REPORTE DE PRODUCTIVIDAD DINET S.A.

COMPAÑÍA MINERA ARGENTUM – UNIDAD MOROCOCHA


Producción 19 de Julio 2021
DISPONIBILIDAD VOLQUETES

REPORTE DE GERENCIA- MOROCOCHA -19 JULIO

ESTADO Disponibilidad Mecánica (und) Disponibilidad Mecánica (%) Operadores (und) Disponibilidad Operativa (und)
25 TN 25 TN Total 25 TN
TURNO GUARDIA Total 25 TN SCANIA DM Prom Total
SCANIA SCANIA operación Afiliacion SCANIA
META 9.00 8.00 100% 100% 9.00 9.00 9.0 9.0
DÍA A 8.00 8.00 89% 89% 9.00 8.00 0.0 8.0 100%
NOCHE B 8.00 8.00 89% 89% 9.00 8.00 0.0 8.0 100%
PROM 8.00 8.00 89% 89% 9.00 8.00 0.0 8.0 100%

2
PRODUCCIÓN POR TURNO

Producción (TN) Cumplimiento (%)


Relleno
TURNO GUARDIA Mineral Desmonte Ripio Total Mineral Desmonte Total
Cementado
META 784 616 0 0 1,400 100% 100% 100%

DÍA A 616 775 0 200 1,591 79% 158% 114%

NOCHE B 616 850 50 0 1,516 79% 146% 108%

PROM 616 813 25 100 1,554 79% 152% 111%

DESARROLLO DIARIO

STATUS Mineral Desmonte Total

Programa 1,568 1,232 2,800

Ejecutado 1,232 1,875 3,107


Porcentaje de
79% 152% 111%
cumplimiento

3
TRANSPORTE MINERAL
TRANSPORTE DE MINERAL - EJECUTADO VS PROGRAMA (DIARIO) EJECUTADO VS PROGRAMA
2,000
(ACUM. A LA FECHA)
1,800 35,000
1,568
1,600
1,400
1,200
-20% 29,792
30,000
1,000
800
1,239 1,252 1,300 1,234 1,239 1,248 1,276 1,363 1,308 1,297 1,344
600 1,213 1,141 1,232
983 25,000
23,689
400
200
-
05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20,000
Tonelaje Ejecutado Tonelaje Contractual

TRANSPORTE DE MINERAL - EJECUTADO VS PROGRAMA (ACUMULADO A LA 15,000


35,000 FECHA)
29,792
30,000 28,224
26,656
25,088 10,000
25,000 23,520
21,952
20,384 23,689
20,000
18,816 22,457
17,248 21,113
15,680 19,816 5,000
14,112 18,509
15,000 12,544 17,146
10,976 14,887 15,870
9,408 13,746
10,000 7,840 12,533
11,285 -
10,046
8,811 Ton. Ejecutado Ton. Contractual
5,000 7,512
6,260

-
05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul

4 Tonelaje Ejecutado Tonelaje Contractual


TRANSPORTE DESMONTE
TRANSPORTE DE DESMONTE - EJECUTADO VS PROGRAMA (DIARIO)
EJECUTADO VS PROGRAMA
3,000
2,725
(ACUM. A LA FECHA)
40,000
2,500
2,050
2,000
2,025 2,100
1,900 2,000 1,925 1,875 35,000 34,175
+46%
1,700 1,700 1,675 1,750
1,600 1,575
1,500
1,200
30,000
1,000 1,232

500 25,000 23,408


-
05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul
20,000

40,000 TRANSPORTE DE DESMONTE - EJECUTADO VS PROGRAMA (ACUMULADO A LA FECHA) 15,000


34,175
35,000 32,300
30,550 10,000
30,000
28,875
27,300
26,100
24,175
25,000
21,450 5,000
19,450 23,408
20,000 17,550 22,176
15,450 20,944
19,712
13,750 18,480
15,000 12,150 17,248 -
10,450 16,016 Ton. Ejecutado
14,784
8,400 13,552
10,000 12,320 Ton. Contractual
11,088
9,856
8,624
5,000 7,392
6,160
-
05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul

5 Tonelaje Ejecutado Tonelaje Contractual


TRANSPORTE DE MATERIAL
TONELAJETOTAL
TOTAL (M+D) - EJECUTADO VS PROGRAMA (DIARIO) EJECUTADO VS PROGRAMA
4,500 (ACUM. A LA FECHA)
4,000 3,708 70,000

3,500 3,264 3,302 3,348


3,141 3,201
3,000
3,000
2,834 2,939
3,113
2,883 2,972 3,094 3,107
+9%
2,563 60,000 57,864
2,500 2,800
53,200
2,000
50,000
1,500

1,000

500 40,000
-
05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul

Tonelaje Ejecutado Tonelaje Contractual 30,000

TONELAJE TOTAL (M+D) - EJECUTADO VS PROGRAMA (ACUMULADO A LA FECHA)


70,000
20,000
57,864
60,000 54,757
51,663
48,691
50,000 45,809 53,200
43,246 50,400 10,000
40,045 47,600
40,000 36,337 44,800
33,196 42,000
30,083 39,200
26,735 36,400
30,000
23,796 33,600 -
20,961 30,800
17,962 28,000
20,000 14,660 22,400
25,200 Ton. Ejecutado Ton. Contractual
19,600
16,800
10,000 14,000

-
05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul
6 Tonelaje Ejecutado Tonelaje Contractual
DISPONIBILIDAD LÍNEA AMARILLA

REPORTE DE GERENCIA-LINEA AMARILLA MOROCOCHA - 19 JULIO

ESTADO Disponibilidad Mecanica (und) Operadores (und) Disponibilidad Operativa (und)

META 1- Motoniv 2- Mini 3.0 1- Motoniv 1- Mini 2.0 1- Motoniv 1- Mini 2.0

DIA A 1.0 2.0 3.0 1.0 1.0 2.0 1.0 1.0 2.0

NOCHE B 1.0 2.0 3.0 1.0 1.0 2.0 1.0 1.0 2.0

PROM 1.0 2.0 3.0 1.0 1.0 2.0 1.0 1.0 2.0

7
Equipo de Línea Amarilla : Motoniveladora

Valorización Diaria
10.0

8.0
8.0

6.0

4.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0
6.0 6.0
2.0 4.0

0.0 0.0 0.0


Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche
Dia

Dia

Noche

Noche

Noche
Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia
05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul

Total horas Horas Minimas

Horas Minimas 304.00 100%


Horas Operativas 263.00 87%
Equipo de Línea Amarilla : Minicargador 246 D

Valorización Diaria
10.0

8.0
8.0

6.0

4.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0

2.0

0.0
Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche

Noche
Noche

Noche

Dia
Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia

Dia
05-Jul 06-Jul 07-Jul 08-Jul 09-Jul 10-Jul 11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul

Total horas Horas Minimas

Horas Minimas 304.00 100%


Horas Operativas 304.00 100%