SECTOR ITANYOCC

DEMOLICION DE CANAL EXISTENTE


ITEM TIPO INICIO FIN LONG(m) AREA (m2) VOL. (m3)
1 rectangular 0+000.00 0+835.00 835.00 0.29 242.15
2 rectangular 1+273.40 1+289.10 15.70 0.34 5.34
3 rectangular 1+391.20 1+396.60 5.40 0.47 2.54
4 rectangular 1+402.60 1+417.80 15.20 0.61 9.27
5 rectangular 1+665.90 1+675.00 9.10 0.34 3.09
6 rectangular 1+749.50 1+793.00 43.50 0.40 17.40
7 rectangular 1+815.00 1+832.00 17.00 0.28 4.76
8 rectangular 1+851.90 1+858.40 6.50 0.47 3.05
9 rectangular 1+867.40 1+881.60 14.20 0.32 4.54
10 rectangular 2+487.60 2+550.60 63.00 0.28 17.64
11 rectangular 2+561.00 2+626.80 65.80 0.34 22.37
12 rectangular 2+673.00 2+683.60 10.60 0.12 1.27
13 rectangular 2+696.60 2+717.40 20.80 0.28 5.82
14 rectangular 2+732.50 2+743.20 10.70 0.32 3.42
15 rectangular 2+845.50 2+890.00 44.50 0.32 14.24
TOTAL (m3) 356.92

DEMOLICION DE ACUEDUCTO EXISTENTE


ACUEDUCTO TIPO I, L=5 m (01 UND)
ITEM COMPONENTE INICIO FIN LONG(m) AREA (m2) VOL. (m3)
1 Canal 1+396.60 1+402.60 6.00 0.48 2.88
2 Estribo inicial 1+396.60 - 2.00 0.35 0.70
3 Estribo final - 1+402.60 2.50 0.13 0.31
TOTAL (m3) 3.89

ACUEDUCTO TIPO I, L=8 m (01 UND)


ITEM COMPONENTE INICIO FIN LONG(m) AREA (m2) VOL. (m3)
1 Canal 1+852.00 1+861.00 9.00 0.47 4.23
2 Estribo inicial 1+852.00 - 2.00 0.35 0.70
3 Estribo final - 1+861.00 2.50 0.13 0.31
TOTAL (m3) 5.24

SECTOR QEQRA

DEMOLICION DE CANAL EXISTENTE


ITEM TIPO INICIO FIN LONG(m) AREA (m2) VOL. (m3)
1 rectangular 3+955.60 3+995.00 39.40 0.26 10.09
2 rectangular 7+082.53 7+097.33 14.80 0.20 2.95
TOTAL (m3) 13.03
e A.INT H. INT. AREA VOLUMEN
0.18 0.56 0.34 0.29 240.48
0.18 0.50 0.54 0.35 5.48
0.25 0.60 0.50 0.53 2.83
0.35 0.60 0.50 0.80 12.24
0.18 0.50 0.54 0.35 3.18
0.25 0.60 0.50 0.53 22.84
0.15 0.48 0.54 0.28 4.74
0.18 0.46 0.90 0.47 3.07
0.18 0.50 0.46 0.32 4.55
0.15 0.49 0.50 0.27 16.87
0.18 0.47 0.55 0.35 22.86
0.18 - 0.68 0.12 1.30 (Solo es el lado izquierdo del canal
0.15 0.52 0.47 0.26 5.48
0.18 0.52 0.48 0.33 3.53
0.18 0.52 0.48 0.33 14.70
TOTAL (m3) 364.14

e A.INT H. INT. AREA VOLUMEN


0.10 0.49 0.59 0.19 7.37
0.10 0.42 0.40 0.14 2.10
TOTAL (m3) 9.47