UNIVERSIDAD ANDINA

"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

ACERO GRADO 60 PARA ZAPATAS F'Y=4200 Kg/cm2


Eje 1-1 entre eje A - D
L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.46

1/2 12.7

0.46

3.68

3.75

3.75

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.46

1/2 12.7

0.46

3.68

3.75

3.75

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.46

1/2 12.7

0.46

3.68

3.75

3.75

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.46

1/2 12.7

0.46

3.68

3.75

3.75

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.46

1/2 12.7

0.46

3.68

3.75

3.75

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.46

1/2 12.7

0.46

3.68

3.75

3.75

Eje 2-2 entre eje A - D

Eje 3-3 entre eje A - D

Eje 4-4 entre eje A - D

Eje 5-5 entre eje A - D

Eje 6-6 entre eje A - D

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

Eje 7-7 entre eje A - D


L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.46

1/2 12.7

0.46

3.68

3.75

3.75

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.76

1/2 12.7

0.76

9.12

9.30

9.30

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.76

1/2 12.7

0.76

9.12

9.30

9.30

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.76

1/2 12.7

0.76

9.12

9.30

9.30

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.76

1/2 12.7

0.76

9.12

9.30

9.30

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

L = 0.76

1/2 12.7

0.76

9.12

9.30

9.30

L = 1.06

1/2 12.7

1.06

16.96

17.30

17.30

ZAPATA N 2

Eje 2-2 entre eje B - C

Eje 3-3 entre eje B - C

Eje 4-4 entre eje B - C

Eje 5-5 entre eje B - C

Eje 6-6 entre eje B - C

Eje 7-7 entre eje B - C

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

L = 0.76

TOTAL

#REF!

Pulg.

mm.

1/2 12.7

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

0.76

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

9.12

9.30

ACERO GRADO 60 PARA ZAPATAS F'Y=4200 Kg/cm2

(KG)

Peso Parcial Kg.

4.04K/m

9.30

306.98

#REF!
Columnas de 0.15x.0.45 (C-1)
Eje 1-1 , Entre Ejes A - C - D

JARDIN

L= 0.25

L = 4.10

1/2 12.7

4.35

17.40

17.75

17.75

L= 0.25
L= 0.25
L= 0.25

L = 4.10
L = 4.10
L = 4.10

1/2 12.7
1/2 12.7
1/2 12.7

4
4
4

1
1
1

4.35
4.35
4.35

17.40
17.40
17.40

17.75
17.75
17.75

17.75
17.75
17.75

L= 0.25

L = 4.10

3/8 9.525

4.35

17.40

10.09

10.09

L= 0.25

L = 4.10

3/8 9.525

4.35

17.40

10.09

10.09

1/4 6.35

70

0.79

221.20

L = 4.35

1/2 12.7

4.35

8.70

8.87

8.87

L = 4.35

1/2 12.7

4.35

8.70

8.87

8.87

L = 4.35

1/2 12.7

4.35

8.70

8.87

8.87

L = 4.35

1/2 12.7

4.35

8.70

8.87

8.87

L = 4.35

3/8 9.525

4.35

8.70

5.05

5.05

L = 4.35

3/8 9.525

4.35

8.70

5.05

5.05

Estribos

L= 0.79

55.30

55.30

Eje 1 - 2 , Entre eje C - D


JARDIN

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Estribos

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

1/4 6.35

70

0.79

110.60

L = 7.65

1/2 12.7

12

7.65

91.80

93.64

93.64

L = 7.56

1/2 12.7

12

7.56

90.72

92.53

92.53

L = 7.65

1/2 12.7

12

7.65

91.80

93.64

93.64

L = 7.65

1/2 12.7

12

7.65

91.80

93.64

93.64

L = 7.65

3/8 9.525

12

7.65

91.80

53.24

53.24

L = 7.65

3/8 9.525

12

7.65

91.80

53.24

53.24

3/8 9.525

12

112

0.79

1061.76

615.82

615.82

L= 0.79

27.65

1
4.04K/m

27.65

Eje 2-3-4-5-6-7 , Entre Eje A - D

Estribos

L= 0.79

Columnas de 0.15x.0.45 (C-2)


Eje 2-3-4-5-6-7 , Entre Eje B-C
Acero Sup.

L = 7.65

1/2 12.7

12

7.65

91.80

93.64

93.64

Acero Sup.

L = 7.65

1/2 12.7

12

7.65

91.80

93.64

93.64

Acero Sup.

L = 7.65

1/2 12.7

12

7.65

91.80

93.64

93.64

Acero Inf.

L = 7.65

1/2 12.7

12

7.65

91.80

93.64

93.64

Acero Inf.

L = 7.65

3/8 9.525

12

7.65

91.80

53.24

53.24

Acero Inf.

L = 7.65

3/8 9.525

12

7.65

91.80

53.24

53.24

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Estribos

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

3/8 9.525

12

112

0.79

1061.76

L = 4.35

1/2 12.7

4.35

13.05

13.31

13.31

L = 4.35

1/2 12.7

4.35

13.05

13.31

13.31

L = 4.35

1/2 12.7

4.35

13.05

13.31

13.31

L = 4.35

1/2 12.7

4.35

13.05

13.31

13.31

1/4 6.35

30

0.80

72.00

L = 4.35

1/2 12.7

4.35

8.70

8.87

8.87

L = 4.35

1/2 12.7

4.35

8.70

8.87

8.87

L = 4.35

1/2 12.7

4.35

8.70

8.87

8.87

L = 4.35

1/2 12.7

4.35

8.70

8.87

8.87

1/4 6.35

30

0.80

48.00

L= 0.79

615.82

1
4.04K/m

615.82

Columnas de 0.15 x 0.30 (C-3)


Eje 1-2 , Entre Eje A-C
JARDIN

Estribos

L= 0.80

18.00

18.00

Eje 7 - 7 Entre Eje A - D

Estribos

CURSO:COSTOS Y PRESUPUESTOS

L= 0.80

12.00

12.00

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

Eje 8 - 8 Entre Eje A-B-C-D


Columnas de 0.30x.0.50 (C-5)

Estribos

L = 4.35

1/2 12.7

4.35

17.40

17.75

17.75

L = 4.35

1/2 12.7

4.35

17.40

17.75

17.75

L = 4.35

1/2 12.7

4.35

17.40

17.75

17.75

L = 4.35

1/2 12.7

4.35

17.40

17.75

17.75

1/4 6.35

30

0.80

96.00

L= 0.80

TOTAL

#REF!

24.00

24.00

(KG)

2626.05

#REF! #REF!
Viga VS ( EJE A - A, ENTRE 2 - 7
L= 0.25 Acero Sup.

L = 15.75

L= 0.25

1/2 12.7

16.25

16.25

16.58

16.58

L= 0.25 Acero Sup.

L = 15.75

L= 0.25

1/2 12.7

16.25

16.25

16.58

16.58

L= 0.25 Acero Sup.

L = 15.75

L= 0.25

1/2 12.7

16.25

16.25

16.58

16.58

L= 0.25 Acero Inf.

L = 15.75

L= 0.25

1/2 12.7

16.25

16.25

16.58

16.58

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.
Estribos

Pulg.

L= 1.16

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

1/4 6.35

86

1.16

99.76

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

24.94

Peso Parcial Kg.

4.04K/m

24.94

Viga VS ( EJE A - B, , ENTRE 2 - 3


L= 0.25 Acero Sup.

L = 4.10

L= 0.25

1/2 12.7

4.60

4.60

4.69

4.69

L= 0.25 Acero Sup.

L = 4.10

L= 0.25

1/2 12.7

4.60

4.60

4.69

4.69

L= 0.25 Acero Sup.

L = 4.10

L= 0.25

1/2 12.7

4.60

4.60

4.69

4.69

L= 0.25 Acero Inf.

L = 4.10

L= 0.25

1/2 12.7

4.60

4.60

4.69

4.69

1/4 6.35

28

1.16

32.48

Estribos

L= 1.16

8.12

8.12

Viga VS ( EJE A - B, ENTRE 4 -5


L= 0.25 Acero Sup.

L = 2.40

L= 0.25

1/2 12.7

2.90

2.90

2.96

2.96

L= 0.25 Acero Sup.

L = 2.40

L= 0.25

1/2 12.7

2.90

2.90

2.96

2.96

L= 0.25 Acero Sup.

L = 2.40

L= 0.25

1/2 12.7

2.90

2.90

2.96

2.96

L= 0.25 Acero Inf.

L = 2.40

L= 0.25

1/2 12.7

2.90

2.90

2.96

2.96

1/4 6.35

20

1.16

23.20

Estribos

L= 1.16

Viga VS ( EJE B - B, ENTRE 2 - 7 )

CURSO:COSTOS Y PRESUPUESTOS

5.80

5.80

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

L= 0.25 Acero Sup.

L = 16.55

L= 0.25

1/2 12.7

17.05

17.05

17.39

17.39

L= 0.25 Acero Sup.

L = 16.55

L= 0.25

1/2 12.7

17.05

17.05

17.39

17.39

L= 0.25 Acero Sup.

L = 16.55

L= 0.25

1/2 12.7

17.05

17.05

17.39

17.39

L= 0.25 Acero Inf.

L = 16.55

L= 0.25

1/2 12.7

17.05

17.05

17.39

17.39

1/4 6.35

90.25

1.16

104.69

Estribos

L= 1.16

26.17

26.17

Viga VS ( EJE C - D, ENTRE 1 - 7 )


L= 0.25 Acero Sup.

L = 19.25

L= 0.25

1/2 12.7

19.75

39.50

40.29

40.29

L= 0.25 Acero Sup.

L = 19.25

L= 0.25

1/2 12.7

19.75

39.50

40.29

40.29

L= 0.25 Acero Sup.

L = 19.25

L= 0.25

1/2 12.7

19.75

39.50

40.29

40.29

L= 0.25 Acero Inf.

L = 19.25

L= 0.25

1/2 12.7

19.75

39.50

40.29

40.29

1/4 6.35

104

1.16

241.28

Estribos

L= 1.16

60.32

60.32

Viga VS ( EJE 3 - 3, ENTRE A - B )


L= 0.25 Acero Sup.

L = 3.80

L= 0.25

1/2 12.7

4.30

4.30

4.39

4.39

L= 0.25 Acero Sup.

L = 3.80

L= 0.25

1/2 12.7

4.30

4.30

4.39

4.39

L= 0.25 Acero Sup.

L = 3.80

L= 0.25

1/2 12.7

4.30

4.30

4.39

4.39

L= 0.25 Acero Inf.

L = 3.80

L= 0.25

1/2 12.7

4.30

4.30

4.39

4.39

1/4 6.35

27

1.16

62.64

Estribos
CURSO:COSTOS Y PRESUPUESTOS

L= 1.16

15.66

15.66

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

Viga VS ( EJE 4 - 5 - 7, ENTRE A - D


L= 0.25 Acero Sup.

L = 10.10

L= 0.25

1/2 12.7

10.60

31.80

32.44

32.44

L= 0.25 Acero Sup.

L = 10.10

L= 0.25

1/2 12.7

10.60

31.80

32.44

32.44

L= 0.25 Acero Sup.

L = 10.10

L= 0.25

1/2 12.7

10.60

31.80

32.44

32.44

L= 0.25 Acero Inf.

L = 10.10

L= 0.25

1/2 12.7

10.60

31.80

32.44

32.44

1/4 6.35

58

1.16

201.84

Estribos

L= 1.16

50.46

50.46

Viga VA ( EJE 2" - 2, ENTRE C - D


L= 0.15 Acero Sup.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

L= 0.15 Acero Sup.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

L= 0.15 Acero Sup.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

L= 0.15 Acero Inf.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

L= 0.15 Acero Inf.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

1/4 6.35

21

0.68

28.56

Estribos

CURSO:COSTOS Y PRESUPUESTOS

L= 0.68

7.14

7.14

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

Viga VA ( EJE 3 - 3, ENTRE B - D


L= 0.15 Acero Sup.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

L= 0.15 Acero Sup.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

L= 0.15 Acero Sup.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

L= 0.15 Acero Inf.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

L= 0.15 Acero Inf.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

1/4 6.35

39

0.68

26.52

Estribos

L= 0.68

6.63

6.63

Viga VA (EJE 6 - 6 , ENTRE A - D


L= 0.15 Acero Sup.

L = 10.10

L= 0.15

1/2 12.7

10.40

10.40

10.61

10.61

L= 0.15 Acero Sup.

L = 10.10

L= 0.15

1/2 12.7

10.40

10.40

10.61

10.61

L= 0.15 Acero Inf.

L = 10.10

L= 0.15

1/2 12.7

10.40

10.40

10.61

10.61

L= 0.15 Acero Inf.

L = 10.10

L= 0.15

1/2 12.7

10.40

10.40

10.61

10.61

1/4 6.35

58

0.68

39.44

Estribos

L= 0.68

9.86

9.86

Viga 101 (EJE 7 - 7 volado, ENTRE A - D


L= 0.25 Acero Sup.

L = 10.10

L= 0.25

1/2 12.7

10.60

10.60

10.81

10.81

L= 0.25 Acero Sup.

L = 10.10

L= 0.25

1/2 12.7

10.60

10.60

10.81

10.81

L= 0.25 Acero Inf.

L = 10.10

L= 0.25

1/2 12.7

10.60

10.60

10.81

10.81

L= 0.25 Acero Inf.

L = 10.10

L= 0.25

1/2 12.7

10.60

10.60

10.81

10.81

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Estribos

Pulg.

L= 0.88

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

1/4 6.35

58

0.88

51.04

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

12.76

Peso Parcial Kg.

4.04K/m

12.76

Viga 101 (EJE 1" - 1" , ENTRE EJE C - D


L= 0.25 Acero Sup.

L = 2.70

L= 0.25

1/2 12.7

3.20

3.20

3.26

3.26

L= 0.25 Acero Sup.

L = 2.70

L= 0.25

1/2 12.7

3.20

3.20

3.26

3.26

L= 0.25 Acero Inf.

L = 2.70

L= 0.25

1/2 12.7

3.20

3.20

3.26

3.26

L= 0.25 Acero Inf.

L = 2.70

L= 0.25

1/2 12.7

3.20

3.20

3.26

3.26

1/4 6.35

21

0.88

18.48

Estribos

L= 0.88

4.62

4.62

Viga 101 (EJE 2" - 2 , ENTRE EJE B -C volado


L= 0.25 Acero Sup.

L = 4.90

L= 0.25

1/2 12.7

5.40

5.40

5.51

5.51

L= 0.25 Acero Sup.

L = 4.90

L= 0.25

1/2 12.7

5.40

5.40

5.51

5.51

L= 0.25 Acero Inf.

L = 4.90

L= 0.25

1/2 12.7

5.40

5.40

5.51

5.51

L= 0.25 Acero Inf.

L = 4.90

L= 0.25

1/2 12.7

5.40

5.40

5.51

5.51

1/4 6.35

32

0.88

28.16

1/2 12.7

7.80

7.80

Estribos

L= 0.88

7.04

7.04

Viga 101 (EJE 2 - 2 , ENTRE EJE A - c


L= 0.25 Acero Sup.

CURSO:COSTOS Y PRESUPUESTOS

L = 7.30

L= 0.25

7.96

7.96

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

L= 0.25 Acero Sup.

L = 7.30

L= 0.25

1/2 12.7

7.80

7.80

7.96

7.96

L= 0.25 Acero Inf.

L = 7.30

L= 0.25

1/2 12.7

7.80

7.80

7.96

7.96

L= 0.25 Acero Inf.

L = 7.30

L= 0.25

1/2 12.7

7.80

7.80

7.96

7.96

1/4 6.35

44

0.88

38.72

Estribos

L= 0.88

9.68

9.68

Viga 101 (EJE 7- 7 volado , ENTRE EJE A - D


L= 0.25 Acero Sup.

L = 10.10

L= 0.25

1/2 12.7

10.60

10.60

10.81

10.81

L= 0.25 Acero Sup.

L = 10.10

L= 0.25

1/2 12.7

10.60

10.60

10.81

10.81

L= 0.25 Acero Inf.

L = 10.10

L= 0.25

1/2 12.7

10.60

10.60

10.81

10.81

L= 0.25 Acero Inf.

L = 10.10

L= 0.25

1/2 12.7

10.60

10.60

10.81

10.81

1/4 6.35

58

0.88

51.04

Estribos

L= 0.88

12.76

12.76

VIGAS EN SEGUNDO PISO


VS EJE A - A ENTRE ,EJE 2 - 7
L= 0.25 Acero Sup.

L = 15.75

L= 0.25

1/2 12.7

16.25

16.25

16.58

16.58

L= 0.25 Acero Sup.

L = 15.75

L= 0.25

1/2 12.7

16.25

16.25

16.58

16.58

L= 0.25 Acero Inf.

L = 15.75

L= 0.25

1/2 12.7

16.25

16.25

16.58

16.58

L= 0.25 Acero Inf.

L = 15.75

L= 0.25

1/2 12.7

16.25

16.25

16.58

16.58

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Estribos

Pulg.

L= 1.16

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

1/4 6.35

86

1.16

99.76

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

24.94

Peso Parcial Kg.

4.04K/m

24.94

VS EJE A - B ENTRE ,EJE 2 - 3


L= 0.25 Acero Sup.

L = 4.10

L= 0.25

1/2 12.7

4.60

4.60

4.69

4.69

L= 0.25 Acero Sup.

L = 4.10

L= 0.25

1/2 12.7

4.60

4.60

4.69

4.69

L= 0.25 Acero Inf.

L = 4.10

L= 0.25

1/2 12.7

4.60

4.60

4.69

4.69

L= 0.25 Acero Inf.

L = 4.10

L= 0.25

1/2 12.7

4.60

4.60

4.69

4.69

1/4 6.35

28

1.16

32.48

Estribos

L= 1.16

8.12

8.12

VS EJE A - B ENTRE ,EJE 4 - 5


L= 0.25 Acero Sup.

L = 2.40

L= 0.25

1/2 12.7

2.90

2.90

2.96

2.96

L= 0.25 Acero Sup.

L = 2.40

L= 0.25

1/2 12.7

2.90

2.90

2.96

2.96

L= 0.25 Acero Inf.

L = 2.40

L= 0.25

1/2 12.7

2.90

2.90

2.96

2.96

L= 0.25 Acero Inf.

L = 2.40

L= 0.25

1/2 12.7

2.90

2.90

2.96

2.96

1/4 6.35

20

1.16

23.20

1/2 12.7

17.05

17.05

Estribos

L= 1.16

5.80

5.80

VS EJE B - B , ENTRE ,EJE 2 - 7


L= 0.25 Acero Sup.

CURSO:COSTOS Y PRESUPUESTOS

L = 16.55

L= 0.25

17.39

17.39

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

L= 0.25 Acero Sup.

L = 16.55

L= 0.25

1/2 12.7

17.05

17.05

17.39

17.39

L= 0.25 Acero Inf.

L = 16.55

L= 0.25

1/2 12.7

17.05

17.05

17.39

17.39

L= 0.25 Acero Inf.

L = 16.55

L= 0.25

1/2 12.7

17.05

17.05

17.39

17.39

1/4 6.35

90

1.16

104.40

Estribos

L= 1.16

26.10

26.10

VS EJE C - D ENTRE ,EJE 1" - 7


L= 0.25 Acero Sup.

L = 19.25

L= 0.25

1/2 12.7

19.75

39.50

40.29

40.29

L= 0.25 Acero Sup.

L = 19.25

L= 0.25

1/2 12.7

19.75

39.50

40.29

40.29

L= 0.25 Acero Inf.

L = 19.25

L= 0.25

1/2 12.7

19.75

39.50

40.29

40.29

L= 0.25 Acero Inf.

L = 19.25

L= 0.25

1/2 12.7

19.75

39.50

40.29

40.29

1/4 6.35

104

1.16

241.28

Estribos

L= 1.16

60.32

60.32

VS EJE 4 - 5 ENTRE ,EJE A - D


L= 0.25 Acero Sup.

L = 10.10

L= 0.25

1/2 12.7

10.60

21.20

21.62

21.62

L= 0.20 Acero Sup.

L = 10.10

L= 0.20

1/2 12.7

10.50

21.00

21.42

21.42

L= 0.20 Acero Inf.

L = 10.10

L= 0.20

1/2 12.7

10.50

21.00

21.42

21.42

L= 0.20 Acero Inf.

L = 10.10

L= 0.20

1/2 12.7

10.50

21.00

21.42

21.42

1/4 6.35

58

1.16

134.56

Estribos

CURSO:COSTOS Y PRESUPUESTOS

L= 1.16

33.64

33.64

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

VA EJE 2" - 2 ENTRE ,EJE C - D


L= 0.15 Acero Sup.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

L= 0.15 Acero Sup.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

L= 0.15 Acero Inf.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

L= 0.15 Acero Inf.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

L= 0.15 Acero Inf.

L = 2.70

L= 0.15

1/2 12.7

3.00

6.00

6.12

6.12

1/4 6.35

21

0.68

28.56

Estribos

L= 0.68

7.14

7.14

VA EJE 3 - 3 ENTRE ,EJE A - D


L= 0.15 Acero Sup.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

L= 0.15 Acero Sup.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

L= 0.15 Acero Inf.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

L= 0.15 Acero Inf.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

L= 0.15 Acero Inf.

L = 6.35

L= 0.15

1/2 12.7

6.65

6.65

6.78

6.78

1/4 6.35

39

0.68

26.52

Estribos

L= 0.68

6.63

6.63

VA EJE 6 - 7 ENTRE ,EJE A - D


L= 0.15 Acero Sup.

L = 10.10

L= 0.15

1/2 12.7

10.40

20.80

21.22

21.22

L= 0.15 Acero Sup.

L = 10.10

L= 0.15

1/2 12.7

10.40

20.80

21.22

21.22

L= 0.15 Acero Inf.

L = 10.10

L= 0.15

1/2 12.7

10.40

20.80

21.22

21.22

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

L= 0.15 Acero Inf.

L = 10.10

L= 0.15

1/2 12.7

10.40

20.80

21.22

21.22

L= 0.15 Acero Inf.

L = 10.10

L= 0.15

1/2 12.7

10.40

20.80

21.22

21.22

1/4 6.35

58

0.68

78.88

12.7
12.7
12.7
12.7

1
1
1
1

1
1
1
1

7.80
7.80
7.80
7.80

7.80
7.80
7.80
7.80

1/4 6.35

44

0.88

38.72

Estribos

L= 0.68

V101 EJE 2- 2 ENTRE ,EJE A - C


L= 0.25 Acero Sup.
L = 7.30
L= 0.25 Acero Sup.
L = 7.30
L= 0.25 Acero Inf.
L = 7.30
L= 0.25 Acero Inf.
L = 7.30

Estribos

L= 0.25
L= 0.25
L= 0.25
L= 0.25

L= 0.88

1/2
1/2
1/2
1/2

19.72

19.72

7.96
7.96
7.96
7.96

7.96
7.96
7.96
7.96

9.68

9.68

V101 EJE 2" - 2 ENTRE ,EJE C- B volado


L= 0.25 Acero Sup.

L = 4.90

L= 0.25

1/2 12.7

5.40

5.40

5.51

5.51

L= 0.20 Acero Sup.

L = 4.90

L= 0.20

1/2 12.7

5.30

5.30

5.41

5.41

L= 0.20 Acero Inf.

L = 4.90

L= 0.20

1/2 12.7

5.30

5.30

5.41

5.41

L= 0.20 Acero Inf.

L = 4.90

L= 0.20

1/2 12.7

5.30

5.30

5.41

5.41

1/4 6.35

32

0.88

28.16

Estribos

L= 0.88

7.04

7.04

VB EJE 2" - 2 ENTRE EJE D - C volado


L= 0.15 Acero Sup.

L = 3.10

L= 0.15

5/8 15.875

3.40

3.40

5.44

5.44

L= 0.15 Acero Sup.

L = 3.10

L= 0.15

5/8 15.875

3.40

3.40

5.44

5.44

L= 0.15 Acero Inf.

L = 3.10

L= 0.15

5/8 15.875

3.40

3.40

5.44

5.44

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.
L= 0.15 Acero Inf.

Estribos

L = 3.10

Pulg.
L= 0.15

L= 0.48

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

5/8 15.875

3.40

3.40

3/8 9.525

23

0.48

11.04

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

5.44

5.44

6.40

6.40

VB EJE C - C ENTRE EJE 2" - 2


L= 0.15 Acero Sup.

L = 2.80

L= 0.15

3/4 19.05

3.10

3.10

7.01

7.01

L= 0.15 Acero Sup.

L = 2.80

L= 0.15

3/4 19.05

3.10

3.10

7.01

7.01

L= 0.15 Acero Sup.

L = 2.80

L= 0.15

5/8 15.875

3.10

3.10

L= 0.15 Acero Inf.

L = 2.80

L= 0.15

25.4

3.10

3.10

3/8 9.525

22

0.48

10.56

Estribos

L= 0.48

TOTAL

#REF!

4.96

4.96
12.52

6.12

12.52

6.12

(KG)

1909.80

#REF! #REF!
TRAMO 01

CURSO:COSTOS Y PRESUPUESTOS

L = 7.9

1/2 12.7

7.90

47.40

48.35

48.35

L = 6.19

1/2 12.7

6.19

37.14

37.88

37.88

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

L = 3.62

1/2 12.7

3.62

21.72

L = 1.12

3/8 9.525

16

1.12

17.92

1/2 12.7

11

3.53

38.83

39.61

39.61

1/2 12.7

11

3.42

37.62

38.37

38.37

1/2 12.7

7.31

43.86

44.74

44.74

1/2 12.7

8.12

48.72

49.69

49.69

L = 3.21

1/2 12.7

3.21

19.26

19.65

19.65

L = 2.2

1/2 12.7

2.20

13.20

13.46

13.46

1/2 12.7

12

1.12

26.88

27.42

27.42

L = 3.53

L = 3.42

22.15

1
4.04K/m

10.39

22.15

10.39

TRAMO 2

L = 7.31

L = 8.12

L = 1.12
Vigas de Apoyo en las Escaleras
L= 0.10 Acero Sup.

L = 2.32

L= 0.10

1/2 12.7

2.52

7.56

7.71

7.71

L= 0.10 Acero Sup.

L = 2.32

L= 0.10

1/2 12.7

2.52

7.56

7.71

7.71

L= 0.10 Acero Inf.

L = 2.32

L= 0.10

1/2 12.7

2.52

7.56

7.71

7.71

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.
L= 0.10 Acero Inf.

Estribos

Pulg.

L = 2.32

L= 0.10

L= 1.16

TOTAL

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

1/2 12.7

2.52

7.56

1/4 6.35

19

1.16

66.12

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

7.71

16.53

#REF!

Peso Parcial Kg.

4.04K/m

7.71

16.53

(KG)

399.09

METRADO DE LOSA ALIGERADA FY=210KG/CM2


Primer Nivel
EJE 1" - 2 ENTRE EJE C - D

A1

Acero Inf.

L = 2.63

1/2 12.7

2.63

15.78

16.10

16.10

L= 0.20 Acero Sup.

L = 1.02

1/2 12.7

1.22

7.32

7.47

7.47

Acero Sup.

L = 1.02

1/2 12.7

1.22

7.32

7.47

7.47

Acero Tem.

L = 2.50

1/4 6.35

2.50

22.50

5.63

5.63

1/4 6.35

10

0.37

22.20

5.55

5.55

1/2 12.7

11

7.88

86.68

88.41

88.41

1/2 12.7

11

2.70

29.70

30.29

30.29

L= 0.20

L = 0.37

A2
L= 0.20 Acero Inf.

L = 7.48

Acero Inf.

L = 2.70

CURSO:COSTOS Y PRESUPUESTOS

L= 0.20

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.
L= 0.20 Acero Sup.

L = 0.82

Acero Sup.

L = 2.52

Acero Sup.

Acero Tem.

Pulg.

Vez

Parcial Sub Total

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

11

1.02

11.22

11.44

11.44

1/2 12.7

11

2.72

29.92

30.52

30.52

L = 2.05

1/2 12.7

11

2.05

22.55

23.00

23.00

L = 3.95

1/4 6.35

29

3.95

114.55

28.64

28.64

1/4 6.35

11

29

0.37

118.03

29.51

29.51

1/2 12.7

17

6.01

102.17

104.21

104.21

1/2 12.7

17

7.89

134.13

136.81

136.81

1/2 12.7

17

1.02

17.34

17.69

17.69

1/2 12.7

17

1.52

25.84

26.36

26.36

L= 0.20

EJE 3 - 3, 4 -4,5-5,6-6,7-7 ENTRE EJE A - D


L= 0.20 Acero Inf.

L = 5.81

Acero Inf.

L = 7.69

L= 0.20

L= 0.20 Acero Sup.

L = 0.82

Acero Sup.

L = 1.32

Acero Sup.

L = 2.05

1/2 12.7

17

2.05

69.70

71.09

71.09

Acero Sup.

L = 2.55

1/2 12.7

17

2.55

86.70

88.43

88.43

Acero Tem.

L = 8.50

1/4 6.35

39

8.50

331.50

82.88

82.88

1/4 6.35

17

39

0.37

245.31

61.33

61.33

L= 0.20

L = 0.37

A4

Longitud (m)

1/2 12.7

L = 0.37

A3

mm.

N
Piezas
Veces

EJE 4-4, 5-5, 6-6 ENTRE EJE A-B-C

Acero Inf.

L = 3.28

1/2 12.7

3.28

19.68

20.07

20.07

Acero Sup.

L = 3.40

1/2 12.7

3.40

20.40

20.81

20.81

Acero Tem.

L = 2.70

1/4 6.35

10

2.70

27.00

CURSO:COSTOS Y PRESUPUESTOS

6.75

6.75

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.
L = 0.37

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

1/4 6.35

12

0.37

26.64

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

6.66

Peso Parcial Kg.

4.04K/m

6.66

Segundo Nivel

A5

EJE 1 - 1, 2 -2 ENTRE EJE A - H

Acero Inf.

L = 3.67

1/2 12.7

3.67

18.35

18.72

18.72

Acero Sup.

L = 3.67

1/2 12.7

3.67

18.35

18.72

18.72

Acero Tem.

L = 2.25

1/4 6.35

11

2.25

24.75

6.19

6.19

1/4 6.35

14

0.37

25.90

6.48

6.48

L = 0.37

Acero Inf.

L = 3.07

1/2 12.7

3.07

21.49

21.92

21.92

Acero Sup.

L = 3.07

1/2 12.7

3.07

21.49

21.92

21.92

Acero Tem.

L = 4.60

1/4 6.35

135

4.60

621.00

155.25

155.25

1/4 6.35

28

0.37

72.52

18.13

18.13

1/2 12.7

3.07

24.56

25.05

25.05

1/2 12.7

3.07

24.56

25.05

25.05

1/4 6.35

10

0.37

29.60

1/2 12.7

1.97

11.82

12.06

12.06

1/2 12.7

1.97

11.82

12.06

12.06

1/4 6.35

0.37

13.32

L = 0.37

A2
pendiente

EJE 2-3 ENTRE EJE B - D


L= 0.20 Acero Inf.

L = 2.87

Acero Inf.

L = 2.87

L= 0.20
L = 0.37

ZONA escalera

L= 0.20 Acero Sup.

Acero Inf.

L = 1.77
L = 1.77

L= 0.20

L = 0.37
CURSO:COSTOS Y PRESUPUESTOS

7.40

3.33

7.40

3.33

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

TRAMO 2
L= 0.20 Acero Inf.

L = 7.48

1/2 12.7

11

7.88

86.68

88.41

88.41

Acero Inf.

L = 2.70

1/2 12.7

11

2.70

29.70

30.29

30.29

L= 0.20 Acero Sup.

L = 0.82

1/2 12.7

11

1.02

11.22

11.44

11.44

Acero Sup.

L = 2.05

1/2 12.7

11

2.05

22.55

23.00

23.00

Acero Tem.

L = 3.95

1/4 6.35

29

3.95

114.55

28.64

28.64

1/4 6.35

11

29

0.37

118.03

29.51

29.51

1/2 12.7

17

6.01

102.17

104.21

104.21

1/2 12.7

17

7.89

134.13

136.81

136.81

1/2 12.7

17

1.02

17.34

17.69

17.69

1/2 12.7

17

1.52

25.84

26.36

26.36

L= 0.20

L = 0.37

A3

EJE 3-3, 4-4, 5-5, 6-6,7-7 ENTRE EJE A - D


L= 0.20 Acero Inf.

L = 5.81

Acero Inf.

L = 7.69

L= 0.20

L= 0.20 Acero Sup.

L = 0.82

Acero Sup.

L = 1.32

Acero Sup.

L = 2.05

1/2 12.7

17

2.05

69.70

71.09

71.09

Acero Sup.

L = 2.55

1/2 12.7

17

2.55

86.70

88.43

88.43

Acero Tem.

L = 8.50

1/4 6.35

39

8.50

331.50

82.88

82.88

1/4 6.35

17

39

0.37

245.31

61.33

61.33

L= 0.20

L = 0.37

CURSO:COSTOS Y PRESUPUESTOS

UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"

CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL

HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015

Hecho Por
Revisado Por
HOJA:
N 1

Diametro

Partida

OBS.
A4

Pulg.

mm.

Longitud (m)

Vez

Parcial Sub Total

N
Piezas
Veces

Acero
1/4

3/8

1/2

5/8

3/4

0.25K/m

0.58K/m

1.02K/m

1.60K/m

2.26K/m

Peso Parcial Kg.

4.04K/m

EJE 4-4, 5-5, 6-6 ENTRE EJE A-B-C

Acero Inf.

L = 3.28

1/2 12.7

3.28

19.68

20.07

20.07

Acero Sup.

L = 3.40

1/2 12.7

3.40

20.40

20.81

20.81

Acero Tem.

L = 2.70

1/4 6.35

10

2.70

27.00

6.75

6.75

1/4 6.35

12

0.37

26.64

6.66

6.66

L = 0.37

TOTAL

CURSO:COSTOS Y PRESUPUESTOS

LOSA ALIGERADA

(KG)

2164.28