Está en la página 1de 21

ANALISIS SISMICO ESTATICO Prob 01

hn= 32
CT= 60 PÓRTICOS.Y.PLACAS
TX= 0.533
Z= 0.45 Zona 4-LIMA
S= 1 Suelo S1
TP= 0.4 S1
TL= 2.5 S1
U= 1 Oficinas C
C= 1.875
R= 7 Dual CA Ro=7
Ia= 1
Ip= 1

PESO EDIFICIO 1288.06 ton


ZUCS/R 0.1205 Coeficiente Sismico
VEXX= 155.26 ton
C/R>0.11 0.268 OK

DISTRIBUCION DE FUERZAS LATERALES DIRECCION XX

VEXX= 155.26
Tx= 0.533
k= 1.0167

PESO POR Alturas Pi*hi^k alfai Fi Vi


NIVEL
TON m ton ton
PISO 09 138.64 32.0 4700.29 0.194 30.08 30.08
PISO 08 143.18 28.5 4314.94 0.178 27.62 57.70
PISO 07 143.18 25.0 3776.78 0.156 24.17 81.87
PISO 06 143.18 21.5 3239.87 0.134 20.74 102.60
PISO 05 143.18 18.0 2704.43 0.111 17.31 119.91
PISO 04 143.18 14.5 2170.73 0.089 13.89 133.80
PISO 03 143.18 11.0 1639.20 0.068 10.49 144.29
PISO 02 143.18 7.5 1110.52 0.046 7.11 151.40
PISO 01 147.16 4.0 602.40 0.025 3.86 155.26
24259.16 1.000 155.26
01

hn= 32
CT= 60 PÓRTICOS.Y.PLACAS
Ty= 0.533
Z= 0.45 Zona 4-LIMA
S= 1 Suelo S1
TP= 0.4 S1
TL= 2.5 S1
U= 1 Oficinas C
C= 1.875
R= 7 Dual CA Ro=7
Ia= 1
Ip= 1

PESO EDIFICIO 1288.06 ton


ZUCS/R 0.1205 Coeficiente Sismico
VEYY= 155.26 ton
C/R>0.11 0.268 OK
K= 1.01666667

f vs piso
PISO 09 30.08

PISO 08 27.62

PISO 07 24.17
f vs piso
PISO 09 30.08

PISO 08 27.62

PISO 07 24.17

PISO 06 20.74

PISO 05 17.31

PISO 04 13.89

PISO 03 10.49

PISO 02 7.11

PISO 01 3.86

Vx vs PISO

PISO 09 30.08

PISO 08 57.70

PISO 07 81.87

102.60
PISO 06

119.91
PISO 05

133.80
PISO 04

144.29
PISO 03

151.40
PISO 02

155.26
PISO 01
PISO 01 155.26
PISO 02 151.40
PISO 03 144.29
PISO 04 133.80
PISO 05 119.91
PISO 06 102.60
PISO 07 81.87
PISO 08 57.70
PISO 09 30.08

PISO 01 3.86
PISO 02 7.11
PISO 03 10.49
PISO 04 13.89
PISO 05 17.31
PISO 06 20.74
PISO 07 24.17
PISO 08 27.62
PISO 09 30.08
primer.piso 147.16

carga.muerta(peso.propio)

Elemento Descripción Cantidad b(m) h(m) Z(m) ꙋ(ton/m3) Parcial(ton)

V30x60 2 0.30 0.60 5.80 2.40 5.01


Vigas X
V30x60 2 0.30 0.60 4.90 2.40 4.23
V25x60 3 0.25 0.60 6.20 2.40 6.70
Vigas Y V25x60 2 0.25 0.60 4.70 2.40 3.38
V25x60 1 0.25 0.60 3.85 2.40 1.39
Losa Alig h=0.30 3 6.20 6.50 - 0.42 50.78
PL e=0.25 2 0.25 1.80 4.00 2.40 8.64
Placas PL e=0.30 2 0.30 1.25 4.00 2.40 7.20
PL e=0.25 1 0.25 2.35 4.00 2.40 5.64
Columnas C30x60 6 0.30 0.60 4.00 2.40 10.37

carga.muerta.adicional(tabiqueria.y.acabados)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa Acabado + Tabiqueria 3 6.50 6.20 0.30 36.27

carga.viva(según.dato)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa 25% (S/C=250kgf/m2) 3 6.50 6.20 0.0625 7.56

piso.tipico 143.18

carga.muerta(peso.propio)

Elemento Descripción Cantidad b(m) h(m) Z(m) ꙋ(ton/m3) Parcial(ton)

V30x60 2 0.30 0.60 5.80 2.40 5.01


Vigas X
V30x60 2 0.30 0.60 4.90 2.40 4.23
V25x60 3 0.25 0.60 6.20 2.40 6.70
Vigas Y V25x60 2 0.25 0.60 4.70 2.40 3.38
V25x60 1 0.25 0.60 3.85 2.40 1.39
Losa Alig h=0.30 3 6.20 6.50 - 0.42 50.78
PL e=0.25 2 0.25 1.80 3.50 2.40 7.56
Placas PL e=0.30 2 0.30 1.25 3.50 2.40 6.30
PL e=0.25 1 0.25 2.35 3.50 2.40 4.94
Columnas C30x60 6 0.30 0.60 3.50 2.40 9.07

carga.muerta.adicional(tabiqueria.y.acabados)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa Acabado + Tabiqueria 3 6.50 6.20 0.30 36.27

carga.viva(según.dato)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa 25% (S/C=250kgf/m2) 3 6.50 6.20 0.0625 7.56

Carga viva en Azotea

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa 25% (S/C=100kgf/m2) 3 6.50 6.20 0.025 3.02

peso sísmico: 1erPiso Ps1= 147.16 ton


Piso Típico Ps2= 143.18 ton
Ps = 100%CM + 25%CV Último Piso Ps3= 138.64 ton

Ps= 1288.06 ton


Tabla N° 1 Tabla N° 3
FACTORES DE ZONA "Z" FACTOR DE SUELO "S"
ZONA Z ZONA / SUELO S0
4 0.45 Z4 0.80
3 0.35 Z3 0.80
2 0.25 Z2 0.80
1 0.10 Z1 0.80

Tabla N° 4
PERIODOS "Tp" Y "TL"
Perfil de sue
S0
Tp (s) 0.30
TL (s) 3.00
Peso (ton) N° de pisos Parcial (ton)

Ps1= 197.52 1 197.52


Ps2= 173.15 7 1212.05
Ps3= 170.58 1 170.58

Ps= 1580.15
Tabla N° 3
FACTOR DE SUELO "S"
S1 S2 S3
1.00 1.05 1.10
1.00 1.15 1.20
1.00 1.20 1.40
1.00 1.60 2.00

Tabla N° 4
PERIODOS "Tp" Y "TL"
Perfil de suelo
S1 S2 S3
0.40 0.60 1.00
2.50 2.00 1.60
ANALISIS SISMICO ESTATICO Prob 02

hn= 28
CT= 60 Muros.estructurales
TX= 0.467 s
Z= 0.35 Zona 3-AREQUIPA
S= 1.15 Suelo S2
TP= 0.6 S2
TL= 2 S2
U= 1 Vivienda C
C= 2.5
R= 5.4 Muros Ro=6
Ia= 0.9 Irregularidad.esquinas.entrantes
Ip= 1

PESO EDIFICIO 1580.15 ton


VE=ZUCS/R 0.1863 Coeficiente Sismico
VEXX= 294.45 ton
C/R>0.11 0.463 OK

DISTRIBUCION DE FUERZAS LATERALES DIRECCION XX

VEXX= 294.45
Tx= 0.467
k= 1.0

PESO POR Alturas Pi*hi^k alfai Fi Vi


NIVEL
TON m ton ton
PISO 09 170.58 28.0 4776.24 0.191 56.35 56.35
PISO 08 173.15 25.0 4328.75 0.173 51.07 107.41
PISO 07 173.15 22.0 3809.30 0.153 44.94 152.35
PISO 06 173.15 19.0 3289.85 0.132 38.81 191.16
PISO 05 173.15 16.0 2770.40 0.111 32.68 223.85
PISO 04 173.15 13.0 2250.95 0.090 26.56 250.40
PISO 03 173.15 10.0 1731.50 0.069 20.43 270.83
PISO 02 173.15 7.0 1212.05 0.049 14.30 285.13
PISO 01 197.52 4.0 790.08 0.032 9.32 294.45
24959.12 1.000 294.45

PISO 01 9.32 PISO 01


PISO 02 14.30 PISO 02
PISO 03 20.43 PISO 03
PISO 04 26.56 PISO 04
PISO 05 32.68 PISO 05
PISO 06 38.81 PISO 06
PISO 07 44.94 PISO 07
PISO 08 51.07 PISO 08
PISO 09 56.35 PISO 09

f VS piso v
PISO 0 9 56.35 PISO 0 9 56.35

PISO 0 8 51.07 PISO 0 8 107.41

PISO 0 7 44.94 PISO 0 7 152.35

PISO 0 6 38.81 PISO 0 6 191.

PISO 0 5 32.68 PISO 0 5 2

PISO 0 4 26.56 PISO 0 4

PISO 0 3 20.43 PISO 0 3

PISO 0 2 14.30 PISO 0 2

PISO 0 1 9.32 PISO 0 1


02

hn= 28
CT= 35 PÓRTICOS
Ty= 0.800 S
Z= 0.35 Zona 3-AREQUIPA
S= 1.15 Suelo S2
TP= 0.6 S2
TL= 2 S2
U= 1 Vivienda C
C= 1.875
R= 7.2 Porticos Ro=8
Ia= 0.9 Irregularidad.esquinas.entrantes
Ip= 1

PESO EDIFICIO 1580.15 ton


VE=ZUCS/R 0.1048 Coeficiente Sismico
VEYY= 165.63 ton
C/R>0.11 0.260 OK

X DISTRIBUCION DE FUERZAS LATERALES DIREC

VEYY= 165.63
Ty= 0.800
k= 1.15

PESO POR Alturas Pi*hi^k


NIVEL
TON m
PISO 09 170.58 28.0 7873.36
PISO 08 173.15 25.0 7015.42
PISO 07 173.15 22.0 6056.32
PISO 06 173.15 19.0 5116.69
PISO 05 173.15 16.0 4199.14
PISO 04 173.15 13.0 3307.18
PISO 03 173.15 10.0 2445.81
PISO 02 173.15 7.0 1622.88
PISO 01 197.52 4.0 972.70
38609.48

294.45 PISO 01 4.17


285.13 PISO 02 6.96
270.83 PISO 03 10.49
250.40 PISO 04 14.19
223.85 PISO 05 18.01
191.16 PISO 06 21.95
152.35 PISO 07 25.98
107.41 PISO 08 30.09
56.35 PISO 09 33.78

v vs piso f vs piso
56.35 PISO 0 9 33.78
PISO 0 9

107.41 PISO 0 8 30.09


PISO 0 8

152.35 PISO 0 7 25.98


PISO 0 7

191.16 PISO 0 6 21.95


PISO 0 6

223.85 PISO 0 5 18.01


PISO 0 5

250.40 PISO 0 4 14.19


PISO 0 4

270.83 PISO 0 3 10.49


PISO 0 3

285.13 PISO 0 2 6.96


PISO 0 2

294.45 PISO 0 1 4.17


PISO 0 1
AS LATERALES DIRECCION YY

alfai Fi Vi

ton ton
0.204 33.78 33.78
0.182 30.09 63.87
0.157 25.98 89.85
0.133 21.95 111.80
0.109 18.01 129.81
0.086 14.19 144.00
0.063 10.49 154.49
0.042 6.96 161.45
0.025 4.17 165.63
1.000 165.63

PISO 01 165.63
PISO 02 161.45
PISO 03 154.49
PISO 04 144.00
PISO 05 129.81
PISO 06 111.80
PISO 07 89.85
PISO 08 63.87
PISO 09 33.78

v vs piso
PISO 09 33.78

PISO 08 63.87

PISO 07 89.85

PISO 06 111.80

PISO 05 129.81

PISO 04 144.00

PISO 03 154.49

PISO 02 161.45

PISO 01 165.63
primer.piso 197.52

carga.muerta(peso.propio)

Elemento Descripción Cantidad b(m) h(m) Z(m) ꙋ(ton/m3) Parcial(ton)

V30x60 2 0.30 0.60 3.55 2.40 3.07


Vigas X
V30x60 2 0.30 0.60 3.70 2.40 3.20
V30x60 5 0.30 0.60 5.20 2.40 11.23
Vigas Y
V30x60 4 0.30 0.60 1.40 2.40 2.42
Maciza h=0.20 2 3.55 5.80 0.20 2.40 19.77
Maciza h=0.20 1 1.70 3.55 0.20 2.40 2.90
Losa
Maciza h=0.20 2 3.70 5.80 0.20 2.40 20.60
Maciza h=0.20 2 3.70 1.70 0.20 2.40 6.04
PL e=0.30 3 0.30 3.55 4.00 2.40 30.67
Placas
PL e=0.30 4 0.30 3.70 4.00 2.40 42.62
Columnas C30x60 14 0.30 0.60 4.00 2.40 24.19

carga.muerta.adicional(tabiqueria.y.acabados)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Acabado + Tabiqueria 2 3.55 5.80 0.25 10.30


Acabado + Tabiqueria 1 1.70 3.55 0.25 1.51
Losa
Acabado + Tabiqueria 2 3.70 5.80 0.25 10.73
Acabado + Tabiqueria 2 3.70 1.70 0.25 3.145

carga.viva(según.dato)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

25% (S/C=200kgf/m2) 2 3.55 5.80 0.050 2.06


25% (S/C=200kgf/m2) 1 1.70 3.55 0.050 0.30
Losa
25% (S/C=200kgf/m2) 2 3.70 5.80 0.050 2.15
25% (S/C=200kgf/m2) 2 3.70 1.70 0.050 0.63

piso.tipico 173.15

carga.muerta(peso.propio)
Elemento Descripción Cantidad b(m) h(m) Z(m) ꙋ(ton/m3) Parcial(ton)

V30x60 2 0.30 0.60 3.55 2.40 3.07


Vigas X
V30x60 2 0.30 0.60 3.70 2.40 3.20
V30x60 5 0.30 0.60 5.20 2.40 11.23
Vigas Y
V30x60 4 0.30 0.60 1.40 2.40 2.42
Maciza h=0.20 2 3.55 5.80 0.20 2.40 19.77
Maciza h=0.20 1 1.70 3.55 0.20 2.40 2.90
Losa
Maciza h=0.20 2 3.70 5.80 0.20 2.40 20.60
Maciza h=0.20 2 3.70 1.70 0.20 2.40 6.04
PL e=0.30 3 0.30 3.55 3.00 2.40 23.00
Placas
PL e=0.30 4 0.30 3.70 3.00 2.40 31.97
Columnas C30x60 14 0.30 0.60 3.00 2.40 18.14

carga.muerta.adicional(tabiqueria.y.acabados)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Acabado + Tabiqueria 2 3.55 5.80 0.25 10.30


Acabado + Tabiqueria 1 1.70 3.55 0.25 1.51
Losa
Acabado + Tabiqueria 2 3.70 5.80 0.25 10.73
Acabado + Tabiqueria 2 3.70 1.70 0.25 3.145

carga.viva(según.dato)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

25% (S/C=200kgf/m2) 2 3.55 5.80 0.050 2.06


25% (S/C=200kgf/m2) 1 1.70 3.55 0.050 0.30
Losa
25% (S/C=200kgf/m2) 2 3.70 5.80 0.050 2.15
25% (S/C=200kgf/m2) 2 3.70 1.70 0.050 0.63

Carga viva en Azotea

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa 25% (S/C=100kgf/m2) 2 3.55 5.80 0.025 1.03


Losa 25% (S/C=100kgf/m2) 1 1.70 3.55 0.025 0.15
Losa 25% (S/C=100kgf/m2) 2 3.70 5.80 0.025 1.07
Losa 25% (S/C=100kgf/m2) 2 3.70 1.70 0.025 0.31

peso sísmico: 1erPiso Ps1= 197.52 ton


Piso.Tipico Ps2= 173.15 ton
Ps = 100%CM + 25%CV Ultimo.Piso Ps3= 170.58 ton

Ps= 1580.15 ton

piso.tipico 143.18

carga.muerta(peso.propio)

Elemento Descripción Cantidad b(m) h(m) Z(m) ꙋ(ton/m3) Parcial(ton)

V30x60 2 0.30 0.60 5.80 2.40 5.01


Vigas X
V30x60 2 0.30 0.60 4.90 2.40 4.23
V25x60 3 0.25 0.60 6.20 2.40 6.70
Vigas Y V25x60 2 0.25 0.60 4.70 2.40 3.38
V25x60 1 0.25 0.60 3.85 2.40 1.39
Losa Alig h=0.30 3 6.20 6.50 - 0.42 50.78
PL e=0.25 2 0.25 1.80 3.50 2.40 7.56
Placas PL e=0.30 2 0.30 1.25 3.50 2.40 6.30
PL e=0.25 1 0.25 2.35 3.50 2.40 4.94
Columnas C30x60 6 0.30 0.60 3.50 2.40 9.07

carga.muerta.adicional(tabiqueria.y.acabados)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa Acabado + Tabiqueria 3 6.50 6.20 0.30 36.27

carga.viva(según.dato)

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa 25% (S/C=250kgf/m2) 3 6.50 6.20 0.0625 7.56

Carga viva en Azotea

Elemento Descripción Cantidad L(m) B(m) S/C(ton/m2) Parcial(ton)

Losa 25% (S/C=100kgf/m2) 3 6.50 6.20 0.025 3.02

peso sísmico: 1erPiso Ps1= 147.16 ton


Piso.Tipico Ps2= 143.18 ton
Ps = 100%CM + 25%CV Ultimo.Piso Ps3= 138.64 ton

Ps= 1288.06 ton