PROYECTO: PROGRAMA NACIONAL DE RECONSTRUCCIÓN EN EL SECTOR EDUCATIVO
ESTADO: CIUDAD DE MÉXICO
NOMBRE DEL PLANTEL: CONALEP 11 AZTAHUACAN
DOMICILIO: PLAN DE AYALA 395, ZONA URBANA EJIDAL SANTA MARÍA AZTAHUACAN, IZTAPALAPA, 09500 CIUDAD DE MÉXICO, CDMX
CLAVE DEL CENTRO DE TRABAJO (CCT): 09DPT0005Y
ALCALDIA/MUNICIPIO: IZTAPALAPA
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES 9 MES 10 MES 11 MES 12 MES 13 MES 14
TOTAL
CLAVE CONCEPTO FECHA INICIO FECHA TERMINO 11/11/2022 12/12/2022 12/01/2023 12/02/2023 12/03/2023 12/04/2023 12/05/2023 12/06/2023 12/07/2023 12/08/2023 12/09/2023 12/10/2023 12/11/2023 11/12/2023
$ 18,548,067.29 11/12/2022 11/01/2023 11/02/2023 11/03/2023 11/04/2023 11/05/2023 11/06/2023 11/07/2023 11/08/2023 11/09/2023 11/10/2023 11/11/2023 11/12/2023 12/01/2024
1 I.- Seguridad estructural y condiciones generales de funcionamiento. $ 16,551,827.93
1.1 BIBLIOTECA $ 985,911.55
1.1.1 PRELIMINARES 11/11/2022 11/12/2022 $ 52,920.70 $52,920.70
1.1.2 DESMONTAJES 11/11/2022 11/12/2022 $ 63,608.95 $63,608.96
1.1.3 DEMOLICIONES 11/11/2022 11/12/2022 $ 353,626.24 $353,626.24
1.1.4 ALBAÑILERÍAS 11/11/2022 11/12/2022 $ 515,755.66 $515,755.66
1.2 GALERA $ 446,966.66
1.2.1 SEPARACIÓN DE EDIFICIO 11/11/2022 11/12/2022 $ 12,189.01 $12,189.02
1.2.2 CONSTRUCCIÓN DE MURO POSTERIOR DE TALLERES 11/11/2022 11/12/2022 $ 352,734.81 $352,734.82
1.2.3 PUERTA DE ACCESO A TALLER DE COSTURA 11/11/2022 11/12/2022 $ 63,118.57 $1,402.33 $61,716.24
1.2.4 RE CONEXIÓN DE TABLEROS ELÉCTRICOS 11/11/2022 11/12/2022 $ 18,924.27 $11,083.08 $7,841.20
1.3 EDIFICIO A $ 8,278,329.13
1.3.1 DESMONTAJES 11/11/2022 11/01/2023 $ 521,738.04 $522,274.08 $1,152.21
1.3.2 DEMOLICIONES 12/12/2022 11/01/2023 $ 984,445.49 $432,766.82 $551,678.68
1.3.3 PRELIMINARES 12/12/2022 11/01/2023 $ 42,793.10 $5,502.60 $37,290.50
1.3.4 CIMENTACIÓN 12/01/2023 11/05/2023 $ 2,983,293.05 $1,132,810.67 $395,940.80 $72,376.59 $984,379.81 $294,916.36 $19,445.49 $83,423.33
1.3.5 ESTRUCTURA 12/02/2023 11/05/2023 $ 1,968,449.22 $187,437.35 $271,080.16 $938,400.28 $744,522.90 $371,972.78
1.3.6 ESTRUCTURA-ESCALERA 12/03/2023 11/04/2023 $ 67,165.08 $81,322.13
1.3.7 ALBAÑILERIA 12/03/2023 11/05/2023 $ 326,641.43 $23,555.44 $38,039.37 $222,953.11 $42,093.51
1.3.8 CANCELERÍA Y HERRERIA 12/04/2023 11/06/2023 $ 458,532.16 $458,532.16
1.3.9 ACABADOS 12/04/2023 11/06/2023 $ 554,840.74 $277,420.37 $277,420.37
1.3.10 INSTALACIÓN ELÉCTRICA 12/05/2023 11/06/2023 $ 370,430.82 $17,145.00 $353,285.82
1.4 EDIFICIO B $ 6,840,620.59
1.4.1 PRELIMINARES 12/05/2023 11/06/2023 $ 4,992.60 $4,992.60
1.4.2 CIMENTACIÓN 12/05/2023 11/08/2023 $ 2,983,293.05 $1,132,810.67 $286,433.17 $1,046,913.59 $315,967.41 $109,507.63 $91,660.58
1.4.3 ESTRUCTURA 12/07/2023 11/09/2023 $ 1,968,449.22 $187,437.35 $644,199.83 $246,222.12 $94,373.31 $1,245,912.00 $4,278.07 $108,335.71
1.4.4 ESTRUCTURA-ESCALERA 12/08/2023 11/09/2023 $ 67,165.08 $20,388.51 $67,450.11
1.4.5 ALBAÑILERIA 12/08/2023 11/10/2023 $ 303,163.85 $33,445.55 $80,445.52 $41,833.54 $75,706.38 $29,237.46 $42,495.40
1.4.6 CANCELERÍA Y HERRERIA 12/08/2023 11/10/2023 $ 562,721.99 $562,721.99
1.4.7 ACABADOS 12/09/2023 11/11/2023 $ 580,403.98 $199,019.15 $290,201.99 $91,182.84
1.4.8 INSTALACIÓN ELÉCTRICA 12/09/2023 11/11/2023 $ 370,430.82 $73,921.54 $78,392.50 $146,989.18 $71,127.60
2 II.- Servicios sanitarios. $ 736,754.67
2.1 MÓDULO DE SANITARIOS_EDIFICIO A $ 736,754.67
2.1.1 ALBAÑILERÍAS 12/02/2023 11/03/2023 $ 188,065.32 $94,032.66 $94,032.66
2.1.2 ACABADOS 12/03/2023 11/04/2023 $ 68,795.74 $34,397.87 $34,397.87
2.1.3 HERRERÍA Y CANCELERÍA 12/03/2023 11/04/2023 $ 105,418.47 $52,709.24 $52,709.24
2.1.4 INSTALACIÓN HIDROSANITARIA 12/03/2023 11/05/2023 $ 48,292.50 $56,341.25
2.1.5 MUEBLES SANITARIOS 12/04/2023 11/06/2023 $ 171,752.16 $85,876.08 $85,876.08
2.1.6 ACCESORIOS 12/04/2023 11/05/2023 $ 55,759.86 $27,879.93 $27,879.93
2.1.7 INSTALACIÓN ELÉCTRICA 12/03/2023 11/05/2023 $ 30,613.09 $15,306.55 $15,306.55
2.1.8 TINACOS 12/04/2023 11/05/2023 $ 68,057.53 $34,028.77 $34,028.77
3 VIII.- Espacios de usos múltiples. $ 1,259,484.69
3.1 OBRA EXTERIOR EDIFICIO A Y B $ 1,259,484.69
3.1.1 PLAZA 12/08/2023 11/11/2023 $ 907,032.71 $907,032.72
3.1.2 RED ELÉCTRICA 12/10/2023 11/11/2023 $ 217,644.97 $217,644.98
3.1.3 RED HIDROSANITARIA 12/10/2023 11/11/2023 $ 134,807.01 $1,819,199.27
TOTAL DEL PRESUPUESTO $3,608,022.35 $316,133.42 $1,067,302.10 $315,967.41 $1,155,150.86 $352,044.26 $1,051,829.92 $560,801.73 $1,694,703.06 $1,099,706.86 $947,853.33 $931,518.21 $1,879,387.95 $6,403,879.20
ACUMULADO $3,608,022.35 $3,924,155.77 $4,991,457.87 $5,307,425.28 $6,462,576.14 $6,814,620.40 $7,866,450.32 $8,427,252.05 $10,121,955.11 $11,221,661.97 $12,169,515.30 $13,101,033.51 $14,980,421.46 $21,384,300.66
PORCENTAJE PERIODO 16.87% 1.48% 4.99% 1.48% 5.40% 1.65% 4.92% 2.62% 7.92% 5.14% 4.43% 4.36% 8.79% 29.95%
PORCENTAJE ACUMULADO 16.87% 18.35% 23.34% 24.82% 30.22% 31.87% 36.79% 39.41% 47.33% 52.48% 56.91% 61.26% 70.05% 100.00%
OBRAS Y CONSTRUCCIONES DIARAM, S.A. DE C.V.
LUIS ALBERTO RAMIREZ OLMOS
c.diaram@yahoo.com.mx
Corregidora No. 94-G Col. Miguel Hidalgo, Deleg. Tlalpan, C.P.14260 México, D.F.