ITEM DESCRIPCION UND CANTIDAD P. UNITARIO P.

TOTAL
OBRAS PROVISIONALES, OBRAS PRELIMINARES, SEGURIDAD Y SALUD EN EL
1.00.00 S/ 33,850.00
TRABAJO
OBRAS PROVISIONALES
CERCO PERIMETRAL DE OBRA ML 130.00 S/ 25.00 S/ 3,250.00
HABILITACION DE PUNTO DE ENERGIA GLB 1.00 S/ 1,800.00 S/ 1,800.00
HABILITACION DE PUNTO DE AGUA GLB 1.00 S/ 2,500.00 S/ 2,500.00
OBRAS PRELIMINARES
MOVILIZACION Y DESMOVILIZACION DE HERRAMIENTAS, EQUIPOS Y
GLB 1.00 S/ 3,500.00 S/ 3,500.00
MATERIALES
TRAZO Y REPLANTEO M2 2,300.00 S/ 1.00 S/ 2,300.00
SERVICIO DE TOPOGRAFIA MES 2.00 S/ 3,000.00 S/ 6,000.00
SEGURIDAD Y SALUD EN EL TRABAJO
SEÑALIZACION DE OBRA GLB 1.00 S/ 1,500.00 S/ 1,500.00
EQUIPOS DE PORTECCION PERSONAL Y COLECTIVA GLB 1.00 S/ 3,000.00 S/ 3,000.00
PAZ SOCIAL GLB 1.00 S/ 10,000.00 S/ 10,000.00
2.00.00 ESTRUCTURA S/ 170,540.05
MOVIMIENTO DE TIERRA
ZAPATA Y CIMENTACION
EXCAVACION DE TERRENO NATURAL M3 180.00 S/ 35.00 S/ 6,300.00
ELIMINACION DE MATERIAL EXCEDENTE M3 120.00 S/ 45.00 S/ 5,400.00
RELLENO COMPACTADO CON MATERIAL PROPIO EN CIMENTACION M3 60.00 S/ 30.00 S/ 1,800.00
VIGA DE CIMENTACION PARA PORTON
EXCAVACION MANUAL DE TERRENO NATURAL M3 8.32 S/ 35.00 S/ 291.20
ELIMINACION DE MATERIAL EXCAVADO M3 12.55 S/ 45.00 S/ 564.75
OBRAS DE CONCRETO SIMPLE
SOLADO E=10 CM
CONSTRUCCION DE SOLADO 1:12 PARA ZAPATAS M3 12.00 S/ 250.00 S/ 3,000.00
CONSTRUCCION DE SOLADO 1:12 PARA VIGA DE CIMENTACION M3 1.00 S/ 250.00 S/ 250.00
CIMIENTO CORRIDO H=80 CM
CONSTRUCCION DE CIMIENTO CORRIDO 1:12 + 30% P.G (10") M3 52.00 S/ 350.00 S/ 18,200.00
OBRAS DE CONCRETO ARMADO
ZAPATA DE COLUMNAS CERCO PERIMETRICO
ACERO DE REFUERZO KG 585.00 S/ 6.50 S/ 3,802.50
CONCRETO F'C 210 KG/CM2 M3 28.00 S/ 550.00 S/ 15,400.00
ZAPATA COLUMNAS PORTICO
ACERO DE REFUERZO KG 206.21 S/ 6.50 S/ 1,340.37
CONCRETO F'C 210 KG/CM2 M3 6.00 S/ 550.00 S/ 3,300.00
COLUMNA C-1 Y C-2 (30X30 CM / 25X25 CM)
ACERO DE REFUERZO KG 2,252.20 S/ 6.50 S/ 14,639.30
ENCOFRADO Y DESENCOFRADO NORMAL M2 174.48 S/ 55.00 S/ 9,596.56
CONCRETO F'C 210 KG/CM2 M3 20.00 S/ 550.00 S/ 11,000.00
COLUMNA DE PORTON 30X50 CM
ACERO DE REFUERZO KG 546.85 S/ 6.50 S/ 3,554.53
ENCOFRADO Y DESENCOFRADO NORMAL M2 40.45 S/ 55.00 S/ 2,224.75
CONCRETO F'C 210 KG/CM2 M3 5.00 S/ 550.00 S/ 2,750.00
SOBRECIMIENTO ARMADO(H=90 CM, E=15 CM)
ACERO DE REFUERZO KG 2,287.37 S/ 6.50 S/ 14,867.90
ENCOFRADO Y DESENCOFRADO NORMAL M2 218.38 S/ 55.00 S/ 12,010.90
CONCRETO F'C 210 KG/CM2 M3 18.00 S/ 550.00 S/ 9,900.00
VIGA VA (25X25 CM)
ACERO DE REFUERZO KG 1,078.62 S/ 8.00 S/ 8,629.00
ENCOFRADO Y DESENCOFRADO NORMAL M2 78.40 S/ 55.00 S/ 4,312.00
CONCRETO F'C 210 KG/CM2 M3 11.00 S/ 550.00 S/ 6,050.00
VIGA DE PORTON (50X25 CM)
ACERO DE REFUERZO KG 420.42 S/ 8.00 S/ 3,363.36
ENCOFRADO Y DESENCOFRADO NORMAL M2 16.43 S/ 55.00 S/ 903.65
CONCRETO F'C 210 KG/CM2 M3 2.20 S/ 550.00 S/ 1,210.00
VIGA DE CIMENTACION PARA RIEL PORTON (50X25 CM)
ACERO DE REFUERZO KG 459.91 S/ 8.00 S/ 3,679.28
CONCRETO F'C 210 KG/CM2 M3 4.00 S/ 550.00 S/ 2,200.00
3.00.00 ARQUITECTURA S/ 33,640.00
ALBAÑILERIA
ASENTADO DE SOGA DE LADRILLO K.K 18 HUECOS, CARAVISTA. INCL.
M2 240.00 S/ 65.00 S/ 15,600.00
ANDAMIOS
REVOQUES Y REVESTIMIENTOS
TARRAJEO DE SOBRECIMIENTO C/PULIDO M2 150.00 S/ 50.00 S/ 7,500.00
TARRAJEO DE COLUMNAS M2 80.00 S/ 50.00 S/ 4,000.00
TARRAJEO DE VIGAS M2 100.00 S/ 60.00 S/ 6,000.00
CORTE Y JUNTAS
SUMINISTRO E INSTALACION DE TECNOPOR DE 1" ENTRE COLUMNAS ML 54.00 S/ 10.00 S/ 540.00
4.00.00 VARIOS S/ 13,250.00
ESTADIA DE PERSONAL MOVILIDAD + ALIMENTACION GLB 1.00 S/ 10,000.00 S/ 10,000.00
CONSTRUCCION DE PISO PROVISIONAL PARA CASETA DE VIGILANCIA M2 10.00 S/ 150.00 S/ 1,500.00
SUMINISTRO E INSTALACION DE CASETA PREFABRICADA 2X2 MT APROX UND 1.00 S/ 1,750.00 S/ 1,750.00
5.00.00 INSTALACIONES ELECTRICAS S/ 29,900.00
INSTALACIONES ELÉCTRICAS - CERCO PERIMETRICO-CASETA DE VIGILANCIA -
SSHH
SUMINISTRO E INSTALACION DE TUBERIA CONDUIT EMT 3/4" PARA
ML 96.00 25.00 S/ 2,400.00
ALUMBRADO INCLUYE ACCESORIOS
SUMINISTRO Y CABLEADO DE TUBERIAS PARA ALUMBRADO ML 96.00 S/ 25.00 S/ 2,400.00
SUMINISTRO E INSTALACION DE PASTORALES Y REFLECTORES DE 200W Y
UND 8.00 600.00 S/ 4,800.00
REFLECTOR PUBLICO CON PANEL SOLAR
SUMINISTRO E INSTALACION DE TABLERO ELECTRICO GENERAL Y 02
SUBTABLEROS, INCLUYE CABLEADO Y LLAVES TERMOMAGNETICAS Y UND 2.00 S/ 3,900.00 S/ 7,800.00
DIFERENCIALES
SUMINISTRO E INSTALACIÓN DE POZO A TIERRA UND 1.00 S/ 4,000.00 S/ 4,000.00
ALIMENTADOR DE TABLERO GENERAL, INCLUYE TUBERIAS GLB 1.00 S/ 8,500.00 S/ 8,500.00
COSTO DIRECTO S/ 281,180.05
DSCT S/ 5,180.05
MONTO TOTAL S/ 276,000.00