LOSAS
TRADICIONALES
Y
LOSAS NERVADAS

LOSA PREFABRICADA

COMPONENTES DEL SISTEMA


BOVEDILLA
ELECTROMALLA
ACERO 6.20mm Y 4.50mm
VIGUETA DE CONCRETO

BOVEDILLA
LA BOVEDILLA ES UN RELLENO SEGURO,
DISEADO PARA SOPORTAR DIFERENTES
TEMPERATURAS.
SE UTILIZA EN 3 DIFERENTES MEDIDAS
BOVEDILLA
DE 0.10 mts
DE 0.15 mts
DE 0.20 mts

ESPESOR DE LOSA TERMINADA


t=0.15
t=0.20
t=0.25

ELECTROMALLA
SE UTILIZA EN LA CAPA DE FUNDICION DE
5 CM. COMO REFUERZO DE TEMPERATURA PARA
EVITAR QUE ESTA SE AGRIETE.
PUEDE SER DE:
6X6 9/9 CORRUGADA
6X6 10/10 LISA
U OTRO A DISPOCISION DEL CLIENTE
SOBRE PEDIDO

ACERO
6.20mm (PARA RIGIDIZANTES Y BASTONES)
RIGIDIZANTES: SE ARMA PERPENDICULAR A LAS
VIGUETAS, ES LO QUE CONOCEMOS COMO UNA
COSTILLA Y SU FUNCION ES CONTRIBUIR A QUE
LAS VIGUETAS NO SE DEFLECTEN Y SE COLOCA A
UNA DISTANCIA MAXIMA DE 1.50 MT.
BASTONES: SIRVEN PARA ENGRAPAR NUESTRA
LOSA A LA SOLERA DE CORONA, DANDO LUGAR A
REFORZAR LAS PARTES DE UNION ENTRE LA
SOLERA Y LAS VIGUETAS.

ACERO
4.50mm (PARA RIGIDIZANTES)
ES NECESARIO PARA EL ARMADO DE LOS
RIGIDIZANTES O COSTILLAS, SE DEBE DE UTILIZAR
COMO ESLABONES.

VIGUETA
ESTE ES EL ELEMENTO QUE SOPORTA LAS
DIFERENTES CARGAS (PESO PROPIO, ACABADOS,
CARGA VIVA).
LAS VIGUETAS ESTAN FORMADAS POR UNA
PASTILLA DE CONCRETO DE 12 X 5 centimetros Y
UNA ARMADURA DE ACERO DE ALTA RESISTENCIA.

CARGAS
PESO PROPIO: ES EL PESO DE LA LOSA
UNA VEZ FUNDIDA.
LOSA TERMINADA DE:
15 CM ES DE 240 KG/MT2
20 CM ES DE 320 KG/MT2
25 CM ES DE 400 KG/MT2

CARGA VIVA
CARGA VIVA:
ES LA PRODUCIDA POR LAS PERSONAS
PARA ENTREPISOS SE CONSIDERA 200 KG/MT2
PARA TECHOS SE CONSIDERA 100 KG/MT2

ACABADOS
AQU SE CONSIDERAN:
RELLENOS PARA NIVELAR PISOS,
REPELLOS Y CERNIDOS, MEZCLONES
SE CONSIDERA UNA CARGA DE 130 KG/MT2

VENTAJAS
AHORRO EN TIEMPO DE INSTALACION
FACILMENTE LA MITAD DEL TIEMPO QUE SE LLEVA
COMUNMENTE UNA LOSA TRADICIONAL, LO CUAL
IMPLICA REDUCCION EN COSTO DE MANO DE OBRA Y
TIEMPO DE ENTREGA.
AHORRO EN MATERIALES:
PRINCIPALMENTE MADERA, LA CUAL SE REDUCE EN
UN 40%.
CONTROL DE CALIDAD:
TANTO LA VIGUETA COMO LA BOVEDILLA SE
FABRICAN BAJO NORMAS DE CALIDAD.

LOSA
TRADICIONAL

ARMADO DE LOSA

LAS LOSAS DE CONCRETO FORMAN LA PARTE MAS DIFICIL Y QUE AL MISMO


TIEMPO REQUIERE MAS TRABAJO DEL PROCESO CONSTRUCTIVO, POR LO
QUE DEBEN HACERSE EN FORMA CUIDADOSA CON OBJETO DE EVITAR
POSIBLES ACCIDENTES MOTIVADOS POR DEFECTOS DE CONSTRUCCION.
LAS LOSAS DE CONCRETO ARMADO SE APOYAN SOBRE MUROS O VIGAS. EL
ARMADO SE HACE CON VARILLA DEL NUMERO 2 1/2 O DEL 3.
EL ARMADO SE HACE IGUAL QUE PARA CUALQUIER TAMAO DE LOSA LO
QUE CAMBIA ES LA CANTIDAD DE VARILLA Y LA SEPARACION DE ESTAS ,
QUE ES DE ACUERDO AL TAMAO DEL CUARTO. SIEMPRE Y CUANDO LA
SUMA DEL LADO MAYOR Y MENOR DE LA LOSA NO SUMEN MAS DE 9
METROS, POR QUE DE SER ASI NECESITARIA UNA VIGA EN MEDIO.
LOSA DE CONCRETO: CUBIERTA PLANA, QUE CUBRE Y CIERRA UNA CASA EN
SU PARTE SUPERIOR Y QUE QUEDA BASTANTE RESISTENTE COMO PARA
ANDAR SOBRE ELLA.
LAS LOSAS SON ELEMENTOS ESTRUCTURALES CUYAS DIMENSIONES EN
PLANTA SON RELATIVAMENTE GRANDES COMPARADAS CON SU ESPESOR.
UNA LOSA NO ES MAS QUE UNA PLACA APOYADA EN UN CONJUNTO DE
VIGAS, MUROS O LINEAS RESISTENTES SUBDIVIDIDA EN TABLEROS.
LOSA: SUPERFICIE QUE ESTA POR ENCIMA DE LOS LIMITES SUPERIORES DE
LAS PAREDES DE UNA HABITACION.

COMPONENTES DE UNA LOSA

PROCESO CONSTRUCTIVO

ENCOFRADO

ARMADO

ARMADO

FABRICACION DE CONCRETO

FUNDICION

FRAGUADO Y DESENCOFRADO

ELEMENTOS DE LA LOSA

EJEMPLO

LOSAS
TRADICIONALES

EJEMPLO
DATOS:

fc = 281kg/cm2
fy = 2810 kg/cm 2
Carga Viva = ESCUELA
Sobrecarga = 50
kg/cm2
Acabados = 60 kg/cm2
Seccin Viga= 20x40
Columna = 25x25

ii

iii

iv

5.00

5.25

4.95

5.75

PASO 1: Cmo
trabajar la losa
b

mI = a = 4.75 = 0.99 1.00


b
4.80
mII = a = 4.80 = 0.86 0.85
b
5.55
mIII = a = 4.75 = 0.94 0.95
b 5.05
mIV = a = 5.05 = 0.91 0.90
b
5.55

a = lado corto
b = lado largo

m = a 0.5
b
m = a 0.5
b

PASO 2: Espesor de
la losa (t)

tI = a + b = 4.75+ 4.80 = 0.1 0.11


90
90
tII = a + b = 4.80+ 5.55 = 0.12
90
90
tIII = a + b = 4.75+ 5.05 = 0.11
90
90
tiv = a + b = 5.05+ 5.55 = 0.12
90
90
t = 12 cms.

Cuando t es 13 cms
LOSA NERVADA O PREFABRICADA

Cuando t es 13 cms
LOSA TRADICIONAL

1 SENTIDO
t=l
20

2 SENTIDOS
t = 2a + 2b
180

VOLADIZO
t=l
10

VOLADIZO
t=a+b
90

PASO 3: Integracin
de Cargas

CM = 2400 x t + ACABADOS + SOBRECARGA


CM = 2400 x 0.12mt + 60 + 50
CM = 398 kg/cm2
CMu= 1.4(398 kg/cm2) = 557.2
kg/cm2
CV = 1.7 (300kg/cm2) = 510 kg/cm2
CU= 557.2 kg/cm2 + 510 kg/cm2
CU= 1067.20 kg/cm2

Para calcular CARGA MUERTA


CM = (t x 2400kg/cm2) +
ACABADOS + SOBREGARGA
Para calcular CARGA ULTIMA
CU = 1.4 CM + 1.7 CV

PASO 4: Clculo de
Momentos
CASO 4

LOSA 1
Ma- = (coef) (CU) (a )
Ma- = (0.05)(1067.20)(4.75) 2
Ma- = 1203.94 kg-m
2

Mb- = (coef)(CU)(b2)
Mb- = (0.05)(1067.20)(4.80) 2
Mb- = 1229.41 kg-m
Ma+= (coef)(CMu)(a) 2 + (coef)(CVu)(a) 2
Ma+= (0.027)(557.2)(4.75) 2 + (0.032)
(510)(4.75) 2
Ma+= 707.66kg-m
Mb+= (coef)(CMu)(b) 2 + (coef)(CVu)(b) 2
Mb+= (0.027)(557.2)(4.8) 2 + (0.027)
(510)(4.8) 2
Mb+= 722.60 kg-m

mI = 1

Ma+ = 707.66 = 235.89


3
3
Mb+ = 722.60 = 240.87
3
3
240.87

1203.99

235.89
722.6

5.00
707.66

1229.41

4.95

PASO 4: Clculo de
Momentos
CASO 4

LOSA 2
Ma- = (coef) (CU) (a )
Ma- = (0.066)(1067.20)(4.8) 2
Ma- = 1622.83 kg-m
2

Mb- = (coef)(CU)(b2)
Mb- = (0.034)(1067.20)(5.55) 2
Mb- = 1117.66 kg-m
Ma+= (coef)(CMu)(a) 2 + (coef)(CVu)(a) 2
Ma+= (0.036)(557.2)(4.8) 2 + (0.043)
(510)(4.8) 2
Ma+= 967.43 kg-m
Mb+= (coef)(CMu)(b) 2 + (coef)(CVu)(b) 2
Mb+= (0.019)(557.2)(5.55) 2 + (0.023)
(510)(5.55) 2
Mb+= 687.41 kg-m

mII = 0.85

Ma+ = 967.43 = 322.48


3
3
Mb+ = 687.41 = 229.14
3
3
322.48

229.14

1117.66
967.43

5.00
687.41

1622.83

5.75

PASO 4: Clculo de
Momentos
CASO 4

LOSA 3
Ma- = (coef) (CU) (a )
Ma- = (0.055)(1067.20)(4.75) 2
Ma- = 1324.94 kg-m
2

Mb- = (coef)(CU)(b2)
Mb- = (0.045)(1067.20)(5.05) 2
Mb- = 1224.73 kg-m
Ma+= (coef)(CMu)(a) 2 + (coef)(CVu)(a) 2
Ma+= (0.030)(557.2)(4.75) 2 + (0.035)
(510)(4.75) 2
Ma+= 799.90 kg-m
Mb+= (coef)(CMu)(b) 2 + (coef)(CVu)(b) 2
Mb+= (0.024)(557.2)(5.05) 2 + (0.023)
(510)(5.55) 2
Mb+= 718.22 kg-m

mIII = 0.95

Ma+ = 799.90= 259.97


3
3
Mb+ = 718.22= 239.41
3
3
1224.73

1324.94

259.97
718.22

5.25
779.90

239.41

4.95

PASO 4: Clculo de
Momentos
CASO 4

LOSA 4
Ma- = (coef) (CU) (a )
Ma- = (0.060)(1067.20)(5.05) 2
Ma- = 1632.98 kg-m
2

Mb- = (coef)(CU)(b2)
Mb- = (0.040)(1067.20)(5.55) 2
Mb- = 1314.90 kg-m
Ma+= (coef)(CMu)(a) 2 + (coef)(CVu)(a) 2
Ma+= (0.033)(557.2)(5.05) 2 + (0.039)
(510)(5.05) 2
Ma+= 976.17 kg-m
Mb+= (coef)(CMu)(b) 2 + (coef)(CVu)(b) 2
Mb+= (0.022)(557.2)(5.55) 2 + (0.026)
(510)(5.55) 2
Mb+= 786.03 kg-m

mIV= 0.90

Ma+ = 976.17= 325.39


3
3
Mb+ = 786.03= 262.01
3
3
1632.98

262.01

1314.90
976.17

5.25
786.03

325.39

5.75

PASO 4: Clculo de
Momentos
240.87

322.48

1203.99 1117.66

235.89

229.14

722.6

5.00
707.66

967.43
687.41

1229.41

1622.83

1224.73

1632.98

4.95

1324.94 1314.90

259.97

262.01

718.22

5.25
779.90

239.41

976.17
786.03

325.39

4.95

5.75

PASO 5: Balance
Eje x

> M2 Rigidez M1 = Mayor


< M2 Promedio M2 = Menor

M = 1227.07

M = 1319.62
1324.33

1203.99

1314.90

1117.66

LOSA I II

80 % M1

LOSA III IV

(1229.41)(0.80) = 983.53
983.53< 1224.73

(1324.33)(0.80) = 1059.46
1059.49 < 1314.90

1224.73+ 1229.41
2

1324.33 + 1314.90
2

Mb = 1227.07

Mb = 1319.62

PASO 5: Balance
Eje y

> M2 Rigidez M1 = Mayor


< M2 Promedio M2 = Menor

M = 1229.41

M = 1627.41

1229.41

1632.98
1622.83

1224.73

LOSA I II

80 % M1

LOSA III IV

(1203.99)(0.80) = 963.19
963.19 < 1117.66

(1632.98)(0.80) = 1306.38
1306.38< 1622.83

1203.99 + 1117.6
2

1632.98 + 1622.83
2

Mb = 1160.83

Mb = 1627.41

240.87

322.48

1160.83
1203.99 1117.66

235.89

229.14

722.6

5.00
707.66

967.43
687.41

1229.41

1227.07

1224.73

4.95

1622.83
1632.98

1627.41

1324.94 1314.90

259.97

262.01

718.22

5.25

976.17

1319.62

779.90

239.41

786.03

325.39

4.95

5.75

PASO 6: Acero Requerido

M (-) = 1627.41 kg-m


AsReq(-/+)=
40%

(bd) -

M(+)= 976.17 kg-m


(bxd) 2 -

Mu(b)

(0.003825) fc

b=100cms
(0.85)fc x
fy

AsReq(-)= (100x9.03)- (100x9.03) 2 - 1627.41(100) (0.85)(281) x


40%
(0.003825)(281)
2810
AsReq(-)= 2.99 cm 2
AsReq(+)= (100x9.03)- (100x9.03) 2 - 976.17(100)
(0.85)(281) x
40%
(0.003825)(281)
2810
d = t recubrimiento EJE = 10-2.5=7.5 /2
AsReq(-)= 1.76 cm 2
SE MULTIPLICA POR EL 40% Y ESE SER EL VALOR REQUERIDO PARA LOSAS

PASO 7: Acero
Requerido Mnimo y
Mximo

As min = 14.1 x (b)(d)


fy

40%

As min = 14.1 x (100)(9.03)


40%
2810
As min = 1.81 cm2

Asmax = 0.5

bal (b)(d) 40%

Asmax= 0.5(0.037)(100)(9.03)
40%
As max = 6.68 cm2

PASO 8: Proposicin
de Armado

PASO 9

As(-) = 2.99
As(+) = 1.76
Asmin = 1.81
Asmax = 6.68
5.00

Astemp = 0.002(b)(t) = 2.44 cm2


As(-)
--Asmin x 40% ---

5.25

4.95

5.75

100
S

S = 0.71 x 100 =23.75


2.99
Smax= 3t = 3(12) = 36cms.