
24,050.00

33,612.24
6,879.54
0.00

CALCU
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

Monto Maximo =

Monto Max. Solicitado

<= 10 % Del Monto Contratado

Descripcion

Monto de Adelanto
Directo

Adelanto Solicitado

S/. 29,475.92

Adelanto Otorgado =

29,475.92

(Sin IGV)

CALCULO DE AMORTIZACIN DEL ADELANTO DI


Amortizacin del Adelanto Directo

Amort. = ( % Adel. Direc. Otorg. ) * V

VALORIZACIN

MONTO

Fecha

VALORIZADO (Sin/IGV)

1
2
3

31-May-15
30-Jun-15
29-Jul-15

S/. 117,195.80
S/. 93,247.11
S/. 84,316.32

SUMATORIA

S/. 294,759.23

CALCULO DE DEDUCCIONES DE REAJUSTES


QUE NO CORRESPONDEN POR EL ADELANTO DI
Deduccin de Reajuste que no corresponde por Adelanto en Efectivo:

D = ( V * (A/C) ) * ( (Kr/Ka) - 1)
Donde:
D

: Deduccin de reajuste que no corresponde

: Valorizacin ejecutada sin IGV

: Adelanto Directo Otorgado sin IGV

: Monto del Contrato principal sin IGV

Kr

: Coeficiente de Reajuste de la Valorizacin

Ka

: Coeficiente de Reajuste del mes en que se otorg el Adelanto Directo


4 de mayo de 2015

VALORIZACIN

MONTO

Fecha

VALORIZADO (Sin/IGV)

1
2
3

31-May-15
30-Jun-15
29-Jul-15

S/. 117,195.80
S/. 93,247.11
S/. 84,316.32

SUMATORIA

S/. 294,759.23

ADELANTO DIRECTO
CALCULO DEL MONTO MAXIMO A SOLITAR

SAN MIGUEL - PIURA.

Valor Referencial =
Valor Referencial =
Monto Contractual =
Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =
Area Geografica =
Monto Mx. a Solicitar (A.D.) =
Monto Mx. a Solicitar (A.D.) =

el Monto Contratado
I.G.V.
( 18 % )
5,305.67

TOTAL
S/. 34,781.59

4 de mayo de 2015

TIZACIN DEL ADELANTO DIRECTO

Amort. = ( V * (A/C) )

Otorg. ) * Valoriz.
Amortizacin

Amortiz.

Saldo a

del Adel. Dir.

Acumulada

Amortizar

11,719.58
21,044.29
29,475.92

17,756.34
8,431.63
(0.00)

11,719.58
9,324.71
8,431.63
29,475.92

DEDUCCIONES DE REAJUSTES
NDEN POR EL ADELANTO DIRECTO

to en Efectivo:

ue se otorg el Adelanto Directo

Amortizacin

Kr

Ka

del Adel. Dir.

Valoriz.

Adelanto

Deduccin

1.037
1.039
1.039

1.037
1.037
1.037

S/. 0.00
S/. 13.63
S/. 10.71

11,719.58
9,324.71
8,431.63
29,475.92

S/. 29,475.92

S/. 24.34

III.

(Sin IGV)
(Con IGV)
(Sin IGV)
(Con IGV)

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

S/. 320,390.47
S/. 378,060.76
S/. 294,759.23
S/. 347,815.90
0.92000
80
Dias Calendario
11 de mayo de 2015
29 de julio de 2015

1
S/. 29,475.92
S/. 34,781.59

SI CUMPLE

(Sin IGV)
(Con IGV)

CALCULO DE LOS "K


Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

SIMBOLO

ELEMENTO

Indice
Unificado

Mo
I
Ac
C-Af

Mn-Mqn-D

Mano de Obra

47

Indice gral. de prec. al consum.

39

Acero de construc. corrugado

03

Cemento portland tipo I


Agregado Fino

21
04

Madera nacional p/encofrados


Maquinaria y equipo nacional

43
48
30

Dlar + inflacion de mercado USA

B-Al-Mqi

Bloque y Ladrillo
Acero de construccin liso
Maquinaria y equipo importado

Ag-He-Ho

Agregado Grueso
Herramienta Manual
Hormign

SUMATORIA =

17
02
49
05
37
38

III.

IIIIII IIIII
IIIIIIIII

CALCULO DE LOS "K" - REAJUSTES MENSUALES

GUEL - PIURA.

Valor Referencial =
Valor Referencial =
Monto Contractual =
Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =
Area Geografica =

(Sin IGV)
(Con IGV)
(Sin IGV)
(Con IGV)

Coefic. de

Imo

Incidencia

Agrup.

(Enero/14)

Ima

Ima

0.279

100.00

498.10

523.15

0.293

523.15

0.171

100.00

393.46

411.50

0.179

413.82

0.113

100.00

474.67

505.20

0.120

497.61

0.131

87.79
12.21

460.44
523.06

454.07
520.55

0.129

461.43
520.47

0.163

94.24
5.14
0.61

646.07
339.09
381.51

675.16
354.51
429.32

0.171

679.52
355.41
434.47

0.085

71.56
19.62
8.81

578.76
479.33
249.28

583.17
510.43
279.73

0.087

581.18
503.88
282.51

0.058

42.78
24.35
32.87

432.50
298.19
428.11

447.27
296.12
416.74

0.058

443.68
297.38
414.61

1.000

Apr-15

May-15

1.037
Apr-15

May-15

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

S/.
S/.
S/.
S/.
0.92
80

320,390.47
378,060.76
294,759.23
347,815.90
Dias Calendario

11 de mayo de 2015
29 de julio de 2015

May-15

Jun-15
K

Ima

0.293

523.15

0.293

0.180

415.20

0.180

0.119

496.56

0.118

0.131

460.35
521.08

0.131

0.172

677.84
356.20
438.07

0.171

0.087

580.34
502.54
283.41

0.087

0.058

444.72
299.68
414.95

0.058

1.039
May-15

1.039

Jun-15

RESUMEN DE METRADOS
(Del 01/Jun/15
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =
ITEM

1.00.00
1.01.00
1.02.00
1.03.00
2.00.00
2.01.00
2.02.00
3.00.00
3.01.00
3.02.00
3.02.00
4.00.00
4.01.00
4.02.00
4.03.00
5.00.00
5.01.01
5.01.02
5.02.01

5.02.02
5.02.03
5.03.01
5.03.02
5.03.03
5.04.01
5.04.02
5.04.03
5.05.01
5.05.02
5.05.03
5.06.01
5.06.02
5.06.03
5.07.01
5.07.02
5.07.03
5.07.04
5.08.01
5.08.02
5.08.03
6.00.00
6.01.00
6.02.00
7.00.00
7.01.00

VALORIZACIN DE AVA
(Del 01/Jun/15
Obra
=
Entidad
=
Ubicacin =

Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =
ITEM

1.00.00
1.01.00
1.02.00
1.03.00
2.00.00
2.01.00
2.02.00
3.00.00
3.01.00
3.02.00
3.02.00
4.00.00
4.01.00
4.02.00
4.03.00
5.00.00
5.01.01
5.01.02
5.02.01
5.02.02
5.02.03
5.03.01
5.03.02
5.03.03
5.04.01
5.04.02
5.04.03
5.05.01
5.05.02

5.05.03
5.06.01
5.06.02
5.06.03
5.07.01
5.07.02
5.07.03
5.07.04
5.08.01
5.08.02
5.08.03
6.00.00
6.01.00
6.02.00
7.00.00
7.01.00

Obra
Entidad

=
=

Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =
ITEM

1.00
1.1

2.00
2.1

3.00
3.1
3.2

4.00
4.1
4.1.1

4.2
4.2.1

SON =

RESUMEN DE METRADOS - VALORIZACIN N


(Del 01/Jun/15

al

28/Jun/15)

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya
PARTIDA

METRADOS - Val. 01
UNIDAD

OBRAS PROVISIONALES
Caseta para Oficinas y Almacen
Cartel de Obra (2.40m x 4.80m)
Agua para la Construccin

m2.
Und.
Global

OBRAS PRELIMINARES
Limpieza Manual del Terreno
Trazo, Nivel y Replanteo

m2.
m2.

MOVIMIENTO DE TIERRAS
Excavaciones Manuales Simples
Relleno Compactado con Material Propio
Eliminacion de Material Excedente, Distancia Prom. 10 Km.

m3.
m3.
m3.

OBRAS DE CONCRETO SIMPLE


Cimientos Corridos, Concreto 1:10 + 30% P.G.
Solado, Concreto 1:12, Espesor 10 cm.
Falso Piso, Concreto 1:10, Espesor 10 cm.

m3.
m2.
m2.

OBRAS DE CONCRETO ARMADO


Zapatas, Concreto f`c = 210 Kg/cm2.
Zapatas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Viga de Cimentacion, Concreto f`c = 210 Kg/cm2.

m3.
kg.
m3.

m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
und.
m3.
m2.
kg.

Viga de Cimentacion, Encofrado y Desencofrado.


Viga de Cimentacin, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Sobrecimientos, Concreto f`c = 175 Kg/cm2.
Sobrecimientos, Encofrado y Desencofrado.
Sobrecimiento, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Estructurales, Concreto f`c = 210 Kg/cm2.
Columnas Estructurales, Encofrado y Desencofrado.
Columnas Estructurales, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Confinamiento, Concreto f`c = 175 Kg/cm2.
Columnas de Confinamiento, Encofrado y Desencofrado.
Columnas de Confin., Acero Grado 60 - f`y = 4,200 Kg/cm2.
Vigas, Concreto f`c = 210 Kg/cm2.
Vigas, Encofrado y Desencofrado.
Vigas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Concreto f`c = 210 Kg/cm2.
Losa Aligerada, Encofrado y Desencofrado.
Losa Aligerada, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Ladrillo Hueco h = 0.15 m.
Escalera, Concreto f`c = 210 Kg/cm2.
Escalera, Encofrado y Desencofrado
Escalera, Acero Grado 60 - f`y = 4,200 Kg/cm2.
ALBAILERIA

m2.
m2.

Muros de Cabeza, con Ladrillo Maquinado, Mortero 1:4 (c-a)


Muros de Soga, con Ladrillo Maquinado, Mortero 1:5 (c-a)
LIMPIEZA, VARIOS

Global

Limpieza Final de Obra

VALORIZACIN DE AVANCE DE OBRA - N 0


(Del 01/Jun/15
CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.
GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.

al

28/Jun/15)

ENERO DEL 2,014.


CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya
PARTIDA
UNIDAD

OBRAS PROVISIONALES
Caseta para Oficinas y Almacen
Cartel de Obra (2.40m x 4.80m)
Agua para la Construccin

m2.
Und.
Global

OBRAS PRELIMINARES
Limpieza Manual del Terreno
Trazo, Nivel y Replanteo

m2.
m2.

MOVIMIENTO DE TIERRAS
Excavaciones Manuales Simples
Relleno Compactado con Material Propio
Eliminacion de Material Excedente, Distancia Prom. 10 Km.

m3.
m3.
m3.

OBRAS DE CONCRETO SIMPLE


Cimientos Corridos, Concreto 1:10 + 30% P.G.
Solado, Concreto 1:12, Espesor 10 cm.
Falso Piso, Concreto 1:10, Espesor 10 cm.

m3.
m2.
m2.

OBRAS DE CONCRETO ARMADO


Zapatas, Concreto f`c = 210 Kg/cm2.
Zapatas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Viga de Cimentacion, Concreto f`c = 210 Kg/cm2.
Viga de Cimentacion, Encofrado y Desencofrado.
Viga de Cimentacin, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Sobrecimientos, Concreto f`c = 175 Kg/cm2.
Sobrecimientos, Encofrado y Desencofrado.
Sobrecimiento, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Estructurales, Concreto f`c = 210 Kg/cm2.
Columnas Estructurales, Encofrado y Desencofrado.
Columnas Estructurales, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Confinamiento, Concreto f`c = 175 Kg/cm2.
Columnas de Confinamiento, Encofrado y Desencofrado.

m3.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.

Columnas de Confin., Acero Grado 60 - f`y = 4,200 Kg/cm2.


Vigas, Concreto f`c = 210 Kg/cm2.
Vigas, Encofrado y Desencofrado.
Vigas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Concreto f`c = 210 Kg/cm2.
Losa Aligerada, Encofrado y Desencofrado.
Losa Aligerada, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Ladrillo Hueco h = 0.15 m.
Escalera, Concreto f`c = 210 Kg/cm2.
Escalera, Encofrado y Desencofrado
Escalera, Acero Grado 60 - f`y = 4,200 Kg/cm2.

kg.
m3.
m2.
kg.
m3.
m2.
kg.
und.
m3.
m2.
kg.

ALBAILERIA
Muros de Cabeza, con Ladrillo Maquinado, Mortero 1:4 (c-a)
Muros de Soga, con Ladrillo Maquinado, Mortero 1:5 (c-a)

m2.
m2.

LIMPIEZA, VARIOS
Limpieza Final de Obra

Global

COSTO DIRECTO DE OB
GASTO GENERAL ( 10%
UTILIDAD
( 10%
SUB TOTAL DE OBRA

SUB TOTAL CONTRACT


I. G. V. (18%)

PRESUPUESTO ESTR

RESUMEN DE VA

(Del 01
CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.
GOBIERNO REGIONAL - PIURA.

DISTRITO, PROVINCIA, REGIN - PIURA.


ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya
DESCRIPCION

MONTO
CONTRATADO

VALORIZACION CONTRACTUAL ( V )
Valorizacin Contractual (Sin I.G.V.)
Total Contractual
% de Avance a la Fecha

Err:509
Err:509

REAJUSTE ( R )
Reajuste de Valorizacion Contractual

DEDUCCIONES ( D )
Deduccin Adelanto Directo
Deduccin Adelanto para Materiales

Total de Reajustes
VALORIZACION BRUTA ( VB = V + R)

AMORTIZACIONES ( A )
Adelanto Directo
Monto de Adelanto Directo Otorgado (Sin I.G.V.)

Adelanto Materiales
Monto de Adelanto Materiales Otorgado (Sin I.G.V.)

TOTAL DE AMORTIZACIONES ( A )

S/. 29,475.92
S/. 29,475.92

S/. 69,159.80
S/. 69,159.80
S/. 98,635.72

VALORIZACION NETA ( V.N. = V.B. - A )


RETENCION DE GARANTIA, Fiel Cumplimiento (Rt)

S/. 0.00

VALORIZACION LIQUIDA ( V.L. = V.N. - Rt )


IMPUESTO GENERAL A LAS VENTAS ( I.G.V. )
VALORIZACION LIQUIDA TOTAL

MONTO A CANCELAR AL CONTRATISTA EN LA PRESENTE VALORIZ


QQQQQQQQ

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

ALORIZACIN N 01

28/Jun/15)
Valor Referencial =
Valor Referencial =
Monto Contractual =
Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =

METRADOS - Val. 01

(Sin IGV)
(Con IGV)
(Sin IGV)
(Con IGV)

S/. 320,390.47
S/. 378,060.76
S/. 294,759.23
S/. 347,815.90
0.92000
80
Dias Cal.
11 de mayo de 2015
29 de julio de 2015

RESUMEN DE METRADOS

CANTIDAD

ANTERIOR

EJECUTADO

ACUMULADO

SALDO

30.00
1.00
0.33

0.00
0.00
0.00

30.00
1.00
0.33

30.00
1.00
0.33

0.00
0.00
0.67

440.00
722.75

0.00
0.00

440.00
722.75

440.00
722.75

0.00
0.00

111.05
92.49
0.00

0.00
0.00
0.00

111.05
92.49
0.00

111.05
92.49
0.00

0.00
0.00
80.00

66.22
40.76
349.14

0.00
0.00
0.00

66.22
40.76
349.14

66.22
40.76
349.14

0.00
0.00
0.00

12.37
491.67
1.64

0.00
0.00
0.00

12.37
491.67
1.64

12.37
491.67
1.64

0.00
0.00
0.00

13.12
269.92
8.99
92.18
523.48
1.44
16.80
250.83
4.01
57.18
624.75
0.00
54.84
1,068.23
0.00
141.74
994.80
1,181.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

13.12
269.92
8.99
92.18
523.48
1.44
16.80
250.83
4.01
57.18
624.75
0.00
54.84
1,068.23
0.00
141.74
994.80
1,181.00
0.00
0.00
0.00

13.12
269.92
8.99
92.18
523.48
1.44
16.80
250.83
4.01
57.18
624.75
0.00
54.84
1,068.23
0.00
141.74
994.80
1,181.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
4.32
50.40
752.49
12.02
171.53
1,874.25
34.52
164.52
3,204.68
49.61
425.22
2,984.40
3,543.00
4.33
30.16
345.13

132.75
75.60

0.00
0.00

132.75
75.60

132.75
75.60

132.75
75.60

0.00

0.00

0.00

0.00

1.00

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

DE OBRA - N 01

28/Jun/15)
Valor Referencial =
Valor Referencial =
Monto Contractual =

(Sin IGV)
(Con IGV)
(Sin IGV)

S/. 320,390.47
S/. 378,060.76
S/. 294,759.23

Monto Contractual =
(Con IGV)
Factor de Relacin =
Plazo Contractual =
(Dias Cal.)
Inicio del Plazo Contractual =
Termino del Plazo Contractual =

S/. 347,815.90
0.92000
80
Dias Cal.
1 de junio de 2015
18 de agosto de 2015

ANTERIOR

PRESUPUESTO INICIAL
CANTIDAD

P. UNIT.

P. PARCIAL

P. TOTAL

METRADO

P. PARCIAL

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

2,861.23
30.00
1.00
1.00

38.73
1,099.21
600.00

1,162.02
1,099.21
600.00
1,309.63

440.00
722.75

1.02
1.19

449.68
859.95
8,509.79

111.05
92.49
80.00

30.66
37.39
20.59

3,404.85
3,458.04
1,646.89
26,820.83

66.22
40.76
349.14

199.47
31.40
35.33

13,207.80
1,279.77
12,333.25
196,844.29

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
5.76
67.20
1,003.32
16.03
228.70

347.79
4.10
396.18
59.80
4.10
364.07
57.04
4.10
464.05
62.21
4.10
427.38
57.26

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
2,672.96
4,180.85
4,110.84
6,848.83
13,095.13

2,498.99
34.52
219.36
4,272.90
49.61
566.96
3,979.20
4,724.00
4.33
30.16
345.13

4.10
401.95
75.05
4.10
419.38
62.09
4.10
2.27
444.20
64.58
4.10

10,239.02
13,873.73
16,463.80
17,507.19
20,805.21
35,200.08
16,303.81
10,724.52
1,922.95
1,947.61
1,414.08

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00

0.00

29,665.18
265.50
151.20

83.51
49.56

22,172.35
7,492.83
981.12

1.00

981.12

981.12

S/. =
S/. =
S/.
=
S/. =

266,992.06
26,699.21
26,699.21
320,390.47

0.00
0.00
0.00
0.00

B TOTAL CONTRACTUAL S/. =


V. (18%)
S/. =

294,759.23
53,056.66

0.00
0.00

347,815.90

0.00

STO DIRECTO DE OBRA


STO GENERAL ( 10% )
LIDAD
( 10% )
B TOTAL DE OBRA

ESUPUESTO ESTRUCTURAS

S/.

AVANCE PROGRAMADO =
AVANCE EJECUTADO =

0.00%
0.00%

RESUMEN DE VALORIZACIN N 01 - MAYO 2015


(Del 01/May/15

al

28/May/15)
Amortizacin del Adelanto Directo =
Amortizacin del Adelanto Materiales =

11,719.58
23,439.16

MONTO

VALORIZ. ACUM.

VALORIZACION

VALORIZ. ACUM.

CONTRATADO

ANTERIOR

ACTUAL

ACTUAL

Err:509

S/. 0.00

S/. 117,195.80

S/. 117,195.80

Err:509

S/. 0.00
0.00%

S/. 117,195.80
Err:509

S/. 117,195.80
Err:509

S/. 0.00
S/. 0.00

S/. 4,387.25
S/. 4,387.25

S/. 4,387.25
S/. 4,387.25

S/. 0.00
S/. 0.00
S/. 0.00

S/. 0.00
S/. 0.00
S/. 0.00

S/. 0.00
S/. 0.00
S/. 0.00

S/. 0.00
S/. 0.00

S/. 4,387.25
S/. 121,583.05

S/. 4,387.25
S/. 121,583.05

S/. 29,475.92
S/. 29,475.92

S/. 0.00
S/. 0.00

S/. 11,719.58
S/. 11,719.58

S/. 11,719.58
S/. 11,719.58

S/. 69,159.80
S/. 69,159.80

S/. 0.00
S/. 0.00

S/. 23,439.16
S/. 23,439.16

S/. 23,439.16
S/. 23,439.16

S/. 98,635.72

S/. 0.00

S/. 35,158.74

S/. 35,158.74

S/. 0.00

RESENTE VALORIZACION

S/. 0.00

S/. 86,424.31

S/. 86,424.31

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00
S/. 0.00

S/. 86,424.31
S/. 15,556.38

S/. 86,424.31
S/. 15,556.38

S/. 0.00

S/. 101,980.68

S/. 101,980.68

S/. 101,980.68

ACTUAL

ACUMULADO

SALD

METRADO

P. PARCIAL

METRADO

P. PARCIAL

METRADO

30.00
1.00
0.33

1,162.02
1,099.21
198.00

30.00
1.00
0.33

1,162.02
1,099.21
198.00

100.00%
100.00%
33.00%

0.00
0.00
0.67

440.00
722.75

449.68
859.95

440.00
722.75

449.68
859.95

100.00%
100.00%

0.00
0.00

111.05
92.49
0.00

3,404.85
3,458.04
0.00

111.05
92.49
0.00

3,404.85
3,458.04
0.00

100.00%
100.00%
0.00%

0.00
0.00
80.00

66.22
40.76
349.14

13,207.80
1,279.77
12,333.25

66.22
40.76
349.14

13,207.80
1,279.77
12,333.25

100.00%
100.00%
100.00%

0.00
0.00
0.00

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
1.44
16.80
250.83
4.01
57.18

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
668.24
1,045.21
1,027.71
1,712.21
3,273.78

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
1.44
16.80
250.83
4.01
57.18

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
668.24
1,045.21
1,027.71
1,712.21
3,273.78

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
25.00%
25.00%
25.00%
25.00%
25.00%

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
4.32
50.40
752.49
12.02
171.53

624.75
0.00
54.84
1,068.23
0.00
141.74
994.80
1,181.00
0.00
0.00
0.00

2,559.75
0.00
4,115.95
4,376.80
0.00
8,800.02
4,075.95
2,681.13
0.00
0.00
0.00

624.75
0.00
54.84
1,068.23
0.00
141.74
994.80
1,181.00
0.00
0.00
0.00

2,559.75
0.00
4,115.95
4,376.80
0.00
8,800.02
4,075.95
2,681.13
0.00
0.00
0.00

25.00%
0.00%
25.00%
25.00%
0.00%
25.00%
25.00%
25.00%
0.00%
0.00%
0.00%

1,874.25
34.52
164.52
3,204.68
49.61
425.22
2,984.40
3,543.00
4.33
30.16
345.13

132.75
75.60

11,086.18
3,746.41

132.75
75.60

11,086.18
3,746.41

50.00%
50.00%

132.75
75.60

0.00

0.00

0.00

0.00

0.00%

1.00

106,155.62
10,615.56
10,615.56
127,386.74

106,155.62
10,615.56
10,615.56
127,386.74

117,195.80
21,095.24

117,195.80
21,095.24

138,291.05

138,291.05

31.64%
39.76%

31.64%
39.76%

VALORIZ. ACUM.

SALDO POR

ACTUAL

DE AVANCE

VALORIZAR

S/. 117,195.80

Err:509

Err:509

S/. 117,195.80
Err:509

Err:509
Err:509

S/. 4,387.25
S/. 4,387.25

S/. 0.00
S/. 0.00
S/. 0.00

S/. 4,387.25
S/. 121,583.05

S/. 11,719.58
S/. 11,719.58

S/. 17,756.34
S/. 17,756.34

S/. 23,439.16
S/. 23,439.16

S/. 45,720.64
S/. 45,720.64

S/. 35,158.74

S/. 63,476.98

S/. 86,424.31
S/. 0.00
S/. 86,424.31
S/. 15,556.38

S/. 101,980.68

S/. 0.00

SALDO
P. PARCIAL

0.00
0.00
402.00

0.00%
0.00%
67.00%

0.00
0.00

0.00%
0.00%

0.00
0.00
1,646.89

0.00%
0.00%
100.00%

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,004.72
3,135.64
3,083.13
5,136.63
9,821.35

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
75.00%
75.00%
75.00%
75.00%
75.00%

7,679.26
13,873.73
12,347.85
13,130.39
20,805.21
26,400.06
12,227.86
8,043.39
1,922.95
1,947.61
1,414.08

75.00%
100.00%
75.00%
75.00%
100.00%
75.00%
75.00%
75.00%
100.00%
100.00%
100.00%

11,086.18
3,746.41

50.00%
50.00%

981.12

100.00%

160,836.45
16,083.65
16,083.65
193,003.74
177,563.44
31,961.42

209,524.86
68.36%
60.24%

347,815.91

RESUMEN DE METRAD

(Del 01/Jul/15
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =
ITEM

1.00.00
1.01.00
1.02.00
1.03.00
2.00.00
2.01.00
2.02.00
3.00.00
3.01.00
3.02.00
3.02.00
4.00.00
4.01.00
4.02.00
4.03.00
5.00.00
5.01.01
5.01.02
5.02.01

5.02.02
5.02.03
5.03.01
5.03.02
5.03.03
5.04.01
5.04.02
5.04.03
5.05.01
5.05.02
5.05.03
5.06.01
5.06.02
5.06.03
5.07.01
5.07.02
5.07.03
5.07.04
5.08.01
5.08.02
5.08.03
6.00.00
6.01.00
6.02.00
7.00.00
7.01.00

VALORIZACIN DE A

(Del 01/Jul/15
Obra
=
Entidad
=
Ubicacin =

Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =
ITEM

1.00.00
1.01.00
1.02.00
1.03.00
2.00.00
2.01.00
2.02.00
3.00.00
3.01.00
3.02.00
3.02.00
4.00.00
4.01.00
4.02.00
4.03.00
5.00.00
5.01.01
5.01.02
5.02.01
5.02.02
5.02.03
5.03.01
5.03.02
5.03.03
5.04.01
5.04.02
5.04.03
5.05.01
5.05.02

5.05.03
5.06.01
5.06.02
5.06.03
5.07.01
5.07.02
5.07.03
5.07.04
5.08.01
5.08.02
5.08.03
6.00.00
6.01.00
6.02.00
7.00.00
7.01.00

RESUMEN DE METRADOS - VALORIZACIN N


(Del 01/Jul/15

al

28/Jul/15)

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya
PARTIDA

METRADOS - Val. 01
UNIDAD

OBRAS PROVISIONALES
Caseta para Oficinas y Almacen
Cartel de Obra (2.40m x 4.80m)
Agua para la Construccin

m2.
Und.
Global

OBRAS PRELIMINARES
Limpieza Manual del Terreno
Trazo, Nivel y Replanteo

m2.
m2.

MOVIMIENTO DE TIERRAS
Excavaciones Manuales Simples
Relleno Compactado con Material Propio
Eliminacion de Material Excedente, Distancia Prom. 10 Km.

m3.
m3.
m3.

OBRAS DE CONCRETO SIMPLE


Cimientos Corridos, Concreto 1:10 + 30% P.G.
Solado, Concreto 1:12, Espesor 10 cm.
Falso Piso, Concreto 1:10, Espesor 10 cm.

m3.
m2.
m2.

OBRAS DE CONCRETO ARMADO


Zapatas, Concreto f`c = 210 Kg/cm2.
Zapatas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Viga de Cimentacion, Concreto f`c = 210 Kg/cm2.

m3.
kg.
m3.

m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
und.
m3.
m2.
kg.

Viga de Cimentacion, Encofrado y Desencofrado.


Viga de Cimentacin, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Sobrecimientos, Concreto f`c = 175 Kg/cm2.
Sobrecimientos, Encofrado y Desencofrado.
Sobrecimiento, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Estructurales, Concreto f`c = 210 Kg/cm2.
Columnas Estructurales, Encofrado y Desencofrado.
Columnas Estructurales, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Confinamiento, Concreto f`c = 175 Kg/cm2.
Columnas de Confinamiento, Encofrado y Desencofrado.
Columnas de Confin., Acero Grado 60 - f`y = 4,200 Kg/cm2.
Vigas, Concreto f`c = 210 Kg/cm2.
Vigas, Encofrado y Desencofrado.
Vigas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Concreto f`c = 210 Kg/cm2.
Losa Aligerada, Encofrado y Desencofrado.
Losa Aligerada, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Ladrillo Hueco h = 0.15 m.
Escalera, Concreto f`c = 210 Kg/cm2.
Escalera, Encofrado y Desencofrado
Escalera, Acero Grado 60 - f`y = 4,200 Kg/cm2.
ALBAILERIA

m2.
m2.

Muros de Cabeza, con Ladrillo Maquinado, Mortero 1:4 (c-a)


Muros de Soga, con Ladrillo Maquinado, Mortero 1:5 (c-a)
LIMPIEZA, VARIOS

Global

Limpieza Final de Obra

VALORIZACIN DE AVANCE DE OBRA - N


(Del 01/Jul/15
CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.
GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.

al

28/Jul/15)

ENERO DEL 2,014.


CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya
PARTIDA
UNIDAD

OBRAS PROVISIONALES
Caseta para Oficinas y Almacen
Cartel de Obra (2.40m x 4.80m)
Agua para la Construccin

m2.
Und.
Global

OBRAS PRELIMINARES
Limpieza Manual del Terreno
Trazo, Nivel y Replanteo

m2.
m2.

MOVIMIENTO DE TIERRAS
Excavaciones Manuales Simples
Relleno Compactado con Material Propio
Eliminacion de Material Excedente, Distancia Prom. 10 Km.

m3.
m3.
m3.

OBRAS DE CONCRETO SIMPLE


Cimientos Corridos, Concreto 1:10 + 30% P.G.
Solado, Concreto 1:12, Espesor 10 cm.
Falso Piso, Concreto 1:10, Espesor 10 cm.

m3.
m2.
m2.

OBRAS DE CONCRETO ARMADO


Zapatas, Concreto f`c = 210 Kg/cm2.
Zapatas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Viga de Cimentacion, Concreto f`c = 210 Kg/cm2.
Viga de Cimentacion, Encofrado y Desencofrado.
Viga de Cimentacin, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Sobrecimientos, Concreto f`c = 175 Kg/cm2.
Sobrecimientos, Encofrado y Desencofrado.
Sobrecimiento, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Estructurales, Concreto f`c = 210 Kg/cm2.
Columnas Estructurales, Encofrado y Desencofrado.
Columnas Estructurales, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Confinamiento, Concreto f`c = 175 Kg/cm2.
Columnas de Confinamiento, Encofrado y Desencofrado.

m3.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.

Columnas de Confin., Acero Grado 60 - f`y = 4,200 Kg/cm2.


Vigas, Concreto f`c = 210 Kg/cm2.
Vigas, Encofrado y Desencofrado.
Vigas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Concreto f`c = 210 Kg/cm2.
Losa Aligerada, Encofrado y Desencofrado.
Losa Aligerada, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Ladrillo Hueco h = 0.15 m.
Escalera, Concreto f`c = 210 Kg/cm2.
Escalera, Encofrado y Desencofrado
Escalera, Acero Grado 60 - f`y = 4,200 Kg/cm2.

kg.
m3.
m2.
kg.
m3.
m2.
kg.
und.
m3.
m2.
kg.

ALBAILERIA
Muros de Cabeza, con Ladrillo Maquinado, Mortero 1:4 (c-a)
Muros de Soga, con Ladrillo Maquinado, Mortero 1:5 (c-a)

m2.
m2.

LIMPIEZA, VARIOS
Limpieza Final de Obra

Global

COSTO DIRECTO DE OBR


GASTO GENERAL ( 10% )
UTILIDAD
( 10%
SUB TOTAL DE OBRA

SUB TOTAL CONTRACTU


I. G. V. (18%)

PRESUPUESTO ESTRU

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

VALORIZACIN N 02
28/Jul/15)
Valor Referencial =
Valor Referencial =
Monto Contractual =
Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =

METRADOS - Val. 01

(Sin IGV)
(Con IGV)
(Sin IGV)
(Con IGV)

S/.
S/.
S/.
S/.
0.92000
80

320,390.47
378,060.76
294,759.23
347,815.90

1 de junio de 2015
18 de agosto de 2015

RESUMEN DE METRADOS

CANTIDAD

ANTERIOR

EJECUTADO

ACUMULADO

SALDO

0.00
0.00
0.33

30.00
1.00
0.33

0.00
0.00
0.33

30.00
1.00
0.66

0.00
0.00
0.34

0.00
0.00

440.00
722.75

0.00
0.00

440.00
722.75

0.00
0.00

0.00
0.00
30.00

111.05
92.49
0.00

0.00
0.00
30.00

111.05
92.49
30.00

0.00
0.00
50.00

0.00
0.00
0.00

66.22
40.76
349.14

0.00
0.00
0.00

66.22
40.76
349.14

0.00
0.00
0.00

0.00
0.00
0.00

12.37
491.67
1.64

0.00
0.00
0.00

12.37
491.67
1.64

0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
2.88
33.60
501.66
8.01
114.35
1,249.50
17.26
109.68
2,136.45
24.80
141.74
994.80
1,181.00
4.33
30.16
345.13

13.12
269.92
8.99
92.18
523.48
1.44
16.80
250.83
4.01
57.18
624.75
0.00
54.84
1,068.23
0.00
141.74
994.80
1,181.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
2.88
33.60
501.66
8.01
114.35
1,249.50
17.26
109.68
2,136.45
24.80
141.74
994.80
1,181.00
4.33
30.16
345.13

13.12
269.92
8.99
92.18
523.48
4.32
50.40
752.49
12.02
171.53
1,874.25
17.26
164.52
3,204.68
24.80
283.48
1,989.60
2,362.00
4.33
30.16
345.13

0.00
0.00
0.00
0.00
0.00
1.44
16.80
250.83
4.01
57.18
624.75
17.26
54.84
1,068.23
24.80
283.48
1,989.60
2,362.00
0.00
0.00
0.00

66.38
37.80

132.75
75.60

66.38
37.80

199.13
113.40

66.38
37.80

0.50

0.00

0.50

0.50

0.50

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

CE DE OBRA - N 02
28/Jul/15)
Valor Referencial =
Valor Referencial =
Monto Contractual =

(Sin IGV)
(Con IGV)
(Sin IGV)

S/. 320,390.47
S/. 378,060.76
S/. 294,759.23

Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =

(Con IGV)
(Dias Cal.)

S/. 347,815.90
0.92000
80
11 de mayo de 2015
29 de julio de 2015

ANTERIOR

PRESUPUESTO INICIAL
CANTIDAD

P. UNIT.

P. PARCIAL

P. TOTAL

METRADO

2,861.23
30.00
1.00
1.00

38.73
1,099.21
600.00

1,162.02
1,099.21
600.00

30.00
1.00
0.33
1,309.63

440.00
722.75

1.02
1.19

449.68
859.95

440.00
722.75
8,509.79

111.05
92.49
80.00

30.66
37.39
20.59

3,404.85
3,458.04
1,646.89

111.05
92.49
0.00
26,820.83

66.22
40.76
349.14

199.47
31.40
35.33

13,207.80
1,279.77
12,333.25

66.22
40.76
349.14
196,844.29

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
5.76
67.20
1,003.32
16.03
228.70

347.79
4.10
396.18
59.80
4.10
364.07
57.04
4.10
464.05
62.21
4.10
427.38
57.26

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
2,672.96
4,180.85
4,110.84
6,848.83
13,095.13

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
1.44
16.80
250.83
4.01
57.18

2,498.99
34.52
219.36
4,272.90
49.61
566.96
3,979.20
4,724.00
4.33
30.16
345.13

4.10
401.95
75.05
4.10
419.38
62.09
4.10
2.27
444.20
64.58
4.10

10,239.02
13,873.73
16,463.80
17,507.19
20,805.21
35,200.08
16,303.81
10,724.52
1,922.95
1,947.61
1,414.08

624.75
0.00
54.84
1,068.23
0.00
141.74
994.80
1,181.00
0.00
0.00
0.00
29,665.18

265.50
151.20

83.51
49.56

22,172.35
7,492.83

132.75
75.60
981.12

1.00

981.12

981.12

0.00

S/. =
S/. =
S/.
=
S/. =

266,992.06
26,699.21
26,699.21
320,390.47

B TOTAL CONTRACTUAL S/. =


V. (18%)
S/. =

294,759.23

STO DIRECTO DE OBRA


STO GENERAL ( 10% )
LIDAD
( 10% )
B TOTAL DE OBRA

ESUPUESTO ESTRUCTURAS

S/.

53,056.66

AVANCE PROGRAMADO =
AVANCE EJECUTADO =

347,815.90

S/.
S/.
S/.
S/.

320,390.47
378,060.76
294,759.23
347,815.90
Dias Cal.

1 de junio de 2015
18 de agosto de 2015

S/. 320,390.47
S/. 378,060.76
S/. 294,759.23

S/. 347,815.90
Dias Cal.
11 de mayo de 2015
29 de julio de 2015

ANTERIOR

ACTUAL

ACUMULADO

P. PARCIAL

METRADO

P. PARCIAL

METRADO

P. PARCIAL

1,162.02
1,099.21
198.00

0.00
0.00
0.33

0.00
0.00
198.00

30.00
1.00
0.66

1,162.02
1,099.21
396.00

449.68
859.95

0.00
0.00

0.00
0.00

440.00
722.75

449.68
859.95

3,404.85
3,458.04
0.00

0.00
0.00
30.00

0.00
0.00
617.58

111.05
92.49
30.00

3,404.85
3,458.04
617.58

13,207.80
1,279.77
12,333.25

0.00
0.00
0.00

0.00
0.00
0.00

66.22
40.76
349.14

13,207.80
1,279.77
12,333.25

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
668.24
1,045.21
1,027.71
1,712.21
3,273.78

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2.88
33.60
501.66
8.01
114.35

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,336.48
2,090.42
2,055.42
3,424.42
6,547.57

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
4.32
50.40
752.49
12.02
171.53

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
2,004.72
3,135.64
3,083.13
5,136.63
9,821.35

2,559.75
0.00
4,115.95
4,376.80
0.00
8,800.02
4,075.95
2,681.13
0.00
0.00
0.00

1,249.50
17.26
109.68
2,136.45
24.80
141.74
994.80
1,181.00
4.33
30.16
345.13

5,119.51
6,936.87
8,231.90
8,753.59
10,402.60
8,800.02
4,075.95
2,681.13
1,922.95
1,947.61
1,414.08

1,874.25
17.26
164.52
3,204.68
24.80
283.48
1,989.60
2,362.00
4.33
30.16
345.13

7,679.26
6,936.87
12,347.85
13,130.39
10,402.60
17,600.04
8,151.90
5,362.26
1,922.95
1,947.61
1,414.08

11,086.18
3,746.41

66.38
37.80

5,543.09
1,873.21

199.13
113.40

16,629.27
5,619.62

0.00

0.50

490.56

0.50

490.56

106,155.62
10,615.56
10,615.56
127,386.74

84,462.96
8,446.30
8,446.30
101,355.55

190,618.58
19,061.86
19,061.86
228,742.30

117,195.80

93,247.11

210,442.91

21,095.24

16,784.48

37,879.72

138,291.05

110,031.59

248,322.64

31.64%
39.76%

45.95%
31.64%

77.60%
71.39%

ULADO

SALDO

METRADO

P. PARCIAL

100.00%
100.00%
66.00%

0.00
0.00
0.34

0.00
0.00
204.00

0.00%
0.00%
34.00%

100.00%
100.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

100.00%
100.00%
37.50%

0.00
0.00
50.00

0.00
0.00
1,029.31

0.00%
0.00%
62.50%

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
75.00%
75.00%
75.00%
75.00%
75.00%

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.44
16.80
250.83
4.01
57.18

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
668.24
1,045.21
1,027.71
1,712.21
3,273.78

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
25.00%
25.00%
25.00%
25.00%
25.00%

75.00%
50.00%
75.00%
75.00%
50.00%
50.00%
50.00%
50.00%
100.00%
100.00%
100.00%

624.75
17.26
54.84
1,068.23
24.80
283.48
1,989.60
2,362.00
0.00
0.00
0.00

2,559.75
6,936.87
4,115.95
4,376.80
10,402.60
17,600.04
8,151.90
5,362.26
0.00
0.00
0.00

25.00%
50.00%
25.00%
25.00%
50.00%
50.00%
50.00%
50.00%
0.00%
0.00%
0.00%

75.00%
75.00%

66.38
37.80

5,543.09
1,873.21

25.00%
25.00%

50.00%

0.50

490.56

50.00%

76,373.49
7,637.35
7,637.35
91,648.19
84,316.33
15,176.94

99,493.27
22.40%
28.61%

347,815.91

RESUMEN DE METRADOS
(Del 01/Agost./15
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =
ITEM

1.00.00
1.01.00
1.02.00
1.03.00
2.00.00
2.01.00
2.02.00
3.00.00
3.01.00
3.02.00
3.02.00
4.00.00
4.01.00
4.02.00
4.03.00
5.00.00
5.01.01
5.01.02
5.02.01

5.02.02
5.02.03
5.03.01
5.03.02
5.03.03
5.04.01
5.04.02
5.04.03
5.05.01
5.05.02
5.05.03
5.06.01
5.06.02
5.06.03
5.07.01
5.07.02
5.07.03
5.07.04
5.08.01
5.08.02
5.08.03
6.00.00
6.01.00
6.02.00
7.00.00
7.01.00

VALORIZACIN DE AVA
(Del 01/Agost./15
Obra
=
Entidad
=
Ubicacin =

Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =
ITEM

1.00.00
1.01.00
1.02.00
1.03.00
2.00.00
2.01.00
2.02.00
3.00.00
3.01.00
3.02.00
3.02.00
4.00.00
4.01.00
4.02.00
4.03.00
5.00.00
5.01.01
5.01.02
5.02.01
5.02.02
5.02.03
5.03.01
5.03.02
5.03.03
5.04.01
5.04.02
5.04.03
5.05.01
5.05.02

5.05.03
5.06.01
5.06.02
5.06.03
5.07.01
5.07.02
5.07.03
5.07.04
5.08.01
5.08.02
5.08.03
6.00.00
6.01.00
6.02.00
7.00.00
7.01.00

RESUMEN DE METRADOS - VALORIZACIN N


(Del 01/Agost./15

al

18/Agost/15)

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya
PARTIDA

METRADOS - Val. 01
UNIDAD

OBRAS PROVISIONALES
Caseta para Oficinas y Almacen
Cartel de Obra (2.40m x 4.80m)
Agua para la Construccin

m2.
Und.
Global

OBRAS PRELIMINARES
Limpieza Manual del Terreno
Trazo, Nivel y Replanteo

m2.
m2.

MOVIMIENTO DE TIERRAS
Excavaciones Manuales Simples
Relleno Compactado con Material Propio
Eliminacion de Material Excedente, Distancia Prom. 10 Km.

m3.
m3.
m3.

OBRAS DE CONCRETO SIMPLE


Cimientos Corridos, Concreto 1:10 + 30% P.G.
Solado, Concreto 1:12, Espesor 10 cm.
Falso Piso, Concreto 1:10, Espesor 10 cm.

m3.
m2.
m2.

OBRAS DE CONCRETO ARMADO


Zapatas, Concreto f`c = 210 Kg/cm2.
Zapatas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Viga de Cimentacion, Concreto f`c = 210 Kg/cm2.

m3.
kg.
m3.

m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
und.
m3.
m2.
kg.

Viga de Cimentacion, Encofrado y Desencofrado.


Viga de Cimentacin, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Sobrecimientos, Concreto f`c = 175 Kg/cm2.
Sobrecimientos, Encofrado y Desencofrado.
Sobrecimiento, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Estructurales, Concreto f`c = 210 Kg/cm2.
Columnas Estructurales, Encofrado y Desencofrado.
Columnas Estructurales, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Confinamiento, Concreto f`c = 175 Kg/cm2.
Columnas de Confinamiento, Encofrado y Desencofrado.
Columnas de Confin., Acero Grado 60 - f`y = 4,200 Kg/cm2.
Vigas, Concreto f`c = 210 Kg/cm2.
Vigas, Encofrado y Desencofrado.
Vigas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Concreto f`c = 210 Kg/cm2.
Losa Aligerada, Encofrado y Desencofrado.
Losa Aligerada, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Ladrillo Hueco h = 0.15 m.
Escalera, Concreto f`c = 210 Kg/cm2.
Escalera, Encofrado y Desencofrado
Escalera, Acero Grado 60 - f`y = 4,200 Kg/cm2.
ALBAILERIA

m2.
m2.

Muros de Cabeza, con Ladrillo Maquinado, Mortero 1:4 (c-a)


Muros de Soga, con Ladrillo Maquinado, Mortero 1:5 (c-a)
LIMPIEZA, VARIOS

Global

Limpieza Final de Obra

VALORIZACIN DE AVANCE DE OBRA - N 03


(Del 01/Agost./15
CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.
GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.

al

18/Agost/15)

ENERO DEL 2,014.


CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya
PARTIDA
UNIDAD

OBRAS PROVISIONALES
Caseta para Oficinas y Almacen
Cartel de Obra (2.40m x 4.80m)
Agua para la Construccin

m2.
Und.
Global

OBRAS PRELIMINARES
Limpieza Manual del Terreno
Trazo, Nivel y Replanteo

m2.
m2.

MOVIMIENTO DE TIERRAS
Excavaciones Manuales Simples
Relleno Compactado con Material Propio
Eliminacion de Material Excedente, Distancia Prom. 10 Km.

m3.
m3.
m3.

OBRAS DE CONCRETO SIMPLE


Cimientos Corridos, Concreto 1:10 + 30% P.G.
Solado, Concreto 1:12, Espesor 10 cm.
Falso Piso, Concreto 1:10, Espesor 10 cm.

m3.
m2.
m2.

OBRAS DE CONCRETO ARMADO


Zapatas, Concreto f`c = 210 Kg/cm2.
Zapatas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Viga de Cimentacion, Concreto f`c = 210 Kg/cm2.
Viga de Cimentacion, Encofrado y Desencofrado.
Viga de Cimentacin, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Sobrecimientos, Concreto f`c = 175 Kg/cm2.
Sobrecimientos, Encofrado y Desencofrado.
Sobrecimiento, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Estructurales, Concreto f`c = 210 Kg/cm2.
Columnas Estructurales, Encofrado y Desencofrado.
Columnas Estructurales, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Columnas de Confinamiento, Concreto f`c = 175 Kg/cm2.
Columnas de Confinamiento, Encofrado y Desencofrado.

m3.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.
kg.
m3.
m2.

Columnas de Confin., Acero Grado 60 - f`y = 4,200 Kg/cm2.


Vigas, Concreto f`c = 210 Kg/cm2.
Vigas, Encofrado y Desencofrado.
Vigas, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Concreto f`c = 210 Kg/cm2.
Losa Aligerada, Encofrado y Desencofrado.
Losa Aligerada, Acero Grado 60 - f`y = 4,200 Kg/cm2.
Losa Aligerada, Ladrillo Hueco h = 0.15 m.
Escalera, Concreto f`c = 210 Kg/cm2.
Escalera, Encofrado y Desencofrado
Escalera, Acero Grado 60 - f`y = 4,200 Kg/cm2.

kg.
m3.
m2.
kg.
m3.
m2.
kg.
und.
m3.
m2.
kg.

ALBAILERIA
Muros de Cabeza, con Ladrillo Maquinado, Mortero 1:4 (c-a)
Muros de Soga, con Ladrillo Maquinado, Mortero 1:5 (c-a)

m2.
m2.

LIMPIEZA, VARIOS
Limpieza Final de Obra

Global

COSTO DIRECTO DE OB
GASTO GENERAL ( 10%
UTILIDAD
( 10%
SUB TOTAL DE OBRA

SUB TOTAL CONTRACT


I. G. V. (18%)

PRESUPUESTO ESTR

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

LORIZACIN N 03

8/Agost/15)
Valor Referencial =
(Sin IGV)
Valor Referencial =
(Con IGV)
Monto Contractual =
(Sin IGV)
Monto Contractual =
(Con IGV)
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =

METRADOS - Val. 01

S/.
S/.
S/.
S/.
0.92000
80

320,390.47
378,060.76
294,759.23
347,815.90

1 de junio de 2015
18 de agosto de 2015

RESUMEN DE METRADOS

CANTIDAD

ANTERIOR

EJECUTADO

ACUMULADO

SALDO

0.00
0.00
0.34

30.00
1.00
0.66

0.00
0.00
0.34

30.00
1.00
1.00

0.00
0.00
0.00

0.00
0.00

440.00
722.75

0.00
0.00

440.00
722.75

0.00
0.00

0.00
0.00
50.00

111.05
92.49
30.00

0.00
0.00
50.00

111.05
92.49
80.00

0.00
0.00
0.00

0.00
0.00
0.00

66.22
40.76
349.14

0.00
0.00
0.00

66.22
40.76
349.14

0.00
0.00
0.00

0.00
0.00
0.00

12.37
491.67
1.64

0.00
0.00
0.00

12.37
491.67
1.64

0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
1.44
16.80
250.83
4.01
57.18
624.75
17.26
54.84
1,068.23
24.80
283.48
1,989.60
2,362.00
0.00
0.00
0.00

13.12
269.92
8.99
92.18
523.48
4.32
50.40
752.48
12.02
171.53
1,874.25
17.26
164.52
3,204.68
24.80
283.48
1,989.60
2,362.00
4.33
30.16
345.13

0.00
0.00
0.00
0.00
0.00
1.44
16.80
250.83
4.01
57.18
624.75
17.26
54.84
1,068.23
24.80
283.48
1,989.60
2,362.00
0.00
0.00
0.00

13.12
269.92
8.99
92.18
523.48
5.76
67.20
1,003.31
16.03
228.70
2,498.99
34.52
219.36
4,272.90
49.61
566.96
3,979.20
4,724.00
4.33
30.16
345.13

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

66.38
37.80

199.13
113.40

66.38
37.80

265.50
151.20

0.00
0.00

0.50

0.50

0.50

1.00

0.00

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

DE OBRA - N 03

8/Agost/15)
Valor Referencial =
Valor Referencial =
Monto Contractual =

(Sin IGV)
(Con IGV)
(Sin IGV)

S/. 320,390.47
S/. 378,060.76
S/. 294,759.23

Monto Contractual =
(Con IGV)
Factor de Relacin =
Plazo Contractual =
(Dias Cal.)
Inicio del Plazo Contractual =
Termino del Plazo Contractual =

S/. 347,815.90
0.92000
80
11 de mayo de 2015
29 de julio de 2015

ANTERIOR

PRESUPUESTO INICIAL
CANTIDAD

P. UNIT.

P. PARCIAL

P. TOTAL

METRADO

2,861.23
30.00
1.00
1.00

38.73
1,099.21
600.00

1,162.02
1,099.21
600.00

30.00
1.00
0.66
1,309.63

440.00
722.75

1.02
1.19

449.68
859.95

440.00
722.75
8,509.79

111.05
92.49
80.00

30.66
37.39
20.59

3,404.85
3,458.04
1,646.89

111.05
92.49
30.00
26,820.83

66.22
40.76
349.14

199.47
31.40
35.33

13,207.80
1,279.77
12,333.25

66.22
40.76
349.14
196,844.29

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
5.76
67.20
1,003.32
16.03
228.70

347.79
4.10
396.18
59.80
4.10
364.07
57.04
4.10
464.05
62.21
4.10
427.38
57.26

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
2,672.96
4,180.85
4,110.84
6,848.83
13,095.13

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
4.32
50.40
752.49
12.02
171.53

2,498.99
34.52
219.36
4,272.90
49.61
566.96
3,979.20
4,724.00
4.33
30.16
345.13

4.10
401.95
75.05
4.10
419.38
62.09
4.10
2.27
444.20
64.58
4.10

10,239.02
13,873.73
16,463.80
17,507.19
20,805.21
35,200.08
16,303.81
10,724.52
1,922.95
1,947.61
1,414.08

1,874.25
17.26
164.52
3,204.68
24.80
283.48
1,989.60
2,362.00
4.33
30.16
345.13
29,665.18

265.50
151.20

83.51
49.56

22,172.35
7,492.83

199.13
113.40
981.12

1.00

981.12

981.12

0.50

S/. =
S/. =
S/.
=
S/. =

266,992.06
26,699.21
26,699.21
320,390.47

B TOTAL CONTRACTUAL S/. =


V. (18%)
S/. =

294,759.23

STO DIRECTO DE OBRA


STO GENERAL ( 10% )
LIDAD
( 10% )
B TOTAL DE OBRA

ESUPUESTO ESTRUCTURAS

S/.

53,056.66

347,815.90

AVANCE PROGRAMADO =
AVANCE EJECUTADO =

S/.
S/.
S/.
S/.

320,390.47
378,060.76
294,759.23
347,815.90
Dias Cal.

1 de junio de 2015
18 de agosto de 2015

34.52
219.36
4,272.90
49.61
566.96
3,979.20
4,724.00
4.33
30.16
345.13

265.50
151.20

1.00

S/. 320,390.47
S/. 378,060.76
S/. 294,759.23

S/. 347,815.90
Dias Cal.
11 de mayo de 2015
29 de julio de 2015

ANTERIOR

ACTUAL

ACUMULADO

P. PARCIAL

METRADO

P. PARCIAL

METRADO

P. PARCIAL

1,162.02
1,099.21
396.00

0.00
0.00
0.34

0.00
0.00
204.00

30.00
1.00
1.00

1,162.02
1,099.21
600.00

449.68
859.95

0.00
0.00

0.00
0.00

440.00
722.75

449.68
859.95

3,404.85
3,458.04
617.58

0.00
0.00
50.00

0.00
0.00
1,029.31

111.05
92.49
80.00

3,404.85
3,458.04
1,646.89

13,207.80
1,279.77
12,333.25

0.00
0.00
0.00

0.00
0.00
0.00

66.22
40.76
349.14

13,207.80
1,279.77
12,333.25

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
2,004.72
3,135.64
3,083.13
5,136.63
9,821.35

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1.44
16.80
250.83
4.01
57.18

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
668.24
1,045.21
1,027.71
1,712.21
3,273.78

12.37
491.67
1.64
13.12
269.92
8.99
92.18
523.48
5.76
67.20
1,003.32
16.03
228.70

4,301.51
2,014.51
649.74
784.55
1,105.93
3,274.26
5,258.35
2,144.84
2,672.96
4,180.85
4,110.84
6,848.83
13,095.13

7,679.26
6,936.87
12,347.85
13,130.39
10,402.60
17,600.04
8,151.90
5,362.26
1,922.95
1,947.61
1,414.08

624.75
17.26
54.84
1,068.23
24.80
283.48
1,989.60
2,362.00
0.00
0.00
0.00

2,559.75
6,936.87
4,115.95
4,376.80
10,402.60
17,600.04
8,151.90
5,362.26
0.00
0.00
0.00

2,498.99
34.52
219.36
4,272.90
49.61
566.96
3,979.20
4,724.00
4.33
30.16
345.13

10,239.02
13,873.73
16,463.80
17,507.19
20,805.21
35,200.08
16,303.81
10,724.52
1,922.95
1,947.61
1,414.08

16,629.27
5,619.62

66.38
37.80

5,543.09
1,873.21

265.50
151.20

22,172.35
7,492.83

490.56

0.50

490.56

1.00

981.12

190,618.58
19,061.86
19,061.86
228,742.30

76,373.49
7,637.35
7,637.35
91,648.18

266,992.07
26,699.21
26,699.21
320,390.48

210,442.91

84,316.32

294,759.23

37,879.72

15,176.94

53,056.66

248,322.64

99,493.26

347,815.90

77.60%
71.39%

22.40%
28.61%

100.00%
100.00%

ULADO

SALDO

METRADO

P. PARCIAL

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

100.00%
100.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

100.00%
100.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

100.00%

0.00

0.00

0.00%

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00%
0.00%

347,815.90

CALCULO DEL R
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

PROGRAMADO

VALORIZACIN

Fecha

31-May-15

30-Jun-15

29-Jul-15

93,271.71
93,271.71
135,452.84
228,724.55
66,034.69
294,759.23

K
1.037
1.039
1.039

PARA OBRAS ATRAZADAS

<

Mximo Reajuste Reconocido


Reajustes Programados
El Avance Real Acumulado esta por debajo del Avance
Programado Acumulado, a un Periodo Determinado

Basta que la Obra entre en atraso de un periodo, a

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

CALCULO DEL REINTEGRO AUTORIZADO

GUEL - PIURA.

Valor Referencial =
Valor Referencial =
Monto Contractual =
Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =

AMADO

EJECUTADO
R=V*(K-1)
3,491.64
3,491.64
5,276.10
8,767.74
2,559.02
11,326.76

V
117,195.80
117,195.80
93,247.11
210,442.91
84,316.32
294,759.23

K
1.037
1.039
1.039

R=V*(K-1)
4,387.25
4,387.25
3,632.12
8,019.36
3,267.48
11,286.85

ESTADO DE
OBRA
Adelantada
Atrasada
Culmino

PARA OBRAS PERMANEN

Programados
el Avance
minado

Mximo Reajuste Reconocido


El Avance Real Acumulado
Programado Acumulado

atraso de un periodo, as se adelante nuevamente; para aplicar el concepto de Reajuste, se

(Sin IGV)
(Con IGV)
(Sin IGV)
(Con IGV)

S/.
S/.
S/.
S/.
0.92000
80

320,390.47
378,060.76
294,759.23
347,815.90
Dias Cal.

11 de mayo de 2015
29 de julio de 2015

Reajuste Bruto
Autorizado

4,387.25
4,387.25
3,632.12
8,019.36
3,267.48
11,286.85

DEDUCCIONES
DIRECTO

MATERIALES

13.63
13.63
10.71
24.34

RA OBRAS PERMANENTE ADELANTADAS

eajuste Reconocido
Reajustes Ejecutados
nce Real Acumulado esta por encima del Avance
ramado Acumulado, a un Periodo Determinado

ncepto de Reajuste, ser de una Obra Atrasada

46.56
46.56
1.70
48.26

REAJUSTE
AUTORIZADO

4,387.25
4,387.25
3,571.93
7,959.18
3,255.07
11,214.25

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

RESUMEN DE VALORIZACIN N 01
( MAYO 2015 )
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

VALORIZACIN DEL MES ( V ) =


(Indices de Abril)
REAJUSTES AUTORIZADO ( R ) =
DEDUCCIN DE REAJUSTES ( - ) (D)
Deduccin por Adelanto Directo
=
Deduccin por Adelanto Materiales =

S/. 4,387.25
S/. 0.00
S/. 0.00
S/. 0.00

VALORIZACIN BRUTA (V.B.=V+R -D) =


AMORTIZACIN DE ADELANTOS ( - ) (A)
Amortizacin por Adelanto Directo
=
Amortizacin por Adelanto Materiales =

S/. 35,022.82
S/. 11,719.58
S/. 23,303.24

VALORIZACIN NETA (V.N.= V.B. - A) =


Impuesto General a las Ventas (IGV)

CANCELAR AL CONTRATISTA (C.C.= V.N. + IGV) =

S/. 15,580.84

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

RESUMEN DE VALORIZACIN N 02
( JUNIO 2015 )
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

VALORIZACIN DEL MES ( V ) =


(Indices de Mayo)
REAJUSTES AUTORIZADO ( R ) =
DEDUCCIN DE REAJUSTES ( - ) (D)
Deduccin por Adelanto Directo
=
Deduccin por Adelanto Materiales =

S/. 3,632.12
S/. 60.19
S/. 13.63
S/. 46.56

VALORIZACIN BRUTA (V.B.=V+R -D) =


AMORTIZACIN DE ADELANTOS ( - ) (A)
Amortizacin por Adelanto Directo
=
Amortizacin por Adelanto Materiales =

S/. 27,865.99
S/. 9,324.71
S/. 18,541.28

VALORIZACIN NETA (V.N.= V.B. - A) =


Impuesto General a las Ventas (IGV)

CANCELAR AL CONTRATISTA (C.C.= V.N. + IGV) =

S/. 12,411.55

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

RESUMEN DE VALORIZACIN N 03
( JULIO 2015 )
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

VALORIZACIN DEL MES ( V ) =


(Indices de Junio)
REAJUSTES AUTORIZADO ( R ) =
DEDUCCIN DE REAJUSTES ( - ) (D)
Deduccin por Adelanto Directo
=
Deduccin por Adelanto Materiales =

S/. 3,267.48
S/. 12.41
S/. 10.71
S/. 1.70

VALORIZACIN BRUTA (V.B.=V+R -D) =


AMORTIZACIN DE ADELANTOS ( - ) (A)
Amortizacin por Adelanto Directo
=
Amortizacin por Adelanto Materiales =

S/. 25,197.11
S/. 8,431.63
S/. 16,765.48

VALORIZACIN NETA (V.N.= V.B. - A) =


Impuesto General a las Ventas (IGV)

CANCELAR AL CONTRATISTA (C.C.= V.N. + IGV) =

S/. 11,227.37

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

RIZACIN N 01

15 )

IGUEL - PIURA.

S/. 117,195.80

S/. 4,387.25
S/. 0.00
S/. 0.00
S/. 0.00

S/. 121,583.05
S/. 35,022.82
S/. 11,719.58
S/. 23,303.24

S/. 86,560.23
S/. 15,580.84

S/. 102,141.07

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

RIZACIN N 02

15 )

IGUEL - PIURA.

S/. 93,247.11

S/. 3,632.12
S/. 60.19
S/. 13.63
S/. 46.56

S/. 96,819.04
S/. 27,865.99
S/. 9,324.71
S/. 18,541.28

S/. 68,953.05
S/. 12,411.55

S/. 81,364.60

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

RIZACIN N 03

15 )

IGUEL - PIURA.

S/. 84,316.32

S/. 3,267.48
S/. 12.41
S/. 10.71
S/. 1.70

S/. 87,571.39
S/. 25,197.11
S/. 8,431.63
S/. 16,765.48

S/. 62,374.28
S/. 11,227.37

S/. 73,601.65

S/. 102,141.07

S/. 81,364.60

S/. 73,601.65

CONTROL DE VALORIZACIONES
( MAYO 2015 )
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL - PIURA.


GOBIERNO REGIONAL - PIURA.
DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

Formulas Polinomicas

Adel. Directo

OBRAS DE ESTRUCTURAS

29,475.92

Fecha

Monto
Valorizado

Reajustes
del Mes

1
2
3

31-May-15
30-Jun-15
29-Jul-15

117,195.80
93,247.11
84,316.32

4,387.25
3,632.12
3,267.48

294,759.23

11,286.84

VALORIZACIN

SUMATORIA

Montos sin

III.

III

RESUMEN DE PAGOS EN

( MAYO - JULIO
Obra
=
Entidad
=
Ubicacin =
Fecha
=
Proceso
=
Modalidad =
Contratista =
Residente =
Supervisor =

CONSTRUCCION DE 8 AULAS - I.E. SAN MIGUEL GOBIERNO REGIONAL - PIURA.


DISTRITO, PROVINCIA, REGIN - PIURA.
ENERO DEL 2,014.
CONCURSO N 016-2014-GRP/CE
SUMA ALZADA
BARLUM S.A.C.
Ing. Luis Valdez Giron
Ing. Miguel Angel Alvarado Otoya

1.- MONTO DE LAS VALORIZACIONES =


(Monto Contractual, sin Reajuste)
2.- REAJUSTES AUTORIZADOS
DE LAS VALORIZACIONES

3.- DEDUCCION DEL REAJUSTE


Deduccin por Adelanto Directo
=
Deduccin por Adelanto Materiales =
4.- MONTO BRUTO VALORIZ. REAJUSTADO (1+2-3)
5.- AMORTIZACION DE LOS ADELANTOS
Amortizacin por Adelanto Directo
=
Amortizacin por Adelanto Materiales =
6.- MONTO NETO VALORIZ. REAJUSTADO (4+5)
7.- IMPUESTO GENERAL A LAS VENTAS (IGV)

8.- TOTAL CANCELADO AL CONTRATISTA =

RESUMEN DE PAGOS EN
1.- MONTO DE LAS VALORIZACIONES PAGADAS =

(Con IGV)
Valorizacin N 01
Valorizacin N 02
Valorizacin N 03

=
=
=

S/. 102,141.07
S/. 81,364.60
S/. 73,601.65

2.- MONTO DE LOS ADELANTOS PAGADOS =


(Con IGV)
Adelanto Directo =
Adelanto para Materiales =

S/. 34,781.59
S/. 69,159.80

3.- TOTAL CANCELADO AL CONTRATISTA =


(Con IGV)

4.- MONTO CONTRACTUAL DE LA OBRA =


(Con IGV)

ORIZACIONES

015 )
Valor Referencial =
Valor Referencial =
Monto Contractual =
Monto Contractual =
Factor de Relacin =
Plazo Contractual =
Inicio del Plazo Contractual =
Termino del Plazo Contractual =
Area Geografica =

Montos sin I.G.V.


Adel. Mater.

58,610.00

Del Contrato

294,759.23

Adel. Directo

Adel. Mater.

Valorizacin
BRUTA

Adel. Directo

0.00
13.63
10.71

0.00
46.56
1.70

121,583.05
96,819.04
87,571.39

11,719.58
9,324.71
8,431.63

24.34

48.26

305,973.48

29,475.92

DEDUCCIONES

III.

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

AMORTOZACIONES

N DE PAGOS EN VALORIZACINES
( MAYO - JULIO, 2015 )

S - I.E. SAN MIGUEL - PIURA.

IN - PIURA.

S/. 294,759.23

S/. 11,286.84

S/. 72.60
S/. 24.34
S/. 48.26
S/. 305,973.48
S/. 88,085.92
S/. 29,475.92
S/. 58,610.00
S/. 217,887.55
S/. 39,219.76

S/. 257,107.32

N DE PAGOS EN VALORIZACINES
S/. 257,107.32

S/. 102,141.07
S/. 81,364.60
S/. 73,601.65
S/. 103,941.40
S/. 34,781.59
S/. 69,159.80

S/. 361,048.71

S/. 347,815.90

III.

ntractual =
ntractual =
Relacin =
tractual =
Plazo Contractual =
el Plazo Contractual =

IIIIII IIIII IIIIIIII IIIII


IIIIIIIII IIIII

(Sin IGV)
(Con IGV)
(Sin IGV)
(Con IGV)

S/.
S/.
S/.
S/.
80

320,390.47
378,060.76
294,759.23
347,815.90
0.92000
Dias Calendario

11 de mayo de 2015

29 de julio de 2015

Adel. Mater.

Valorizacin
NETA

I.G.V.
( 18% )

Valorizacin
LIQUIDA

23,303.24
18,541.28
16,765.48

86,560.23
68,953.05
62,374.28

15,580.84
12,411.55
11,227.37

102,141.07
81,364.60
73,601.65

58,610.00

217,887.55

39,219.76

257,107.31

AMORTOZACIONES

También podría gustarte