CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.46
1/2 12.7
0.46
3.68
3.75
3.75
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.46
1/2 12.7
0.46
3.68
3.75
3.75
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.46
1/2 12.7
0.46
3.68
3.75
3.75
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.46
1/2 12.7
0.46
3.68
3.75
3.75
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.46
1/2 12.7
0.46
3.68
3.75
3.75
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.46
1/2 12.7
0.46
3.68
3.75
3.75
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.46
1/2 12.7
0.46
3.68
3.75
3.75
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.76
1/2 12.7
0.76
9.12
9.30
9.30
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.76
1/2 12.7
0.76
9.12
9.30
9.30
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.76
1/2 12.7
0.76
9.12
9.30
9.30
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.76
1/2 12.7
0.76
9.12
9.30
9.30
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
L = 0.76
1/2 12.7
0.76
9.12
9.30
9.30
L = 1.06
1/2 12.7
1.06
16.96
17.30
17.30
ZAPATA N 2
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
L = 0.76
TOTAL
#REF!
Pulg.
mm.
1/2 12.7
Longitud (m)
Vez
N
Piezas
Veces
0.76
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
9.12
9.30
(KG)
4.04K/m
9.30
306.98
#REF!
Columnas de 0.15x.0.45 (C-1)
Eje 1-1 , Entre Ejes A - C - D
JARDIN
L= 0.25
L = 4.10
1/2 12.7
4.35
17.40
17.75
17.75
L= 0.25
L= 0.25
L= 0.25
L = 4.10
L = 4.10
L = 4.10
1/2 12.7
1/2 12.7
1/2 12.7
4
4
4
1
1
1
4.35
4.35
4.35
17.40
17.40
17.40
17.75
17.75
17.75
17.75
17.75
17.75
L= 0.25
L = 4.10
3/8 9.525
4.35
17.40
10.09
10.09
L= 0.25
L = 4.10
3/8 9.525
4.35
17.40
10.09
10.09
1/4 6.35
70
0.79
221.20
L = 4.35
1/2 12.7
4.35
8.70
8.87
8.87
L = 4.35
1/2 12.7
4.35
8.70
8.87
8.87
L = 4.35
1/2 12.7
4.35
8.70
8.87
8.87
L = 4.35
1/2 12.7
4.35
8.70
8.87
8.87
L = 4.35
3/8 9.525
4.35
8.70
5.05
5.05
L = 4.35
3/8 9.525
4.35
8.70
5.05
5.05
Estribos
L= 0.79
55.30
55.30
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Estribos
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
1/4 6.35
70
0.79
110.60
L = 7.65
1/2 12.7
12
7.65
91.80
93.64
93.64
L = 7.56
1/2 12.7
12
7.56
90.72
92.53
92.53
L = 7.65
1/2 12.7
12
7.65
91.80
93.64
93.64
L = 7.65
1/2 12.7
12
7.65
91.80
93.64
93.64
L = 7.65
3/8 9.525
12
7.65
91.80
53.24
53.24
L = 7.65
3/8 9.525
12
7.65
91.80
53.24
53.24
3/8 9.525
12
112
0.79
1061.76
615.82
615.82
L= 0.79
27.65
1
4.04K/m
27.65
Estribos
L= 0.79
L = 7.65
1/2 12.7
12
7.65
91.80
93.64
93.64
Acero Sup.
L = 7.65
1/2 12.7
12
7.65
91.80
93.64
93.64
Acero Sup.
L = 7.65
1/2 12.7
12
7.65
91.80
93.64
93.64
Acero Inf.
L = 7.65
1/2 12.7
12
7.65
91.80
93.64
93.64
Acero Inf.
L = 7.65
3/8 9.525
12
7.65
91.80
53.24
53.24
Acero Inf.
L = 7.65
3/8 9.525
12
7.65
91.80
53.24
53.24
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Estribos
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
3/8 9.525
12
112
0.79
1061.76
L = 4.35
1/2 12.7
4.35
13.05
13.31
13.31
L = 4.35
1/2 12.7
4.35
13.05
13.31
13.31
L = 4.35
1/2 12.7
4.35
13.05
13.31
13.31
L = 4.35
1/2 12.7
4.35
13.05
13.31
13.31
1/4 6.35
30
0.80
72.00
L = 4.35
1/2 12.7
4.35
8.70
8.87
8.87
L = 4.35
1/2 12.7
4.35
8.70
8.87
8.87
L = 4.35
1/2 12.7
4.35
8.70
8.87
8.87
L = 4.35
1/2 12.7
4.35
8.70
8.87
8.87
1/4 6.35
30
0.80
48.00
L= 0.79
615.82
1
4.04K/m
615.82
Estribos
L= 0.80
18.00
18.00
Estribos
CURSO:COSTOS Y PRESUPUESTOS
L= 0.80
12.00
12.00
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
Estribos
L = 4.35
1/2 12.7
4.35
17.40
17.75
17.75
L = 4.35
1/2 12.7
4.35
17.40
17.75
17.75
L = 4.35
1/2 12.7
4.35
17.40
17.75
17.75
L = 4.35
1/2 12.7
4.35
17.40
17.75
17.75
1/4 6.35
30
0.80
96.00
L= 0.80
TOTAL
#REF!
24.00
24.00
(KG)
2626.05
#REF! #REF!
Viga VS ( EJE A - A, ENTRE 2 - 7
L= 0.25 Acero Sup.
L = 15.75
L= 0.25
1/2 12.7
16.25
16.25
16.58
16.58
L = 15.75
L= 0.25
1/2 12.7
16.25
16.25
16.58
16.58
L = 15.75
L= 0.25
1/2 12.7
16.25
16.25
16.58
16.58
L = 15.75
L= 0.25
1/2 12.7
16.25
16.25
16.58
16.58
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Estribos
Pulg.
L= 1.16
mm.
Longitud (m)
Vez
N
Piezas
Veces
1/4 6.35
86
1.16
99.76
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
24.94
4.04K/m
24.94
L = 4.10
L= 0.25
1/2 12.7
4.60
4.60
4.69
4.69
L = 4.10
L= 0.25
1/2 12.7
4.60
4.60
4.69
4.69
L = 4.10
L= 0.25
1/2 12.7
4.60
4.60
4.69
4.69
L = 4.10
L= 0.25
1/2 12.7
4.60
4.60
4.69
4.69
1/4 6.35
28
1.16
32.48
Estribos
L= 1.16
8.12
8.12
L = 2.40
L= 0.25
1/2 12.7
2.90
2.90
2.96
2.96
L = 2.40
L= 0.25
1/2 12.7
2.90
2.90
2.96
2.96
L = 2.40
L= 0.25
1/2 12.7
2.90
2.90
2.96
2.96
L = 2.40
L= 0.25
1/2 12.7
2.90
2.90
2.96
2.96
1/4 6.35
20
1.16
23.20
Estribos
L= 1.16
CURSO:COSTOS Y PRESUPUESTOS
5.80
5.80
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
L = 16.55
L= 0.25
1/2 12.7
17.05
17.05
17.39
17.39
L = 16.55
L= 0.25
1/2 12.7
17.05
17.05
17.39
17.39
L = 16.55
L= 0.25
1/2 12.7
17.05
17.05
17.39
17.39
L = 16.55
L= 0.25
1/2 12.7
17.05
17.05
17.39
17.39
1/4 6.35
90.25
1.16
104.69
Estribos
L= 1.16
26.17
26.17
L = 19.25
L= 0.25
1/2 12.7
19.75
39.50
40.29
40.29
L = 19.25
L= 0.25
1/2 12.7
19.75
39.50
40.29
40.29
L = 19.25
L= 0.25
1/2 12.7
19.75
39.50
40.29
40.29
L = 19.25
L= 0.25
1/2 12.7
19.75
39.50
40.29
40.29
1/4 6.35
104
1.16
241.28
Estribos
L= 1.16
60.32
60.32
L = 3.80
L= 0.25
1/2 12.7
4.30
4.30
4.39
4.39
L = 3.80
L= 0.25
1/2 12.7
4.30
4.30
4.39
4.39
L = 3.80
L= 0.25
1/2 12.7
4.30
4.30
4.39
4.39
L = 3.80
L= 0.25
1/2 12.7
4.30
4.30
4.39
4.39
1/4 6.35
27
1.16
62.64
Estribos
CURSO:COSTOS Y PRESUPUESTOS
L= 1.16
15.66
15.66
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
L = 10.10
L= 0.25
1/2 12.7
10.60
31.80
32.44
32.44
L = 10.10
L= 0.25
1/2 12.7
10.60
31.80
32.44
32.44
L = 10.10
L= 0.25
1/2 12.7
10.60
31.80
32.44
32.44
L = 10.10
L= 0.25
1/2 12.7
10.60
31.80
32.44
32.44
1/4 6.35
58
1.16
201.84
Estribos
L= 1.16
50.46
50.46
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
1/4 6.35
21
0.68
28.56
Estribos
CURSO:COSTOS Y PRESUPUESTOS
L= 0.68
7.14
7.14
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
1/4 6.35
39
0.68
26.52
Estribos
L= 0.68
6.63
6.63
L = 10.10
L= 0.15
1/2 12.7
10.40
10.40
10.61
10.61
L = 10.10
L= 0.15
1/2 12.7
10.40
10.40
10.61
10.61
L = 10.10
L= 0.15
1/2 12.7
10.40
10.40
10.61
10.61
L = 10.10
L= 0.15
1/2 12.7
10.40
10.40
10.61
10.61
1/4 6.35
58
0.68
39.44
Estribos
L= 0.68
9.86
9.86
L = 10.10
L= 0.25
1/2 12.7
10.60
10.60
10.81
10.81
L = 10.10
L= 0.25
1/2 12.7
10.60
10.60
10.81
10.81
L = 10.10
L= 0.25
1/2 12.7
10.60
10.60
10.81
10.81
L = 10.10
L= 0.25
1/2 12.7
10.60
10.60
10.81
10.81
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Estribos
Pulg.
L= 0.88
mm.
Longitud (m)
Vez
N
Piezas
Veces
1/4 6.35
58
0.88
51.04
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
12.76
4.04K/m
12.76
L = 2.70
L= 0.25
1/2 12.7
3.20
3.20
3.26
3.26
L = 2.70
L= 0.25
1/2 12.7
3.20
3.20
3.26
3.26
L = 2.70
L= 0.25
1/2 12.7
3.20
3.20
3.26
3.26
L = 2.70
L= 0.25
1/2 12.7
3.20
3.20
3.26
3.26
1/4 6.35
21
0.88
18.48
Estribos
L= 0.88
4.62
4.62
L = 4.90
L= 0.25
1/2 12.7
5.40
5.40
5.51
5.51
L = 4.90
L= 0.25
1/2 12.7
5.40
5.40
5.51
5.51
L = 4.90
L= 0.25
1/2 12.7
5.40
5.40
5.51
5.51
L = 4.90
L= 0.25
1/2 12.7
5.40
5.40
5.51
5.51
1/4 6.35
32
0.88
28.16
1/2 12.7
7.80
7.80
Estribos
L= 0.88
7.04
7.04
CURSO:COSTOS Y PRESUPUESTOS
L = 7.30
L= 0.25
7.96
7.96
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
L = 7.30
L= 0.25
1/2 12.7
7.80
7.80
7.96
7.96
L = 7.30
L= 0.25
1/2 12.7
7.80
7.80
7.96
7.96
L = 7.30
L= 0.25
1/2 12.7
7.80
7.80
7.96
7.96
1/4 6.35
44
0.88
38.72
Estribos
L= 0.88
9.68
9.68
L = 10.10
L= 0.25
1/2 12.7
10.60
10.60
10.81
10.81
L = 10.10
L= 0.25
1/2 12.7
10.60
10.60
10.81
10.81
L = 10.10
L= 0.25
1/2 12.7
10.60
10.60
10.81
10.81
L = 10.10
L= 0.25
1/2 12.7
10.60
10.60
10.81
10.81
1/4 6.35
58
0.88
51.04
Estribos
L= 0.88
12.76
12.76
L = 15.75
L= 0.25
1/2 12.7
16.25
16.25
16.58
16.58
L = 15.75
L= 0.25
1/2 12.7
16.25
16.25
16.58
16.58
L = 15.75
L= 0.25
1/2 12.7
16.25
16.25
16.58
16.58
L = 15.75
L= 0.25
1/2 12.7
16.25
16.25
16.58
16.58
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Estribos
Pulg.
L= 1.16
mm.
Longitud (m)
Vez
N
Piezas
Veces
1/4 6.35
86
1.16
99.76
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
24.94
4.04K/m
24.94
L = 4.10
L= 0.25
1/2 12.7
4.60
4.60
4.69
4.69
L = 4.10
L= 0.25
1/2 12.7
4.60
4.60
4.69
4.69
L = 4.10
L= 0.25
1/2 12.7
4.60
4.60
4.69
4.69
L = 4.10
L= 0.25
1/2 12.7
4.60
4.60
4.69
4.69
1/4 6.35
28
1.16
32.48
Estribos
L= 1.16
8.12
8.12
L = 2.40
L= 0.25
1/2 12.7
2.90
2.90
2.96
2.96
L = 2.40
L= 0.25
1/2 12.7
2.90
2.90
2.96
2.96
L = 2.40
L= 0.25
1/2 12.7
2.90
2.90
2.96
2.96
L = 2.40
L= 0.25
1/2 12.7
2.90
2.90
2.96
2.96
1/4 6.35
20
1.16
23.20
1/2 12.7
17.05
17.05
Estribos
L= 1.16
5.80
5.80
CURSO:COSTOS Y PRESUPUESTOS
L = 16.55
L= 0.25
17.39
17.39
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
L = 16.55
L= 0.25
1/2 12.7
17.05
17.05
17.39
17.39
L = 16.55
L= 0.25
1/2 12.7
17.05
17.05
17.39
17.39
L = 16.55
L= 0.25
1/2 12.7
17.05
17.05
17.39
17.39
1/4 6.35
90
1.16
104.40
Estribos
L= 1.16
26.10
26.10
L = 19.25
L= 0.25
1/2 12.7
19.75
39.50
40.29
40.29
L = 19.25
L= 0.25
1/2 12.7
19.75
39.50
40.29
40.29
L = 19.25
L= 0.25
1/2 12.7
19.75
39.50
40.29
40.29
L = 19.25
L= 0.25
1/2 12.7
19.75
39.50
40.29
40.29
1/4 6.35
104
1.16
241.28
Estribos
L= 1.16
60.32
60.32
L = 10.10
L= 0.25
1/2 12.7
10.60
21.20
21.62
21.62
L = 10.10
L= 0.20
1/2 12.7
10.50
21.00
21.42
21.42
L = 10.10
L= 0.20
1/2 12.7
10.50
21.00
21.42
21.42
L = 10.10
L= 0.20
1/2 12.7
10.50
21.00
21.42
21.42
1/4 6.35
58
1.16
134.56
Estribos
CURSO:COSTOS Y PRESUPUESTOS
L= 1.16
33.64
33.64
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
L = 2.70
L= 0.15
1/2 12.7
3.00
6.00
6.12
6.12
1/4 6.35
21
0.68
28.56
Estribos
L= 0.68
7.14
7.14
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
L = 6.35
L= 0.15
1/2 12.7
6.65
6.65
6.78
6.78
1/4 6.35
39
0.68
26.52
Estribos
L= 0.68
6.63
6.63
L = 10.10
L= 0.15
1/2 12.7
10.40
20.80
21.22
21.22
L = 10.10
L= 0.15
1/2 12.7
10.40
20.80
21.22
21.22
L = 10.10
L= 0.15
1/2 12.7
10.40
20.80
21.22
21.22
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
L = 10.10
L= 0.15
1/2 12.7
10.40
20.80
21.22
21.22
L = 10.10
L= 0.15
1/2 12.7
10.40
20.80
21.22
21.22
1/4 6.35
58
0.68
78.88
12.7
12.7
12.7
12.7
1
1
1
1
1
1
1
1
7.80
7.80
7.80
7.80
7.80
7.80
7.80
7.80
1/4 6.35
44
0.88
38.72
Estribos
L= 0.68
Estribos
L= 0.25
L= 0.25
L= 0.25
L= 0.25
L= 0.88
1/2
1/2
1/2
1/2
19.72
19.72
7.96
7.96
7.96
7.96
7.96
7.96
7.96
7.96
9.68
9.68
L = 4.90
L= 0.25
1/2 12.7
5.40
5.40
5.51
5.51
L = 4.90
L= 0.20
1/2 12.7
5.30
5.30
5.41
5.41
L = 4.90
L= 0.20
1/2 12.7
5.30
5.30
5.41
5.41
L = 4.90
L= 0.20
1/2 12.7
5.30
5.30
5.41
5.41
1/4 6.35
32
0.88
28.16
Estribos
L= 0.88
7.04
7.04
L = 3.10
L= 0.15
5/8 15.875
3.40
3.40
5.44
5.44
L = 3.10
L= 0.15
5/8 15.875
3.40
3.40
5.44
5.44
L = 3.10
L= 0.15
5/8 15.875
3.40
3.40
5.44
5.44
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
L= 0.15 Acero Inf.
Estribos
L = 3.10
Pulg.
L= 0.15
L= 0.48
mm.
Longitud (m)
Vez
N
Piezas
Veces
5/8 15.875
3.40
3.40
3/8 9.525
23
0.48
11.04
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
5.44
5.44
6.40
6.40
L = 2.80
L= 0.15
3/4 19.05
3.10
3.10
7.01
7.01
L = 2.80
L= 0.15
3/4 19.05
3.10
3.10
7.01
7.01
L = 2.80
L= 0.15
5/8 15.875
3.10
3.10
L = 2.80
L= 0.15
25.4
3.10
3.10
3/8 9.525
22
0.48
10.56
Estribos
L= 0.48
TOTAL
#REF!
4.96
4.96
12.52
6.12
12.52
6.12
(KG)
1909.80
#REF! #REF!
TRAMO 01
CURSO:COSTOS Y PRESUPUESTOS
L = 7.9
1/2 12.7
7.90
47.40
48.35
48.35
L = 6.19
1/2 12.7
6.19
37.14
37.88
37.88
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
L = 3.62
1/2 12.7
3.62
21.72
L = 1.12
3/8 9.525
16
1.12
17.92
1/2 12.7
11
3.53
38.83
39.61
39.61
1/2 12.7
11
3.42
37.62
38.37
38.37
1/2 12.7
7.31
43.86
44.74
44.74
1/2 12.7
8.12
48.72
49.69
49.69
L = 3.21
1/2 12.7
3.21
19.26
19.65
19.65
L = 2.2
1/2 12.7
2.20
13.20
13.46
13.46
1/2 12.7
12
1.12
26.88
27.42
27.42
L = 3.53
L = 3.42
22.15
1
4.04K/m
10.39
22.15
10.39
TRAMO 2
L = 7.31
L = 8.12
L = 1.12
Vigas de Apoyo en las Escaleras
L= 0.10 Acero Sup.
L = 2.32
L= 0.10
1/2 12.7
2.52
7.56
7.71
7.71
L = 2.32
L= 0.10
1/2 12.7
2.52
7.56
7.71
7.71
L = 2.32
L= 0.10
1/2 12.7
2.52
7.56
7.71
7.71
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
L= 0.10 Acero Inf.
Estribos
Pulg.
L = 2.32
L= 0.10
L= 1.16
TOTAL
mm.
Longitud (m)
Vez
N
Piezas
Veces
1/2 12.7
2.52
7.56
1/4 6.35
19
1.16
66.12
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
7.71
16.53
#REF!
4.04K/m
7.71
16.53
(KG)
399.09
A1
Acero Inf.
L = 2.63
1/2 12.7
2.63
15.78
16.10
16.10
L = 1.02
1/2 12.7
1.22
7.32
7.47
7.47
Acero Sup.
L = 1.02
1/2 12.7
1.22
7.32
7.47
7.47
Acero Tem.
L = 2.50
1/4 6.35
2.50
22.50
5.63
5.63
1/4 6.35
10
0.37
22.20
5.55
5.55
1/2 12.7
11
7.88
86.68
88.41
88.41
1/2 12.7
11
2.70
29.70
30.29
30.29
L= 0.20
L = 0.37
A2
L= 0.20 Acero Inf.
L = 7.48
Acero Inf.
L = 2.70
CURSO:COSTOS Y PRESUPUESTOS
L= 0.20
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
L= 0.20 Acero Sup.
L = 0.82
Acero Sup.
L = 2.52
Acero Sup.
Acero Tem.
Pulg.
Vez
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
11
1.02
11.22
11.44
11.44
1/2 12.7
11
2.72
29.92
30.52
30.52
L = 2.05
1/2 12.7
11
2.05
22.55
23.00
23.00
L = 3.95
1/4 6.35
29
3.95
114.55
28.64
28.64
1/4 6.35
11
29
0.37
118.03
29.51
29.51
1/2 12.7
17
6.01
102.17
104.21
104.21
1/2 12.7
17
7.89
134.13
136.81
136.81
1/2 12.7
17
1.02
17.34
17.69
17.69
1/2 12.7
17
1.52
25.84
26.36
26.36
L= 0.20
L = 5.81
Acero Inf.
L = 7.69
L= 0.20
L = 0.82
Acero Sup.
L = 1.32
Acero Sup.
L = 2.05
1/2 12.7
17
2.05
69.70
71.09
71.09
Acero Sup.
L = 2.55
1/2 12.7
17
2.55
86.70
88.43
88.43
Acero Tem.
L = 8.50
1/4 6.35
39
8.50
331.50
82.88
82.88
1/4 6.35
17
39
0.37
245.31
61.33
61.33
L= 0.20
L = 0.37
A4
Longitud (m)
1/2 12.7
L = 0.37
A3
mm.
N
Piezas
Veces
Acero Inf.
L = 3.28
1/2 12.7
3.28
19.68
20.07
20.07
Acero Sup.
L = 3.40
1/2 12.7
3.40
20.40
20.81
20.81
Acero Tem.
L = 2.70
1/4 6.35
10
2.70
27.00
CURSO:COSTOS Y PRESUPUESTOS
6.75
6.75
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
L = 0.37
mm.
Longitud (m)
Vez
N
Piezas
Veces
1/4 6.35
12
0.37
26.64
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
6.66
4.04K/m
6.66
Segundo Nivel
A5
Acero Inf.
L = 3.67
1/2 12.7
3.67
18.35
18.72
18.72
Acero Sup.
L = 3.67
1/2 12.7
3.67
18.35
18.72
18.72
Acero Tem.
L = 2.25
1/4 6.35
11
2.25
24.75
6.19
6.19
1/4 6.35
14
0.37
25.90
6.48
6.48
L = 0.37
Acero Inf.
L = 3.07
1/2 12.7
3.07
21.49
21.92
21.92
Acero Sup.
L = 3.07
1/2 12.7
3.07
21.49
21.92
21.92
Acero Tem.
L = 4.60
1/4 6.35
135
4.60
621.00
155.25
155.25
1/4 6.35
28
0.37
72.52
18.13
18.13
1/2 12.7
3.07
24.56
25.05
25.05
1/2 12.7
3.07
24.56
25.05
25.05
1/4 6.35
10
0.37
29.60
1/2 12.7
1.97
11.82
12.06
12.06
1/2 12.7
1.97
11.82
12.06
12.06
1/4 6.35
0.37
13.32
L = 0.37
A2
pendiente
L = 2.87
Acero Inf.
L = 2.87
L= 0.20
L = 0.37
ZONA escalera
Acero Inf.
L = 1.77
L = 1.77
L= 0.20
L = 0.37
CURSO:COSTOS Y PRESUPUESTOS
7.40
3.33
7.40
3.33
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
TRAMO 2
L= 0.20 Acero Inf.
L = 7.48
1/2 12.7
11
7.88
86.68
88.41
88.41
Acero Inf.
L = 2.70
1/2 12.7
11
2.70
29.70
30.29
30.29
L = 0.82
1/2 12.7
11
1.02
11.22
11.44
11.44
Acero Sup.
L = 2.05
1/2 12.7
11
2.05
22.55
23.00
23.00
Acero Tem.
L = 3.95
1/4 6.35
29
3.95
114.55
28.64
28.64
1/4 6.35
11
29
0.37
118.03
29.51
29.51
1/2 12.7
17
6.01
102.17
104.21
104.21
1/2 12.7
17
7.89
134.13
136.81
136.81
1/2 12.7
17
1.02
17.34
17.69
17.69
1/2 12.7
17
1.52
25.84
26.36
26.36
L= 0.20
L = 0.37
A3
L = 5.81
Acero Inf.
L = 7.69
L= 0.20
L = 0.82
Acero Sup.
L = 1.32
Acero Sup.
L = 2.05
1/2 12.7
17
2.05
69.70
71.09
71.09
Acero Sup.
L = 2.55
1/2 12.7
17
2.55
86.70
88.43
88.43
Acero Tem.
L = 8.50
1/4 6.35
39
8.50
331.50
82.88
82.88
1/4 6.35
17
39
0.37
245.31
61.33
61.33
L= 0.20
L = 0.37
CURSO:COSTOS Y PRESUPUESTOS
UNIVERSIDAD ANDINA
"NESTOR CACERES VELASQUEZ"
CARRERA ACADEMICO
PROFESIONAL DE INGENIERIA CIVIL
HOJA DE METRADOS
Obra
: VIVIENDA MULTIFAMILIAR
Propietar:
Fecha : 30 DE ABRIL DEL 2015
Hecho Por
Revisado Por
HOJA:
N 1
Diametro
Partida
OBS.
A4
Pulg.
mm.
Longitud (m)
Vez
N
Piezas
Veces
Acero
1/4
3/8
1/2
5/8
3/4
0.25K/m
0.58K/m
1.02K/m
1.60K/m
2.26K/m
4.04K/m
Acero Inf.
L = 3.28
1/2 12.7
3.28
19.68
20.07
20.07
Acero Sup.
L = 3.40
1/2 12.7
3.40
20.40
20.81
20.81
Acero Tem.
L = 2.70
1/4 6.35
10
2.70
27.00
6.75
6.75
1/4 6.35
12
0.37
26.64
6.66
6.66
L = 0.37
TOTAL
CURSO:COSTOS Y PRESUPUESTOS
LOSA ALIGERADA
(KG)
2164.28