Está en la página 1de 8

S10

Precios y cantidades de recursos requeridos

Obra 0492001 PUENTE CARROZABLE UCLITA


Subpresupuesto 001 PUENTE CARROZABLE UCLITA
Fecha 17/10/2005
Lugar 020511 ANCASH - BOLOGNESI - LA PRIMAVERA

Código Recurso Unidad Cantidad

0147000032 TOPOGRAFO hh 3.9900


0147010002 OPERARIO hh 1,611.0476
0147010003 OFICIAL hh 1,562.8771
0147010004 PEON hh 22,687.1589 2,727.9354
0202010061 CLAVOS kg 22.0000
0202040010 ALAMBRE NEGRO N° 8 kg 50.4710
0202040066 ALAMBRE N°16 kg 995.6255
0202040067 ALAMBRE N°8 kg 52.1880
0202100103 CLAVOS DE 3" kg 54.2822
0202100104 CLAVOS DE 4" kg 78.0885
0202310002 PERFIL DE ACERO3'X3"X1/4" m 12.7600
0202510104 PERNOS 3/4" X5" pza 63.9980
0202970004 ACERO CORRUGADO kg 21,357.7457
0203020004 ESTACA DE FIERRO und 60.0000
0204000000 ARENA FINA m3 0.0840
0205000032 PIEDRA CHANCADA 1/2" (NO AFECTO m3 34.1334
0205010004 ARENA GRUESA m3 30.0575
0205010015 MATERIAL DE RELLENO m3 166.5000
0205020021 PIEDRA GRANDE m3 7.2450
0221000000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 2,380.2423
0227000007 GUIA m 390.8298
0227020012 FULMINANTE COMUN # 6 DE 35 mm und 512.9000
0228000023 EXPLOSIVO SEMEXA 60 kg 51.2900
0230020031 BARRENO DE 7/8" X 3 PIES und 1.0258
0230460011 PEGAMENTO PARA PVC AGUA FORDUgln 0.6000
0230550011 TEODOLITO hm 3.9900
0230650022 NEOPRENO CM3 30,000.0000
0230650023 NEOPRENO,JEBE NATURAL 1/4"X0.20 m 8.8200
0232510002 FLETE TERRESTRE GLB 1.0000
0232970003 MOVILIZACION Y DESMOVILIZACION GLB 1.0000
0238000000 HORMIGON m3 224.9130
0243010003 MADERA TORNILLO p2 8,224.5490
0243720001 MADERA EUCALIPTO ROLLIZO p2 2,188.7800
0251010061 PERFIL ACERO ANGULO 3"X3"X1/4" m 17.6400
0251010062 PLATINA DE FIERRO 3"X1/4" m 17.6400
0256220103 PLANCHA DE ACERO 0.20X0.25X1/2" und 15.9984
0263510001 BARANDA DE Fo Go 3" m 88.0000
0272020098 TUBO PVC SAP 3" X 5 M und 1.2780
0280010001 YESO DE 40 KG BOL 1.5000
0283010001 ALMACEN GLB 1.0000
0337010001 HERRAMIENTAS MANUALES %MO
0337020045 JALONES hm 8.0100
0337540006 MIRA TOPOGRAFICA hm 3.9900
0348010011 MEZCLADORA DE CONCRETO DE 9 - hm 129.7537
0348080002 MOTOBOMBA 12 HP 4" hm 595.9800
0349070003 VIBRADOR DE CONCRETO 4 HP 1.50" hm 129.7537
0349100021 PLANCHA COMPACTADORA 5.8 HP hm 30.8303

Total

La columna parcial es el producto del precio por la cantidad requerida; y en la última columna se muestra el Monto Real que se está utilizando
Página : 1

rsos requeridos

Precio S/. Parcial S/. Presupuestado S/.

8.00 31.92 33.00


4.22 6,798.63 6,826.46
3.83 5,985.83 5,920.76
1.25 3,409.93 3,407.62
8.00 176.00 176.00
3.50 176.65 176.65
3.50 3,484.71 3,584.26
3.50 182.67 182.66
3.50 189.98 189.99
3.50 273.32 275.92
33.00 421.08 421.08
3.00 192.00 191.84
2.70 57,665.93 57,685.81
0.30 18.00 18.00
30.00 2.40 2.52
40.00 1,365.20 1,365.33
30.00 901.80 901.74
2.00 333.00 333.00
2.50 18.13 18.11
19.00 45,224.56 45,224.60
0.50 195.42 194.90
0.50 256.45 256.45
10.00 512.90 512.90
320.00 329.60 328.25
50.00 30.00 30.00
10.30 41.10 42.00
0.15 4,500.00 4,500.00
10.00 88.20 88.20
17,775.09 17,775.09 17,775.09
1,000.00 1,000.00 1,000.00
10.00 2,249.10 2,249.13
3.00 24,673.65 24,673.64
0.80 1,751.02 1,750.98
25.00 441.00 441.00
10.00 176.40 176.40
20.00 320.00 319.88
60.00 5,280.00 5,280.00
10.00 12.80 12.78
6.50 9.75 9.00
400.00 400.00 400.00
492.09 492.09
0.79 6.33 6.00
1.10 4.39 3.00
25.00 3,243.75 3,244.79
6.00 3,575.88 3,575.88
8.00 1,038.00 1,037.66
15.00 462.45 462.04

S/. 195,717.07 195,797.41

S/. 195,797.41

al que se está utilizando


FONCODES / DEPI

CALCULO DEL FLETE

OBRA : PUENTE UCLITA


OFICINA ZONAL : HUARAZ
N. EXPEDIENTE : 1320050195

1- DATOS GENERALES

A-POR PESO

MATERIALES UNIDAD AFECTO IGV PESO.UNIT. PESO.TOTAL


CEMENTO BL. 2,380.00 42.50 101,150.00
ALAMBRE, FIERRO,CLAVOS KG 22,687.00 1.00 22,687.00
MADERA TORNILLO P2 8,225.00 1.20 9,870.00

PESO TOTAL . 133,707.00

B-POR VOLUMEN

EN AGREGADOS Y MADERA
DESCRIPC. UNIDAD AFECTOS IGV SIN IGV
ARENA Y GRAVA M3 0.00
PIEDRA M3 0.00
HORMIGÓN M3 0.00
MADERA ROLLIZA P2 0.00 2,189.00

VOLUMEN TOTAL 5.17


CAPACIDAD DEL CAMION (M3) 8.00
NUMERO DE VIAJES 0.65
REDONDEO 0.75

EN TUBERIA UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.


CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML No de tubos No VIAJES
Tub de 3/4 U 0.00 0.00
Tub, 1" U 0.00 0.00
Tub,1 1/2" U 0.00 0.00
Tub 2:" U 0.00 0.00
Tub, 3" U
Tub 4": U
Tub 6:" U-PVC U 0.00 0.00
Tub 8" U-PVC U
Tub 6'; CSN U
Tub 8'; CSN U
NUMERO TOTAL DE VIAJES
REDONDEO
TUBERIA EN VOLUMEN

Ing.ISABEL
2- FLETE TERRESTRE
HUARAZ- UCLITA ( PIE DE OBRA)
UNIDAD DE TRANSPORTE
UNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTE
CAPACIDAD DEL CAMION ( M3 ) 10.00 CAPACIDAD DEL CAMION /M3 8.00
COSTO POR VIAJE S/. 1,000.00 COSTO POR VIAJE S/. 400.00
CAPACIDAD DEL CAMION (KG) 7,000.00 CAPACIDAD DEL CAMION / KG 8,000.00
FLETE POR KG 0.14

AFECTO IGV SIN IGV FLETE POR PESO =Peso Total * Flete por peso
FLETE POR PESO MATERIALES 18,718.98 FLETE POR VOLUMEN=No viajes*costo por viaje
FLETE POR VOLUMEN MADERA ROLLIZA 300.00

COSTO TOTAL FLETE TERR. 19,018.98

RESUMEN FLETE TOTAL

AFECTO IGV SIN IGV


FLETE TERRESTRE 19,018.98
FLETE FLUVIAL
FLETE CON ACEMILA
FLETES TOTALES S/. 19,018.98

Ing.ISABEL
Ing.ISABEL
R PESO =Peso Total * Flete por peso
R VOLUMEN=No viajes*costo por viaje

Ing.ISABEL