Está en la página 1de 7

HOJA DE METRADOS

: “MEJORAMIENTO DEL SERVICIO EDUCATIVO DE NIVEL PRIMARIA EN LA INSTITUCIÓN EDUCATIVA N° 38072 DE SACHABAMBA,
OBRA DISTRITO DE CHIARA - HUAMANGA - AYACUCHO”
FORMULA : CERCO PERIMETRICO
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE CHIARA
FECHA : OCTUBRE DEL 2022
LUGAR : SACHABAMBA

DIMENSIONES (M)
Item Und. Nº de Veces PARCIAL TOTAL
LARGO ANCHO ALTURA
18 CONSTRUCCION CERCO PERIMETRICO
18.01 CERCO TIPO I
18.01.01 TRABAJOS PRELIMINARES
18.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 153.01
Cerco (Lado A-B ) 1.00 85.42 0.50 42.71
Cerco (Lado B-C ) 1.00 137.81 0.50 68.91
Cerco (Lado C-D) 1.00 82.79 0.50 41.40

18.01.01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION m2 153.01


Cerco (Lado A-B ) 1.00 85.42 0.50 42.71
Cerco (Lado B-C ) 1.00 137.81 0.50 68.91
Cerco (Lado C-D) 1.00 82.79 0.50 41.40

18.01.02 MOVIMIENTO DE TIERRAS


18.01.02.01 EXCAVACIONES
18.01.02.01.01 EXCAVACION DE ZANJA PARA CIMIENTOS HASTA H=1.0M m3 153.01
Cerco (Lado A-B ) 1.00 85.42 0.50 1.00 42.71
Cerco (Lado B-C ) 1.00 137.81 0.50 1.00 68.91
Cerco (Lado C-D) 1.00 82.79 0.50 1.00 41.40

18.01.02.02 RELLENOS
18.01.02.02.01 RELLENO MANUAL CON MATERIAL PROPIO m3 14.47
Parte superior de cimiento
Cerco (Lado B-C ) 137.81 0.35 Area= 0.30 14.47

18.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE


18.01.02.03.01 ACARREO MANUAL DE MATERIAL EXCEDENTE m3 ceof. Esponj 166.25
producto de la excavación 1.20 138.54 166.25

18.01.02.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 166.25


material acarreo 1.00 166.25 166.25

18.01.03 OBRAS DE CONCRETO SIMPLE


18.01.03.01 SOLADO
18.01.03.01.01 SOLADO MEZCLA 1:10 CEMENTO-HORMIGON, E=0.10M m2 34.50
Ubicacion de columnas 138.00 0.50 0.50 34.50

18.01.03.02 CIMIENTOS CORRIDOS


18.01.03.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON + 30% m3 153.01
Cerco (Lado A-B ) 1.00 85.42 0.50 1.00 42.71
Cerco (Lado B-C ) 1.00 137.81 0.50 1.00 68.91
Cerco (Lado C-D) 1.00 82.79 0.50 1.00 41.40

18.01.04 OBRAS DE CONCRETO ARMADO


18.01.04.02 SOBRECIMIENTOS
18.01.04.02.01 SOBRECIMIENTOS, CONCRETO F'C=175 KG/CM2 m3 32.13
Cerco (Lado A-B ) 1.00 85.42 0.15 0.70 8.97
Cerco (Lado B-C ) 1.00 137.81 0.15 0.70 14.47
Cerco (Lado C-D) 1.00 82.79 0.15 0.70 8.69

18.01.04.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 428.43


Cerco (Lado A-B ) 2.00 85.42 0.70 119.59
Cerco (Lado B-C ) 2.00 137.81 0.70 192.93
Cerco (Lado C-D) 2.00 82.79 0.70 115.91

18.01.04.02.03 SOBRECIMIENTOS, ACERO FY=4200 KG/CM2 kg 1.00 1,984.29 1984.29 1,984.29

18.01.04.03 COLUMNAS
18.01.04.03.01 COLUMNAS, CONCRETO F'C=175 KG/CM2 m3 24.15
Total columnas 138.00 0.25 0.25 2.80 24.15

18.01.04.03.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 386.40


Perimetro
Total columnas 138.00 1.00 2.80 386.40

18.01.04.03.03 COLUMNAS, ACERO FY=4200 KG/CM2 kg 4068.79


ver planilla de metrados para aceros 1.00 4,068.79 4068.79

18.01.04.04 VIGAS
18.01.04.04.01 VIGAS, CONCRETO F'C=175 KG/CM2 m3 Area 15.30
Cerco (Lado A-B ) 1.00 85.42 0.25 0.20 4.27
Cerco (Lado B-C ) 1.00 137.81 0.25 0.20 6.89
Cerco (Lado C-D) 1.00 82.79 0.25 0.20 4.14

Página 1
HOJA DE METRADOS
: “MEJORAMIENTO DEL SERVICIO EDUCATIVO DE NIVEL PRIMARIA EN LA INSTITUCIÓN EDUCATIVA N° 38072 DE SACHABAMBA,
OBRA DISTRITO DE CHIARA - HUAMANGA - AYACUCHO”
FORMULA : CERCO PERIMETRICO
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE CHIARA
FECHA : OCTUBRE DEL 2022
LUGAR : SACHABAMBA

DIMENSIONES (M)
Item Und. Nº de Veces PARCIAL TOTAL
LARGO ANCHO ALTURA
18.01.04.04.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 198.91
Cerco (Lado A-B ) 1.00 85.42 0.65 55.52
Cerco (Lado B-C ) 1.00 137.81 0.65 89.58
Cerco (Lado C-D) 1.00 82.79 0.65 53.81

18.01.04.04.03 VIGAS, ACERO FY=4200 KG/CM2 kg 1152.37


ver planilla de metrados para aceros 1.00 1,152.37 1152.37

18.01.05 MUROS Y TABIQUES


18.01.05.01 MURO DE SOGA CARAVISTA DE LADRILLO KK M:1:4 JUNTA 1.5 C m2 513.95
Cerco (Lado A-B ) 27.00 2.67 1.90 136.97
1.00 3.44 1.90 6.54
Cerco (Lado B-C ) 45.00 2.67 1.90 228.28
1.00 1.66 1.90 3.15
Cerco (Lado C-D) 27.00 2.67 1.90 136.97
1.00 1.07 1.90 2.03

18.01.06 REVOQUES
18.01.06.01 TARRAJEO EN CONTRAZOCALOS m2 428.43
Cerco (Lado A-B ) 2.00 85.42 0.70 119.59
Cerco (Lado B-C ) 2.00 137.81 0.70 192.93
Cerco (Lado C-D) 2.00 82.79 0.70 115.91

18.01.06.02 TARRAJEO EN COLUMNAS m2 386.40


Total de columnas 138.00 1.00 2.80 386.40

18.01.06.03 TARRAJEO EN VIGA m2 198.91


Cerco (Lado A-B ) 1.00 85.42 0.65 55.52
Cerco (Lado B-C ) 1.00 137.81 0.65 89.58
Cerco (Lado C-D) 1.00 82.79 0.65 53.81

18.01.07 PINTURA
18.01.07.01 PINTURA ESMALTE SINTETICO 2 MANOS EN CONTRAZOCALOS m2 428.43
Cerco (Lado A-B ) 2.00 85.42 0.70 119.59
Cerco (Lado B-C ) 2.00 137.81 0.70 192.93
Cerco (Lado C-D) 2.00 82.79 0.70 115.91

18.01.07.02 PINTURA LATEX 2 MANOS EN COLUMNAS m2 386.40


Total de columnas 138.00 1.00 2.80 386.40

18.01.07.03 PINTURA LATEX 2 MANOS EN VIGA m2 198.91


Cerco (Lado A-B ) 1.00 85.42 0.65 55.52
Cerco (Lado B-C ) 1.00 137.81 0.65 89.58
Cerco (Lado C-D) 1.00 82.79 0.65 53.81

18.01.07.03 PINTURA LATEX 2 MANOS EN MUROS m2 1027.90


Cerco (Lado A-B ) 2 27.00 2.67 1.90 273.94
2 1.00 3.44 1.90 13.07
Cerco (Lado B-C ) 2 45.00 2.67 1.90 456.57
2 1.00 1.66 1.90 6.31
Cerco (Lado C-D) 2 27.00 2.67 1.90 273.94
2 1.00 1.07 1.90 4.07

18.02 CERCO TIPO II


18.02.01 TRABAJOS PRELIMINARES
18.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 71.48
Cerco (Lado A-D Ingreso principal) 1.00 142.97 0.50 71.48
18.02.01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION m2 71.48
Cerco (Lado A-D Ingreso principal) 1.00 142.97 0.50 71.48

18.02.02 MOVIMIENTO DE TIERRAS


18.02.02.01 EXCAVACIONES
18.02.02.01.01 EXCAVACION DE ZANJA PARA CIMIENTOS HASTA H=1.0M m3 71.48
Cerco (Lado A-D Ingreso principal) 1.00 142.97 0.50 1.00 71.48

18.02.02.02 RELLENOS
18.02.02.02.01 RELLENO MANUAL CON MATERIAL PROPIO m3 15.01
Parte superior de cimiento
Cerco (Lado A-D Ingreso principal) 1.00 142.97 0.35 0.30 15.01

Página 2
HOJA DE METRADOS
: “MEJORAMIENTO DEL SERVICIO EDUCATIVO DE NIVEL PRIMARIA EN LA INSTITUCIÓN EDUCATIVA N° 38072 DE SACHABAMBA,
OBRA DISTRITO DE CHIARA - HUAMANGA - AYACUCHO”
FORMULA : CERCO PERIMETRICO
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE CHIARA
FECHA : OCTUBRE DEL 2022
LUGAR : SACHABAMBA

DIMENSIONES (M)
Item Und. Nº de Veces PARCIAL TOTAL
LARGO ANCHO ALTURA

18.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE


18.02.02.03.01 ACARREO MANUAL DE MATERIAL EXCEDENTE m3 ceof. Esponj 67.77
producto de la excavación 1.20 56.47 67.77
18.02.02.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 67.77
material acarreo 1.00 67.77 67.77

18.02.03 OBRAS DE CONCRETO SIMPLE


18.02.03.01 SOLADO
18.01.03.01.01 SOLADO MEZCLA 1:10 CEMENTO-HORMIGON, E=0.10M m2 17.50
Ubicación de columnetas 70.00 0.50 0.50 17.50

18.02.03.01 CIMIENTOS CORRIDOS


18.02.03.01.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON + 30% m3 71.48
Cerco (Lado A-D Ingreso principal) 1.00 142.97 0.50 1.00 71.48

18.02.03.02 SOBRECIMIENTO
18.02.03.02.01 SOBRECIMIENTOS, CONCRETO F'C=175 KG/CM2 m3 50.04
Cerco (Lado A-D Ingreso principal) 1.00 142.97 0.50 0.70 50.04

18.02.03.02.02 SOBRECIMIENTOS, ENCOFRADO Y DESENCOFRADO m2 142.97


Cerco (Lado A-D Ingreso principal) 2.00 142.97 0.50 142.97

18.02.04 OBRAS DE CONCRETO ARMADO


18.02.04.01 COLUMNAS
18.02.04.01.01 COLUMNAS, CONCRETO F'C=175 KG/CM2 m3 4.38
Cerco (Lado A-D Ingreso principal) 70.00 0.25 0.25 1.00 4.38
18.02.04.01.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO (2 USOS) m2 Perimetro 70.00
Cerco (Lado A-D Ingreso principal) 70.00 1.00 1.00 70.00
18.02.04.01.03 COLUMNAS, ACERO FY=4200 KG/CM2 kg 627.20
ver planilla de metrados para aceros 1.00 627.20 627.20

18.01.05 REVOQUES
18.01.05.01 TARRAJEO EN CONTRAZOCALOS m2 142.97
Cerco (Lado A-D Ingreso principal) 2.00 142.97 0.50 142.97

18.01.05.02 TARRAJEO EN COLUMNAS m2 70.00


Total de columnas 70.00 1.00 1.00 70.00

18.04.06 CERRAJERIA METALICA


18.04.06.01 REJA METALICA SEGÚN DISEÑO m 142.97
Cerco (Lado A-D Ingreso principal) 142.97 142.97

18.01.07 PINTURA
18.01.07.01 PINTURA ESMALTE SINTETICO 2 MANOS EN CONTRAZOCALOS m2 142.97
Cerco (Lado A-D Ingreso principal) 2.00 142.97 0.50 142.97

18.01.07.02 PINTURA LATEX 2 MANOS EN COLUMNAS m2 70.00


Total de columnas 70.00 1.00 1.00 70.00

18.01.07.03 PINTURA EN REJA METALICA m2 285.94


Cerco (Lado A-D Ingreso principal) 142.97 2.00 285.94

Página 3
HOJA DE SUSTENTO DE METRADOS (ACERO)
: “MEJORAMIENTO DEL SERVICIO EDUCATIVO DE NIVEL PRIMARIA EN LA INSTITUCIÓN EDUCATIVA N° 38072 DE SACHABAMBA,
OBRA DISTRITO DE CHIARA - HUAMANGA - AYACUCHO”

FORMULA : CERCO PERIMETRICO


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE CHIARA
FECHA : OCTUBRE DEL 2022
LUGAR : SACHABAMBA

ACERO EN CERCO PERIMETRICO


Diam, Nº N° Long(m.l) Total(m.l) Total(m.l) Total(m.l) Total(m.l) Total(m.l) Parcial(Kg) TOTAL
item detalle (pulgada) KG/m veces piezas 1/4" 3/8" 1/2" 5/8" 3/4" KG
18.01 CERCO TIPO I
18.01.04 OBRAS DE CONCRETO ARMADO
18.01.04.02 SOBRECIMIENTOS 1984.29
acero vertical 3/8 0.56 33 45 1.50 2227.50 1247.400
3/8 0.56 1 37 1.50 55.50 31.080
3/8 0.56 1 19 1.50 27.90 15.624

acero horizontal 3/8 0.56 33 4 9.00 1188.00 665.280


3/8 0.56 1 4 7.40 29.60 16.576
3/8 0.56 1 4 3.72 14.88 8.333

18.01.04.03 COLUMNAS 4068.79


acero principal 1/2 0.99 138 4 4.50 2484.00 2469.096

estribos 3/8 0.56 138 23 0.90 2856.60 1599.696

18.01.04.04 VIGAS 1152.37


acero principal 3/8 0.56 33.00 4 9.00 1188.00 665.280
3/8 0.56 1.00 4 7.40 29.60 16.576
3/8 0.56 1.00 4 3.72 14.88 8.333
estribos 1/4 0.25 33.00 60 0.90 1782.00 445.500
1/4 0.25 1.00 49 0.90 44.40 11.100
1/4 0.25 1.00 25 0.90 22.32 5.580
HOJA DE SUSTENTO DE METRADOS (ACERO)
: “MEJORAMIENTO DEL SERVICIO EDUCATIVO DE NIVEL PRIMARIA EN LA INSTITUCIÓN EDUCATIVA N° 38072 DE SACHABAMBA,
OBRA DISTRITO DE CHIARA - HUAMANGA - AYACUCHO”

FORMULA : CERCO PERIMETRICO


PROPIETARIO : MUNICIPALIDAD DISTRITAL DE CHIARA
FECHA : OCTUBRE DEL 2022
LUGAR : SACHABAMBA

ACERO EN CERCO PERIMETRICO


Diam, Nº N° Long(m.l) Total(m.l) Total(m.l) Total(m.l) Total(m.l) Total(m.l) Parcial(Kg) TOTAL
item detalle (pulgada KG/m veces piezas 1/4" 3/8" 1/2" 5/8" 3/4" KG
18.02 CERCO TIPO II
18.02.04 OBRAS DE CONCRETO ARMADO
18.02.04.01 COLUMNAS 627.20
acero principal 3/8 0.56 70 4 2.00 560.00 313.600
estribos 3/8 0.56 70 8 1.00 560.00 313.600
RESUMEN DE METRADOS
: “MEJORAMIENTO DEL SERVICIO EDUCATIVO DE NIVEL PRIMARIA EN LA
OBRA INSTITUCIÓN EDUCATIVA N° 38072 DE SACHABAMBA, DISTRITO DE CHIARA -
HUAMANGA - AYACUCHO”
FORMULA : CERCO PERIMETRICO
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE CHIARA
FECHA : OCTUBRE DEL 2022
LUGAR : SACHABAMBA
18 CONSTRUCCION CERCO PERIMETRICO
18.01 CERCO TIPO I
18.01.01 TRABAJOS PRELIMINARES
18.01.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 153.01
18.01.01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION m2 153.01
18.01.02 MOVIMIENTO DE TIERRAS
18.01.02.01 EXCAVACIONES
18.01.02.01.01 EXCAVACION DE ZANJA PARA CIMIENTOS HASTA H=1.0M m3 153.01
18.01.02.02 RELLENOS
18.01.02.02.01 RELLENO MANUAL CON MATERIAL PROPIO m3 14.47
18.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE
18.01.02.03.01 ACARREO MANUAL DE MATERIAL EXCEDENTE m3 166.25
18.01.02.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 166.25
18.01.03 OBRAS DE CONCRETO SIMPLE
18.01.03.01 SOLADO
18.01.03.01.01 SOLADO MEZCLA 1:10 CEMENTO-HORMIGON, E=0.10M m2 34.50
18.01.03.02 CIMIENTOS CORRIDOS
18.01.03.02.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON + 30% m3 153.01
18.01.04 OBRAS DE CONCRETO ARMADO
18.01.04.02 SOBRECIMIENTOS
18.01.04.02.01 SOBRECIMIENTOS, CONCRETO F'C=175 KG/CM2 m3 32.13
18.01.04.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 428.43
18.01.04.02.03 SOBRECIMIENTOS, ACERO FY=4200 KG/CM2 kg 1,984.29
18.01.04.03 COLUMNAS
18.01.04.03.01 COLUMNAS, CONCRETO F'C=175 KG/CM2 m3 24.15
18.01.04.03.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 386.40
18.01.04.03.03 COLUMNAS, ACERO FY=4200 KG/CM2 kg 4068.79
18.01.04.04 VIGAS
18.01.04.04.01 VIGAS, CONCRETO F'C=175 KG/CM2 m3 15.30
18.01.04.04.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 198.91
18.01.04.04.03 VIGAS, ACERO FY=4200 KG/CM2 kg 1152.37
18.01.05 MUROS Y TABIQUES
18.01.05.01 MURO DE SOGA CARAVISTA DE LADRILLO KK M:1:4 JUNTA 1.5 C m2 513.95
18.01.06 REVOQUES
18.01.06.01 TARRAJEO EN CONTRAZOCALOS m2 428.43
18.01.06.02 TARRAJEO EN COLUMNAS m2 386.40
18.01.06.03 TARRAJEO EN VIGA m2 198.91
18.01.07 PINTURA
18.01.07.01 PINTURA ESMALTE SINTETICO 2 MANOS EN CONTRAZOCALOS m2 428.43
18.01.07.02 PINTURA LATEX 2 MANOS EN COLUMNAS m2 386.40
18.01.07.03 PINTURA LATEX 2 MANOS EN VIGA m2 198.91
18.01.07.03 PINTURA LATEX 2 MANOS EN MUROS m2 1027.90
18.02 CERCO TIPO II
18.02.01 TRABAJOS PRELIMINARES
18.02.01.01 TRAZO Y REPLANTEO PRELIMINAR m2 71.48
18.02.01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION m2 71.48
18.02.02 MOVIMIENTO DE TIERRAS
18.02.02.01 EXCAVACIONES
18.02.02.01.01 EXCAVACION DE ZANJA PARA CIMIENTOS HASTA H=1.0M m3 71.48
18.02.02.02 RELLENOS
18.02.02.02.01 RELLENO MANUAL CON MATERIAL PROPIO m3 15.01
18.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE
18.02.02.03.01 ACARREO MANUAL DE MATERIAL EXCEDENTE m3 67.77
18.02.02.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 67.77
18.02.03 OBRAS DE CONCRETO SIMPLE
18.02.03.01 SOLADO
18.01.03.01.01 SOLADO MEZCLA 1:10 CEMENTO-HORMIGON, E=0.10M m2 17.50
18.02.03.01 CIMIENTOS CORRIDOS
18.02.03.01.01 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON + 30% m3 71.48
18.02.03.02 SOBRECIMIENTO
18.02.03.02.01 SOBRECIMIENTOS, CONCRETO F'C=175 KG/CM2 m3 50.04
18.02.03.02.02 SOBRECIMIENTOS, ENCOFRADO Y DESENCOFRADO m2 142.97
18.02.04 OBRAS DE CONCRETO ARMADO
18.02.04.01 COLUMNAS
18.02.04.01.01 COLUMNAS, CONCRETO F'C=175 KG/CM2 m3 4.38
18.02.04.01.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO (2 USOS) m2 70.00

Página 6
RESUMEN DE METRADOS
: “MEJORAMIENTO DEL SERVICIO EDUCATIVO DE NIVEL PRIMARIA EN LA
OBRA INSTITUCIÓN EDUCATIVA N° 38072 DE SACHABAMBA, DISTRITO DE CHIARA -
HUAMANGA - AYACUCHO”
FORMULA : CERCO PERIMETRICO
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE CHIARA
FECHA : OCTUBRE DEL 2022
LUGAR : SACHABAMBA
18.02.04.01.03 COLUMNAS, ACERO FY=4200 KG/CM2 kg 627.20
18.01.05 REVOQUES
18.01.05.01 TARRAJEO EN CONTRAZOCALOS m2 142.97
18.01.05.02 TARRAJEO EN COLUMNAS m2 70.00
18.04.06 CERRAJERIA METALICA
18.04.06.01 REJA METALICA SEGÚN DISEÑO m 142.97
18.01.07 PINTURA
18.01.07.01 PINTURA ESMALTE SINTETICO 2 MANOS EN CONTRAZOCALOS m2 142.97
18.01.07.02 PINTURA LATEX 2 MANOS EN COLUMNAS m2 70.00
18.01.07.03 PINTURA EN REJA METALICA m2 285.94