Está en la página 1de 4

CALENDARIO DE AVANCE DE OBRA VALORIZADO

Presupuesto REFORMULACION DEL EXPEDIENTE TECNICO: “REPARACION DE PLAZOLETA EN LA MUNICIPALIDAD DISTRITAL DE LA PUNTA EN LA LOCALIDAD LA PUNTA, DISTRITO DE LA PUNTA, GOBIERNO DEL CALLAO”.
Cliente MUNICIPALIDAD DISTRITAL DE LA PUNTA
Lugar CALLAO - CALLAO - LA PUNTA

PLAZO DE EJECUCION 90 DIAS CALENDARIOS


MES 01 MES 02 MES 03
Item Descripción Und. Metrado Precio S/. Parcial S/. 30 DIAS 30 DIAS 30 DIAS TOTAL
% METRADO MONTO % METRADO MONTO % METRADO MONTO
01 OBRAS PROVISIONALES
MOVILIZACION Y DESMOVILIZACION DE EQUIPOS, MAQUINAS Y
01.01 glb 1.00 3,200.00 3,200.00 40.00% 0.40 1,280.00 20.00% 0.20 640.00 40.00% 0.40 1,280.00 3,200.00
HERRAMIENTAS
01.02 CERCO PROVISIONAL DE OBRA C/PINTURA BLANCA m 80.00 126.86 10,148.80 100.00% 80.00 10,148.80 0.00% - 0.00% - 10,148.80
01.03 ALQUILER DE ALMACEN Y OFICINA mes 3.00 800.00 2,400.00 33.33% 1.00 800.00 33.33% 1.00 800.00 33.33% 1.00 800.00 2,400.00
01.04 ALQUILER DE BAÑOS PORTATILES mes 3.00 800.00 2,400.00 33.33% 1.00 800.00 33.33% 1.00 800.00 33.33% 1.00 800.00 2,400.00
01.05 CARTEL DE IDENTIFICACION DE OBRA 4.80 X 3.60m u 1.00 1,530.74 1,530.74 100.00% 1.00 1,530.74 0.00% - 0.00% - 1,530.74
02 OBRAS PRELIMINARES 0.00 - -
02.01 TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2 400.00 3.23 1,292.00 33.33% 133.33 430.67 33.33% 133.33 430.67 33.33% 133.33 430.67 1,292.00
INSTALACION Y DESINSTALACION DE ANDAMIOS METALICOS
02.02 mes 3.00 2,509.71 7,529.13 33.33% 1.00 2,509.71 33.33% 1.00 2,509.71 33.33% 1.00 2,509.71 7,529.13
NORMADOS
02.03 DEMOLICION DE PISO CERAMICO m2 59.45 13.87 824.57 100.00% 59.45 824.57 0.00% - 0.00% - 824.57
02.04 DEMOLICION DE PASO CONTRAPASO ESCALERA TERRAZO m2 39.73 16.64 661.11 100.00% 39.73 661.11 0.00% - 0.00% - 661.11
03 SEGURIDAD Y SALUD EN OBRA 0.00 - -
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN
03.01 glb 1.00 1,000.00 1,000.00 33.33% 0.33 333.33 33.33% 0.33 333.33 33.33% 0.33 333.33 1,000.00
DE SEGURIDAD Y SALUD EN EL TRABAJO
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN
03.02 glb 1.00 1,000.00 1,000.00 33.33% 0.33 333.33 33.33% 0.33 333.33 33.33% 0.33 333.33 1,000.00
AMBIENTAL
03.03 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 2,614.70 2,614.70 33.33% 0.33 871.57 33.33% 0.33 871.57 33.33% 0.33 871.57 2,614.70
03.04 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 3,227.24 3,227.24 33.33% 0.33 1,075.75 33.33% 0.33 1,075.75 33.33% 0.33 1,075.75 3,227.24
03.05 SEÑALIZACION TEMPORAL DE SEGURIDAD mes 3.00 1,018.64 3,055.92 33.33% 1.00 1,018.64 33.33% 1.00 1,018.64 33.33% 1.00 1,018.64 3,055.92
RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN
03.06 glb 1.00 2,143.06 2,143.06 33.33% 0.33 714.35 33.33% 0.33 714.35 33.33% 0.33 714.35 2,143.06
SEGURIDAD Y SALUD DURANTE EL TRABAJO
04 COVID 19 0.00 - -
04.01 KIT DE LIMPIEZA Y DESINFECCION PERSONAL ANTE COVID-19 mes 3.00 387.18 1,161.54 33.33% 1.00 387.18 33.33% 1.00 387.18 33.33% 1.00 387.18 1,161.54
04.02 EQUIPOS DE PROTECCION PERSONAL ANTE COVID-19 mes 3.00 263.28 789.84 33.33% 1.00 263.28 33.33% 1.00 263.28 33.33% 1.00 263.28 789.84
ELABORACION, IMPLEMENTACION Y ADMINISTRACION DE PLAN
04.03 glb 1.00 4,200.00 4,200.00 33.33% 0.33 1,400.00 33.33% 0.33 1,400.00 33.33% 0.33 1,400.00 4,200.00
PARA PREVENCION CONTRA COVID-19
04.04 SEÑALIZACIÓN INFORMATIVA DE CUIDADOS ANTE EL COVID-19 u 1.00 211.38 211.38 33.33% 0.33 70.46 33.33% 0.33 70.46 33.33% 0.33 70.46 211.38
04.05 PRUEBA MOLECULAR COVID-19 mes 3.00 800.00 2,400.00 33.33% 1.00 800.00 33.33% 1.00 800.00 33.33% 1.00 800.00 2,400.00
04.06 PRUEBA ANTÍGENA COVID-19 mes 3.00 960.00 2,880.00 33.33% 1.00 960.00 33.33% 1.00 960.00 33.33% 1.00 960.00 2,880.00
05 GLORIETA DE PLAZA DE ARMAS 0.00 - -
05.01 DESMONTAJE CONTROLADO DE GLORIETA 0.00 - -
05.01.01 DESMONTAJE CONTROLADO DE GLORIETA glb 1.00 13,109.48 13,109.48 100.00% 1.00 13,109.48 0.00% - 0.00% - 13,109.48
05.01.02 ACARREO Y ELIMINACION DE GLORIETA glb 1.00 4,395.02 4,395.02 100.00% 1.00 4,395.02 0.00% - 0.00% - 4,395.02
05.02 OBRAS DE CONCRETO 0.00 - -
05.02.01 REHABILITACION Y REFORZAMIENTO DE COLUMNA < 1.50 M Und. 2.00 1,394.97 2,789.94 100.00% 2.00 2,789.94 0.00% - 0.00% - 2,789.94
05.02.02 MOLDES DE FIBRA DE VIDRIO PARA PEDESTALES DE COLUMNAS Und. 2.00 445.00 890.00 100.00% 2.00 890.00 0.00% - 0.00% - 890.00
05.03 CAPINTERIA DE MADERA 0.00 - -
05.03.01 COLUMNAS DE MADERA p2 1,194.67 23.72 28,337.57 0.00% 0.00 100.00% 1,194.67 28,337.57 0.00% - 28,337.57
05.03.02 VIGAS DE MADERA 3"X5" p2 140.00 23.72 3,320.80 0.00% 0.00 66.67% 93.33 2,213.87 33.33% 46.67 1,106.93 3,320.80
05.03.03 VIGAS DE AMARRE O SOLERA DE MADERA 5"X3" p2 140.00 23.72 3,320.80 0.00% 0.00 53.33% 74.67 1,771.09 46.67% 65.33 1,549.71 3,320.80
CALENDARIO DE AVANCE DE OBRA VALORIZADO

Presupuesto REFORMULACION DEL EXPEDIENTE TECNICO: “REPARACION DE PLAZOLETA EN LA MUNICIPALIDAD DISTRITAL DE LA PUNTA EN LA LOCALIDAD LA PUNTA, DISTRITO DE LA PUNTA, GOBIERNO DEL CALLAO”.
Cliente MUNICIPALIDAD DISTRITAL DE LA PUNTA
Lugar CALLAO - CALLAO - LA PUNTA

PLAZO DE EJECUCION 90 DIAS CALENDARIOS


MES 01 MES 02 MES 03
Item Descripción Und. Metrado Precio S/. Parcial S/. 30 DIAS 30 DIAS 30 DIAS TOTAL
% METRADO MONTO % METRADO MONTO % METRADO MONTO
05.03.04 COLLARIN MADERAS 3"X5" p2 120.00 23.72 2,846.40 0.00% 0.00 40.00% 48.00 1,138.56 60.00% 72.00 1,707.84 2,846.40
05.03.05 TRAVESAÑO 2"X4" p2 160.00 23.72 3,795.20 0.00% 0.00 26.67% 42.67 1,012.05 73.33% 117.33 2,783.15 3,795.20
05.03.06 CUERDA DE AMARRE DE MADERA 1 1/2"X4" p2 112.00 23.72 2,656.64 0.00% 0.00 13.33% 14.93 354.22 86.67% 97.07 2,302.42 2,656.64
05.03.07 MACHIEMBRADO 4"X3/8" (CIELO RASO Y CUBIERTA) p2 1,062.50 23.72 25,202.50 0.00% 0.00 0.00% - 100.00% 1,062.50 25,202.50 25,202.50
05.03.08 ARCOS TECHO CONTRAPLACADA TRIPLAY 6MM m2 23.49 206.85 4,858.91 0.00% 0.00 0.00% - 100.00% 23.49 4,858.91 4,858.91
05.03.09 ESTRUCTURA TAMBOR p2 425.00 23.52 9,996.00 0.00% 0.00 0.00% - 100.00% 425.00 9,996.00 9,996.00
05.03.10 SECADO HORNO MADERA p2 3,354.17 1.63 5,467.30 0.00% 0.00 100.00% 3,354.17 5,467.30 0.00% - 5,467.30
05.03.11 TRATAMIENTO DE MADERA p2 3,354.17 1.46 4,897.09 0.00% 0.00 100.00% 3,354.17 4,897.09 0.00% - 4,897.09
05.04 CARPINTERIA METÁLICA 0.00 - -
05.04.01 ANCLAJES Y ACCESORIOS FIERRO COLUMNA MADERA glb 1.00 2,693.90 2,693.90 0.00% 0.00 100.00% 1.00 2,693.90 0.00% - 2,693.90
05.04.02 ANCLAJES Y ACCESORIOS FIERRO VIGAS MADERA glb 1.00 3,605.90 3,605.90 0.00% 0.00 100.00% 1.00 3,605.90 0.00% - 3,605.90
05.04.03 REJA ORNAMENTAL SEGÚN DISEÑO (GALVANIZADO EN CALIENTE) u 8.00 2,101.42 16,811.36 0.00% 0.00 40.00% 3.20 6,724.54 60.00% 4.80 10,086.82 16,811.36
05.05 VIDRIOS 0.00 - -
05.05.01 CRISTAL TEMPLADO 6mm CUPULA m2 4.84 158.80 768.59 0.00% 0.00 0.00% - 100.00% 4.84 768.59 768.59
05.06 CUBIERTAS 0.00 - -
05.06.01 TEJA ASFALTICA m2 85.00 111.03 9,437.55 0.00% 0.00 0.00% - 100.00% 85.00 9,437.55 9,437.55
05.07 PISOS Y PAVIMENTOS 0.00 - -
05.07.01 PASO Y CONTRAPASO ESCALERA EN TERRAZO m2 39.73 83.56 3,319.84 0.00% 0.00 0.00% - 100.00% 39.73 3,319.84 3,319.84
05.07.02 PISO CERAMICO ESPAÑOL COLOR DE 40X40 CM m2 59.45 98.89 5,879.01 0.00% 0.00 0.00% - 100.00% 59.45 5,879.01 5,879.01
05.08 MOBILIARIO URBANO 0.00 - -
SUMINISTRO E INSTALACION DE BANCAS ORNAMENTALES SEGUN
05.08.01 u 4.00 763.74 3,054.96 0.00% 0.00 0.00% - 100.00% 4.00 3,054.96 3,054.96
DETALLE
05.09 PINTURA 0.00 - -
05.09.01 PINTURA DUCO CIELO RASO MACHIHEMBRADO EN ALTURA m2 85.00 36.37 3,091.45 0.00% 0.00 0.00% - 100.00% 85.00 3,091.45 3,091.45
05.09.02 PINTURA BARNIZ DD MADERA p2 3,354.17 2.24 7,513.34 0.00% 0.00 0.00% - 100.00% 3,354.17 7,513.34 7,513.34
05.09.03 PINTURA COBERTURA TEJA EN ALTURA m2 85.00 25.27 2,147.95 0.00% 0.00 0.00% - 100.00% 85.00 2,147.95 2,147.95
PINTURA BARANDA DE CONCRETO (INCLUYE RETIRO DE PINTURA
05.09.04 m 26.64 9.56 254.68 0.00% 0.00 0.00% - 100.00% 26.64 254.68 254.68
EXISTENTE)
05.09.05 PINTURA REJAS METALICAS ESMALTE EPOXICO u 8.00 80.61 644.88 0.00% 0.00 0.00% - 100.00% 8.00 644.88 644.88

05.10 INSTALACIONES ELECTRICAS Y MANTENIMIENTO DE LUMINARIAS 0.00 - -

05.10.01 SALIDA DE PARED pto 4.00 292.87 1,171.48 0.00% 0.00 0.00% - 100.00% 4.00 1,171.48 1,171.48
05.10.02 CAMBIO DE PLACAS DE TOMACORRIENTES pto 4.00 197.73 790.92 0.00% 0.00 0.00% - 100.00% 4.00 790.92 790.92
05.10.03 REFLECTORES EN GLORIETA u 4.00 558.02 2,232.08 0.00% 0.00 0.00% - 100.00% 4.00 2,232.08 2,232.08
05.10.04 LUMINARIAS DE PISO SIMILAR A LA EXISTENTE u 4.00 685.20 2,740.80 0.00% 0.00 0.00% - 100.00% 4.00 2,740.80 2,740.80
05.10.05 CABLE ELECTRICO NYY 3X4mm2 m 180.00 12.32 2,217.60 0.00% 0.00 0.00% - 100.00% 180.00 2,217.60 2,217.60
05.10.06 PRUEBAS DE RESISTIVIDAD, CONTINUIDAD Y AISLAMIENTO glb 1.00 2,100.00 2,100.00 0.00% 0.00 0.00% - 100.00% 1.00 2,100.00 2,100.00
06 REPOSICION AREAS VERDES 0.00 - -
06.01 TIERRA DE CHACRA m2 61.60 20.29 1,249.86 0.00% 0.00 0.00% - 100.00% 61.60 1,249.86 1,249.86
06.02 AREA VERDE INC. ABONO Y SEMBRADO DE GRASS m2 61.60 14.10 868.56 0.00% 0.00 0.00% - 100.00% 61.60 868.56 868.56
07 VARIOS 0.00 - -
CALENDARIO DE AVANCE DE OBRA VALORIZADO

Presupuesto REFORMULACION DEL EXPEDIENTE TECNICO: “REPARACION DE PLAZOLETA EN LA MUNICIPALIDAD DISTRITAL DE LA PUNTA EN LA LOCALIDAD LA PUNTA, DISTRITO DE LA PUNTA, GOBIERNO DEL CALLAO”.
Cliente MUNICIPALIDAD DISTRITAL DE LA PUNTA
Lugar CALLAO - CALLAO - LA PUNTA

PLAZO DE EJECUCION 90 DIAS CALENDARIOS


MES 01 MES 02 MES 03
Item Descripción Und. Metrado Precio S/. Parcial S/. 30 DIAS 30 DIAS 30 DIAS TOTAL
% METRADO MONTO % METRADO MONTO % METRADO MONTO
REPARACION DE PISOS DE PIEDRA EN PLAZA DE ARMAS POR
07.01 est 1.00 1,540.07 1,540.07 0.00% 0.00 0.00% - 100.00% 1.00 1,540.07 1,540.07
TRABAJOS
07.02 LIMPIEZA PERMANENTE Y FINAL DE OBRA glb 1.00 3,696.00 3,696.00 0.00% 0.00 0.00% - 100.00% 1.00 3,696.00 3,696.00
CALENDARIO DE AVANCE DE OBRA VALORIZADO

Presupuesto REFORMULACION DEL EXPEDIENTE TECNICO: “REPARACION DE PLAZOLETA EN LA MUNICIPALIDAD DISTRITAL DE LA PUNTA EN LA LOCALIDAD LA PUNTA, DISTRITO DE LA PUNTA, GOBIERNO DEL CALLAO”.
Cliente MUNICIPALIDAD DISTRITAL DE LA PUNTA
Lugar CALLAO - CALLAO - LA PUNTA

PLAZO DE EJECUCION 90 DIAS CALENDARIOS


MES 01 MES 02 MES 03
Item Descripción Und. Metrado Precio S/. Parcial S/. 30 DIAS 30 DIAS 30 DIAS TOTAL
% METRADO MONTO % METRADO MONTO % METRADO MONTO
COSTO DIRECTO 248,384.46 48,397.93 71,624.37 128,362.16 248,384.46
GASTOS GENERALES 14.50% 36,015.75 7,017.70 10,385.53 18,612.52 36,015.75
GASTOS GENERALES FIJOS 0.59% 1,460.00 284.48 421.01 754.51 1,460.00
GASTOS GENERALES VARIABLES 13.91% 34,555.75 6,733.22 9,964.53 17,858.00 34,555.75
UTILIDAD 8.00% 19,870.76 3,871.83 5,729.95 10,268.97 19,870.76
=========== =========== =========== =========== ===========
SUBTOTAL 304,270.97 59,287.46 87,739.85 157,243.65 304,270.97
IGV 18.00% 54,768.77 10,671.74 15,793.17 28,303.86 54,768.77
=========== =========== =========== =========== ===========
TOTAL 359,039.74 69,959.20 103,533.02 185,547.51 359,039.74
PORCENTAJE MENSUAL DE AVANCE DE OBRA 19.49% 28.84% 51.68%
PORCENTAJE ACUMULADO DE AVANCE DE OBRA 19.49% 48.32% 100.00%