VALORIZACION Nº 02 - DICIEMBRE 2022

OBRA :
“MEJORAMIENTO Y AMPLIACION DEL CAMPO DEPORTIVO EN EL CASERIO DE AHIJADERO DISTRITO DE SAN JUAN PROVINCIA DE SIHUAS REGION ANCASH”

PROPIETARIOMUNICIPALIDAD
: DISTRITAL DE SAN JUAN
MONTO DE EJECUCION 61,859.28
LUGAR AHIJADERO
: FECHA DE INICIO DE OBRA 18/11/2022
SUPERVISORING.
: BRAULIO FRANCISCO DE LA CRUZ DOMINGUEZ PLAZO DE EJECUCION 30 días calendarios.
RESIDENTE ING.
: MILTON ABIMAEL GUILLEN CHUCHO FECHA TERMINO OBRA 17/12/2022

AVANCES
PRESUPUESTO
ITEM DESCRIPCION ANTERIOR ACTUAL ACUMULADO SALDO
Valoriz. Valoriz. Valoriz. Valoriz.
Und. Metrado Precio S/. Parcial S/. Metrado % Metrado % Metrado % Metrado %
(S/.) (S/.) (S/.) (S/.)

01 OBRAS PROVISIONALES 2,068.47 2,068.47 0.00 2,068.47 0.00

01.01 CARTEL DE OBRA 2.40 x 3.60 m. UND 1.00 559.67 559.67 1.00 559.67 100.00% 0.00 0.00 0.00% 1.00 559.67 100.00% 0.00 0.00 0.00%

01.02 ALMACEN DE OBRA glb 1.00 243.36 243.36 1.00 243.36 100.00% 0.00 0.00 0.00% 1.00 243.36 100.00% 0.00 0.00 0.00%

01.03 MOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 1,265.45 1,265.45 1.00 1265.45 100.00% 0.00 0.00 0.00% 1.00 1265.45 100.00% 0.00 0.00 0.00%

2.0 OBRAS PRELIMINARES 2,340.10 1,950.74 65.37 2,016.10 324.00

2.1 TALA DE ARBOLES Y ELIMINACION DE RAICES CON EQUIPO und 50.00 11.78 588.92 50.00 588.92 100.00% 0.00 0.00 0.00% 50.00 588.92 100.00% 0.00 0.00 0.00%

2.2 TRAZO N IVELACION Y REPLANTEO m2 2,700.00 0.36 972.45 2,700.00 972.45 100.00% -900.00 -324.00 0.00% 1,800.00 648.45 66.67% 900.00 324.00 33.33%

2.3 DEMOLICION DE CONSTRUCCION EXISTENTE glb 1.00 778.74 778.74 0.50 389.37 50.00% 0.50 389.37 50.00% 1.00 778.74 100.00% 0.00 0.00 0.00%

3.0 MOVIMIENTO DE TIERRA 24,608.75 17,320.75 2,476.24 19,796.99 4,813.58

3.1 CORTE DE MATERIAL SUELTO RENDIMIENTO 400M3/DIA m3 2,535.50 5.26 13,327.79 1,635.50 8596.96 64.50% 346.57 1822.95 13.67% 1,982.07 10419.91 78.17% 553.43 2911.04 21.83%

3.2 RELLENO CON MATERIAL DE CORTE m3 540.48 4.95 2,677.92 540.48 2677.92 100.00% -253.98 -1257.20 0.00% 286.50 1420.72 53.01% 253.98 1257.20 46.99%

3.3 ELIMINACION DE MATERIAL DE CORTE CON CARGADOR m3 1,995.02 4.31 8,603.04 1,402.02 6045.87 70.28% 443.27 1910.49 22.22% 1,845.29 7956.36 92.49% 149.73 645.34 7.51%

4.0 VARIOS 4,965.23 4,965.23 0.00 4,965.23 0.00

4.1 SUMINISTRO E INSTALACION DE ARCO PARA FUTBOL und 2.00 2,482.61 4,965.23 2.00 4965.23 100.00% 0.00 0.00 0.00% 2.00 4965.23 100.00% 0.00 0.00 0.00%

MEDIDAS PARA PREVENCION Y CONTROL FRENTE A LA


5.0 3,541.31 3,541.31 0.00 3,541.31 0.00
PROPAGACION DE COVID - 19

MEDIDAS PARA PREVENCION Y CONTROL FRENTE A LA PROPAGACION


5.1 glb 1.00 3,541.31 3,541.31 1.00 3541.31 100.00% 0.00 0.00 0.00% 1.00 3541.31 100.00% 0.00 0.00 0.00%
DE COVID - 19

6 FLETE 5,000.95 5,000.95 0.00 5,000.95 0.00

6.1 FLETE TERRESTRE glb 1.00 5,000.95 5,000.95 1.00 5,000.95 100.00% 0.00 0.00 0.00% 1.00 5,000.95 100.00% 0.00 0.00 0.00%

COSTO DIRECTO S/. 42,524.80 S/. 34,847.45 81.95% S/. 2,541.61 5.98% S/. 37,389.06 87.92% S/. 5,137.58 12.08%

GASTOS GENERALES (13.27658584%) S/. 5,645.84 S/. 4,626.55 S/. 337.44 S/. 4,963.99 S/. 682.10

UTILIDAD (9.999999999999%) S/. 4,252.48 S/. 3,484.75 S/. 254.16 S/. 3,738.91 S/. 513.75

SUB TOTAL S/. 52,423.13 S/. 42,958.75 S/. 3,133.21 S/. 46,091.96 S/. 6,333.43

IGV S/. 9,436.16 S/. 7,732.57 S/. 563.98 S/. 8,296.55 S/. 1,140.02

TOTAL EJECUCION S/. 61,859.28 S/. 50,691.30 81.95% S/. 3,694.52 5.97% S/. 54,385.82 87.92% S/. 7,473.46 12.08%