Activity Activity Orig Early Early

2008 2009 2010


ID Description Dur Start Finish J A S O N D J F M A M J J A S O N D J F
PNPB NITRATE-PRILLING PLANT (TARGET)
HI HITO
HITO HITO

H1400 Project Startup 0 14JUL08*


H1170 Detailed Engineering Nitrate Plant Startup 0 01SEP08*
H1180 Crystallization Engineering HPD Startup 0 01SEP08*
H1000 Bertrams Chemical Contract Startup 0 03NOV08*
H1100 Bertrams Heatec Contract Startup 0 03DEC08*
H1190 Hazop Nitrate Plant 2 22DEC08 23DEC08
H1300 Basic Engineering Bertrams Heatec End 0 01APR09*
H1200 Basic Engineering Bertrams Chemicals End 0 01APR09*
H1210 Hazop Prilling Plant 2 04MAY09 05MAY09
H1500 Basic Engineering End 0 01JUN09*
H1310 Detailed Engineering End 0 02OCT09*
H1290 Management & Administration Paquerte of Requisit 0 15JAN10*
CB INGENIERIA CONCEPTUAL-BASICA
2000 GENERAL
FS Proceso
FSPCB21001 Trade Off Localización Nitrato - Prilado (DW) 23 14JUL08 14AUG08
FSDCB21001 Trade Off Localización Nitrato - Prilado 23 14JUL08 14AUG08
SE Estructura
SEDCB20001 PLANO BASICO MOV.DE TIERRAS PLANTA 9 20OCT08 30OCT08
SEDCB21005 CUBICACIONES 10 03NOV08 14NOV08
ME Mecánica
MEDCB20002 Mechanical Design Criteria - Wet Harvest & Prill 10 26AUG08 08SEP08
MEDCB20004 Material Take Off - Wet Harvest & Prilling 5 02SEP08 08SEP08
MEDCB21001 Technical Report (Process Support) 10 09SEP08 24SEP08
MEDCB20003 Cost Report - Wet Harvest & Prilling 5 09SEP08 15SEP08
MEPCB21001 Contribution PL-SK-001 3 25SEP08 29SEP08
MEPCB21002 Contribution PL-SK-002 3 25SEP08 29SEP08
IN Instrumentación
INDCB20001 DESIGN CRITERIA 42 15OCT08 15DEC08
INDCB20002 INSTRUMENT AND CONTROL COST REPORT 42 15OCT08 15DEC08
INDCB20003 SPEC - INSTRUMENTATION & CONTROL IN MAYOR EQUIP 42 15OCT08 15DEC08
INDCB20004 INSTRUMENTS LIST 42 15OCT08 15DEC08

H1600 Basic Engineering General Area End 0 15DEC08*


3000 WET HARVEST
FS Proceso
FSPCB30001 Process Flow Diagrams 29 14JUL08 25AUG08
FSDCB30001 Design Criteria Update 20 14JUL08 11AUG08
FSDCB30002 Process Data Sheet 29 01AUG08 10SEP08

Start Date 14JUL08 PNPB Sheet 1 of 8


Early Bar
Finish Date 15JAN10 ATACAMA MINERALS Date Revision Checked Approved
Progress Bar
Data Date 14JUL08
Run Date 20NOV08 11:11 Critical Activity
NITRATE-PRILLING PLANT (TARGET)

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early
2008 2009 2010
ID Description Dur Start Finish J A S O N D J F M A M J J A S O N D J F
FSDCB30003 Process Data Sheet 28 01AUG08 10SEP08
FSDCB30004 Process Data Sheet 28 01AUG08 10SEP08
FSDCB30005 Process Data Sheet 29 01AUG08 10SEP08
FSPCB30002 P & ID 29 01AUG08 10SEP08
SE Estructura
SEPCB30001 PLANO BASICO MOV.DE TIERRAS PLANTA 11 10SEP08 26SEP08
SEPCB32001 PLANO PREDISEÑO DE ESTRUCTURA HARNERO 10 12NOV08 25NOV08
SEDCB32001 MEMORIA DE CALCULO DE PREDISEÑO HANERO 5 12NOV08 18NOV08
ME Mecánica
MEDCB30004 Wet Harvest Zone 5 26AUG08 01SEP08
MEDCB31001 Duty Specification - Mudcat 3 02SEP08 04SEP08
MEDCB32002 Duty Specification - Dewatering Screen 3 02SEP08 04SEP08
MEDCB33003 Duty Specification - Belt conveyor 3 02SEP08 04SEP08
PD Piping
PDPCB30001 PIPING PLOT PLAN 7 02SEP08 10SEP08
PDCCB30003 CALCULATION - BOX 2 11SEP08 12SEP08
PDDCB30001 DATA SHEET - PUMP 1 11SEP08 11SEP08
PDDCB30002 DATA SHEET - BOX 1 15SEP08 15SEP08
EE Electricidad
EEPCB30001 ONE LINE DIAGRAM 1 06AUG08 06AUG08
EEDCB30001 MTO 43 08AUG08 10OCT08
EEPCB30002 MAIN FEEDERS LAYOUT 19 22SEP08 17OCT08
EEPCB30004 GROUNDING SYSTEM (REV) 18 23SEP08 17OCT08
EEPCB30005 ELECTRICALS EQUIPMENTS LAYOUT 17 24SEP08 17OCT08
EEDCB30002 MTO 22 29SEP08 29OCT08
EEDCB30003 DATA SHEET SUBESTATION 22 29SEP08 29OCT08
EEDCB30004 DATA SHEET LOCAL PANEL 22 29SEP08 29OCT08
EEPCB30003 ONE LINE DIAGRAM 20 10NOV08 05DEC08
EEDCB30005 POWER CIRCUIT LIST (REV) 18 14NOV08 10DEC08

H1700 Basic Engineering Wet Harvest Area End 0 15DEC08*


4000 NITRATE PLANT
FS Proceso
FSDCB40001 Revisión Ingeniería Básica 74 14JUL08 30OCT08
SE Estructura
SEDCB43001 MEMORIA CALCULO PREDISEÑO EDIF. CRISTALIZADORES 5 15OCT08 21OCT08
PD Piping
PDDCB40004 DATA SHEET - TANK - BUFFER TANK N°1 66 22AUG08 27NOV08
PDDCB40005 DATA SHEET - TANK - BUFFER TANK N°2 66 22AUG08 27NOV08
PDDCB40006 DATA SHEET - TANK - BUFFER TANK N°3 66 22AUG08 27NOV08
PDDCB41013 DATA SHEET - TANK - MLK TANK 66 22AUG08 27NOV08
PDDCB41014 DATA SHEET - TANK - CENTRATE TANK N°1 66 22AUG08 27NOV08
PDDCB42024 DATA SHEET - TANK - CENTRATE TANK N°2 66 22AUG08 27NOV08

Start Date 14JUL08 PNPB Sheet 2 of 8


Early Bar
Finish Date 15JAN10 ATACAMA MINERALS Date Revision Checked Approved
Progress Bar
Data Date 14JUL08
Run Date 20NOV08 11:11 Critical Activity
NITRATE-PRILLING PLANT (TARGET)

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early
2008 2009 2010
ID Description Dur Start Finish J A S O N D J F M A M J J A S O N D J F
PDDCB42025 DATA SHEET - TANK - OVERFLOW TANK 66 22AUG08 27NOV08
PDDCB42026 DATA SHEET - TANK - STRONG SOLUTION TANK 66 22AUG08 27NOV08
PDDCB43035 DATA SHEET - TANK - HOT WATER TANK 66 22AUG08 27NOV08
PDDCB43036 DATA SHEET - TANK - MOTHER LIQUOR TANK 66 22AUG08 27NOV08
PDDCB43037 DATA SHEET - TANK - CENTRATE TANK N°3 66 22AUG08 27NOV08
PDDCB40001 GENERAL SPECIFICATION - PIPING MATERIAL 42 22AUG08 23OCT08
PDDCB41007 DATA SHEET - PUMP - FEED TANK N°1 PUMP 109 10SEP08 18FEB09
PDDCB41008 DATA SHEET - PUMP - MLK TANK N°1 PUMP 109 10SEP08 18FEB09
PDDCB41009 DATA SHEET - PUMP - TH N°1 UNDER FLOW PUMP 109 10SEP08 18FEB09
PDDCB41010 DATA SHEET - PUMP - FEED TANK N°2 PUMP 109 10SEP08 18FEB09
PDDCB41011 DATA SHEET - PUMP - CENTRATE TANK N°1 PUMP 109 10SEP08 18FEB09
PDDCB41012 DATA SHEET - PUMP - HEAT EXCHANGER N°2 CIRCULATI 109 10SEP08 18FEB09
PDDCB42015 DATA SHEET - PUMP - HEAT EXCHANGER N°3 CIRCULATI 109 10SEP08 18FEB09
PDDCB42016 DATA SHEET - PUMP - REACTOR N°4 PUMP 109 10SEP08 18FEB09
PDDCB42017 DATA SHEET - PUMP - TH N°2 UNDER FLOW PUMP 109 10SEP08 18FEB09
PDDCB42018 DATA SHEET - PUMP - REACTOR N°5 PUMP 109 10SEP08 18FEB09
PDDCB42019 DATA SHEET - PUMP - TH N°3 OVER FLOW FILTER N°1, 109 10SEP08 18FEB09
PDDCB42020 DATA SHEET - PUMP - TH N°3 UNDER FLOW PUMP 109 10SEP08 18FEB09
PDDCB42021 DATA SHEET - PUMP - CENTRATE TANK N°2 PUMP 109 10SEP08 18FEB09
PDDCB42022 DATA SHEET - PUMP - STRONG SOLUTION TANK PUMP 109 10SEP08 18FEB09
PDDCB42023 DATA SHEET - PUMP - FEED TANK N°3 PUMP 109 10SEP08 18FEB09
PDDCB43027 DATA SHEET - PUMP - CONDENSATE FEED BOX PUMP 109 10SEP08 18FEB09
PDDCB43028 DATA SHEET - PUMP - HOT WATER TANK PUMP 109 10SEP08 18FEB09
PDDCB43029 DATA SHEET - PUMP - TH N°4 UNDER FLOW PUMP 109 10SEP08 18FEB09
PDDCB43030 DATA SHEET - PUMP - CENTRATE TANK N°3 109 10SEP08 18FEB09
PDDCB43031 DATA SHEET - PUMP - MLK TANK N°2 PUMP 109 10SEP08 18FEB09
PDDCB43032 DATA SHEET - PUMP - PURGE MLK PUMP 109 10SEP08 18FEB09
PDDCB43033 DATA SHEET - PUMP - FEED TANK N°4 109 10SEP08 18FEB09
PDDCB43034 DATA SHEET - PUMP - TRANSFER CRISTALIZATION N°2 109 10SEP08 18FEB09
PDDCB40003 DATA SHEET - PUMP - BUFFER PUMP N°1 Y N°2 109 17SEP08 25FEB09
PDDCB40002 REPORT - PROCESSES PUMP SYSTEMS 104 26SEP08 25FEB09

H1800 Basic Engineering Nitrate Plant Area End 0 26FEB09*


5000 PRILLING PLANT
FS Proceso
FSDCB50004 Balance de Masa Global (3 Productos) 20 15SEP08 15OCT08
FSDCB50005 Balance de Energía Global (3 Productos) 20 15SEP08 15OCT08
FSPCB50001 Flow Diagrams General 20 15SEP08 15OCT08
FSDCB52001 Pruebas para diseño Sistema de Ducheo 40 03NOV08 30DEC08
FSDCB50006 Mass Balance, Prilling Plant KNO3-NaNO3-SPO 20 01DEC08 30DEC08
FSDCB52015 Process Data Sheet Prilling Area 20 01DEC08 30DEC08
FSDCB52016 Process Data Sheet Prilling Area 20 01DEC08 30DEC08
FSDCB52002 Resultados de Pruebas Piloto Sistema de Ducheo 18 03DEC08 30DEC08
FSDCB51013 Process Data Sheet Melting and Circulation Area 18 03DEC08 30DEC08
Start Date 14JUL08 PNPB Sheet 3 of 8
Early Bar
Finish Date 15JAN10 ATACAMA MINERALS Date Revision Checked Approved
Progress Bar
Data Date 14JUL08
Run Date 20NOV08 11:11 Critical Activity
NITRATE-PRILLING PLANT (TARGET)

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early
2008 2009 2010
ID Description Dur Start Finish J A S O N D J F M A M J J A S O N D J F
FSDCB51014 Process Data Sheet Melting and Circulation Area 18 03DEC08 30DEC08
FSPCB51002 Flow Diagrams Melting and Circulation Area, KNO3 18 03DEC08 30DEC08
FSPCB51004 Flow Diagrams Melting and Circulation Area, SPO 18 03DEC08 30DEC08
FSPCB51006 Flow Diagrams Melting and Circulation Area, NaNO 18 03DEC08 30DEC08
FSPCB51008 P&ID Melting and Circulation Area, P.P. KNO3 18 03DEC08 30DEC08
FSPCB51010 P&ID Melting and Circulation Area, SPO 18 03DEC08 30DEC08
FSPCB51012 P&ID Melting and Circulation Area, NaNO3 18 03DEC08 30DEC08
FSDCB50010 Equipment Dimensioning Prilling Plant 10 30DEC08 13JAN09
FSDCB50011 Process Control Loop List Prilling Plant 10 30DEC08 13JAN09
FSPCB52003 Flow Diagrams Prilling Area, Prilling Plant KNO3 18 31DEC08 26JAN09
FSPCB52005 Flow Diagrams Prilling Area, Prilling Plant SPO 18 31DEC08 26JAN09
FSPCB52007 Flow Diagrams Prilling Area, Prilling Plant NaNO 18 31DEC08 26JAN09
FSPCB52009 P&ID Prilling Area, Prilling Plant KNO3 18 31DEC08 26JAN09
FSPCB52011 P&ID Prilling Area, Prilling Plant SPO 18 31DEC08 26JAN09
FSPCB52013 P&ID Prilling Area, Prilling Plant NaNO3 18 31DEC08 26JAN09
FSDCB50003 Informe Descripción del Proceso 10 31DEC08 14JAN09
FSDCB50007 Energy Balance, Prilling Plant KNO3-NaNO3-SPO 20 02FEB09 27FEB09
FSDCB50008 Design Criteria Prilling Plant 20 02FEB09 27FEB09
FSDCB50009 Equipment List Prilling Plant 20 02FEB09 27FEB09
FSDCB50012 Opex Prilling Plant 3 02MAR09 04MAR09
SE Estructura
SEDCB51001 MEMORIA DE CALCULO DE PREDISEÑO HORNO 5 02APR09 08APR09
SEDCB51002 MEMORIA DE CALCULO DE PREDISEÑO PLATAFORMAS 5 09APR09 16APR09
SEDCB51003 MEMORIA DE CALCULO DE PREDISEÑO GRUA 5 17APR09 23APR09
SEDCB52006 MEMORIA DE CALCULO DE PREDISEÑO ASCENSOR 5 24APR09 30APR09
SEDCB52004 MEMORIA DE CALCULO DE PREDISEÑO PRILADO ACERO 5 24APR09 30APR09
SEDCB52005 MEMORIA CALCULO DE PREDISEÑO PRILADO FUNDACIONE 5 24APR09 30APR09
SEPCB51001 PLANO PREDISEÑO DE FORMA HORMIGON FUNDACIONES 5 04MAY09 08MAY09
SEPCB50001 PLANO BASICO MOV.DE TIERRAS PLANTA 5 04MAY09 08MAY09
SEPCB51003 PLANO PREDISEÑO DE ESTRUCTURAS PUENTE GRUA 5 11MAY09 15MAY09
SEPCB51002 PLANO PREDISEÑO DE ESTRUCTURAS PLATAFORMAS 5 11MAY09 15MAY09
SEPCB51008 PLANO PREDISEÑO DE ESTRUCTURAS HORNO 5 18MAY09 25MAY09
SEPCB52005 PLANO PREDISEÑO DE ESTRUCTURAS PRILADO ACERO 5 18MAY09 25MAY09
SEPCB51004 PLANO PREDISEÑO ESTRUCTURAS ELEVADOR DE CAPACHO 5 18MAY09 25MAY09
SEPCB52002 PLANO PREDISEÑO DE ESTRUCTURAS ASCENSOR 5 26MAY09 01JUN09
SEPCB52006 PLANO PREDISEÑO DE ESTRUCTURAS PRILADO ACERO 5 26MAY09 01JUN09
SEPCB52007 PLANO PREDISEÑO ESTRUC. PRILADO Y ASCENSOR FUNDA 5 26MAY09 01JUN09
ME Mecánica
MEDCB50001 Melting and Circulation & Prilling Plant 10 02APR09 16APR09
MEDCB50002 Melting and Circulation & Prilling Plant - Eleva 10 17APR09 30APR09
MEDCB51003 Melting, Circulation and Tower TK 5 17APR09 23APR09
MEDCB51004 Filter 3 04MAY09 06MAY09
MEDCB51005 Melting Boiler 3 04MAY09 06MAY09
MEDCB51006 Bridge Crane 3 07MAY09 11MAY09

Start Date 14JUL08 PNPB Sheet 4 of 8


Early Bar
Finish Date 15JAN10 ATACAMA MINERALS Date Revision Checked Approved
Progress Bar
Data Date 14JUL08
Run Date 20NOV08 11:11 Critical Activity
NITRATE-PRILLING PLANT (TARGET)

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early
2008 2009 2010
ID Description Dur Start Finish J A S O N D J F M A M J J A S O N D J F
MEDCB52007 Tray Conveyor 3 07MAY09 11MAY09
MEDCB52008 Hoist 3 12MAY09 14MAY09
PD Piping
PDDCB50003 REPORT - PUMP SYSTEMS 15 03DEC08 24DEC08
PDDCB50004 DATA SHEET - PUMP - TOWER PUMP 15 26DEC08 16JAN09
PDDCB50001 LINE LIST 15 26DEC08 16JAN09
PDDCB50002 VALVE LIST 15 26DEC08 16JAN09
PDDCB50005 DATA SHEET - PUMP - CIRCULATION PUMP 15 26DEC08 16JAN09
PDPCB50001 PIPING PLOT PLAN 15 19JAN09 06FEB09
PDPCB50002 PIPING KEY PLAN 15 09FEB09 27FEB09
EE Electricidad
EEPCB50003 ONE LINE DIAGRAM MT 5 02APR09 08APR09
EEDCB50001 MTO 5 02APR09 08APR09
EEPCB50001 GENERAL ONE LINE DIAGRAM 5 09APR09 16APR09
EEDCB50003 POWER CIRCUIT LIST 5 09APR09 16APR09
EEPCB50005 ONE LINE DIAGRAM LV 5 09APR09 16APR09
EEDCB50002 MTO 5 09APR09 16APR09
EEPCB50002 GENERAL ONE LINE DIAGRAM 5 09APR09 16APR09
EEPCB50008 GROUNDING SYSTEM 5 17APR09 23APR09
EEPCB50004 ONE LINE DIAGRAM LV 5 17APR09 23APR09
EEPCB50006 ELECTRICALS EQUIPMENTS LAYOUT 5 17APR09 23APR09
EEPCB50007 ELECTRICALS EQUIPMENTS LAYOUT 5 17APR09 23APR09
EEDCB50004 DATA SHEET ELECTRICAL ROOM 3 24APR09 28APR09
EEDCB50005 DATA SHEET MCC LV 3 24APR09 28APR09
EEDCB50006 DATA SHEET MCC MT 3 24APR09 28APR09
EEDCB50007 DATA SHEET SUBESTATION 3 24APR09 28APR09

H1900 Basic Engineering Prilling Plant Area End 0 01JUN09*


6000 DRYING, SCREENING, COOLING AND STORAGE AREA
FS Proceso
FSDCB60001 Eq. Dimensioning Screening, Cooling and Storage 20 02APR09 30APR09
FSPCB62001 Flow Diagrams Screening Area, Prilling Plant KNO 20 02APR09 30APR09
FSPCB62003 Flow Diagrams Screening Area, Prilling Plant SP 20 02APR09 30APR09
FSPCB62005 Flow Diagrams Screening Area, P. Plant NaNO3 20 02APR09 30APR09
FSPCB63002 Flow Diagrams Storage and Bagging Area, KNO3 20 02APR09 30APR09
FSPCB63004 Flow Diagrams Storage and Bagging Area, SPO 20 02APR09 30APR09
FSPCB63006 Flow Diagrams Storage and Bagging Area, NaNO3 20 02APR09 30APR09
FSDCB62002 Process Data Sheet Screening Area 10 04MAY09 15MAY09
FSDCB62003 Process Data Sheet Screening Area 10 04MAY09 15MAY09
FSDCB63004 Process Data Sheet Storage and Bagging Area 10 04MAY09 15MAY09
FSDCB63005 Process Data Sheet Storage and Bagging Area 10 04MAY09 15MAY09
FSPCB62007 P&ID Screening Area, Prilling Plant KNO3 10 04MAY09 15MAY09
FSPCB62009 P&ID Screening Area, Prilling Plant SPO 10 04MAY09 15MAY09
FSPCB62011 P&ID Screening Area, Prilling Plant NaNO3 10 04MAY09 15MAY09
Start Date 14JUL08 PNPB Sheet 5 of 8
Early Bar
Finish Date 15JAN10 ATACAMA MINERALS Date Revision Checked Approved
Progress Bar
Data Date 14JUL08
Run Date 20NOV08 11:11 Critical Activity
NITRATE-PRILLING PLANT (TARGET)

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early
2008 2009 2010
ID Description Dur Start Finish J A S O N D J F M A M J J A S O N D J F
FSPCB63008 P&ID Storage and Bagging Area, P. Plant KNO3 10 04MAY09 15MAY09
FSPCB63010 P&ID Storage and Bagging Area, P. Plant SPO 10 04MAY09 15MAY09
FSPCB63012 P&ID Storage and Bagging Area, P. Plant NaNO3 10 04MAY09 15MAY09
PD Piping
PDDCB61001 DATA SHEET - PUMP - DRYER DUST SOLUTION PUMP 109 14JUL08 22DEC08
PDDCB62003 DATA SHEET - PUMP - COOLER DUST SOLUTION PUMP 109 14JUL08 22DEC08
PDDCB61002 DATA SHEET - TANK - ANTICAKING APLICATION TANK 66 14JUL08 20OCT08

H1110 BC-Drying,Screening,Cooling and Storage Area End 0 15MAY09*


7000 S/E Y CONTROL
EE Electricidad
EEDCB70001 CALCULATION REPORT 10 04MAY09 15MAY09
EEDCB70002 POWER CIRCUIT LIST 10 04MAY09 15MAY09
EEDCB70003 MTO 10 04MAY09 15MAY09
EEDCB70004 LOAD FLOW STUDY REPORT (REVIEW) 10 04MAY09 15MAY09
EEPCB70001 DISTRIBUTION LINE 10 04MAY09 15MAY09
EEPCB70002 DISTRIBUTION LINE 10 04MAY09 15MAY09

H1120 Basic Engineering S/E y Control Area End 0 01JUN09*


8000 UTILITIES
FS Proceso
FSDCB80002 Mass Balance Prill Tower Utilities 15 05DEC08 29DEC08
FSDCB80001 Utilities Wet Harvest Mass Balance 15 05DEC08 29DEC08
FSDCB80003 Energy Balance Prill Tower Utilities 15 05DEC08 29DEC08
FSPCB80001 Process Flow Diagrams Prill Tower Utilities 15 05DEC08 29DEC08
EE Electricidad
EEDCB80003 MTO 5 03DEC08 10DEC08
EEDCB80001 DATA SHEET 3 03DEC08 05DEC08
EEDCB80002 DATA SHEET 3 03DEC08 05DEC08
EEDCB80004 POWER CIRCUIT LIST 5 11DEC08 17DEC08
EEPCB80001 GENERAL ONE LINE DIAGRAM 5 11DEC08 17DEC08
EEPCB80002 ELECTRICALS EQUIPMENTS LAYOUT 5 11DEC08 17DEC08
EEPCB80003 ELECTRICALS EQUIPMENTS LAYOUT 5 11DEC08 17DEC08

H1130 Basic Engineering Utilities Area End 0 15APR09*


0080 REVISION INGENIERIA BASICA C-1276
FS Proceso
FSDCB08001 Balance de Masa, KNO3 34 14JUL08 01SEP08
FSDCB08002 Balance de Energía, KNO3 34 14JUL08 01SEP08
FSDCB08005 Balance de Masa, SPO 34 21JUL08 05SEP08
FSDCB08007 Balance de Energía, SPO 34 21JUL08 05SEP08
FSPCB08001 Grinding Area, KNO3 34 21JUL08 05SEP08
FSDCB08004 Dimensonamiento de Equipos, KNO3 34 21JUL08 05SEP08

Start Date 14JUL08 PNPB Sheet 6 of 8


Early Bar
Finish Date 15JAN10 ATACAMA MINERALS Date Revision Checked Approved
Progress Bar
Data Date 14JUL08
Run Date 20NOV08 11:11 Critical Activity
NITRATE-PRILLING PLANT (TARGET)

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early
2008 2009 2010
ID Description Dur Start Finish J A S O N D J F M A M J J A S O N D J F
FSPCB08002 STP Area, KNO3 34 25JUL08 11SEP08
FSDCB08006 Balance de Masa, NaNO3 34 25JUL08 11SEP08
FSDCB08008 Balance de Energía, NaNO3 34 25JUL08 11SEP08
FSPCB08003 Convertion Area, KNO3 34 31JUL08 17SEP08
FSPCB08004 Crystallization I Area, KNO3 34 06AUG08 25SEP08
FSDCB08003 Criterio de Diseño, KNO3 34 11AUG08 30SEP08
FSPCB08005 Crystallization II Area, KNO3 34 12AUG08 01OCT08
FSPCB08006 Drying Area, KNO3 34 19AUG08 07OCT08
FSPCB08007 Cooling and Bagging Area, KNO3 34 25AUG08 14OCT08
FSPCB08008 Dust Pick Up, KNO3 34 29AUG08 20OCT08
FSPCB08009 Crystallization II Area, SPO 34 08SEP08 28OCT08
FSDCB08009 Listado de Equipos, KNO3 - SPO - NaNO3 34 08SEP08 28OCT08
FSDCB08010 Criterio de Diseño, KNO3 - SPO - NaNO3 34 08SEP08 28OCT08
FSPCB08010 Drying Area, SPO 34 12SEP08 04NOV08
FSPCB08011 Cooling and Bagging Area, SPO 34 22SEP08 10NOV08
FSPCB08012 Dust Pick Up, SPO 34 26SEP08 14NOV08
FSPCB08013 Crystallization II Area, NaNO3 34 02OCT08 20NOV08
FSPCB08014 Drying Area, NaNO3 34 08OCT08 26NOV08
FSPCB08015 Cooling and Bagging Area, NaNO3 34 15OCT08 02DEC08
FSPCB08016 Dust Pick Up, NaNO3 34 21OCT08 09DEC08
ME Mecánica
MEPCB08008 PL-0080-GA-008 (Upgrade) 14 01SEP08 22SEP08
MEPCB08006 Silos / Enf 5 22SEP08 26SEP08
MEPCB08007 Silos / Enf. Elevación 5 22SEP08 26SEP08
MEPCB08004 Cristal / Secado Pte 5 10NOV08 14NOV08
MEPCB08005 Cristal / Sec Elevación 5 10NOV08 14NOV08
EE Electricidad
EEPCB08001 GENERAL ONE LINE DIAGRAM (REV) 5 29OCT08 05NOV08
EEDCB08004 LOAD FLOW STUDY REPORT (REVIEW) 5 06NOV08 12NOV08
EEPCB08002 MCC ONE LINE (REV.) 5 06NOV08 12NOV08
EEPCB08003 MCC ONE LINE (REV.) 5 06NOV08 12NOV08
EEPCB08004 MCC ONE LINE (REV.) 5 06NOV08 12NOV08
EEPCB08005 MCC ONE LINE (REV.) 5 06NOV08 12NOV08
EEDCB08003 POWER CIRCUIT LIST (REV) 5 13NOV08 19NOV08
EEDCB08001 CALCULATION REPORT (REV.) 5 20NOV08 26NOV08
EEDCB08002 MTO (REV.) 5 20NOV08 26NOV08
IN Instrumentación
INDCB08001 DESIGN CITERIA 23 01SEP08 03OCT08
INDCB08002 INSTRUMENT AND CONTROL COST REPORT 23 01SEP08 03OCT08
INDCB08003 INSTRUMENTS LIST 23 01SEP08 03OCT08
INPCB08001 BLOCK DIAGRAM 23 01SEP08 03OCT08

H1140 C-1276 Basic Engineering Review 0080 Area End 0 26NOV08*

Start Date 14JUL08 PNPB Sheet 7 of 8


Early Bar
Finish Date 15JAN10 ATACAMA MINERALS Date Revision Checked Approved
Progress Bar
Data Date 14JUL08
Run Date 20NOV08 11:11 Critical Activity
NITRATE-PRILLING PLANT (TARGET)

Classic Schedule Layout


© Primavera Systems, Inc.
Activity Activity Orig Early Early
2008 2009 2010
ID Description Dur Start Finish J A S O N D J F M A M J J A S O N D J F
0090 REVISION INGENIERIA BASICA C-1276
FS Proceso
FSPCB90001 Water Utilities, KNO3 34 14JUL08 01SEP08
FSPCB90002 Boilers, KNO3 34 14JUL08 01SEP08
FSPCB90003 Fuel Oil, Air, Additives and Na2CO3 Ut., KNO3 34 14JUL08 01SEP08
FSPCB90004 Water Utilities, SPO 34 14JUL08 01SEP08
FSPCB90005 Water Utilities, NaNO3 34 14JUL08 01SEP08
FSDCB90001 Balance de Masa Utilities, KNO3 34 14JUL08 01SEP08
FSDCB90002 Dimensionamiento Utilities, KNO3 34 14JUL08 01SEP08
ME Mecánica
MEPCB00001 GA Utilities Area 10 02SEP08 15SEP08

H1150 C-1276 Basic Engineering Review 0090 Area End 0 15SEP08*

Start Date 14JUL08 PNPB Sheet 8 of 8


Early Bar
Finish Date 15JAN10 ATACAMA MINERALS Date Revision Checked Approved
Progress Bar
Data Date 14JUL08
Run Date 20NOV08 11:11 Critical Activity
NITRATE-PRILLING PLANT (TARGET)

Classic Schedule Layout


© Primavera Systems, Inc.

También podría gustarte