ITEM INSUMO UNIDAD CANTIDAD PRECIO PARCIAL 1ER MES 2DO MES TOTAL
1920.0000 27.49 19,423.29
1 TOPOGRAFO hh
9711.645 9711.645 19423.29
10,391.2028 27.49 70,783.72
2 OPERARIO hh
35391.86 35391.86 70783.72
21.2197 21.61 51,430.52
3 OFICIAL hh
25715.26 25715.26 51430.52
54,249.6418 19.56 283,491.93
4 PEON hh
141745.965 141745.965 283491.93
CAPATAZ "A" hh 15,166.8641 32.99 36,738.88
5 18369.44 18369.44 36738.88
2.0000 32.99 65.98
6 CAPATAZ "B" hh
32.99 32.99 65.98
2.0000 5.94 11.88
7 CLAVOS DIFERENTES MEDIDAS kg
5.94 5.94 11.88
410.5000 0.00 0.00
8 CLAVOS DE 3" kg
0 0 0
100.0000 6.78 678.00
9 MALLA DE SEGURIDAD NARANJA m
339 339 678
60.0000 50.85 3,051.00
10 CONOS/CILINDROS u
1525.5 1525.5 3051
3,218.3200 0.00 0.00
11 ACERO CORRUGADO fy=4200 kg/cm2 kg
0 0 0
GRADO 60
14,131.1700 12.63 178,476.65
12 ASFALTO RC-250 gal
89238.325 89238.325 178476.65
2,870.3900 466.10 1,337,890.41
13 MEZCLA ASFALTICA EN CALIENTE m3
668945.205 668945.205 1337890.41
1.3500 25.42 34.32
14 CEMENTO PORTLAND TIPO I (42.5 kg) bls
17.16 17.16 34.32
1,104.0000 15.00 16,559.96
15 YESO EN BOLSAS DE 25 KG bls
8279.98 8279.98 16559.96
SOLVENTE XILOL gal 19.2200 66.30 1,274.52